					     H.E. Project         (2005-                   months        96)                                                Slow progress of Barrage and
     Barrage II (2x15       06)                                                                                     associated HM works.
     MW) TNEB                                                                                                       Reservoir filling issues.
     11.06.99
25   Bhavani Kattalai     Mar-06         07/12    3years 6    99.75 (99-               396.59     297.59   296.85   Delay in award of work.
     H.E. Project         (2005-                   months        00)                                                Slow progress of Barrage and
     Barrage III (2x15      06)                                                                                     associated works.
     MW) TNEB
     27.03.02
                                                           NORTH-EASTERN REGION
                                                                 MEGHALAYA
26   Myntdu (2x42 MW      Oct-06        Feb-12    5 Years 4    363.08   363.08         1173.13    223.10   810.05   Delay in investment decision,
     + (1x42 MW)          (2006-        (2011-     months      (01/99)  (01/99)         (2010)                      MOE&F clearance and award of
     MeSEB 09.06.2003       07)           12)                 Including               Including                     major works, Flooding of HRT,
                                                              IDC & FC                   IDC                        PH in October, 09, May'' 10 and
                                                                                                                    in March, 11.
                                                                   PRIVATE
27   Karcham Wangtoo      Mar-10        Sept-11   1 year 6     5909.59                5909.59      Nil      Nil     Delay in Financial closure.
     (4x250 MW) H.P.      (2009-        (2011-    months                                                            Delay in start of works on right
     Jaypee Karcham         10)           12)                                                                       bank of Sutluj due to agitation by
     Hydro corporation                                                                                              local villagers.
     Ltd., (JKHCL)
     31.3.03 (TEC)
28   Budhil (2x35 MW)     Dec-08        Mar-12    2 Year 11    418.80                  418.80      Nil      Nil     Slow progress of HRT due to
     H.P. Lanco Green     (2008-        (2011-     months                                                           poor geological conditions.
     Power Pvt. Ltd. NA     09)           12)                                                                       Power evacuation
     02.06.06                                                                                                       arrangements.
29   Malana-II            July-09   -   Aug 11    2 year 1     598.00                  747.90     36.40    149.90   Poor geology in HRT.
     (2x50MW) H.P.        (2009-        (2011-    months       (2004)                                               Power evacuation arrangement.
     Everest Power Pvt.     10)           12)
     Ltd. 15.10.2004
     (State Govt)
30   Srinagar (4x82.5     Oct-05        March-    7 Years 4    1699.12                2069.00     21.77    369.88   Financial Closure.
     MW) Uttarnanchal     (2005-          13       months       (3/99)                                              Slow progress of dam works.
     Alaknanda Hydro        06)         (2012-                                                                      MoEF issued notice to stop
     Power company                        13)                                                                       works since 30.05.2011.
     Ltd. 14.6.2000
     (TEC)
31   Maheshwar (10x40     2012-13       Mar-12     10 Yrs.     1569.27     1673.00    2760.00                       Equity gap created by foreign
     MW) SMHPC M.P.                     (2011-                 (96-97)     (4/2000)    (2010)                       partner, resettlement and
     30.12.96                             12)                                                                       rehabilitation problem, Funds
                                                                                                                    constraints, Cash flow issue with
                                                                                                                    BHEL
32   Teesta Stage III       Oct,     Mar-13    2 Years 5   5705.55            5705.55    Nil      Nil     Delay in forest clearance.
     (6X200 MW)             2011     (2012-     months                                                    Works suffered due to
     Sikkim Teesta Urja                13)                                                                earthquake in Sept.2011.
     Limited
     12.05.2006(TEC)
33   Teesta Stage VI       2012-13   2013-14    1 Year     3283.08            3283.08    Nil      Nil     Poor geology.
     (4X125 MW)
     Sikkim Lanco
     Energy Private
     Limited 27.12.
     2006 (TEC)
34   Rangit-IV HE          2012-13   2013-14    1 Year     726.16             726.16     Nil      Nil
     Project (3X40 MW)                  ''
     JPCL 09.12.2005
35   Chujachen (2x49.5     Sept-09   Sept-12    3 Year     448.76    651.50   927.00    106.57   478.24   Slow progress in some stretches
     MW) Sikkim Gati       2009-10   2012-13               (2004)                                         of HRT due to poor geology.
     Infrastructure Ltd.                                                                                  Flash flood occurred on
     30.11.04                                                                                             16.04.09 at Rangpo dam. Coffer
                                                                                                          dam washed away.
            Ongoing HE projects in the country-projects not having time/cost overrun (excluding renewable and projects upto 25 MW capacity under mnes)
Sr     Name of Project          Commissioning Schedule           Delays relating    Project Cost Rupees in crores     Cost increase relating   Critical Area/Remark
No    Capacity/ Agency/                                           to Latest v/s              Price Level                 to latest v/s last
       Date of approval                                          last approved/                                         approved/original
                            Original      Latest       Latest        original      Original      Last       Latest      %age          Rs. crs
                             Mm/yy      Approved      mm/yy                                   Approved
                                          mm/yy
 1             2                3           4             5             6              7           8          9           10             11               12
CENTRAL SECTOR
 1  Kishanganga               Jan-                      Jan-            Nil        3642.04                 3642.04       Nil             Nil  Rainfall in March, 11,
    (3xllOMW) jk              2016                      2016                       (11/07)                 (11/07)                            Cavity in HRT - TBM
    20.07.2007              2015-16                   2015-16                                                                                 portion, Poor geology
                                                                                                                                              in Access tunnel.
STATE SECTOR
NORTHERN REGION
 2  Kashang-I (1x65 MW)     XII plan                  2013-14           Nil         478.02                               Nil             Nil
    HPPCL 31.07.08         (2013-14)                                               (03/08)
    (TEC by HPSEB)
SOUTHERN REGION
 3  Pulichintala 4x30 MW    2011-12                  June -13           Nil         380.00                  396.00                            E&M works.
    Andhra Pradesh                                                                  (2006-
    APGENCO 25.04.07                                                                  07)
 4  Thottiyar Kerla         April 12                 May - 13           Nil         136.79                  144.58                            Land acquisition issue.
    (1x30+1x10) MW                                                                  (2007)
    KSEB 05.06.08
WESTERN REGION
 5  Koyna Left Bank         2014-15                   2014-15                       245.02                  245.02       Nil             Nil
    Power House (2x40
    MW) GOMWRD/
    20.02.2004
    Maharashtra
NORTH-EASTERN
REGION
MEGHALAYA
6   New Umtru (2x20         2011-12                   2013-14        2 years        194.30                  194.30       Nil             Nil
    MW) MeSEB Shillong
    12/06
PRIVATE
 7  Sorang (2x50 MW),       2012-13                     Sept.           Nil         586.00                  586.00       Nil             Nil
    H.P. Himachal Sorang                                2012
    Power Pvt. Ltd.                                    (2012-
    23.09.2004                                           13)

				