					2004 Shutdown Schedule Updated 23-Feb-06 We ek #

[Date]

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday Rad Survey Open muon shields and EFs Retract Be beampipe into ECN Remove N gap hardware Close ECN, EFN Install EFN platform

Saturday

21-Feb Remove SNEGs Inspect interior of EC beampipes Install collapsible beampipe sections Open EF's, CF's, EC's Warm Silicon TFW down Begin retirement of Run I L1Cal Uncable N outer H disk

Stickmic survey

1

26-Feb

Install gap hardware Rad survey

Remove Tedlar membranes Rad survey Wipe Be beampipe Drain Coolant Lines Uncable S outer H disk

Disconnect Be beampipe Cut EC beampipe ends

Drain and purge coolant lines Uncable S inner H disk Install Adapter Cards in N gap Retract Be beampipe into ECN Remove N gap hardware Close ECN, EFN Install EFN platform L1Cal sidewalk operations complete

2

5-Mar

Remove N outer H disk

Remove S outer H disk Install Adapter Cards in N gap

3

12-Mar

Remove S inner H disk Install Adapter Cards in N gap

Uncable N inner H disk

4

19-Mar

Remove Be pipe from Collision Hall Install S gap scaffold Install tables, levels, and north rails 0700-0730 Power Outage Prepare rails in south gap

5

26-Mar

6

2-Apr

Install adapter cards in S gap Install LV cables in S gap Mount stages and align north rails Install south rails Install Long Tool in South Gap Check deflections Install Be beampipe Begin installing L1Cal Upgrade crates

Setup for Run IIa beampipe extraction Complete Dry Run with Dummy Layer 0 Dry run with dummy Layer 0 Transport Layer 0 to DAB Install adapter cards in S Install adapter cards in S gap gap Install LV cables in S gap Install LV cables in S gap Remove N inner H disk Mount stages and align south rails Remove Brunson from N gap Prep stages in N gap Measure capacitance to beampipe Connect Layer 0 cooling manifold Install Layer 0 mounts L1CTT installation complete

Load Layer 0 and Run IIb beampipe into ECN Open EFN and ECN Install gap hardware

Install Layer 0 mounts

Layer 0 Installation Prep

Insert Layer 0 into SMT

7

9-Apr

Install Junction card mounts

Leak test Layer 0 cooling Weld EC beampipes

Install junction cards Connect spool pieces and leak check Verify H disk connections system checkout L1Cal Upggrade Ready for Technical Commissioning Activate SNEGs Open EFs Install BLMs L1CTT Ready for Technical Commissioning system checkout Close CF and EF Likely power outage

8 9

16-Apr 23-Apr

Install junction cards 0700-0730 Power Outage leak check Install beampipe supports make EC Be beampipe joints

Install junction cards Install inner H disks Install rad monitors Install Tedlar membrane

Verfiy Layer 0 connections Cable inner H disks Cable inner H disks Install cooling lines

10

30-Apr

Cool silicon

system checkout

11 12 13

7-May 14-May 21-May

14 15 16 17 18 19 20 21 22 23

28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul first store

system checkout Activate SNEGs Survey EC system checkout Remove SNEG heaters Close clamshells Survey Detector Centerbeam

System checkout Remove gap hardware Close ECs, Efs Survey EC system checkout Survey Detector CenterBeam Test Magnet Power Supplies

Install SNEGs system checkout system checkout

Leakcheck system checkout system checkout

StickMic Survey

Trigger Latency Change

Routine Operation of Upgrade Systems


				