           The DØ Upgrade

             where we are
                 and
           where we’re going

                   Hal Evans
             Columbia University
           for the DØ Collaboration




H. Evans        Beauty 2000 - 15/Sep/00   1
D             The Times They are a
                    Changin’
  •    Tevatron Improvements…
       – Main Injector
       – Antiproton Recycler Ring

                            Ib        IIa           IIa (?)   IIb
Tot. Anti-p     (x1012)     0.3       1.1           4.2       11
Bunches                     6x6       36x36 140x103           140x103
Spacing         [ns]        3500      396           132       132
E-CM            [GeV]       1800      1960          1960      1960
Typ. Lumi.      [cm-2s-1] 0.16        0.86          2.1       5.2
                (x1032)
Lumi/week pb-1              3.2       17.3          42        105
Tot Lumi        fb-1        0.125               2-4           15-20
Int’s/X’ing                 2.5       2.3           1.9       4.8

  •    …mean Detector Challenges
       –     Electronics response time
       –     Occupancies & Pileup
       –     Radiation Damage
       –     Trigger Decision time
  •    …and Physics Opportunities
       – See next talk
  H. Evans                Beauty 2000 - 15/Sep/00                     2
                          Forward Mini-drift
                          chambers
                                                The DØ Upgrade
                                                Central Scintillator
                                                                                       D
                                                                        Forward Scintillator




H. Evans
                          Shielding




Beauty 2000 - 15/Sep/00
                          Tracking: Solenoid,




3
                          Si,Fiber Tracker,Preshowers
                                                                  Electonics,Trigger,DAQ
D                          Silicon

   • 6 Barrels
   • 12 F-Disks
                                               12
                                          91011
   • 4 H-Disks
                                                6
                    23
                       4                 4 5
                  1             2
                                     3                • 793k Channels
                           1
                                          7 8
                                                      • 3.0 m2 Si
                               5 6                      (1.6 m2 D.S.)
                                                      • SVX IIe Readout
                                                      • L2 Trigger (’02)
                      Barrels                  F-Disks         H-Disks
Sensors                72 SS                    144 DS            96
                    144 DS(90)                                 (back-to-
                     216 DS(2)                                   back)
Strip Pitch         50 m (A)              62.5 m (n)          80 m
                   153 m (90)              50 m (p)
                   62.5 m (2)
D.S. Stereo           90o / 2o                      ±15o         ±7.5o
R/O Length            12.4 cm                   7.5 cm         14.6 cm
Inner Radius          2.7 cm                    2.6 cm          9.5 cm
Outer Radius          9.4 cm                   10.5 cm          26 cm
  H. Evans           Beauty 2000 - 15/Sep/00                            4
D                   Fiber Tracker


                                                  Central
Silicon
                                                  Fiber
                                                  Tracker




                                                 Forward
                                                 Preshower


Solenoid

                                                Central
                                                Preshower
  8 Double Cylinders of Scintillating Fibers (830 m)
  • Radii: 20  51 cm
  • Active Lengths:
       – 1.66 m (inner-2); 2.52 m (outer 6)
  •   Axial + Stereo (±3o) Fibers
  •   VLPC Readout: ~77k Channels
       – SIFT + SVX IIe
  •   L1 Trigger Information

  H. Evans            Beauty 2000 - 15/Sep/00           5
D                     Tracking

                      Run I                        Run II
Detectors        Drift chamb’s +              Silicon + Fiber
                       TRD                     Tracker + PS
Solenoid                —                          2.0 T
|| Coverage       <3.0 (FDC)          Si              <3.0
                                       CFT             <1.7
Hit Resolution     50-200 m           Si             10 m
                                       CFT           100 m
PT / PT                —                    8% (PT=45GeV, =0)
r- Impact Par          —                18 m (PT=1GeV, =0)
Trigger                 —                   PT > 1.5 GeV
                                         CFT:L1,2; Si:L2(’02)




  H. Evans         Beauty 2000 - 15/Sep/00                      6
D              Tracking Status

Silicon:
• Ladder/Wedge 90% complete (!)
• Electronics  SVXIIe: all in hand
           SVX support card (HDI): nearly done
•   Detectors                Barrels: 4 / 6 complete
                             F-Disks: 7 / 12 complete
                             H-Disks: ~half done
•   Readout                  Testing full barrel with
                             final readout
Fiber Tracker
• Detector      Installed (29-Jun-00)
• VLPC Cassette 40 / 100 complete
                             (on schedule for 1/01)
•   Waveguides               starting installation




H. Evans           Beauty 2000 - 15/Sep/00              7
D          It’s Really There!


                                        Si Barrel




                                          CFT +
                                          Solenoid
                                          Installed




H. Evans      Beauty 2000 - 15/Sep/00                 8
D                    Preshowers

         Central                            Forward
                                 Calorimeter




                  Solenoid




                         CFT

                    Silicon


                             Central                Forward
Detector                      Triangular Scint. Fibers
Pre-radiator        2Xo (solenoid+Pb)           2Xo (material+Pb)
Fibers             Axial & ±20o stereo               ±22.5o
Channels                      7.7k                    16k
|| Coverage                  <1.2                  1.4 – 2.5
Readout                        VLPCs shared w/ CFT
e-Trig Bgrd Rej               x3–5                   x2–4
Status                    Installed                 Installed
  H. Evans            Beauty 2000 - 15/Sep/00                   9
D                     Calorimetry

 •   Detector Unchanged from Run I (U-LAr)
 •   New Electronics to cope with BX frequency
      – PreAmps:                5k / 55k installed
      – Baseline Subtr          in production

|| Coverage            < 4.0
Granularity             : 0.10.1
Energy Res      EM      14%/E  <1% (~0)
                Had     50%/E
                Jet     80%/E


 •   New Calibration Tools
      – Zbb (b-jet scale)                       E/P
            • Peak pos to 0.3%
            • Requires STT




                                                Electrons
 H. Evans             Beauty 2000 - 15/Sep/00               10
D                  Muon Upgrade


                         PDTs             Central Trigger
                          (Run I)
                                          Scint (A- )
Forward
Trigger Scint
(Pixels)



Shielding



Forward
Tracker (MDTs)



                                               Improved
                Bottom B/C Scint               Trigger
   H. Evans         Beauty 2000 - 15/Sep/00            11
D               Muon Detection

                         Run I                    Run II
|| Coverage              < 3.6                    < 2.0
Total Accept.    only partial scint           90% (1 Layer)
                     coverage                 75% (2 Layer)
Shielding          Calorim: 5-9 I           add beampipe
                  Toroid Fe: 7-9 I            shielding
P Resolution        0.18  0.03PT            0.02  0.02PT
                                            (from inner tracking)

Trigger               PT > 3 GeV              PT > 1.5 GeV
                                            improved accept




  H. Evans        Beauty 2000 - 15/Sep/00                   12
D           Muon Status

Detector
• Central Muons                    commissioning
• Forward Pixels                   A-layer installed
• MDTs                             A&C installed
                                   B assembled
•   Gas System                     design

Electronics
• PDT / MDT                        done
• Scintillators                    September
• Readout                    November
                       (enough for commiss.)




H. Evans     Beauty 2000 - 15/Sep/00               13
D               In the Hall




           A-Layer South Pixels


H. Evans       Beauty 2000 - 15/Sep/00   14
D                            Trigger

 Process               X-Section                  Rate
                                                  (L=21032 cm-2s-1)
 Inelastic pp          50 mb                      10 MHz
 bb (|y|<1)            50 b                      10 kHz
 pp  WX               22 nb                      4.4 Hz
 pp  ZX  bbX         1 nb                       0.2 Hz
 pp  tX               11 pb                      8 / hour
 pp  W/Z H            0.5 pb                     8 / day

7 MHz         Framework                               Data

          L1                   L2                      L3
        4.2 s               100 s                   50 ms
      (128 terms)            (128 terms)             (48 nodes)

                    10 kHz                 1 kHz                  50 Hz


 • Single Sub-Det’s • Correlations                  • Simple Reco
 • Towers, Tracks,      • Calibrated Data           • Physics Algo’s
   ET-miss
                        • Physics Objects
 • Some correl’s          e,,j,,ET-miss
   H. Evans             Beauty 2000 - 15/Sep/00                        15
D              L1 & L2 Systems


    Detector   L1 Trigger                  L2 Trigger
           7 MHz           10 kHz                             1 kHz

    CAL            L1CAL            L2Cal


    FPS
    CPS            L1PS             L2PS


                                                     Global
    CFT            L1CFT            L2CFT
                                                      L2


    SMT                             L2STT

                    L1
                    MU              L2
    MU
                                    MU
                                                L2FW:Combined
                   L1FPD                         objects (e, , j)
    FPD


                   L1FW: towers, tracks

H. Evans              Beauty 2000 - 15/Sep/00                        16
D                Bigger – Faster

                     Run I                        Run II
Rates       In      300 kHz                       7 MHz
            L1      150 Hz                       10 kHz
            L2         —                          1 kHz
            L3        4 Hz                        50 Hz
Terms       L1         32                          128
            L2         —                           128
            L3        128                       arbitrary
Inputs      L1   calorim,muons                cal,mu,trk,ps
            L2         —                     corr’s,phys objs
            L3     vax farm                      pc farm

 Status
 • Note: trigger installation/commissioning does
    not delay detector preparation
 • Framework testing & debugging
 • Level-1        most boards in production
                  firmware: CFT-done, others-prog
 •   Level-2      custom cards: done or production
                  software: in progress
 •   Level-3      basic tools written
                  hardware in Oct.

 H. Evans          Beauty 2000 - 15/Sep/00                  17
D                Installation &
                Commissioning
•    This is a 4D problem!
•    Dec 99 Review  Installation
     sequence changed radically to gain
     contingency
     1. Split Silicon into two halves
           – Installation: S in Nov.; N in Dec.
     2. Push up schedule for installing end
        toroid iron
           – done!
•    Gain ~3 months contingency over
     previous schedule
     – Fallback plans in place
•    Installation is now driving all
     upgrade efforts
     – even with conting. schedule is still tight
•    Commissioning proceeding as
     parts/detectors arrive


H. Evans             Beauty 2000 - 15/Sep/00      18
D            Accomplishments &
                 Deadlines

   Subsystem                Status                  Future
     Silicon         4 barrels assemb          install 11/&12/00
  Fiber tracker            Installed
  Tracker Electr         production             complete 2/01
    Solenoid               working
Central Preshower          installed
     Forward               installed
    Preshower
Intercryostat det.         installed
     Calorim             production            complete 12/00
   Electronics
Luminosity Mon.       measuring lumi
  Muon Central        commissioning
 Muon Forward             installing           complete 11/00
 Trigger & DAQ           prod & use             complete 3/01
      Online                 in use
   Installation         on schedule             complete 2/01
 Commissioning           in progress
   Computing          commissioning
  H. Evans           Beauty 2000 - 15/Sep/00                 19
D                    On the Horizon
                     (beyond 2 fb-1)
   •   RunII Physics Goals
       need 15-20 fb-1
   •   Run IIb Tevatron
        – L51032 cm-2s-1
        – X’ing angle
           z 25  12 cm
   •    Possible Problems for DØ
Rad damage to Si (esp L 1,2)     • Partial/full replacement (?)
                                 • Use SS Si back-to-back
Incr. Material  imp par degrade • Layer 0 (?)
Track Trigger Rate               • Intermediate Si (?)
Central Muon (PDT) Aging         • Regular Zapping

   •   Some Constraints
        –     need to maintain IIa performance
        –     time: Run IIb in 2003?
        –     readout chips: limited SVXIIe’s left
        –     and of course… $$$
   •   Si Solutions under consideration
        – will choose from many options soon

   H. Evans             Beauty 2000 - 15/Sep/00            20
D               Where We Are
             (and where we’ll be)
•   Detector
     – Production working or winding down
            • Worries with Si sensors mainly over
     – Emphasis shift to electronics/readout
•   Installation
     – Many detectors installed
     – Fallback plan  2-3 months contingency
•   Commissioning
     – In full swing!
•   Starting work for > 2 fb-1 (Run IIb)
•   Nostradamus predicts…
            DØ will be ready
           in February 2001*




 * Feb. 16, 2001 to be precise