									               INVITATION TO BID
                BOULDER COUNTY
COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT

                      BID #5810-13
     Item #1 – (FLAGSTONE PAVING)
     Item #2 – (REPOINTING OF EXISTING FLAGSTONE PAVERS)




                     SUBMITTAL DUE:

               Monday, MARCH 11, 2013
                       2:00 p.m.


       BOULDER COUNTY PURCHASING
                     2025 14th STREET
                    BOULDER CO 80302

          Purchasing@bouldercounty.org
                  PROJECT LOCATION & CONTACTS

For: BOULDER COUNTY COURTHOUSE PLAZA FLAGSTONE
              PAVING REPAIR PROJECT
                 Located at: 1325 Pearl Street, Boulder, CO 80302


OWNER
  Boulder County
  P.O. Box 471
  Boulder, CO 80306
  303-441-3905

CONSTRUCTION ADMIN., OWNER REP.
  Boulder County Administrative Services
  Building Services Division
  P.O. Box 471
  Boulder, CO 80306
  303-994-8247
  Contact: Jesse Newcomb

ARCHITECT
  Boulder County Administrative Services
  Architect Division
  P.O. Box 471
  Boulder, CO 80306
  303-441-3905
  Contact: Seth Jacobs

GENERAL CONTRACTOR
  Boulder County Administrative Services
  P.O. Box 471
  Boulder, CO 80306
  303-4343890
  Contact: Gary Gressett
                          PROJECT MANUAL
    BOULDER COUNTY COURTHOUSE FLAGSTONE PAVING REPAIR PROJECT
                           BID # 5810-13

                                                      Table of Contents

  NUM.          SECTION                                                                                         PAGE

DIVISION 00 - BIDDING DOCUMENTS, CONTRACT, & GENERAL CONDITIONS
   000102 - Project Contacts ...................................................................... ............ 000102-1
   000110 - Table of Contents .................................................................... ............ 000110-1
   000115 - Drawing Index......................................................................... ............ 000115-1
   001116 - Invitation to Bid ...................................................................... ............ 001116-1 to -2
   002113 - Instructions to Bidders ............................................................ ............ 002113-1 to -4
   004100 - Bid Form ................................................................................. ............ 004100-1 to -4
    004500 - Contractor's Qualification Statement .................................... ............ 004500-1 to -5
   005000 - Building Construction Contract (Sample) ............................... ............ 005000-1 to-13
   007200 - General Conditions ................................................................. ............ 007200-1 to-
10

DIVISION 01 - GENERAL REQUIREMENTS
   011000 - SUMMARY OF WORK ........................................................ ............ 011000-1 to-3



DIVISION 03 – SITEWORK
   32 1440– STONE PAVING .................................................................... ............ 32 1440-1 to -3

DRAWINGS----------------------------------------------------------------------------------------------------A0,A1,A3,A7,A8
                                                  DRAWING INDEX


These are the drawings included with Bid Package #5810-13. Those that are not deemed important
to this bid (i.e. Mech., Electrical) have been omitted.


COURTHOUSE COMPLEX SITE PLAN .................................................. ............ A0
ENLARGED PLAZA PLAN ....................................................................... ............ A1
ORIGINAL COURTHOUSE PLAZA PLAN ............................................. ............ A3
CONCRETE DETAILS ............................................................................... ............ A7
CONCRETE DETAILS ............................................................................... ............ A8
                                      INVITATION TO BID

Notice is hereby given that Boulder County will accept sealed bids for subcontracts for the BOULDER
COUNTY COURTHOUSE FLAGSTONE PAVING REPAIR PROJECT, Bid #5810-13, located
at 1325 Pearl Street, Boulder CO 80302.

PLEASE NOTE: The Boulder County Architect/Construction Division will be the General
Contractor for this project. Contracts to be bid at this time include only those listed below.

1.       The following items will be bid according to the project plans and specifications:
         Item #1 –FLAGSTONE PAVING
         Item #2 – REPOINTING OF EXISTING FLAGSTONE PAVING

Bid documents, plans and project manuals will be available Tuesday February 26, 2013 at 3:00 pm
Online at Rocky Mountain Bid Net at the web link below:
http://www.rockymountainbidsystem.com

If you are unable to access the project documents, alternate arrangements can be made to pick up a hard
copy of the bid documents at the Administrative Front Desk in the Boulder County Courthouse East
Wing (First Floor), 2025 14th Street. Please call 303-441-3525 to arrange a time to pick up the
documents.

A pre-bid walk-through will be held on Thursday, March 7th, 2013 at 8:00 am at the project site.
The site is located at the Boulder County Courthouse 1325 Pearl Street, Boulder CO, 80302. Bidders
are to meet the County Representative at the plaza area on the south side of the Courthouse.
The pre-bid conference is not mandatory, but bidders are strongly encouraged to attend.
It is the bidder’s responsibility to be familiar with all pre-existing conditions.

Bids are due at the Administrative Services Front Desk or the email box listed below (preferred), for
time and date recording and verification on or before 2:00 p.m., Mountain Time, Monday, March 11,
2013.

Your response can be submitted in the following ways. Please note that e-mail responses to
this solicitation are preferred, but are limited to a maximum of 25MB capacity. Electronic
submittals must be received in the e-mail box listed below. Submittals sent to any other box
will NOT be forwarded or accepted. This e-mail box is only accessed on the due date of your
questions or proposals. Please use the Delivery Receipt option to verify receipt of your email.

E-Mail           purchasing@bouldercounty.org; identified as BID #5810-13 in the subject line.
-OR-
US Mail        Two (2) unbound copies of your proposal, printed double-sided, 11 point, on at least
               50% post-consumer, recycled paper must be submitted in a sealed envelope, clearly
               marked as BID #5810-13, and delivered to the Administrative Services Front Desk at
               2025 14th Street, Boulder, CO 80302. Please allow at least 2 days for delivery of
               USPS Priority and Express Mail. BIDDERS SHOULD USE THE BID FORM IN THE
               PROJECT MANUAL.
All BIDs must be received and time and date recorded and verified at the Administrative Services
Front Desk by the above due date and time. Sole responsibility rests with the Offeror to see that their
BID is received on time at the stated location(s). Any BID’s received after due date and time will be
returned to the bidder. No exceptions will be made.
2.       Questions concerning bidding procedures are to be communicated to the Purchasing
         Department at the number listed above.

3.       Questions concerning Technical Issues will be dealt with by the COUNTY'S
         REPRESENTATIVE, Jesse Newcomb Boulder County Building Services,
         2020 13th St., Boulder, CO 80302, ph. 303-994-8247 (fax: 303-441-1718).

4.       Submittal Due:     Date: Monday March 11, 2013
                            Time: 2:00 P.M.
                            At: Boulder County Administrative Front Desk
                                  2025 14th Street
                                  Boulder, Colorado 80302

5.       Late Bids are those with a date and time stamp from the Boulder County Administrative Front
         Desk after the due date and time. They will be returned unopened.

6.       Bid Opening will occur at the time bids are due or as soon as practical after the due time. All
         bids will be read aloud in the location designated by the Boulder County Purchasing Office.

7.       Evaluation of Contractor's Qualification Statement (A.I.A. Form A305) will be based on the
         following criteria:

         a.    Information on A.I.A. A305 must be current to within 30 days of submittal.

         b.    Though not required for bidding, the County prefers bidders that have been in business
               for at least five (5) years and that have completed at least five projects of similar size
               and/or scope.

         c.    A completed qualification statement may be required for a bid to be recommended to
               the Commissioners.

8.       Final Acceptance of bids is up to the Board of County Commissioners. The Board of County
         Commissioners reserves the right to reject any and all bids, to waive any informalities therein,
         and to accept the bid that in the opinion of the Board of County Commissioners is in the best
         interest of the Board and the County of Boulder, State of Colorado.

9.       All items under the Instructions to Bidders shall be binding on all Bidders.

Americans with Disabilities Act (ADA):
If you need special services provided for under the Americans with Disabilities Act, contact the
ADA Coordinator or the Human Resources office at (303) 441-3525 at least 48 hours before the
scheduled event.
                                 INSTRUCTIONS TO BIDDERS


To be considered, bids must be made in accordance with these Instructions to Bidders.


ARTICLE 1 - Definitions

1.1    Bidding Documents include the Advertisement or Invitation to Bid, Instructions to Bidders,
       the Bid Form, Contractor's Qualification Statement, other sample bidding and contract forms
       and the proposed Contract Documents including any Addenda issued prior to receipt of Bids,
       the plans, specifications and special provisions.

1.2    All definitions set forth in the General Conditions of the Contract for Construction or in other
       Contract Documents are applicable to the Bidding Documents.

1.3    Addenda are written or graphic instruments issued by the Architect or Owner prior to the Bid
       Opening, which modify or interpret the bidding documents by addition, deletion, clarification
       or correction.

1.4    A Bid is a complete and properly signed proposal to do the Work or designated portion
       thereof for the sums stipulated therein supported by data called for by the Bidding
       Documents.

1.5    Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work
       described as the base, to which Work may be added or deducted for sums stated in Alternate
       Bids.

1.6    An alternate bid (or Alternate) is an amount stated in the Bid to be added to or deducted from
       the amount of the Base Bid if the corresponding change in project scope or materials or
       methods of construction described in the Bidding Documents is accepted.

1.7    A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials
       or services as described in the Contract Documents.

1.8    A Bidder is one who submits a Bid for Contract for the Work described in the proposed
       Contract documents and is referred to throughout these instructions as if singular in number
       and masculine in gender.

1.9    A Sub-Bidder is one who submits a Bid to a Bidder for materials or labor for a portion of the
       Work.
ARTICLE 2 – Bidder’s Representation

2.1   Each Bidder by making his Bid represents that:

      a.     He has read and understands the Bidding Documents and his Bid is made in
             accordance therewith.
      b.     He has visited the site and has familiarized himself with the local conditions under
             which the Work is to be performed.
      c.     His Bid is based upon the materials, system and equipment described in the Bidding
             Documents without exceptions.


ARTICLE 3 - Bidding Documents

3.1   Copies
      a.     Bidding Documents can be picked up at the locations designated in the Invitation to
             Bid.
      b.     Bidding Documents shall be used in preparing Bids; the County and Architect
             assume no responsibility for errors or misinterpretations of Bidding Documents.
      c.     The County and Architect, in making copies of the Bidding Documents available on
             the above items, does so only for the purpose of obtaining Bids on the Work and does
             not confer a license or grant for any other use.

3.2   Interpretation or Correction of Bidding Documents
      a.      Bidders shall promptly notify the County Representative listed in the Invitation to
              Bid of any ambiguity, inconsistency, or error which they may discover upon
              examination of the Bidding Documents or of the site and local conditions.
      b.      Bidders requiring clarification or interpretation of the Bidding Documents shall make
              a written request to the County's Representative received at least seven (7) days prior
              to the date of receipt of Bids.
      c.      Any interpretation, correction or change of the Bidding Documents will be made by
              Addendum. Interpretations, corrections and changes of the Bidding Documents made
              in any other manner will not be binding, and Bidder shall not rely upon such
              interpretations, corrections and changes. The County's Representative will not be
              responsible for oral clarification.

3.3   Substitutions
      a.     The materials, products and equipment described in the Bidding Documents establish
             a standard of required function, dimension, appearance and quality to be met by any
             proposed substitution. It is not the intention of the Contract Documents to exclude
             materials equal to those specified.
      b.     Substitution will not be considered unless written request for approval has been
             submitted by the Bidder and has been received by the County's Representative at
             least ten (10) days prior to the date for receipt of Bids. Each such request shall be
             made in accordance with Section 01300 in the Project Manual.
3.4   Addenda
      a.    All who are known by the County's Representative to have received a complete set of
            Bidding Documents will be notified when each addendum is issued.
      b.    Copies of addenda will be made available for inspection wherever Bidding
            Documents are on file for that purpose.
      c.     No addenda will be issued later than three (3) days prior to the date for receipt of
             Bids except an addendum, if necessary, postponing the date for receipt of Bids or
             withdrawing the request for Bids.
      d.     Each Bidder shall ascertain prior to submitting his Bid that he has received all
             addenda issued, and he shall acknowledge their receipt in his Bid. It is the
             responsibility of the Bidder to ensure receipt of all addenda.
      e.     All addenda issued shall become a part of the Contract Documents.


ARTICLE 4 - Bidding Procedure

4.1   Form and Style of Bids
      Failure to comply with the following provisions may be cause for rejection of Bids.
      a.      All blanks on the Bid Forms shall be filled in by typewriter or manually in ink.
              Illegible Bids will be cause for rejection.
      b.      Where so indicated by the makeup of the bid form, sums shall be expressed in both
              words and figures, and in case of discrepancy between the two, the words shall
              govern.
      c.      Any interlineation, alteration or erasure must be initialed by the signer of the Bid.
      d.      All requested alternates shall be bid. If a Bidder wishes not to bid an alternate, it
              shall be marked "NO BID".
      e.      Where there are two or more major items of work for which separate quotations have
              been requested, Bidder may state his refusal to accept less than whatever combination
              of the items he stipulates.
      f.      Bidder shall make no additional stipulations on the bid form nor qualify his bid in
              any other manner.
      g.      Each copy of Bid shall include the legal name of Bidder and a statement whether
              Bidder is a Sole proprietor, a Partnership, a Corporation or any other legal entity, and
              each copy shall be signed by the person or persons legally authorized to bind the
              Bidder to a Contract. A Bid by a Corporation shall further give the state of
              incorporation and have the corporate seal affixed. A Bid submitted by an agent shall
              have a current Power of Attorney attached certifying agent's authority to bind Bidder.

4.2   Collusive Agreements
      Each Bidder submitting a Bid to the County for any portion of the work contemplated by the
      documents on which bidding is based may be required to execute an affidavit to the effect
      that he has not entered into a collusive agreement with any other person, firm, or corporation
      in regard to any Bid submitted.
4.3   Submission of Bids
      a.    Bids are to be submitted to the location or email designated in the Invitation to Bid
            on a form following the requirement of Article 4.1 of these Instructions to Bidders.
      b.    No bid received after the time and date designated in the Invitation to Bid or the
            latest time and date published in any of the Addenda will be considered.
      c.    Oral, telephonic, facsimile (fax), or telegraphic Bids are invalid and will not receive
            consideration.

4.4   Modification or Withdrawal of Bid Prior to Opening
      a.     Before the bids are opened, bidders will be asked if there are any present who wish to
             withdraw their bid. A bidder may then withdraw from bidding if s/he wishes.
             Bidders will them be asked if there are any present who wish to modify their bid only
             with respect to signing a forgotten document or correcting similar clerical errors and
             will be informed that they may then do so. Bidders may not use this time to complete
             a bid, make an outside call to a subcontractor, or any other similar change. A bidder
             wishing to modify a bid shall state the nature of the modification (correction of
             mathematical error, etc.) before being allowed to open the envelope and make such
             modification. Bids turned back to the bidder for modification will not be allowed to
             be removed from the location of the bid opening.
      b.     For the thirty (30) days after the actual opening of Bids, no Bid may be withdrawn or
             modified.

ARTICLE 5 - Consideration of Bids

5.1   Rejection of Bids
      a.     The County shall have the right to reject any or all Bids and in particular to reject a
             Bid not accompanied by any required bid security or data required by the Bidding
             Documents or a Bid in any way incomplete or irregular.
      b.     The County may reject a Bid before or after bid opening, upon receiving and
             reviewing evidence of collusion with intent to defraud or other illegal practices upon
             the part of the Bidder.

5.2   Acceptance of Bid (Award)
      a.    The County shall have the right to accept Alternates in any order or combination and
            to determine the low Bidder on the basis of the sum of the Base Bid and the
            Alternates accepted.
      b.    It is the intent of the County to award a Contract to the lowest responsible and
            responsive Bidder provided the bid has been submitted in accordance with the
            requirements of the Bidding Documents, is judged to be reasonable, and does not
            exceed the funds available.
      c.    Notwithstanding any delay in the preparation and execution of the formal Contract
            Agreement, each Bidder shall be prepared, upon written notice of Bid Award, to
            furnish all required bonds and to commence work within ten (10) days following
            receipt of such written Notice of Award and Order to Proceed, unless otherwise
            specified.
ARTICLE 6 - Qualification of Contractors and Subcontractors

6.1    Contractor's Qualifications
       a.     Successful bidders will submit all the information required by the Contractor's
              Qualification Statement and these Instructions.
       b.     The evaluation committee shall make its decision based on the criteria listed in the
              Invitation to Bid.
       c.     In addition the Contractor will submit:
              1.       A list of the work to be performed by the Bidder with his own forces.
              2.       The proprietary names and the suppliers of principal items or systems of
                       material and equipment proposed for the Work.
              3.       A list of names of Subcontractors or other persons or organizations (including
                       those who are to furnish materials or equipment fabricated to a special
                       design) proposed for all except minor portions of the Work shall be submitted
                       to County within five (5) days after bid award.
       d.     The Bidder will be required to establish to the satisfaction of the County the
              reliability and responsibility of the proposed Subcontractors to furnish and perform
              the Work described in the Sections of the Specifications pertaining to such proposed
              Subcontractors' respective trades.

6.2    Rejection of Subcontractors:
       Prior to the Award of the Contract, the County will notify the Bidder in writing if the County,
       after due investigation, has reasonable and substantial objection to any person or organization
       on such list. If the County has a reasonable and substantial objection to any person or
       organization on such list, and refuses in writing to accept such person or organization, the
       Bidder may, at his option, (1) withdraw his Bid, (2) submit an acceptable substitute
       Subcontractor with an increase in his bid price to cover the difference in cost occasioned by
       such substitution. The County may, at its discretion, accept the increased bid price or it may
       disqualify the Bidder.

6.3    Use of Accepted Subcontractors:
       Subcontractors and other persons and organizations proposed by the Bidder and accepted by
       the County must be used on the work for which they were proposed and accepted and shall
       not be changed except with the written approval of the County.

ARTICLE 7 - Sales Tax

7.1    Attention of Bidders is particularly called to the requirement for certificates of State Tax
       exemption for the Contractors and Subcontractors upon award of Contract. (Title 39-26-114,
       1973, CRS as amended). DO NOT INCLUDE SALES TAX IN THE BID PROPOSAL.
       Questions regarding this provision should be referred to the Colorado State Department of
       Revenue, Sales Tax Division.

7.2    Where applicable, the Contractor must file for applicable permits under the County's General
       Building Permit. Contractors not filing under the County's permit will be responsible for
       applicable taxes at no additional cost to the County.
ARTICLE 8 - Time of Completion

8.1    The Bidder shall insert the number of calendar days to complete the Project, start date, and/or
       finish date as requested in the Bid form. Refer to Invitation to Bid for intended project dates.


ARTICLE 9 - Bonding Requirements

9.1    Performance Bonds and Labor/Material Payment Bonds are required if the total contract
       amount is in excess of Fifty Thousand Dollars ($50,000). For further information and
       requirements see the General Conditions.


ARTICLE 10 - Form of Agreement Between Owner and Contractor

10.1   The Agreement for the Work will be written on the Boulder County Building Construction
       Contract where the basis of payment is a Stipulated Sum, as provided for in the Bidding
       Documents.


ARTICLE 11 - Licenses and Permits

11.1   Contractor and subcontractor shall be licensed if required by State, City or other local
       regulations to perform the work intended.


ARTICLE 12 - RETURN PLANS AND PROJECT MANUALS to:

12.1   Boulder County Administrative Services Front Desk
       2025 14th Street (S.W. corner of 14th & Spruce Streets)
       Boulder, Colorado 80302
       or
       P.O. Box 471
       Boulder, Colorado 80306
                      BID FORM FOR BOULDER COUNTY PROJECT:


            COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT
                                          BID # 5810-13

                       ITEM#1 FLAGSTONE PAVING

                       ITEM#2 REPOINTING OF EXISTING FLAGSTONE PAVING

TO:    BOARD OF COUNTY COMMISSIONERS
       BOULDER COUNTY
       BOULDER, COLORADO

Contractor has examined the Plans and Specifications and the site of the proposed work, and receipt
of Addenda Nos. ________is hereby acknowledged.

Contractor agrees that the other parts of the Contract Documents shall form and be part of the
Contract to be signed by him if this Bid is accepted.


Contractor hereby proposes to furnish all labor, machinery, equipment, materials
and supplies, and to sustain all the expense incurred in doing the work
hereinafter described for what is known as COURTHOUSE PLAZA FLAGSTONE
PAVING REPAIR PROJECT according to all Contract Documents of the County
Commissioners, County of Boulder, of the State of Colorado, dated February 26,
2013.

Contractor agrees to protect his employees on this contract, if awarded, by adequate Workmen's
Compensation Insurance. The Contractor further agrees to provide evidence of Comprehensive
General and Automobile Liability Insurance, as per the limits of the contract, prior to
commencement of Work.

Contractor agrees that the price for any Extra Work or Materials that the County may order
in writing is to be agreed upon, either as a lump sum or unit price, prior to commencing the
Work or supplying the materials.

Contractor hereby agrees to execute a Contract on forms provided by the said County Representative
within ten (10) days (or such further time as may be allowed in writing by the County
Representative) after receiving notification of the Award of Contract based on this bid, and in case
he does not, the County Commissioners may proceed to award the Contract to another, readvertise
the work for bids, or proceed in any lawful manner they deem advisable.
Contractor agrees to commence the work within ten (10) days (or such further time as may be
allowed in writing by the County) after the Contract has been signed and the Contractor has
submitted to the County the Certificate of Insurance and all required Bonds. The Contractor also
agrees to complete the work according to a mutually accepted schedule to be worked out with
Boulder County.

Contractor hereby declares and stipulates that this Bid is made in good faith, without collusion or
connection with any other Contractor, person or persons bidding for the same work.

Contractor understands that the County reserves the right to make the award on the basis of the
Bid deemed most favorable to the County, to waive any informalities, or to reject any or all Bids,
but that this Bid shall remain open and not be withdrawn for a period of thirty (30) days from
the date prescribed for its opening.


NOTE: If Bidder is a corporation, set forth the legal name of the corporation together with the
     signature of the officer or officers authorized to sign contracts on behalf of the
     corporation. If Bidder is a partnership, set forth the name of the firm together with the
     signature of the partner or partners authorized to sign contracts on behalf of the
     partnership.

Documents required to be submitted with this bid form are:

1.   Contractors Qualification Statement (Unless you have filed one with us in the last 6 months.)
     Section 5 of the Contractor’s Qualification Statement (Financial Statement) does not need to be
     submitted with the Bid, but must be submitted within 3 days after being requested by Boulder
     County.

2.   Please submit two copies of this bid.

Incomplete bid packages may be cause for rejection by Board of County Commissioners.
                       BID SUBMITTAL SECTION
                             BID # 5810-13
          COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT



All work described in the Drawings, Specifications and Addenda for this project.
COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT


Item #1 – FLAGSTONE PAVING

Base
           Price:________________________________________________________________
           _dollars

           ($________________)

       Base Time: _________________calendar days to complete all Work.



Item #2 – REPOINT EXISTING FLAGSTONE PAVING

Base
           Price:________________________________________________________________
           _dollars

           and Hourly rate ($________)
                             SIGNATURE PAGE
                               BID # 5810-13
            COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT


Failure to complete, sign and return this submittal page with your proposal may be cause for
rejection.

Contact Information                      Response


Company Name



Name and Title of Primary Contact


Company Address



Phone Number



Fax Number



Email Address



Company Website


By signing below I certify that:
I am authorized to bid on my company’s behalf.
I am not currently an employee of Boulder County.
None of my employees or agents is currently an employee of Boulder County.
I am not related to any Boulder County employee or Elected Official.
I am not a Public Employees’ Retirement Association (PERA) retiree.


_____________________________________________________                     _________________
*Signature of Person Authorized to Bid on Company’s Behalf                       Date

Note: If you cannot certify the above statements, please explain in the space provided below.
                                   BOULDER COUNTY
                          ADMINISTRATIVE SERVICES DEPARTMENT
                               BUILDING SERVICES DIVISION

                 CONTRACTOR’S QUALIFICATION STATEMENT
The undersigned certifies under oath that the information provided herein is true and sufficiently complete
so as not to be misleading.

Submitted to:    Boulder County Administrative Services Dept.
                 Building Services Division
                 P.O. Box 471, Boulder, CO 80306


Submitted by: ________________________________________________________
                                                                                             Type (check one):
                                                                                              B     Corporatio
Name:            ________________________________________________________                       n
                                                                                              B     Partnershi
                                                                                                p
Address:         ________________________________________________________                     B     Individual
                                                                                              B     Joint
                                                                                                Venture
Name of Project: _______________________________________________________                      B     Other


Type of work:    ________________________________________________________




1. Organization

    1.1    How many years has your organization been in business as a Contractor?


    1.2    How many years has your organization been in business under its present business name?


           1.2.1 Under what other or former names has your organization operated?

    1.3    If your organization is a corporation, answer the following:

           1.3.1 Date of incorporation:

           1.3.2 State of incorporation:

           1.3.3 President’s name:
         1.3.4 Vice-president’s name(s):

         1.3.5 Secretary’s name:

         1.3.6 Treasurer’s name:



   1.4   If your organization is a partnership, answer the following:

         1.4.1 Date of organization:

         1.4.2 Type of partnership (if applicable):

         1.4.3 Name(s) of general partner(s):



   1.5   If your organization is individually owned, answer the following:

         1.5.1 Date of organization:

         1.5.2 Name of owner:



   1.6   If the form of your organization is other than those listed above, describe it and name the principals:




2. Licensing

   2.1 List jurisdictions and trade categories in which your organization is legally qualified to do business,
       and indicate registration or license numbers, if applicable.




   2.2 List jurisdictions in which your organization’s partnership or trade name is filed.
3.       Experience


     3.1 List the categories of work that your organization normally performs with its own forces.




     3.2 Claims and Suits. (If the answer to any of the questions below is yes, please attach details.)

           3.2.1 Has your organization ever failed to complete any work awarded to it?


           3.2.2 Are there any judgments, claims, arbitration proceedings or suits pending or outstanding

                 against your organization or its officers?




           3.2.3 Has your organization filed any law suits or requested arbitration with regard to construction

                 contracts within the last five years?




     3.3 Within the last five years, has any officer or principal of your organization ever been an officer or
         principal of another organization when it failed to complete a construction contract? (If the answer is
         yes, please attach details.)




     3.4 On a separate sheet, list major construction projects your organization has in progress, giving the name
         of project, owner, architect/engineers, contract amount, percent complete and scheduled completion
         date.
           3.4.1 State total worth of work in progress and under contract:



     3.5 On a separate sheet, list the major projects your organization has completed in the past five years,
         giving the name of project, owner, architect/engineer, contract amount, date of completion and
         percentage of the cost of work performed with your own forces.
           3.5.1 State average annual amount of construction work performed during the past five years:

     3.6 On a separate sheet, list the construction experience and present commitments of the key individuals
         of your organization.
4.       References

     4.1 Trade References (include attachments as needed):



     4.2 Bank References (include attachments as needed):



     4.3 Surety:

         4.3.1     Name of bonding company:



         4.3.2     Name and address of agent:


5. Financing

     5.1 Financial Statement:

         5.1.1     Attach a financial statement, preferably audited, including your organization’s latest balance
                   sheet and income statement showing the following items:

         Current assets (e.g., cash, joint venture accounts, accounts receivable, notes receivable, accrued
                     income, deposits, materials inventory, and prepaid expenses):

         Net fixed assets:

         Other assets:

         Current liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income
                     taxes, advances, accrued salaries and accrued payroll taxes):

         Other liabilities (e.g., capital , capital stock, authorized and outstanding shares par values, earned
                      surplus and retained earnings):


         5.1.2     Name and address of firm preparing attached financial statement, and date thereof:

         5.1.3     Is the attached financial statement for the identical organization named on page one?

         5.1.4     If not, explain the relationship and financial responsibility of the organization whose financial
                   statement is provided (e.g., parent-subsidiary).


     5.2 Will the organization whose financial statement is attached act as guarantor of the contract for
         construction?
6. Signature

         Dated: ___________________________________________________________
                       Month               Day                Year


Name of Organization: __________________________________________________________


By:      ______________________________________________________________________


Title:   ______________________________________________________________________




____________________________________________________________, being duly sworn, deposes and
says that the information provided herein is true and sufficiently complete so as not to be misleading.




Subscribed and sworn before me this ______________ day of __________________ , ________
                                         Day                     Month            Year



Notary Public:



My Commission Expires:
                              BOULDER COUNTY
                BUILDING CONSTRUCTION CONTRACT (SAMPLE)
             COURTHOUSE PLAZA FLAGSTONE PAVING PROJECT
                              BID NO. 5810-13
______________________________________________________________________________


        THIS CONTRACT is between the Board of County Commissioners of the County of
Boulder, Colorado, hereinafter referred to as the "County", and ________________, hereinafter
referred to as the Contractor, and shall inure to the benefit of, and be binding upon, the successors of
these parties.

       The County and the Contractor agree as follows:

1.     Work. The Contractor will furnish all the work, labor, and materials and perform all the
work required for the complete and prompt execution of Boulder County project, COURTHOUSE
PLAZA FLAGSTONE PAVING PROJECT, BID # 5810-13 The Contractor will perform in a
good and workmanlike manner at its own cost and expense. Performance shall be strictly in
accordance with all contract documents for this project, including the drawings and specifications.
The Documents included and made part of this contract are:

       a.      The Contract Documents: the Drawings, the Bid Documents, and all of this Project
               Manual.

       b.      Addenda to the Contract Documents

       c.      All forms used to execute provisions of the Contract Documents; i.e., bond forms,
               certificates of insurance, stop work orders, change orders, certificates of payment,
               etc.


2.     Compensation. The County will pay the Contractor ______________________ dollars and
______ cents, ($________), and such further amounts as may be required as a result of additional
work or change orders, pursuant to the provisions of the specifications and the general conditions.


3.     Time. Time is of the essence in the performance of the work under this contract. Work shall
begin as soon as possible and shall be completed within the schedule set by Boulder County, unless
additional time is allowed by the County in writing under the provisions of the Contract Documents.


4.     Bonds. Prior to the execution of this contract by the County, the Contractor shall furnish to
the County all bonds required by law, by the Instructions to Bidders and by the General Conditions.
5.     Equal Opportunities. The contractor agrees to comply with the letter and spirit of the
Colorado AntiDiscrimination Act of 1957, C.R.S. 24-34-301, et seq., as amended, and all applicable
laws respecting discrimination and unfair employment practices.


6.      Indemnification. The Contractor shall be solely responsible for all damages to persons or
property which may in whole or in part be caused by the Contractor or its agents or employees, or
which may result or arise in whole or in part from their performing services hereunder, and will
indemnify and hold harmless the County, its elected and appointed officials, and its employees,
agents and representatives, from any and all liability, damage, loss, cost or expense, including but not
limited to attorneys' fees which the County, its elected or appointed officials, or its employees, agents
or representatives may suffer as a result of any and all claims, demands, actions, costs or judgments
made or brought against them by any person or entity, and which arise either in whole or in part out
of the services performed under this Agreement. By demanding this right to indemnification, the
County in no way waives or intends to waive the limitations on liability which are provided to the
County and its employees under the Colorado Governmental Immunity Act, C.R.S.  24-10-101 et
seq., as amended.


7.      Insurance Requirements. The Contractor providing services under this Agreement will be
required to procure and maintain at his own expense and without cost to Boulder County, until final
acceptance of all work covered by the Contract, or proposal, the following types and amounts of
insurance. The policy limits required are to be considered minimum amounts and may increase due
to the scope of risk involved.

         a.      Commercial General Liability. This coverage should be provided on ISO Form
                 CG2503 (1998 Edition) with minimum limits of $1,000,000 combined single limit
                 for each occurrence. Coverage shall include products/completed operations liability.

         b.      Workers Compensation and Employers Liability. Workers’ Compensation must be
                 maintained in accordance with the statutory limits for every person utilized by the
                 Contractor for work under this Contract. Employer’s Liability is required for
                 minimum limits of $100,000 Each Accident; $500,000 Disease-Policy Limit;
                 $100,000 Disease-Each Employee.

         c.      Automobile Liability. Minimum limits are required to be $1,000,000 for each
                 occurrence. Coverage must include:
                        -All vehicles owned, non-owned, hired to be used on the contract
                        -Personal Injury Protection where applicable


         d.      Professional Liability. Minimum limits of $600,000. Coverage written on a claims made basis is
                 acceptable. This insurance is required if the contractor is doing any of the project design work
                 involving state licensed professionals (architects, engineers, etc.). [Delete if not applicable.]


    e.   Pollution Liability. Pollution liability, with minimum limits of $600,000, must include sudden and gradual
   coverage for third party liability including defense costs and completed operations. This is required when and if the

   construction project is known to have an exposure to pollution liability risks. [Delete if not applicable.]



       The Contractor shall provide Certificates of Insurance to Boulder County demonstrating that
       the aforementioned insurance requirements have been met prior to the commencement of
       work under this Contract. The Comprehensive General Liability Certificate of Insurance
       shall indicate Boulder County as an ADDITIONAL INSURED.

                 1.       The Additional Insured wording should be as follows:      The County of
                          Boulder, State of Colorado, a body corporate and politic is named as an
                          additional insured.

                 2.       These Certificates of Insurance shall also contain a valid provision or
                          endorsement that these policies may not be cancelled, terminated, changed or
                          modified, without thirty (30) days written notice to the County.

                 3.       The above notices and Certificates of Insurance must be forwarded to the
                          following designated County representative:

                                   Pam Stonecipher, Risk Manager
                          Boulder County
                          P.O. Box 471
                          Boulder, Colorado 80306
                          303.441.3801 voice
                          303.441.4526 fax


       The Contractor is responsible for ascertaining that its subcontractors are properly insured to
       meet the above requirements before permitting them to commence work under this Contract.




8.      This Contract is subject to all statutory requirements applicable to political subdivisions of
the State. Without limiting this statement, attention is drawn to the following:


       a.        Colorado Labor: Colorado labor shall be employed to perform the work to the extent
                 of not less than eighty percent (80%) of each type or class of labor in the several
                 classifications of skilled and common labor employed in the project, in accordance
                 with Section 8-17-101, et seq., C.R.S. "Colorado Labor" means any person who is a
                 resident of the State of Colorado, at the time of employment, without discrimination
                 as to race, color, creed, sex, age, or religion except when sex or age is a bona fide
                 occupational qualification.

CONTRACT                                                                                             005000 - 24
       b.      Bribery or Abuse of Public Office: Contractor asserts that it is familiar with the
               provisions of Section 18-8-301, et seq., C.R.S. (Bribery and Corrupt Influences) and
               Section 18-8-401, et seq. C.R.S. (Abuse of Public Office) and that no violation of
               such provisions has occurred with regard to this contract.

       c.      Non-Payment to Sub-contractors: Contract Payments may be withheld pursuant to
               Section 38-26-107, C.R.S., if the County receives a verified statement that the
               Contractor has not paid amounts due to any person who has supplied labor or
               materials. for the project.


9.      Solicitations for Subcontractors, Including Procurements of Materials and Equipment: In all
solicitations by the Contractor for any work related to this Contract to be performed under a
subcontract, either by comprehensive bidding or negotiation, and including procurements of
materials or equipment, the Contractor shall notify each potential subcontractor or supplier of the
Contractor's obligations under this Contract, and of all pertinent regulations relative to
nondiscrimination and unfair employment practices on the basis of race, color, national origin,
handicap, or other unfair or discriminatory grounds.


10.     Sanctions for Noncompliance: In the event of the Contractor's noncompliance with the
nondiscrimination and unfair employment practices provisions of this contract, the County shall
impose such sanctions under the Contract as it may determine to be appropriate, including but not
limited to:

       a.      Withholding of payments to the Contractor under the Contract until the Contractor
               complies, and/or

       b.      Cancellation, termination or suspension of the Contract, in whole or in part, effective
               upon seven (7) days written notice to the Contractor pursuant to paragraph 15 below.


11.     Applicability to Subcontractors: The Contractor shall include the provisions of paragraphs 8
through 13 of this contract in every subcontract which it enters for purposes of carrying out this
Contract, including subcontracts for the procurement of materials or equipment. In addition, the
Contractor, if directed by the County or other authorized governmental representatives as a means of
enforcing such regulations, shall take whatever enforcement action the County or authorized
governmental representative may require of the Contractor with respect to the affected subcontract or
procurement, including imposition of the sanctions for noncompliance specified in paragraph 10 of
this Contract, above; provided, however, that in the event a contractor becomes involved in, or is
threatened with, litigation by a subcontractor or supplier as a result of such enforcement action, the
Contractor may request that the County or other affected governmental entity join in such litigation
to protect the interests of the County or other governmental entity.



CONTRACT                                                                              005000 - 25
12.    Permits and Licenses: The Contractor shall have full responsibility for identifying and
obtaining prior to the start of work under this Contract, and for maintaining throughout the term of
this Contract, any governmental permits or licenses which may be requested in order to carry out the
work.


13.     Inspection of Work: The County representatives shall have the right to enter freely and
inspect fully the work site to insure full compliance with this Contract and the Bidding Documents,
so long as such inspection does not interfere unreasonably with the Contractor's prosecution of the
work. The Contractor shall be responsible for keeping a competent and reliable supervisor on the
Work Site at all times during which work under this Contract is being performed. In the event the
Contractor is absent from the Work Site, the superintendent shall stand in the place of the Contractor
as his authorized representative and any notices or directions given by the County or its authorized
representatives to the superintendent which are pertinent to this Contract shall be binding on the
Contractor as if given to it.


14.    Termination:

       a. The provisions of paragraph 2 of this Contract notwithstanding, the County reserves the
          right to terminate work under this Contract if funds are not appropriated, budgeted, or
          otherwise made available for this Contract for any years subsequent to the current fiscal
          year. If the County terminates the Contract for this reason, the County and the Contractor
          shall be released from all obligations to perform work and make payments hereunder,
          except that the County shall be required to make payment for work which has been
          performed by the Contractor prior to the effective date of termination under this
          provision; and, conversely, the Contractor shall be required to complete any work for
          which the County has made payment prior to the effective termination date. Termination
          by the County under this provision shall be effective seven (7) days after the County
          provides notice to the Contractor pursuant to the provisions of paragraph 15, below.


       b.      If the Contractor defaults or persistently fails or neglects to carry out the work in
               accordance with the contract or Bid Documents, or fails to perform any provision of
               the Contract, the County, effective after seven (7) days' written notice to the
               Contractor pursuant to the provisions of paragraph 15, below, and without prejudice
               to any other remedy the County may have, may make good any resulting deficiencies
               in the work and may deduct the cost thereof from any payment then or thereafter due
               to the Contractor; or, at its option, the County may terminate the Contract upon the
               notice required hereunder, and, if the County deems appropriate, may take possession
               of the Work Site and of all materials, tools, and construction equipment and
               machinery located thereon and owned by the Contractor, and may finish the work by
               whatever method it deems expedient. If the unpaid balance outstanding for any work
               which has been performed adequately by the Contractor, exceeds the expense to the
               County of finishing or remedying work under this provision, the County shall pay

CONTRACT                                                                              005000 - 26
                    such excess to the Contractor, but if such expense, whatever its amount, if
                    reasonable, exceeds such unpaid balance, the Contractor shall pay the difference to
                    the County, and shall be liable for any such excess which the Contractor or his surety
                    is unable or unwilling to pay to the County.

   c.    The preceding provisions of this paragraph notwithstanding, performance of work under this Contract may be suspended or terminated,
   either in whole or in part, by the County, for any reason, whenever the County determines that such termination or suspension is in the best
   interests of the County. Such suspension or termination shall be effective after seven (7) days' written notice to the Contractor pursuant to the
   provisions of paragraph 15, below, unless a shorter effective period is specified pursuant to subparagraph d., below. The notice required for
   this purpose shall state the reasons for, and extent and duration of, such suspension or termination and the responsive action to be reasonably
   required by the County of the Contractor. Upon the effective date of such suspension or termination, the Contractor shall take the responsive
   action specified in the Notice, including, if the Notice so specifies, the cancellation or postponement of all outstanding commitments
   concerning the work. The Contractor shall be obligated to take any reasonably required responsive action as diligently and cost effectively as
   possible. The Contractor shall submit to the County a written claim for all outstanding amounts which the County owes the Contractor under
   the Contract, as soon as possible after the County exercises its right to take action under this provision.




        d.          In the event of any emergency or urgent situation related to the work being performed
                    under this Contract, the County, in its discretion, may shorten the effective notice
                    periods specified in subparagraphs a. through c. above. If the County exercises this
                    discretion it shall provide the required notice to the Contractor or his authorized
                    representative by hand-delivery, and shall clearly specify in the notice the effective
                    date of the suspension or termination.
        e.          In the event the County exercises any of the termination rights specified in
                    subparagraphs a. through d. above, this Contract shall cease to be of any further force
                    and effect, with the exception of all contract remedies which are specified herein and
                    may otherwise be available to the parties under law, and with the exception of any
                    rights or liabilities of these parties which may survive by virtue of paragraphs 6
                    through 14 of this Contract.


15.     Notices: For purposes of the notices required to be provided under paragraphs 10 and 14,
above, all such notices shall be in writing, and shall be either sent by Certified US Mail, return
receipt requested, or hand-delivered to the following representatives of the parties at the following
addresses:

                    For the County:                                Jana Petersen
                                                                   Boulder County Administrative Services
                                                                   P.O. Box 471
                                                                   Boulder, Colorado 80306

                    For the Contractor:                            (Name and Address of Contractor)


or, if hand-delivery is used, personally to the Contractor's superintendent at the Work Site pursuant
to paragraph 14, above. In the event a notice is mailed (pursuant to the provisions of this paragraph),
the seven (7) day effective time periods specified under paragraphs 7, 10 and 14, above, shall
commence to run on the day after the postmarked date of mailing.




CONTRACT                                                                                                                     005000 - 27
16.     Acceptance and Final Payment: Within ten days after the Contractor's declaration of
completion of the work, the County will make a final inspection thereof to determine whether the
work has been completed in accordance with the contract. If any list of deficiencies results from
such final inspection, the Contractor shall promptly rectify all items appearing thereon, before final
payment will be made. When the owner indicates acceptance of the work, the Contractor may
requisition final payment, including retainage, on account of the purchase order contract price.



17.    Guaranty and Warranties:

       a.      The Contractor shall promptly correct any Work rejected by the County as defective
               or as failing to conform to the Contract Documents whether observed before or after
               Substantial Completion and whether or not fabricated, installed or completed, and
               shall correct any Work found to be defective or nonconforming within a period of
               one year from the Date of Substantial Completion of the Contract or within such
               longer period of time as may be prescribed by law or by the terms of any applicable
               special warranty required by the Contract Documents. The provisions of this Article
               apply to Work done by Subcontractors or Support Services as well as to Work done
               by direct employees of the Contractor. Corrections shall be made at no expense to
               the County.

       b.      The Contractor shall furnish the County with all guarantees and warranties required
               under the specifications. Unless specifically stated in the specifications, such
               warranties and guarantees shall run from the date of installation, not from the date of
               purchase by the Contractor. Unless stated elsewhere in the Specifications, warranties
               and guarantees shall be for one (1) year.


18.     Post-Completion: Final payment made to the Contractor on account of the work shall not
operate to relieve the Contractor of responsibility for faulty material or workmanship, and unless
otherwise provided, the Contractor shall remedy any defect due thereto and pay for any damages
resultant therefrom which shall appear within one (1) year from the date of the final acceptance of
the work.


19.     Benefit to Successors and Assigns: This Contract, during its term as specified herein, shall
inure and benefit and shall be binding upon the successors, heirs, and assigns of the parties hereto.


20.    Severability: Any provision of this contract which may be rendered null and void shall not
invalidate the remainder of this Contract to the extent the Contract is capable of execution.



CONTRACT                                                                              005000 - 28
21.    This Contract shall be governed by the laws of the State of Colorado and shall be effective
upon execution by both parties. Any litigation between these parties involving this contract shall be
pursued in the District Court in Boulder County, Colorado.



22.     Independent Contractor. The Parties recognize and agree that the Contractor is an
independent contractor for all purposes, both legal and practical, in performing services under this
Agreement, and that the Contractor and its agents and employees are not agents or employees of
Boulder County for any purpose. As an independent contractor, the Contractor shall be responsible
for employing and directing such personnel and agents as it requires to perform the services
purchased hereunder, shall exercise complete authority over its personnel and agents, and shall be
fully responsible for their actions.

        Contractor acknowledges that it is not entitled to unemployment insurance benefits nor
worker's compensation benefits from Boulder County, its elected officials, agents, or any program
administered or funded by Boulder County. Contractor shall be entitled to unemployment insurance
or worker's compensation insurance only if unemployment compensation coverage or worker's
compensation coverage is provided by Contractor, or some other entity that is not a party to this
contract. Contractor is obligated to pay federal and state income tax on any monies earned pursuant
to the contract relationship.


23.     Third-Party Beneficiary. The enforcement of the terms and conditions of this contract and all
rights of action relating to such enforcement, shall be strictly reserved to the County and the
Contractor, and nothing contained in this contract shall give or allow any claim or right of action
whatsoever by any other or third person. It is the express intent of the parties to this contract that any
other person receiving services or benefits under this contract shall be deemed an incidental
beneficiary only.


24.     Prohibitions on Public Contract for Services: Pursuant to Colorado Revised Statute (C.R.S.),
§ 8-17.5-101, et. seq., as amended 5/13/08, the Contractor shall meet the following requirements
prior to signing this Agreement (public contract for service) and for the duration thereof:

        a.      The Contractor shall certify participation in the E-Verify Program (the electronic employment
                verification program that is authorized in 8 U.S.C. § 1324a and jointly administered by the United
                States Department of Homeland Security and the Social Security Administration, or its successor
                program) or the Department Program (the employment verification program established by the
                Colorado Department of Labor and Employment pursuant to C.R.S. § 8-17.5-102(5)) on the attached
                certification.

        b.      The Contractor shall not knowingly employ or contract with an illegal alien to perform work under this
                public contract for services.




CONTRACT                                                                                           005000 - 29
         c.    The Contractor shall not enter into a contract with a subcontractor that fails to certify to the Contractor
               that the subcontractor shall not knowingly employ or contract with an illegal alien to perform work
               under this public contract for services.


    d. At the time of signing this public contract for services, the Contractor has confirmed the employment eligibility
                 of all employees who are newly hired for employment to perform work under this public contract for
                 services through participation in either the E-Verify Program or the Department Program.


    e.         The Contractor shall not use either the E-Verify Program or the Department Program procedures to
               undertake pre-employment screening of job applicants while this public contract for services is being
               performed.


    f.         If Contractor obtains actual knowledge that a subcontractor performing work under this public contract
               for services knowingly employs or contracts with an illegal alien, the Contractor shall: notify the
               subcontractor and the County within three days that the Contractor has actual knowledge that the
               subcontractor is employing or contracting with an illegal alien; and terminate the subcontract with the
               subcontractor if within three days of receiving the notice required pursuant to the previous paragraph,
               the subcontractor does not stop employing or contracting with the illegal alien; except that the
               contractor shall not terminate the contract with the subcontractor if during such three days the
               subcontractor provides information to establish that the subcontractor has not knowingly employed or
               contracted with an illegal alien.


    g.         Contractor shall comply with any reasonable requests by the Department of Labor and Employment
               (the Department) made in the course of an investigation that the Department is undertaking pursuant to
               the authority established in C.R.S. § 8-17.5-102(5).


    h.         If Contractor violates any provisions of this Section of this Agreement, the County may terminate this
               Agreement for breach of contract. If the Agreement is so terminated, the Contractor shall be liable for
               actual and consequential damages to the County.




         IN WITNESS WHEREOF, the parties have signed this Contract.



                                                               BOULDER COUNTY
                                                               STATE OF COLORADO


ATTEST:_________________________                     BY:____________________________________
     Administrative Assistant                              Chair, Board of County Commissioners


CONTRACT                                                                                              005000 - 30
          Clerk to the Board of
          County Commissioners

  Signed this _______day of ________________, 2012 Nunc Pro Tunc

  (SEAL)


                                                      CONTRACTOR




  Attest:_________________________             By:_____________________________________

  Title:__________________________             Title:__________________________________

  (CORPORATE SEAL)                                    Date:_________________________




(If this Agreement is executed on behalf of a corporation, it must be signed by an agent duly authorized
by the corporation to execute such contract, and the corporate seal must be affixed to this Agreement
by the Secretary of the corporation or other authorized keeper of the corporate seal. Authority of the
agent to execute this Agreement must be shown by an accompanying resolution by the Board of
Directors of the corporation, duly certified by the Secretary or other officer of the corporation.)




  CONTRACT                                                                         005000 - 31
       IN WITNESS WHEREOF, the parties have signed this Contract.

                                                    BOULDER COUNTY
                                                    STATE OF COLORADO


ATTEST:__________________________            BY:_____________________________________
                                                   Director, Administrative Services Dept.

Signed this _______day of _________________, 2012 Nunc Pro Tunc

(SEAL)




                                                    CONTRACTOR




Attest:_________________________             By:_____________________________________

Title:__________________________             Title:__________________________________

(CORPORATE SEAL)                             Date:_________________________




(If this Agreement is executed on behalf of a corporation, it must be signed by an agent duly authorized
by the corporation to execute such contract, and the corporate seal must be affixed to this Agreement
by the Secretary of the corporation or other authorized keeper of the corporate seal. Authority of the
agent to execute this Agreement must be shown by an accompanying resolution by the Board of
Directors of the corporation, duly certified by the Secretary or other officer of the corporation.)

(THIS SIGNATURE PAGE IS USED ONLY IF NOT A FORMAL BID.)




GENERAL CONDITIONS                                                                     007200 - 32
                      CONTRACTOR’S CERTIFICATION OF COMPLIANCE

Pursuant to Colorado Revised Statute, § 8-17.5-101, et.seq., as amended 5/13/08, as a prerequisite to
entering into a contract for services with Boulder County, Colorado, the undersigned Contractor hereby
certifies that at the time of this certification, Contractor does not knowingly employ or contract with an
illegal alien who will perform work under the attached contract for services and that the Contractor will
participate in the E-Verify Program or Department program, as those terms are defined in C.R.S. § 8-17.5-
101, et. seq. in order to confirm the employment eligibility of all employees who are newly hired for
employment to perform work under the attached contract for services.

CONTRACTOR:


___________________________                          __________________
Company Name                                               Date


___________________________
Name (Print or Type)


___________________________
Signature


___________________________
Title


Note: Registration for the E-Verify Program can be completed at:
https://www.vis-dhs.com\employerregistration. It is recommended that employers review the sample
“memorandum of understanding” available at the website prior to registering




GENERAL CONDITIONS                                                                      007200 - 33
                                GENERAL CONDITIONS TO
                 BOULDER COUNTY BUILDING CONSTRUCTION CONTRACT
                COURTHOUSE PLAZA FLAGSTONE PAVING REPAIR PROJECT
     ______________________________________________________________________________


A.      COUNTY'S (OWNER'S) RESPONSIBILITIES

        1.    Information on services under the control of the County (hereinafter referred to also as the
              Owner) shall be furnished by the County with reasonable promptness to avoid delay in the
              orderly progress of the Work.

        2.    Based on the observations of the County's Representative and an evaluation of the
              Contractor's Applications for Payment, the County will determine the amounts owing to the
              Contractor and will issue Certificates for Payment in accordance with the General
              Conditions on Progress Payments and Final Payments.

        3.    The Owner's Representative will be the interpreter of the requirements of the Contract
              Documents. He will make decisions on all claims, disputes or other matters in question
              between the Contractor and the Owner but he will not be liable for the results of any
              interpretation or decision rendered in good faith. Decisions of the Architect will be final, if
              consistent with the intent of the Contract Documents.

        4.    The Owner's Representative will have authority to reject Work which does not conform to
              the Contract Documents.

        5.    The Owner's Representative will have the authority to contact any regulatory agency
              concerning any alleged regulatory violation and to secure regulatory ruling or suspend work
              until such ruling is obtained. Such delays if confirmed to be an infraction or variance may
              give rise to charges against the Contractor by the County for delay of timely completion of
              contract work.

        6.    The Owner's Representative will review and approve or take other appropriate action upon
              the Contractor's submittals, such as Shop Drawings, Product Data, and Samples, but only
              for conformance with the design concept of the Work and with the information given in the
              Contract Documents.


B.      CONTRACTOR'S RESPONSIBILITIES

        1.    The Contractor shall supervise and direct the Work, using his best skill and attention and he
              shall be solely responsible for all construction means, methods, techniques, sequences and
              procedures and for coordinating all portions of the Work under the Contract.

        2.    Unless otherwise specifically provided in the Contract Documents, the Contractor shall
              provide and pay for all labor, materials, equipment, tools, construction equipment and
              machinery, transportation, and other facilities and services necessary for the proper

GENERAL CONDITIONS                                                                        007200 - 34
           execution and completion of the Work whether or not incorporated or to be incorporated in
           the Work.

     3.    The Contractor shall at all times enforce strict discipline and good order among his
           employees and shall not employ on the Work any unfit person or anyone not skilled in the
           task assigned to him.

     4.    The Contractor warrants to the County that all materials and equipment incorporated in the
           Work will be new unless otherwise specified, and that all Work will be of good quality, free
           from faults and defects and in conformance with the Contract Documents. All Work not
           conforming to these requirements may be considered defective.

     5.    Unless otherwise provided in the Contract Documents, the Contractor shall pay all sales,
           consumer, use and other similar taxes which are legally enacted at the time bids are
           received and the Contractor will obtain any permits and pay governmental fees, licenses
           and inspections necessary for the proper execution and completion of the Work.

     6.    The Contractor shall give all notices and comply with all laws, ordinances, rules,
           regulations, and lawful orders of any public authority bearing on the performance of the
           Work, and shall promptly notify the County if the Drawings and Specifications are at
           variance therewith. If the Contractor performs any work contrary to such laws, ordinances,
           rules or regulations, he shall bear all costs arising therefore.

     7.    The contractor shall be solely responsible for the acts and omissions of his employees,
           Subcontractors and their agents and employees, and other persons performing any of the
           Work under a contract with the Contractor.

     8.    The Contractor shall review, approve and submit all Product Data and Samples required by
           the Contract Documents. The Work shall be in accordance with approved submittals.

     9.    The Contractor at all times shall keep the premises free from accumulation of waste
           materials or rubbish caused by his operations. At the completion of the Work he shall
           remove all his waste materials or rubbish from and about the Project as well as his tools,
           construction equipment, machinery and surplus materials.

     10.   The Contractor shall pay all royalties and license fees. He shall defend all suits or claims
           for infringement of any patent rights and shall save the County harmless from loss on
           account thereof.

     11.   The Contractor shall confine operations at the site to areas permitted by law, ordinances,
           permits, the Contract documents and the County's representative including storage of any
           materials or equipment.

     12.   The Contractor shall promptly correct any Work rejected by the County as defective or as
           failing to conform to the Contract Documents whether observed before or after Substantial
           Completion and whether or not fabricated, installed or completed, and shall correct any
           Work found to be defective or nonconforming within a period of one year from the Date of

GENERAL CONDITIONS                                                                   007200 - 35
           Substantial Completion of the Contract or within such longer period of time as may be
           prescribed by law or by the terms of any applicable special warranty required by the
           Contract Documents. The provisions of this Article apply to Work done by Subcontractors
           or Support Services as well as to Work done by direct employees of the Contractor.
           Corrections shall be made at no expense to the County.


     13.   Safety:

           a.        The Contractor shall be responsible for initiating, maintaining and supervising all
                     safety precautions and programs in connection with the work. The Contractor shall
                     give all notices and comply with the applicable laws, ordinances, rules, regulations,
                     and orders of any public authority bearing on the safety of persons and property and
                     on their protection from damage, injury or loss. The Contractor shall take all
                     reasonable steps to minimize inconvenience to users of the site and shall take all
                     reasonable precautions for the safety to, and shall provide all reasonable protection
                     to prevent damage, injury, or loss to:

                     1.     All employees on the work site and all other persons, including visitors and
                            passersby who may be affected by the work;

                     2.     All the work and all materials and equipment to be incorporated therein;
                            and

                     3.     All property at the site or adjacent thereto.

           b. The Contractor shall designate a responsible member of the Contractor's organization at
              the site who shall be assigned the duty of the prevention of accidents. This person shall
              be the Contractor's superintendent unless otherwise designated by the Contractor in
              writing to the County. This person will also work closely with the County's work
              superintendent on safety issues and attend regular safety discussions as set by the
              County's work superintendent.

           c. In the event the County's superintendent or his designee notifies the Contractor's
              superintendent of any unsafe conditions or practices, the Contractor shall immediately
              take all actions required under paragraph 13a to ensure the safety of the work. If the
              condition or practice continues to present an imminent hazard, the County shall have
              the authority to stop the work until the condition has been remedied at no expense to the
              County. In no event shall the County be responsible for ensuring the safety of the work
              or for remedying the unsafe condition.

     14.   Liabilities: The Contractor shall promptly remedy all loss or damage to any property or
           persons caused in whole or in part by the Contractor, any Subcontractor, or anyone directly
           or indirectly employed by any of them or by any one for whose acts or omissions any of
           them may be liable. These obligations are in addition to any other obligations under this
           contract.


GENERAL CONDITIONS                                                                      007200 - 36
     15.   Performance Bond and Labor and Materials Bond:

           a.      Prior to the execution of the Contract by the County, the Contractor shall furnish
                   and deliver to the County a Performance Bond and a Labor and Materials Payment
                   Bond acceptable to the County, in a sum equal to the nearest integral of One
                   Hundred Dollars ($100) in excess of the Contract price, duly executed by a
                   Corporate Surety qualified and licensed to do business in Colorado and maintaining
                   a general agent therein. Such bond shall comply with the provisions of Section 38-
                   26-106, CRS. Such bonds are only required if the amount of the contract price
                   is in excess of Fifty Thousand Dollars ($50,000).

           b.      Unless otherwise specified in the Bidding Documents, the bonds shall be written in
                   the form AIA Documents A312, Performance Bond and Labor and Material
                   Payment Bond.

           c.      The Bidder shall require the Attorney-in-Fact who executes the required bonds on
                   behalf of the surety to affix thereto a certified and current copy of his Power of
                   Attorney.


C.   WORK BY OWNER OR BY SEPARATE CONTRACTORS

     1.    The Owner reserves the right to perform work related to the Project with his own forces,
           and to award separate contracts in connection with other portions of the Project or other
           work on the site under these or similar conditions of the Contract. If the Contractor claims
           that delay or additional cost is involved because of such action by the Owner, he shall make
           such claims as provided below.

     2.    Any claim for an increase or decrease in the Contract Price shall be based on written notice
           delivered by the party making the claim to the other party promptly (but in no event later
           than thirty days) after the occurrence of the event giving rise to the claim and stating the
           general nature of the claim. Notice of the amount of the claim with supporting data shall be
           delivered within sixty days after such occurrence and shall be accompanied by claimant's
           written statement that the amount claimed covers all known amounts (direct, indirect and
           consequential) to which the claimant is entitled as a result of the occurrence of said event.
           All claims for adjustment in the Contract Price shall be determined by OWNER if OWNER
           and CONTRACTOR cannot otherwise agree on the amount involved. No claim for an
           adjustment in the Contract Price will be valid if not submitted in accordance with this
           paragraph .

     3.    Any claim for an extension in the Contract Time shall be based on written notice delivered
           by the party making the claim to the other party promptly (but in no event later than thirty
           days) after the occurrence of the event giving rise to the claim. Notice of the extent of the
           claim with supporting data shall be delivered within sixty days after such occurrence and
           shall be accompanied by the claimant's written statement that the adjustment claimed is the
           entire adjustment to which the claimant has reason to believe it is entitled as a result of the
           occurrence of said event. All claims for adjustment in the Contract Time shall be deter-

GENERAL CONDITIONS                                                                     007200 - 37
          mined by OWNER if OWNER and CONTRACTOR cannot otherwise agree. No claim for
          an adjustment in the Contract Time will be valid if not submitted in accordance with the
          requirements of this paragraph.

     4.   The Contractor shall afford the Owner and separate contractors reasonable opportunity for
          the introduction and storage of their materials and equipment and the execution of their
          work, and shall connect and coordinate his Work with theirs as required by the Contract
          Documents.

     5.   Any costs caused by defective or ill-timed work shall be borne by the party responsible
          therefore.


D.   CHANGES IN THE WORK

     1.   The County may order additions, deletions, or modifications in the Work by issuing a
          change order signed by its authorized representatives. These changes will not invalidate the
          Contract; however, the Contract sum and Contract time will be adjusted accordingly by unit
          prices or by negotiated amount where unit prices are not provided.

     2.   The Contract sum and the Contract time may be changed only by Change Order.

     3.   The cost or credit to the County from a change in the Work shall be determined by mutual
          agreement.

     4.   Questions concerning changes, modifications and other construction problems are to be
          submitted to the County for interpretations.


E.   SCHEDULING

     1.   Work is to begin after the County has notified the Contractor to proceed, and a work
          schedule has been agreed to by the County and Contractor. The County and Contractor
          shall each have copies of this schedule.

     2.   The Contractor shall promptly inform the County of items which will not be delivered or
          accomplished according to the initial schedule.

     3.   If the Contractor is delayed at any time in the progress of the Work by changes ordered in
          the Work, by labor disputes, fire, unusual delay in transportation, adverse weather
          conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the
          Contractor's control, or by any other cause which the County determines may justify the
          delay, then the Contract Time shall be extended by Change Order for such reasonable times
          as the County may determine.




GENERAL CONDITIONS                                                                  007200 - 38
F.   PROGRESS PAYMENTS

     1.   If this contract is for eighty thousand dollars ($80,000) or less, partial payments shall be
          authorized by the County for work completed, if the Contractor is performing satisfactorily.
          Partial payments will be made based upon invoices submitted by the Contractor and
          certified by the County. Ten percent (10%) of each amount certified by the County shall be
          retained by the County until final payment is made. The Contractor shall make partial
          payments to his Subcontractors in the same manner as the County pays him, provided the
          Subcontractor is performing satisfactorily.

     2.   If this contract is for more than eighty thousand dollars ($80,000), partial payments of
          compensation due under this contract are subject to the provisions of Section 24-91-101, et.
          seq. CRS. If this contract exceeds Eighty Thousand Dollars ($80,000), partial payments
          shall be authorized by the County for work completed, based upon invoices submitted by
          the Contractor, if the Contractor is performing satisfactorily. Ten percent (10%) of the
          calculated value of any work completed shall be retained until fifty percent (50%) of the
          work required by the contract has been performed. After fifty percent (50%) of the work
          has been performed, the County shall pay amounts which becomes due as work is
          completed, while continuing to hold amounts already retained, if, in the opinion of the
          County, satisfactory progress is being made. The withheld percentage of the contract price
          of any such work, improvement, or construction shall be retained until the contract is
          completed satisfactorily and finally accepted by the public entity. If the public entity finds
          that satisfactory progress is being made in all phases of the contract, it may, upon written
          request by the Contractor, authorize payment from the withheld percentage. Before such
          payment is made, the public entity shall determine that satisfactory and substantial reasons
          exist for the payment and shall require written approval from any surety furnishing bonds
          for the contract work. The Contractor shall make partial payments of the amount due to
          each his subcontractors in the same manner as the public entity is required to pay the
          Contractor under this statue, provided that the subcontractor is satisfactorily performing
          under his contract with the Contractor.

     3.   If it becomes necessary for the County to take over the completion of any contract, all of the
          amounts owing the contractor, including the withheld percentage, shall be applied: First,
          toward the cost of completion of the contract; second, toward performance of the public
          entity's withholding requirement set forth in section 38-26-107, C.R.S.; third, to the surety
          furnishing bonds for the contract work, to the extent such surety has incurred liability or
          expense in completing the contract work or made payments pursuant to section 38-26-106,
          C.R.S.; then, to the contractor. Such retained percentage as may be due any contractor shall
          be due and payable as provided by section 38-26-107,C.R.S.

     4.   Payments may be withheld on account of:

          a.     defective work not remedied;
          b.     claims filed;
          c.     failure of the Contractor to make payments properly to Subcontractors or for labor,
                 materials, or equipment;
          d.     failure to carry out the Work in accordance with the Contract Documents; or

GENERAL CONDITIONS                                                                   007200 - 39
            e.      failure to keep the designated superintendent on the site.
            f.      failure to obtain any necessary permits or licenses necessary to carry out the Work
                    under this Contract.


G.   PREREQUISITES TO SUBSTANTIAL COMPLETION

     1.     Submit specific warranties, workmanship/maintenance bonds, maintenance agreements,
            final certificates and similar documents.

     2.     Furnish a list giving the names, addresses and phone numbers of all subcontractors and
            materials suppliers who provided labor and/or materials for the work, with identification of
            the labor and/or materials provided.

     3.     Obtain and submit releases enabling Owner's full use of the work and access to services and
            utilities, including occupancy permits, and similar releases.

     4.     Submit Record Drawings, maintenance manuals, operating instructions, and similar final
            records information.

     5.     Deliver tools, spare parts, extra stocks of materials, and similar physical items to Owner.

     6.     Make final change-over of locks and transmit keys to Owner.

     7.     Complete startup testing of systems, and instructions of Owner's operating/maintenance
            personnel. Discontinue (or change over) and remove from project site temporary facilities
            and services, along with construction tools and facilities, mock-up, and similar elements.

     8.     Complete final cleanup requirements.



H.   SUBSTANTIAL COMPLETION

     The Work (or a specified part thereof) has progressed to the point where, in the opinion of
     OWNER as evidenced by OWNER'S definitive certificate of Substantial Completion, it is
     sufficiently complete, in accordance with the Contract Documents, so that the Work (or specified
     part) can be utilized for the purposes for which it was intended; or if there be no such certificate
     issued, when final payment is due in accordance with paragraph N of these GENERAL
     CONDITIONS TO BOULDER COUNTY BUILDING CONSTRUCTION CONTRACT. The
     terms "substantially complete" and "substantially completed" as applied to any Work refer to
     Substantial Completion thereof.




GENERAL CONDITIONS                                                                     007200 - 40
I.   SUBSTANTIAL COMPLETION PROCEDURES

     1.      When CONTRACTOR considers the entire Work ready for its intended use
             CONTRACTOR shall notify OWNER in writing that the entire Work is substantially
             complete (except for items specifically listed by CONTRACTOR as incomplete) and
             request that OWNER issue a certificate of Substantial Completion.

     2.      Within a reasonable time thereafter, OWNER and CONTRACTOR shall make an
             inspection of the Work to determine the status of completion.

     3.      If OWNER does not consider the Work substantially complete, OWNER will notify
             CONTRACTOR in writing giving the reasons therefore.
     4.      If OWNER considers the Work substantially complete, OWNER will prepare and deliver to
             CONTRACTOR a tentative certificate of Substantial Completion which shall fix the date
             of Substantial Completion. There shall be attached to the certificate a tentative list of items
             to be completed or corrected before final payment.

             a.      OWNER will within fourteen days execute and deliver to CONTRACTOR a
                     definitive certificate of Substantial Completion with a list of items to be completed
                     or corrected reflecting any changes from the tentative certificate.

             b.      At the time of delivery of the tentative certificate of Substantial Completion
                     OWNER will deliver to CONTRACTOR a written recommendation as to division
                     of responsibilities pending final payment between OWNER and CONTRACTOR
                     with respect to security, operation, safety, maintenance, heat, utilities, insurance and
                     warranties. Unless CONTRACTOR objects in writing and so informs OWNER
                     prior to OWNER'S issuing the definitive certificate of Substantial Completion,
                     OWNER'S aforesaid recommendation will be binding on OWNER and
                     CONTRACTOR until final payment.

     5.      OWNER shall have the right to exclude CONTRACTOR from the Work after the date of
             Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to
             complete or correct items on the tentative list.


J.   LIENS

     No Mechanics lien may be held against a publicly owned building in the State of Colorado.
     Protections are limited to those set out below.


K.   DEDUCTIONS FOR UNCORRECTED WORK

     If the County determines that there is a need to correct work which has not been performed in
     accordance with the Contract, an equitable deduction from the Contract price may be authorized by
     change order.


GENERAL CONDITIONS                                                                        007200 - 41
L.   ACCESS TO WORK

     The County and any architect/engineer retained by the County shall at all times have access to the
     work.


M.   FINAL PAYMENT

     1.        Within ten (10) days after the Contractor's written declaration of completion of the Work,
               the County will make a final inspection thereof to determine whether the Work has been
               completed in accordance with the Contract Documents. If a list of deficiencies results from
               such final inspection, the Contractor shall promptly rectify all items appearing thereon,
               before final payment will be made. When the County indicates acceptance of the Work, the
               Contractor may requisition final payment, including retainage on account of the Contract
               price.

     2.        Final payment is subject to the provisions of Section 38-26-107, CRS. Any proposed final
               settlement for this work shall be duly advertised at least ten (10) days prior thereto by
               publication at least twice in a public newspaper of general circulation. Any creditor that
               has furnished labor, materials, team hire, sustenance, provisions, provender, or other
               supplies used or consumed on this project by the Contractor or its Subcontractors, or that
               supplies rental machinery, tools, or equipment to the extent used in the prosecution of the
               work, whose claim therefore has not been paid by the Contractor or the Subcontractor at
               any time up to and including the time of final settlement, may file with the County a
               verified statement of the amount due and unpaid. Such amounts claimed shall thereafter be
               retained by the County from final settlement pursuant to the provisions of the statute.

     3.        In any event, final payment shall not be authorized until all inspections have been
               completed, and all work has been completed.

          4.      The making of final payments shall constitute a waiver of all claims by the County
                  except those arising from:

                  a.     unsettled claims
                  b.     faulty or defective Work appearing after Substantial Completion
                  c.     failure of the Work to comply with the requirements of the Contract
                         Documents
                  d.     terms of any special warranties required by the Contract Documents.

          5.      The acceptance of final payment shall constitute a waiver of all claims by the
                  Contractor except those previously made in writing and identified by the Contractor
                  as unsettled at the time of the final Application for Payment.




GENERAL CONDITIONS                                                                      007200 - 42
N.   TESTS

     The Contractor shall provide such equipment and facilities as the Architect may require for
     conducting field tests and for collecting and forwarding samples. The Contractor shall not
     use any material or equipment represented by samples found to be unacceptable. The Owner
     shall pay testing laboratory costs for materials testing. The Contractor shall give the
     Architect and testing laboratory timely notice for required tests.


O.   MEASUREMENTS

     Before ordering any materials or doing any work, the Contractor shall verify all
     measurements at the project and shall be responsible for the correctness of same. No extra
     charge or compensation shall be allowed on account of difference between actual dimensions
     and the measurements indicated on the Drawings. Any difference that may be found shall be
     submitted to the Owner for consideration before proceeding with the work. The Architect
     and Owner shall not be responsible for the scaling of Drawings.



     END OF GENERAL CONDITIONS




                                            A43
                           SECTION 011000 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY OF WORK (Bid #5810-13):

  A.   Project Identification: As follows:
       1.    Location: BOULDER COUNTY COURTHOUSE PLAZA
                            1325 Pearl St.
                            Boulder, CO 80302
       2.    Owner: Boulder County
       3.    Description:


  B.   Contract Documents, dated February 26, 2013 (and subsequent dates), were prepared by the
       Boulder County Building Services Division.

  C.   The Work consists of all labor and materials required for the following items, as described in the
       Contract Documents. See specifications and drawings for base bid scope of work.

       Item #1 –FLAGSTONE PAVING

       The water main for Courthouse was repaired recently, which required a portion of the Flagstone Plaza
       to be removed to expose the pipe work. The area that was deconstructed during this repair has been
       backfilled and a new 5” concrete bed poured and is now ready for Flagstone Paving.

       The Masonry Work consists of all labor and materials required for the installation of new Flagstone
       Paving to patch the area that was removed or damaged during the pipe repair.
       For Bidding purposes include a 6’ area outside of the Patch area to cover any damaged pavers from
       heavy equipment. Flagstone must be toothed into existing layout. Special care must be taken with
       expansion joints at various locations.
       After the Flagstone installation a Muriatic acid cleanup is required.
       Water wastes of any kind must be captured so that it does not drain out to the pedestrian Pearl Street
       Mall or get into surrounding storm sewers.

       Item #2 –REPOINTING OF EXISTING FLAGSTONE PAVING

       Over time the mortar joints in the existing flagstone plaza paving have deteriorated and are in
       various stages of disrepair.
       The existing mortar joints which are failing must be removed down to the bedding material
       cleaned completely and replaced with a modified polymer mortar compound.
       After the Flagstone installation a Muriatic acid cleanup is required.
       Water wastes of any kind must be captured so that it does not drain out to the pedestrian Pearl Street
       Mall or get into surrounding storm sewers. This portion of the project will be executed on a
       time and material basis which will be done at a later date; however, a lump sum total
       cost is required for this Bid.

                                                 A44
D.   Particular Project requirements:
     1.     Existing Site Conditions and restrictions.

          The site will be fenced on all sides during construction. Particular attention should be paid to
          public safety as all sides of site will be surrounded by pedestrian and vehicular traffic. Contractor
          vehicle access is allowed on Pearl Street Mall only until 10:00 am each day. Vehicle access points
          to the work site are at 13th and 14th street. Most of the Plaza has a concrete slab under the existing
          Flagstone paving which will allow vehicle traffic; However, the region of the Plaza on the
          Southwest Cannot be driven on with a vehicle due to the Flagstone bedding being sand and not
          concrete. (see Site plan for location)


     2.     Scheduling or Sequencing of Work:

          Boulder County will be acting as general contractor. Items to be Subcontracted include: Flagstone
          Paving.
          Time is of the essence as this is a major Public Space on the downtown pedestrian mall with
          intense use.

          The Install is tentatively scheduled to begin March 18, 2013. The work Must be completed by
          April 2nd 2013 weather depending.
          The Contractor needs to cooperate with the General Contractor (the County) to schedule the work
          to:

            a. Work around the public as may be required. Maintain the ADA access to the south entrance
               of the courthouse.

            b. Minimize noise, dust, smell and traffic and other problems for the public.

     3.     Contractor’s Use of New and Existing Facilities:

          Boulder County will assign space on the work site as needed for the Subcontractor’s use.
          Boulder County will provide water and power. Boulder County will accommodate parking for
          one (1) Subcontractors vehicle.




                                                 A45
1.2         WORK RESTRICTIONS

      A.   Contractor's Use of Premises: During construction, Contractor shall have limited use of site and
           building indicated. Contractor's use of premises is limited only by Owner's right to perform work or
           employ other contractors on portions of Project and as follows:

           1. Boulder County (owner) will be acting as the General Contractor. The work to be done by
              Boulder County crews includes: interior wall framing & sheathing, interior door and window
              installation, millwork, finish work, and electrical. All work is to be coordinated with Boulder
              County crews. Work to be done by other subcontractors includes the building concrete footings,
              foundations and slab, the pre-engineered metal building, and the below-slab plumbing and
              waterproofing.

           2. Boulder County will be the Building Permit holder. Contractors will not be responsible for
              permit fees, but may be responsible for other fees. Contact the City of Boulder for information
              on any such fees.


      B.   Contractor’s work must allow County crews and subcontractors access to building at all times.

      C.   Contractor shall coordinate with owner for parking for its vehicles.

      D.   Contractor shall consult with County crew supervisor to determine locations for staging, if necessary.

      E.   Boulder County is strongly committed to the recycling of construction and waste materials. The
           County will provide recycling areas or containers as required.



      END OF SECTION 011000




                                                      A46
                                           SECTION 32 1440

                                            STONE PAVING

PART 1     GENERAL

1.1   SUMMARY

      A.   Section Includes:
           1.    Installation and supply of Flagstone in a mortar bed with mortar joints in an area that is
                 approximately 630 sqft. with potentially 400 additional sqft for areas damaged by heavy
                 equipment from water main repair project.
                 Pattern and coursing will be based off existing surrounding Flagstone pavers.
                 New Flagstone may vary from 2” to 3 1/2” thick.

      B.   Related Sections:
           1.    Division 01: Administrative, procedural, and temporary work requirements.
           2.    Section 04 0513 - Masonry Mortaring.
           3.    Section 07 9200 - Joint Sealers.

1.2   REFERENCES

      A.   ASTM International (ASTM):
           1.  A185/A185M - Standard Specification for Welded Steel Wire Reinforcement, Plain, for
               Concrete.
           2.  C33 - Standard Specification for Concrete Aggregates.

1.3   SUBMITTALS

      A.   Submittals for Review:
           1.  Product Data: Descriptive data for pavers.
           2.  Samples: [12 x 12 x 2] inch stone samples showing color and surface texture.

1.4   QUALITY ASSURANCE

      A.   Installer Qualifications: Minimum [10] years [documented] experience in work of this Section.

      B.   Obtain stone from a single quarry and from the same area within the quarry.

1.5   DELIVERY, STORAGE AND HANDLING

      A.   Store stone off ground; prevent contact with materials that could cause staining or damage.

1.6   PROJECT CONDITIONS

      A.   Environmental Requirements:
           1.    Do not install mortar when surrounding air or substrate surface temperature is below 40
                 degrees F or above 90 degrees F during or 48 hours after completion of the work.
           2.    At end of working day and during rainy weather, cover work exposed to weather with
                 waterproof coverings, securely anchored.




                                                  A47
PART 2 PRODUCTS

2.1        MATERIALS

           A.      Flagstone:
                   1.    New:
                         a)   Machine cut red sandstone 2” to 3 ½” thick
                         b)   Border Stone: 12” wide coping, random lengths, no shorter than 20”
                         c)   Field stone: random squares and rectangles to achieve ashlar pattern shown on
                            plans.
                              Width 6” minimum, 24” maximum. Length 16” minimum

      B.        Setting bed:
                    1. Type “M” mortar

      C. Joints:
               1.        3/4” to 1” “U-POINT” brand single component, Polymer-Modified, cement based grey
                         mortar compound

      D.        Expansion Joints:
                   1.   1/2” to 3/4” celotex expansion joint material with caulk (Sonneborn “NP 1” color: Stone)

2.2        ACCESSORIES

           A.      Cleaner: [Type recommended by stone supplier.]


PART 3             EXECUTION

3.1        PAVER INSTALLATION

           A.      Clean existing concrete paving bed, removing any loose debris and level surface as required.

           B.      Brush approved bonding agent on concrete paving bed before paving mortar bed is applied.

           C.      Set paver units in full mortar bed minimum [1-1/2] inches thick, to support pavers over full
                   bearing surface.

           D.      Place pavers in Random Ashlar pattern [indicated] from straight reference line. Maintain ¾
                   inch minimum to maximum 1 inch joints between pavers and at abutting vertical surfaces and
                   protrusions.

           E.      Fill joints with pointing mortar. Pack and work into voids. Tool joints to [flush] profile.

           F.      Place control joints over joints in substrate, where pavers abut dissimilar materials,

           G.      Allowable Tolerances: Surfaces true to level or indicated slopes with plus or minus 1/4 inch in
                   10 feet tolerance.

3.2        CLEANING

           A.      Protect adjacent and underlying surfaces.


                                                            A48
B.   Apply cleaner in accordance with manufacturer's instructions.

C.   Thoroughly rinse surfaces with clean water and approved cleaning solution. After completion
     of cleaning; remove all traces of cleaning solution, capture any water and or cleaning liquids
     to keep it from reaching the Pearl street pedestrian mall or adjacent storm drains.




                                    END OF SECTION