									VCCS SIS V8 Upgrade Project
      December 2004 Update
    VCCS SIS V8 Upgrade Project - Working with PeopleSoft
•     PeopleSoft eBusiness Architecture Assessment
       –   On-site review and assessment completed August 16 – 26 for Version 7.6 and Version 8
       –   Recommendations incorporated into Technology Architecture plan

•     PeopleSoft Upgrade Lab assessment and upgrade preparation
       –   Completed August 23 – September 24
       –   Reports and analysis reviewed and completed by ITS staff

•     PeopleSoft Project planning and Independent Validation and Verification
       –   Completed September 20 – 24
       –   Upgrade project plan and project charter based on PeopleSoft COMPASS methodology
           published
       –   Completed initial IV&V review of planning and project charter, fit/gap functional requirements
           and specifications, and Design

•     PeopleSoft certified Version 8 Demo install
       –   Completed September 27 - 30
       –   Hands-on training and knowledge transfer to ITS staff

•     PeopleSoft Upgrade Lab on-site install
       –   Completed October 12 through November 5th
       –   Hands-on training and knowledge transfer to ITS staff
  PeopleSoft Upgrade Lab review of VCCS 7.6 Production Database
  August / September 2004



Online Customization Profile Homepage

         Customer Added

The following graph shows your customization levels
relative to other customers that have come through
the Upgrade Labs for Custom Added Online Objects.
To view this information by object type, click on the
"Details" hyperlink to the right.                         Details



        Customer Modified

The following graph shows your customization levels
relative to other customers that have come through
the Upgrade Labs for Custom Modified Online
Objects. To view this information by object type, click
on the "Details" hyperlink to the right.                  Details
PeopleSoft Upgrade Lab review of VCCS 7.6 Production Database
August / September 2004




 Online Customization Details


        Customer Added                          Customer Modified
 Object Type       Number   Rank   Risk   Object Type     Number    Rank  Risk
 Record Fields          1       2%        Record Fields        7      14%
 Record Pcode         210      64%        Record Pcode        27      38%
 Records              122      56%        Records             36      55%
 Pages                 94      61%        Pages               11      28%
 Components            80      56%        Components          10      64%
 Fields               100      41%        Fields              29      86%
 Translates           256      67%        Translates          50      81%
 Other                                    Other
PeopleSoft Upgrade Lab review of VCCS 7.6 Production Database
August / September 2004



•    “Almost all modifications to objects are well documented. Most are minor in
     nature. Also good naming conventions were used for custom added objects.”

•    “The changes to records and record fields are minor in nature. These
     modifications can be carried forward.”

•    “Most of the modifications are well commented. A few undocumented changes
     could be the result of applying fixes. Reapplying customizations will be the
     most challenging part of the upgrade . . . ..”
•    “Most of the modifications are documented and consist mostly of additional
     fields. Three modified panels are not documented.”
•    “Minor modifications were made to the PeopleSoft panel groups and all but two
     are documented. All of these modifications can be carried forward where
     possible.“
•    “Very minor field changes were made and are documented. Most of the
     modifications consisted of changes in description changes for translate
     modifications. All field changes can be carried forward.”
•    “Most of the changes to the PeopleSoft delivered translate values exist
     because of inactive setting changes. These changes will be carried forward.”
•    “No indexes were modified.”
VCCS SIS V8 Upgrade Project – PeopleSoft Compass Methodology


   •Phases      Strategy, Planning, Structure, Construct, Transition,
                Deploy
   •Activities  major sections of a Phase, consisting of Steps that
                conclude in a project deliverable or milestone
   •Steps       similar tasks that are part of an Activity
   •Application specific information includes table setup sequences,
                application features, integration detail, and
                application-specific tasks


                                    Compass Methodology
                    Strategy Planning Structure Construct Transition    Deploy



     Scalable
VCCS SIS V8 Upgrade Project – PeopleSoft Compass Methodology



•   Strategy Phase
     –   Usually pre-sales
•   Planning Phase
     –   Includes the Upgrade Planning & Technology Assessment Packaged Services
•   Structure Phase
     –   Includes detailed implementation planning, specifically defining requirements and developing
         a project charter, fit/gap analysis, and functional specs
•   Construct Phase
     –   Includes designing, building, and initial testing of the PeopleSoft system
•   Transition Phase
     –   Includes System Test, other testing activities, and getting ready for Production (“Production
         Readiness”)
•   Deploy Phase
     –   Includes “go-live” and production support
VCCS SIS V8 Upgrade Project Plan – Summary as of November 22, 2004

VCCS SIS Version 8 Upgrade Project (Compass Methodology)               Sun 8/15/04    Fri 6/10/05    57%

•    Structure Phase                                                   Sun 8/15/04    Mon 4/11/05    99%
      –    Planning and Project Charter                                Sun 8/15/04    Sat 11/20/04   99%
      –    Delta Fit/Gap Functional Requirements and Specifications    Sun 8/15/04    Mon 4/11/05    98%
•    Close Structure Phase                                             Thu 10/21/04   Thu 10/21/04   0%

•    Construct Phase                                                   Sun 8/15/04    Tue 1/11/05    44%
      –    Design                                                      Sun 8/15/04    Thu 11/18/04   91%
      –    Build and Test                                              Sun 8/15/04    Tue 1/11/05    24%
•    Close Construct Phase                                             Tue 1/11/05    Tue 1/11/05    0%

•    Transition Phase                                                  Sun 8/15/04    Fri 2/25/05    5%
      –    Build Comprehensive Technical Architecture for Production   Mon 12/6/04    Mon 1/10/05    0%
      –    Perform Test Move to Production 2                           Fri 12/10/04   Fri 1/14/05    0%
      –    System Test                                                 Sun 8/15/04    Fri 2/4/05     3%
      –    Perform Test Move to Production 3                           Fri 1/14/05    Fri 1/28/05    0%
      –    Production Readiness                                        Sun 8/15/04    Fri 2/25/05    7%
•    Close Transition Phase                                            Fri 2/25/05    Fri 2/25/05    0%

•    Deploy Phase                                                      Wed 1/19/05    Fri 6/10/05    0%
      –    Perform Test Move to Production 4                           Mon 1/31/05    Fri 2/11/05    0%
      –    Deploy                                                      Wed 1/19/05    Mon 3/7/05     1%
      –    Perform Move to Production                                  Wed 3/2/05     Mon 3/7/05     0%
      –    Provide Post-Project Support                                Mon 3/7/05     Tue 3/29/05    0%
      –    Archive Project Diary                                       Thu 3/24/05    Fri 4/1/05     0%
      –    Conduct Project Acceptance Review                           Fri 4/1/05     Thu 4/7/05     0%
      –    Quality Review Checkpoint - Deploy                          Fri 4/8/05     Thu 4/14/05    0%
      –    Quality Review Checkpoint Complete                          Thu 4/14/05    Thu 4/14/05    0%
      –    Retire Production 7.6 database instances                    Mon 6/6/05     Fri 6/10/05    0%
•    Deploy Complete                                                   Thu 4/14/05    Thu 4/14/05    0%

•    Upgrade Project Complete                                          Fri 6/10/05    Fri 6/10/05    0%
VCCS SIS V8 Upgrade Project Plan – Moves to Production



      • First Test Move to Production
         – October 6th through November 5th
         – 23 days * 8 hours = 184 hours
      • Go-Live / Move to Production
         – March 1st @ 6:00pm through March 7th @ 6:00am
         – 5.5 days * 24 hours = 132 hours


• 1st Test Move to Production created from October 5th Production backup
• 2nd Test Move to Production created from November 10th Production backup
• Time savings already realized through hardware, database and script changes
    1st Test Move to Production data conversion steps took 33.7 processing hours
    2nd Test Move to Production data conversion steps took 13.9 processing hours
VCCS SIS V8 Upgrade Project – Test Plans


• Rik Gillette - Test Coordinator

• Validation testing
   – completed the week of November 8th
   – involving 18 representatives from 12 colleges

• Functional testing
   – Completed November 15th through December 3rd
   – Involving 53 representatives from 19 colleges

• College User Testing
   – Scheduled for mid-December through mid-February
   – College designated testing teams and scenarios

• Performance / Stress Testing
   – Scheduled for January 2005
   – Using automated testing tools and ITS / College developed scripts
    VCCS SIS V8 Upgrade Project – Training Plans
•   Jeff Mitchell named as Training Coordinator

•   Training focus
     –   Delta Training - PeopleSoft instruction on changes in the Version 8 SA products
     –   Workshops - Demonstrations and instruction on the new VCCS SIS
     –   User Productivity Kit - End-user documentation and automated training materials development
     –   Additional Training - Alternative training options to meet specific college needs

•   Regional Core Module Workshops
     –   December 6th, Paul D. Camp Community College
     –   December 14th, Greenfield Education and Training Center
     –   Break out sessions on the following topics
           •   Version 8 Admissions/Academic Advising/Student Records - Sue Cooley (LFCC), Cathy Barker (BRCC), Kathy Harcum (VCCS)
           •   Version 8 Student Financials - Myra Maiorana (TCC), John Thornburg (TCC), Linda Silver (VCCS), Rik Gillette (VCCS)
           •   Version 8 Financial Aid - Cathy Swain (VWCC), Janet Rathbun (VWCC), Kathy Camper (VCCS)
           •   Version 8 Query/Reports - Misty Coles (VCCS)
           •   Version 8 SIS Support - Imad Abi-Falah (VCCS), Annette Sherrill (VCCS), Jeff Mitchell (VCCS)


•   User Productivity Kit
     –   End-User training provided through PeopleSoft’s User Productivity Kit (UPK).
     –   Creates Web-based content and provides a real-time walk through of panels and business process steps.
     –   Context-sensitive tips and guidance can be included at any point in the recorded process.
     –   Once a business process is recorded, it can be accessed by using the “Help” function.
     –   Generate business process documentation, training guides, work aids, and testing scenarios

•   Training Web site - http://164.106.10.30/training/Default.htm
VCCS SIS V8 Upgrade Project – Security Update

•   All existing security related data (logon ids, passwords, security classes, and the model
    operator identifiers) will be automatically recreated under PeopleTools V8.

•   College Roles and Responsibilities during Migration:
     –   Review the security classes and model operator ids.
     –   Request deletion of model operator ids not currently active or assigned to an active user.
     –   Request deletion of all unnecessary security classes.

•   VCCS Information Security Officer
     –   Create all roles used.
     –   Distribute a list of roles and permission lists assigned to each role.
     –   Make the necessary changes to security classes and model operator ids in PS 7.6

•   College Information Security Officer or person(s) fulfilling that role
     –   Review the roles to make sure they are the equivalent of the existing model operator ids.
     –   Submit any changes to permission list or model operator ids
     –   Test every model operator id

•   Other Version 8 Tasks
     –   Completed an audio conference in late October to review the security plan and migration strategy.
     –   Project to replace the current college security spreadsheets with automated reports by February 2005.
     –   ITS will sponsor a SIS security class to provide a high-level overview of how security functions in version 8.

•   November 1st freeze on role and model operator id changes in V7.6
VCCS SIS V8 Upgrade Project – Query / Reports / Mass Change Update

•   Misty Coles is coordinating the Query / Reports / Mass Change review projects.

•   Over 4,000 college queries currently exist.
     –   Many are no longer used or are duplicates of other queries.
     –   Use different strategies and table sources to report data - inconsistent results
     –   Opportunity to convert existing queries into Version 8 is consistent with PeopleSoft “best practices”

•   Develop a pool of common queries and reports for use in PeopleSoft Version 8

•   Create and maintain a searchable query catalog so users may easily locate a query to meet
    their needs.

•   Cataloging existing reports and mass changes being used by colleges
     –   Reports submitted by BRCC, CVCC, GCC, JSRCC, JTCC, MECC, NVCC, PDCCC, RCC, SVCC, TCC,
         VWCC
     –   Mass Changes submitted by JTCC, MECC, PDCCC, SWCC, TCC, VWCC

•   Project websites developed and released through VCCS Discuss
     –   track the project progress,
     –   see the outcome of the review for each query described,
     –   See the selection of a “model query” as a guide for development in version 8,
     –   take a sneak peak of how the query catalog might work.

•   Position VCCS for the next upgrade.
VCCS SIS V8 Upgrade Project – More Information

                                                                                                 Outages - Hours - Privacy & Use - Search - Site Map
                                                                                       PeopleSoft 8 - Performance - System Office - VCCS Colleges - Webmaster


 •   Version 8 Upgrade Project Website -
           http://helpnet.utility.vccs.edu/ASC/Psoft/PSoft8/Psoft8menu.htm

     The VCCS initial version will be SAS V8 SP1 and PeopleTools 8.20.13. All released updates and fixes for SP1 will be applied.
 •   Client Services Version 8 Communications
 •   SIS V8 Updates from the Vice Chancellor
 •   SIS V8 Training Center
 •   Security Presentation: “Differences in PS 7.6 and PS 8 Security"
 •   V8 Upgrade Training Strategy
 •   Technology Council Powerpoint Presentation 10-7-04
 •   http://peoplesoft8vanilla.vccs.edu
 •   PeopleSoft SIS Version8 Demonstration Database
 •   Version 8 Student Administration Upgrade Project Plan Task List
       –     Task Excel version MS Project version
       –     High Level Testing Scenarios for PeopleSoft 8
 •   Version 8 Student Administration Upgrade Project – High Level Task List
 •   Version 8 Student Administration Upgrade Project Plan - College Specific Tasks List
 •   Version 8 Student Administration Upgrade Project Charter
 •   Query Migration Site
 •   Reports & Mass Change Project
 •   SIS Version 8 upgrade Project Planning Guide
 •   SIS Security Overview
 •   PeopleBooks8
 •   Custom SQRs Migrated to PeopleSoft 8



 •   Message of the week

								
To top