Cost Estimates by jianghongl

VIEWS: 1 PAGES: 6

									Cost Estimates 

   Type       ID #                Deficiency Title                    Remedy Work               Cost 
    RR       0131­1      Pavement Cracking                    Seal Pavement                    $59,000 
    RR       0131­2      Pavement Break at Entry              Repair                            $3,600 
    RR       0132­1      Poor Concrete West side              Replace                           $6,500 
    RR       0132­2      Poor Concrete West side stair        Replace                           $6,700 
    RR       0132­3      Uneven Pavement @ courts             Repair                            $6,100 
    RR       0132­4      Aging Pavement                       Seal Pavement                    $14,000 
    RR       0132­5      Exposed Rebar in sidewalk            Repair surface                    $3,300 
    RR       0132­6      Cracked Concrete                     Repair                            $2,800 
    RR       0132­7      No Bollards                          Install bollards                  $5,800 
    RR       0134­1      Rotten Deck                          Replace                         $101,000 
    RR       0134­2      Missing Joists                       Replace                           $3,300 
    RR       0134­3      Joist Checking                       Replace                           $1,400 
    RR       0134­4      Cracked Beraing Blocks @ stairs      Replace                          $14,000 
    RR       0134­5      Corroded Connector                   Repair                            $1,400 
    RR       0134­6      Corroded Rail posts                  Replace                          $19,000 
    RR       0134­7      Split Checked posts                  Replace                          $70,000 
    RR       0135­1      Poor Condition Concrete              Replace                           $5,200 
    RR       0137­1      Damaged Stretcher Bar and            Replace                           $6,100 
                         Leaning Fence 
   RR        0137­2      Gaps under Fence                     Repair                             $700 
   RR        0137­3      Bent Post                            Leave as is                          $0 
   RR        0141­1      covered play area                    replace damaged siding           $4,600 
   RR        0141­1      covered play area                    repaint                         $17,000 
   RR        0143­1      Shed siding                          paint shed siding                  $200 
    F        0143­2      Shed roof                            replace roof                       $400 
   RR        0153­1      Overgrown drainage ditch             Clear & Excavate                $16,000 
   RR        0153­2      Standing Water                       Install catch basins & trench   $27,000 
   RR        0153­3      Ball field surface does not drain    Regrade Ball field               $1,400 
  RR, F      0161­1      Replace utility service              Utility transformer, meters &  $105,000 
                                                              disconnects 
    F        0162­1      Upgrade Parking Area Lighting        Replace existing lighting       $39,000 
  RR,E,F     0162­2      Llighting at Upper Level &           Replace building mounted        $51,000 
                         Stairwells                           lighting.  New conduit and 
                                                              wiring. 
   RR,F      0162­3      Covered play area high bay           Replace High bay fixtures.      $19,000 
                         fixtures                             New conduit and wiring. 
     F       0162­4      Main Entrance Lighting               Add lighting at main entrance    $6,300 
                                                              for artwork. New conduit & 
                                                              wiring. 
    RR       0220­1      Uneven Slab                          Repair                           $2,800 
    RR       0312­1      Fan room floor depression            Repair                           $2,600 
    RR       0312­2      Classroom Floor                      Stiffen Floors                 $187,000 
                         Flexibility/Deflection 
    RR       0313­1      Holes in glue Lams                   Repair                                $0 
    RR       0321­1      Split Column                         Inject epoxy                      $2,000 
    RR       0322­1      Rotten Deck Members                  Temporary repair                 $15,000 
    RR       0322­1      Rotten Deck Members                  Permanent repair                $129,000 
    RR       0322­2      Rotten Roof Beams                    Temporary repair                 $20,000


June 2005              Auke Bay Elementary School Condition Survey Report         Page 223 of 228 
Cost Estimates 
   Type       ID #                Deficiency Title                     Remedy Work                  Cost 
    RR       0322­2      Rotten Roof Beams                     Permanent repair                     $38,000 
    RR       0331­1      Split Bearing Blocks                  Replace                               $5,100 
    C        0332­1      exterior stair between floors         replace railings/ install risers     $20,000 
    C        0332­1      exterior stair between playgrounds    replace railings/ install risers     $10,000 
    RR       0411­1      Split Columns                         Replace                               $2,000 
    RR       0411­1      Asbestos siding                       replace asbestos siding with         $43,000 
                                                               metal siding 
    RR       0411­2      Siding at grade                       replace siding with                  $90,000 
                                                               brick/block wainscot 
    RR       0411­3      Siding condition & finish             replace damaged & repaint            $26,000 
    RR       0411­3      Siding condition & finish             paint remaining siding               $16,000 
    RR       0412­1      Fascia finish                         gutter & downspout                      $900 
    RR       0412­2      Fascia finish                         nail & paint                          $2,800 
    RR       0412­3      Soffit finish                         paint                                $12,000 
    RR       0421­1      Wood Windows                          Replace windows                     $326,000 
     E       0421­2      Wood Windows                          Replace windows                           $0 
     E       0421­3      Vinyl Windows                         Replace windows                      $13,000 
    RR       0422­1      Storefront                            Flashing                                $100 
    RR       0431­1      Exterior wood doors                   Replace wood doors/frames            $54,000 
     E       0431­2      Exterior wood doors                   Replace wood doors/frames                 $0 
    C        0431­3      Exterior wood doors                   Doors do not meet                    $16,000 
                                                               ADA/ANSI­threshold 
    RR       0431­4      Aluminum doors                        Replace                              $26,000 
    C        0431­5      Aluminum doors                        Doors do not meet                     $3,000 
                                                               ADA/ANSI­threshold 
    RR       0431­6      Aluminum doors                        Weatherstripping                      $1,300 
    RR       0431­7      Aluminum doors                        Replace plexi                         $3,000 
    RR       0441­1      Louvers                               Replace                                 $600 
    RR       0443­1      Balcony/railings                      Add horizontal rails                  $6,800 
    RR       0443­2      Deck surface                          Replace                              $17,000 
    RR       0443­3      Balcony/railings                      Repair                                $6,300 
    RR       0443­3      Balcony/railings                      Paint                                 $3,500 
     F       0445­1      Sign                                  School sign                           $4,600 
    RR       0521­1      Slope to Drain                        Add tapered insulation to             $9,200 
                                                               direct water to drain 
    RR       0521­2      Metal Flashing                        Replace                               $3,200 
    RR       0521­2      Metal Flashing                        Paint                                   $700 
    RR       0521­3      Metal Flashing Joints                 Repair & Caulk                        $1,000 
    RR       0521­3      Metal Flashing Joints                 Replace                               $4,000 
    RR       0535­1      Boiler Flue                           Sealant                                 $100 
    RR       0611­1      Damaged gypsum                        Patch                                $11,000 
    RR       0623­1      Relite Wood                           Repair & add base                     $1,100 
    C        0631­1      Wood doors                            Fire rating                           $9,100 
    RR       0631­2      Wood doors sag                        Adjust doors                          $3,000 
    RR       0631­2      Wood doors sag                        Replace door & frame                 $21,000 
    RR       0631­3      Aluminum door sag                     Adjust doors                            $900 
    RR       0631­3      Aluminum door sag                     Replace door & frame                 $13,000 
    RR       0631­4      Aluminum door hardware                Replace hardware                        $600 
    RR       0631­5      Rusted door frame                     Replace frame                         $1,500


June 2005              Auke Bay Elementary School Condition Survey Report            Page 224 of 228 
Cost Estimates 
   Type       ID #                Deficiency Title                    Remedy Work                 Cost 
     F       0632­1      Fire RatedCoiling door                Replace                             $3,600 
     F       0632­2      Abandoned Coiling door                Remove & construct wall             $1,800 
    RR       0641­1      Enameled Hard Board Wainscot          Replace wainscot                  $152,000 
    RR       0641­2      Wall carpet                           Replace wall carpet                $61,000 
    RR       0641­3      Acrylic Wall cover                    Replace Acrylic Wall cover          $2,800 
                                                               (SS) 
    RR       0641­3      Acrylic Wall cover                    Replace Acrylic Wall with           $7,500 
                                                               ceramic tile 
    RR       0641­4      Stainless Steel                       Replace Stainless                  $19,000 
    RR       0641­5      Wall finish                           Paint                             $172,000 
    RR       0642­1      Carpet                                Replace carpet                    $282,000 
    RR       0642­2      12x12 tile at gym                     Repair                              $1,500 
    RR       0642­2      12x12 tile at gym                     Replace with poured urethane      $114,000 
    C        0642­3      Asbestos tile                         Remove                             $44,000 
    RR       0642­4      Sheet Vinyl                           Replace with Sheet Vinyl           $17,000 
    RR       0642­4      Sheet Vinyl                           Replace with Ceramic Tile          $48,000 
    RR       0643­1      12x12 tile                            Repair & paint ceiling             $57,000 
    RR       0643­1      12x12 tile                            Replace                            $78,000 
    RR       0643­2      12x12 tile at gym                     Repair & paint ceiling             $16,000 
    RR       0643­2      12x12 tile at gym                     Replace                            $23,000 
    RR       0643­3      2'x4' Acoustical panel                Replace                            $48,000 
    RR       0651­1      Toilet compartments                   Replace                            $49,000 
    RR       0651­2      Marker boards                         Replace                            $39,000 
    RR       0651­3      Chalkboards                           Replace                            $39,000 
    RR       0651­4      Tackboards                            Replace                            $39,000 
    C        0651­6      Signs                                 Provide new                         $3,800 
    RR       0652­1      Plastic Laminate Cabinets             Replace base cabinets             $342,000 
    RR       0652­1      Plastic Laminate Cabinets             Replace wall cabinets             $118,000 
    RR       0654­1      Damaged blinds and odd types          Replace all but existing           $27,000 
                                                               louver blinds 
    RR       0654­1      Damaged blinds and odd types          Replace all                        $47,000 
    RR       0811­1      Classroom Sinks                       Remove and replace (20)            $32,000 
                                                               Sinks 
    RR       0811­2      First Floor Main Girl’s Toilet        Remove and replace (5) water       $14,000 
                         Room                                  closets, flush valves, (4) Lav 
                                                               and carriers. 
    RR       0811­3      First Floor Main Boy’s Toilet         Remove and replace (1) water       $12,000 
                         Room                                  closets, flush valves, (3) Lav 
                                                               and carriers, (3) Urinals, 
                                                               carriers, and flush valves. 
    RR       0811­4      Main toilet room shower room.         Demolition and                      $9,400 
                                                               reconfiguration space  for 
                                                               storage. 
    RR       0811­5      Oringinal Drinking Fountain           Replace with dual fountain          $5,800 
    RR       0811­6      First Floor Janitor Closet Service    Remove and replace wall             $2,900 
                         Sink                                  mounted service sink 
    RR       0811­7      First Floor North Staff Toilet        Replace fixtures                    $3,600 
    RR       0811­8      Nurse's station sink and toilet room  Reconfigure space/fixtures         $11,000
                                                               for ADA 


June 2005              Auke Bay Elementary School Condition Survey Report          Page 225 of 228 
Cost Estimates 
   Type       ID #                Deficiency Title                 Remedy Work                 Cost 
    RR       0811­9      Teacher’s Lounge                   Remove and replace single           $2,600 
                                                            compartment sink and trim. 
    RR       0811­10  Second floor Staff toilet rooms       Remodel toilet room                 $3,600 
    RR       0811­11  Second Floor South Main Girl’s        Remove and replace (5) water       $13,000 
                      Toilet Room                           closets, flush valves, (4) Lav 
                                                            and carriers. 
    RR       0811­12  Second Floor South Main Boy’s         Remove and replace (2) water       $16,000 
                      Toilet Room                           closets, flush valves, (4) Lav 
                                                            and carriers, (4) Urinals, 
                                                            carriers, and flush valves. 
    RR       0811­13  Warming Kitchen Fixtures              Install (1) double pot sink,        $5,800 
                                                            with ledge and faucet trim, 
                                                            (1) counter mounted single 
                                                            compartment sink with trim 
                                                            for Hand wash. (Cost does 
                                                            not include architectural 
                                                            remodel of space) 
    RR       0812­1      Shell & Tube Domestic Hot Water    Install hot water heat             $22,000 
                         Heat Exchanger and circulation     exchanger/storage tank and 
                         pump                               new circulation pump. 
    RR       0812­2      Kitchen Hot Water Booster and      Remove and install kitchen          $3,200 
                         Heating Pump                       hot water booster heat 
                                                            exchanger and heating 
                                                            circulation pump 
    RR       0813­1      Floor drains not primed            Replace and add trap primers       $38,000 
    RR       0814­1      Domestic Cold Water Piping         Replace cast iron section of      $507,000 
                                                            domestic cold water service 
                                                            above grade.  Pipe lining 
                                                            procedure on hot, cold water, 
                                                            hot water recirculation piping 
                                                            in slab. 
    RR       0814­1      Optional Domestic Cold Water       Use FDA approved pipe             $319,000 
                         Piping                             lining procedure 
    RR       0821­1      Boilers                            Replace boilers, price            $319,000 
                                                            includes renovation of piping 
                                                            and trim. 
    RR       0821­2      Multiple Pumps                     Remove & Replcae pumps             $43,000 
    RR       0822­1      Corrosion of heating piping        Option (1) install dielectric      $17,000 
                         through out building               unions are every location the 
                                                            black steel pipe and copper 
                                                            connect. 25 location 
    RR       0822­1      Corrosion of heating piping        Remove all black steel piping     $116,000
                         through out building               from heating system and 
                                                            replace with copper piping. 
                                                            Option would be best if 
                                                            replacement of boilers and 
                                                            pumps replacement with VFD 
                                                            is done 




June 2005              Auke Bay Elementary School Condition Survey Report       Page 226 of 228 
Cost Estimates 
   Type       ID #                Deficiency Title                    Remedy Work                Cost 
    RR       0822­2      Pipe Insulation                       Install 1­1/2 inch mineral       $22,000 
                                                               fiber insulation of damages 
                                                               sections and pipe not 
                                                               insulated 
    RR       0823­1      VU­1 through VU­5 andEF­1             Remove and replace VU­1         $261,000 
                         through EF­5                          through VU­5 and EF­1 
                                                               through EF­5and clean all 
                                                               associated ductwork 
    RR       0824­1      Dirty ventilation distribution        Clean all ductwork, grilles,     $43,000 
                         system                                diffusers through out the 
                                                               building 
    RR       0828­1      Antiquated pnematic controls          Upgrade heating system          $232,000 
    RR       0831­1      Tamper Switches                       Install valve tamper switch       $5,100 
    RR       0842­1      Single wall oil storage tank          Install 3,000 gallon double      $43,000 
                                                               wall oil tank, with spill 
                                                               prevention, double 
                                                               containment oil piping and 
                                                               appurtenances. 
  RR, F      0911­1      Main Switchboards                     Replace Main and Auxiliary       $40,000 
                                                               Switchboards with new 
                                                               sitchgear 
  RR, F      0912­1      Replace Panels A, B, C, D, L, S,      New panels and feeders.          $77,000 
                         BR, MR, & MR2 
    RR       0913­1      Starters, disconnects and controls    Replace starters, disconnects     $26,000 
                                                               controls, conduit, and wiring. 
  RR,E,F     0921­1      Gymnasium Lighting                    Replace light fixtures, conduit  $32,000 
                                                               and wiring. 
 RR,E, F     0921­2      Classrooms and Admin Spaces           Replace light fixtures, conduit  $279,000 
                                                               and wiring. 
  RR,E,F     0921­3      Corridors & Stairwells                Replace light fixtures, conduit  $59,000 
                                                               and wiring. 
  RR,E,F     0921­4      Restrooms                             Replace light fixtures, conduit  $28,000 
                                                               and wiring. 
  RR,E,F     0921­5      Entry                                 Replace light fixtures, conduit    $6,700 
                                                               and wiring. 
  RR,E,F     0921­6      Mechanical Spaces                     Replace light fixtures, conduit  $107,000 
                                                               and wiring. 
 RR,E,F      0921­7      Egress lighting                       See items 0921­1 & 0921­3              $0 
 RR, E, F    0921­8      Lighting controls                     Replace swiches, conduit and      $50,000 
                                                               wiring 
  RR, F      0931­1      Convenience Receptacles               Replace and upgrade              $153,000 
                                                               receptacles and surface 
                                                               raceways, conduit and wiring 
  RR, C      0931­2      Replace receptacles at sinks with     Replace receptacles at sinks      $14,000 
                         ground fault protected devices        with ground fault protected 
                                                               devices, CONDUIT & 
                                                               WIRING 
    RR       0931­3      Covered Playarea receptacles          Replace receptacles, conduit       $1,200
                                                               and wiring. 



June 2005              Auke Bay Elementary School Condition Survey Report          Page 227 of 228 
Cost Estimates 
   Type        ID #                Deficiency Title                 Remedy Work              Cost 
  RR, C       0941­1      Fire alarm system                  Replace fire alarm control    $114,000 
                                                             panel and devices. 
   RR,F       0942­1      Telephone system                   Replace and upgrade.          $168,000 
    F         0942­2      Network Server Facility            Upgrade headend equipment.     $91,000 
    F         0942­3      Cable TV System for the            Head­end equipment and         $40,000 
                          Classrooms                         outlets 
   RR,F       0943­1      Security system                    Replace and upgrade head­      $83,000 
                                                             end equipment and devices. 
    RR       01013­1  Kitchen Equipment                      Replace                        $11,000 



 Summary of Construction Costs by Deficiency Type 
          Total Construction Cost of Renewal and Replacement (RR) Work                  $5,875,700 
          Total Construction Cost of Renewal and Replacement (RR) Work ­ 
          Including Option 2 Remedies                                                   $6,135,500 
          Total Construction Cost of Building Code (C) Related Work                       $105,900 
          Total Construction Cost of Energy Upgrade (E) Work                               $13,000 
          Total Construction Cost of Functional Upgrade (F) Work                          $186,700 

 Maximum Estimated Construction Cost of Deficiency Work                                 $6,637,600 



 Summary of Construction Costs by Building Systems 

      Total Construction Cost of 0100 Sitework                                            $616,800 
      Total Construction Cost of 0200 Foundations                                           $2,800 
      Total Construction Cost of 0300 Structure                                           $393,700 
      Total Construction Cost of 0400 Exterior Closure                                    $657,900 
      Total Construction Cost of 0500 Roof                                                 $17,500 
      Total Construction Cost of 0600 Interiors                                         $1,788,000 
      Total Construction Cost of 0700 Conveyors                                                 $0 
      Total Construction Cost of 0800 Mechanical                                        $1,786,000 
      Total Construction Cost of 0900 Electrical                                        $1,368,900 
      Total Construction Cost of 1000 Equipment                                            $11,000 

 Maximum Estimated Construction Cost of Deficiency Work                                 $6,642,600 




All construction costs include general contractor mark­ups, contingency, and escalation 
to summer of 2006.  If work is to occur later than summer of 2006 additional escalation 
of estimated construction costs is advised.