Installation of Monitoring Equipment in Hanover Square
The Crossrail tunnel boring machines, Phyllis and Ada, are advancing                                  Duration of work
from Royal Oak to Farringdon and are due to pass under Hanover
Square in spring 2013.                                                                                    Work starts Sunday
                                                                                                           13 January between
                                                                                                           8am and 6pm
As part of these tunnelling works it is necessary to install monitoring
equipment to the external facades of buildings around Hanover Square                                      Preliminary work in St
including Hanover Street, Princes Street, Harewood Place and St George                                     George Street on 11
Street. The equipment will be used to monitor buildings as the tunnel                                      January from 6pm to
boring machines progress.                                                                                  6am on 12 January
                                                                                                      What to expect
Mechanical lifting platforms will need to park outside the buildings in order
to allow the operatives to install the prisms at a variety of heights on the                              Roads will be
external walls. These prisms will allow us to monitor the buildings in real-                               temporarily closed to
time as our tunnelling works progress.                                                                     general traffic
                                                                                                          Parking bays will be
In order to use the lifting platforms it will be necessary to temporarily                                  suspended
close some of the roads and footpaths in the area while the work takes
place. Our intention is to complete the majority of the work on Sunday 13                                 Traffic diversion
January 2013 between 8am and 6pm and reopen the roads and footpaths                                        routes in operation
as soon as possible. There will also be some preliminary work carried out                                 Pedestrian diversions
on buildings in St George Street overnight starting at 6pm on 11 January                                   in operation
to 6am on the 12 January.
                                                                                                      What we will do
During the road closures, we will ensure that deliveries to local                                         Maintain vehicle
businesses can continue. Traffic marshals will be on hand to help                                          access for deliveries
manage deliveries while the works are taking place. There will also be
pedestrian diversions around the works to ensure the safety of the public.                                Traffic marshals will
                                                                                                           help manage traffic
Traffic travelling east on Brook Street towards Cavendish Square via                                       flow and deliveries
Hanover Square will be diverted via New Bond Street, Conduit Street,                                      Monitor noise,
Regent Street and Margaret Street. Hanover Street will be closed until                                     vibration and dust and
mid-morning on the 13 January, following which, traffic entering Hanover                                   keep within permitted
Street from Regent Street will be diverted south along St George Street.                                   levels
Access to Princess Street and Harewood Place will be maintained for
deliveries though there may be minor delays while our marshals manage                                     Ensure that traffic
the traffic.                                                                                               management signage
                                                                                                           is in place
The diagram below shows the diversion routes that will be in place
during the works. Where possible we will assist with special
access/delivery needs while this closure is in place and we encourage
you to call us in advance of these works so that we can discuss any
necessary arrangements.


We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
Crossrail services will commence through the central tunnelled section in late 2018
followed by a phased introduction of services along the rest of the Crossrail route.          C300-XRL-Z-XBU-C125_WS088-50003
We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
Crossrail services will commence through the central tunnelled section in late 2018
followed by a phased introduction of services along the rest of the Crossrail route.          C300-XRL-Z-XBU-C125_WS088-50003
About Crossrail
Crossrail is the new high frequency, convenient and
accessible railway for London and the South East.

When the service opens Crossrail trains will travel
from Maidenhead and Heathrow in the west to
Shenfield and Abbey Wood in the east via new twin
tunnels under central London. It will link Heathrow
Airport, the West End, the City of London and Canary
Wharf.

Travelling on Crossrail will dramatically reduce
journey times:

                                                        With
 Example journey times in minutes          Now
                                                      Crossrail

 Slough – Tottenham Court Road               55           32

 Romford – Bond Street                       43           35

 Whitechapel – Abbey Wood                    49           15

 Ealing Broadway – Farringdon                38           17

 Heathrow – Liverpool Street                 55           32

 Heathrow – Canary Wharf                     71           40

 Maidenhead – Liverpool Street               71           46

 Paddington - Canary Wharf                   30           16
 Drop in to our Visitor Information Centres
 West End 16-18 St Giles High Street, WC2H 8LN.
 Open Tuesdays and Thursdays 11.00 to 19.00
 Whitechapel Idea Store, 321 Whitechapel Road, E1
 1BU. Open Mondays and Wednesdays 11.00 to
 19.00

 Bond Street Community Liaison Panel
 Crossrail run a quarterly meeting to keep local
 community representatives informed of the works
 happening in the area. For more information please
 contact crossrailliaisonpanels@crossrail.co.uk


                     QR Code
                     Scan with your mobile device to be taken to
                     the ‘Near You’ section of our website




   We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
   Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
   Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
   Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
   Crossrail services will commence through the central tunnelled section in late 2018
   followed by a phased introduction of services along the rest of the Crossrail route.          C300-XRL-Z-XBU-C125_WS088-50003

				