Evaluation and optimisation of alternatives
Two cases
-Criteria of judgement
-Matrix evaluation, including costs
-Mitigating measures
Consultant: CMDC Joint Venture
2
Case 1: capacity improvement of highway A12
Aspects assessed: Alternatives assessed:
-Traffic and transport -Reference situation 2x2 lanes
-Infrastructure -Utilisation of current deck 2x3
-Human env. (noise, air, safety) -Minimal enlargement 2x4
-Natural env. (flora, fauna, landscape) -Maximal enlargement 2x4
-Spatial planning (agriculture, housing) -Safe design 4x2
-Economy -Environmentally optimal alternative
-Costs
Consultant: CMDC Joint Venture
3
Case 2: location and technology for a new water
production plant
Aspects assessed: Alternatives assessed:
-Water and soil -Reference situation (existing plant)
-Agriculture -Trench / groundwater
-Nature -Stream channel / groundwater
-Landscape -River bank / bank-groundwater
-Energy, waste, materials -Infiltration area / surface water infiltration
-Management (incl. costs) -Environmentally optimal alternative
Consultant: CMDC Joint Venture
4
Components of the EIA, both cases
Contents of the report:
-Problem definition and objective
-Present and known future situation in study area
-Alternatives
-Most environmentally friendly alternative
-Criteria of judgement of the alternatives
-Impacts
-Comparison of the alternatives
-Compensation and mitigation
Difference: nominal (water) or ordinal (highway) alternatives
Consultant: CMDC Joint Venture
5
Criteria of judgement of the alternatives
Based on insight through public and expert consultations
Defined in scoping
Includes both topic (aspect) and methodology of assessment
Described in the EIA report, before description of impacts
Both qualitative and quantitative or standardised evaluation
Consultant: CMDC Joint Venture
6
Comparison of alternatives: MCA scores
Scores
Theme Aspect Weight Criteria Zero Alt. Wet Alt. Combi Alt. Lake Alt. Creek M.E.F.A.
Nature Flora and 3 increase/de
fauna crease
current and
potential
values 0 5 10 10 10 10
2 change in
w ater
quality 0 5 5 10 5 10
Ecological 1 disturbance
infrastructu through
re recreation 0 -5 -10 -10 -5 -10
2 functioning
as part of
the Green-
blue zone 0 0 0 5 5 0
total 0 1,25 1,25 3,75 3,75 2,5
Consultant: CMDC Joint Venture
7
Comparison of alternatives: MCA weights
Nature Flora and 3 decrease/inc
fauna rease current
and potential
values 0 15 30 30 30 30
2 change in
water quality 0 10 10 20 10 20
Ecological 1 disturbance
infrastructure through
recreation 0 -5 -10 -10 -5 -10
2 functioning
as part of the
Green-blue
zone 0 0 0 10 10 0
total 0 2,5 3,75 6,25 5,6 5,0
Consultant: CMDC Joint Venture
8
Comparison of alternatives: ranking
Highway (no weights agreed)
•Based on scores natural environment: 1 – 3 – 4 – 5 – 6 - 2
•Based on scores human environment: 1 – 3 – 4 – 5 – 6 - 1
•Based on scores traffic: 6 – 5 – 3 – 2 – 1 - 4
•Based on scores economy: 6 – 4 – 3 – 2 – 1 - 4
Water production plant (weights agreed)
•Based on scores: 6 – 4 – 4 – 1 – 1 - 3
•Based on weights: 6 - 5 – 4 – 1 – 2 - 3
Choice of weights and/or point of view = political = subjective
Conclusion for given choice = evidence based = objective
Consultant: CMDC Joint Venture
9
Mitigating measures - types
3 types of measures:
-those who are already foreseen in every alternative
-those who could be elaborated in the next project phase if
desired
-those who are part of the Env. Opt. Alternative but who could
be applied to every other alternative if desired
Consultant: CMDC Joint Venture
10
Mitigating measures – some examples
Measure positive for…
•Optimisation stream of raw materials sustainability
•Maintenance-free design sustainability
•Dam to protect areas prone to dehydration water system
•Plant construction with vegetation visual nuisance
•No construction during brooding season fauna
•Additional noise measures fauna, noise nuisance
•Move monumental trees elsewhere flora, landscape
•Remove/prevent sight obstruction cyclists social safety
•Lights near cyclist tunnels and paths social safety
•Prevent pollution rather than clean afterwards water system, costs
Consultant: CMDC Joint Venture