									W4 REGENT STREET NEWSLETTER: April 2013

Dear neighbour,

W4 Regent Street – a development by The Crown Estate, managed by Exemplar

The W4 development has continued to fly up throughout spring, with steelwork up to the sixth floor and
roof levels and metal decking completed to the fifth floor. This has allowed the floor slabs to be concreted,
and the ground to fourth floor slabs are substantially complete, allowing for the next stage of works to
commence on the lower floors.

Mechanical and Electrical installations in the sub-basement and basement areas have now progressed to
the floor plates with the first fixings now installed on the first floor office areas. Cleaning of the retained
facades commenced this month to clean the existing stone.

Blockwork has also now commenced on the ground floor to create the division between the retail units
along Regent Street, and to divide the boundary between these units and the reception area for the offices.




 Images: Sixth floor steelwork adjacent to Heddon Street up to sixth floor (top left). Steelwork on New
 Burlington Street up to fifth floor (top right). Pouring of the basement slab in the South West corner
 (bottom left). A view of the steelwork up to fourth floor at 15/16 New Burlington Street (bottom right)
W4 REGENT STREET NEWSLETTER: April 2013

Progress on site during spring 2013:

• Commencement of façade restoration works

• Continuation of steelwork and decking up to sixth floor

• Construction of new slab to the top of the listed vaults

• Blockwork to the basement and ground floor areas

• Installation of plant and pipework in the basement areas

• Construction of new ground floor slab in the South West Corner

Over the coming month, our works will include:

• Continuation of blockwork to the ground floor areas and commencement of first floor.

• Completion of steel work up to roof level

• Instillation of plant and pipework to the basement and first floors

• Removal of the two tower cranes and re-positioning one crane to the core

• Concreting of floor plates up to Level 6

If you have any queries related to the works please contact either Jon Mingard (Community Liaison and
Project Manager) on 07789 956541 or email jon.mingard@macegroup.com, alternatively Laurie Furst on
07717 717154 or laurie.furst@macegroup.com.

We will be in touch shortly to confirm the date of the next site visit and community liaison meeting.
Kind Regards




Chris Merrin
Senior Project Manager, Mace

								