					          ACTIVITY IMPLEMENTATION PROPOSAL

                               Capacity building program to enhance public officials’ capacity to design and implement PPP projects in
    PROJECT TITLE
                               infrastructure, both at regional and country level.


    COUNTRY                    OECS & Barbados                        REGION COVERED                     OECS & Barbados


                               Name                                   Contact person                     Email, tel, skype
    LEAD APPLICANT
    (if following a request)
                               EIB                                            Mr Luís Baptista


                               Name                                   Contact person                     Email, tel, skype

    PARTNER APPLICANTS
    (if following a request)   1-
                               2-
                               3-

                               Name                                   Contact person                     Email, tel, skype
    KEY STAKEHOLDERS
    (if following a            1-
    Programme Initiative)
                               2-

                               3-

    RESULT N°1                 TYPE OF ACTIVITY                          WP ACTIVITY NO. 2                   WORK PROGRAMME

                                       Sector Studies on
                 1                                                         WP1.10.1-2.008                               1
                                     investment prospects

    EXPECTED DURATION          BUDGET LINE                           TOTAL COST (IN EURO)                TYPE OF
    (in month)                                                                                           COMMITMENT

    Max. 7 months                             1-2                             174.844 €                  (Imprest / Specific)

    RECEIPT DATE                                                      INTERNAL GREEN LIGHT
    (if following a request)   28/12/2010                             DATE                                28/12/2010
                                                                      (start to draft the AIP)

                                     Restricted procedure
                                                                                                              Global Price
    CONTRACT PROCEDURES          (Competitive)
                                                                      TYPE OF CONTRACT
    TO BE APPLIED              Negotiated Procedure
                                                                                                              Fee-based
                                     Direct Contract

1
    Refer to the list of activities as detailed in the work programme.
2
    As above.



ACP Business Climate Facility (BizClim)                                                              Manual of Procedures
10 ACP RPR 015                                                                    Activity Implementation Proposal (AIP)
                                                                                                                 Page | 1
 COMMENTS RECEIVED FROM THE EU DELEGATION(S)

 EC Delegation in Barbados




     PROGRAMME MANAGER
           COMMENTS
    (Quality of the Proposal
     based on the eligibility
         criteria below)




ACP Business Climate Facility (BizClim)                           Manual of Procedures
10 ACP RPR 015                                 Activity Implementation Proposal (AIP)
                                                                              Page | 2
                PROJECT OVERVIEW (max 2 pages)

 SUMMARY OF THE ACTION                            Describe the activities and the main project objectives


The project will study the potential for using PPPs in the OECS and Barbados, as well as identifying the policy and regulatory reforms
needed to create favourable conditions for the development of PPPs in the region. Key stakeholders will be sensitised by means of a
workshop organised in the OECS region. A concrete and detailed roadmap will be drafted for the promotion of PPPs and presented to a
debriefing meeting in Brussels or in Luxembourg.




ELIGIBILITY CRITERIA                                                                          MET                    COMMENTS

     Eligibility of the Applicant

The applicant is:

             An ACP Regional Economic Communities (RECs)


             An ACP Government

             ACP Private Sector Organizations (PSOs) from two or
              more sub-regions

             The ACP Secretariat


             The African Union

             The European Commission and EC Delegations in ACP
              Countries

             The European Investment Bank                                                                    EIB/OECS/Barbados

     Eligibility of the type of activities

The activities foreseen cover primarily:

             the funding of consultants

             the organisation of events (workshops, seminars,
              conferences and training)

             the communication in turn of the above

     The intervention falls under BizClim target area

As defined in BizClim logical Framework, BizClim target areas




ACP Business Climate Facility (BizClim)                                                                    Manual of Procedures
10 ACP RPR 015                                                                          Activity Implementation Proposal (AIP)
                                                                                                                       Page | 1
ELIGIBILITY CRITERIA                                                      MET             COMMENTS

are consistent     with   the   results   to   be   achieved   by   the
programme:

         The intervention contributes to empower key
          stakeholders (in terms of knowledge, capacities and
          analysis) in undertaking business environment reforms
          and creating more favourable business and investment
          conditions

         The intervention contributes to strengthen public-
          private dialogue on private sector development issues
          (including regional integration), notably through
          support to EU-ACP Business Fora

         The intervention contributes to strengthen the
          capacities of RECs for the formulation of their own
          projects to be financed, including in the framework of
          the RIP of the 10th EDF

         The intervention is facilitating reflection and access to
          information by stakeholders on pertinent themes,
          relating to the enabling environment and linkages with
          key macro, meso and micro issues

Total criteria MET                                                          5




ACP Business Climate Facility (BizClim)                                                  Manual of Procedures
10 ACP RPR 015                                                        Activity Implementation Proposal (AIP)
                                                                                                     Page | 2
       JUSTIFICATION                       Target beneficiaries, Problems to be addressed and Relevance


    Description of the target              Target groups: OECS Secretariat, government officials tasked with planning and managing
    group(s)3 and final                    PPPs
    beneficiaries4 and estimated           Final beneficiaries: the people of OECS region (570.000 people) & Barbados
    number [2.4]

                                           The development of the regulatory framework that would support the strengthening of
                                           public-public and public-private partnerships for sustainable development is needed in the
                                           OECS and Barbados, notably for the promotion of market oriented approaches in
                                           diversifying energy sources. This could take the form of cooperation among Caribbean
                                           SIDS, South-South cooperation, including SIDS-SIDS, and the building of alliances with
                                           the multilateral and bilateral donor communities. In recent times, the government of
                                           Barbados has entered into several public-private partnership (PPP) arrangements mainly
                                           build-operate-lease and transfer (BOLT) contracts to undertake a number of large-scale
                                           public projects.

                                           Programmes to enhance energy efficiency and further develop renewable energy options
                                           require support for the formulation and implementation of integrated and interdisciplinary
                                           policies and programmes, including the implementation of public awareness programmes
    Identification of problems to          in communities and among stakeholder groups on the impact of fossil fuel based energy
                                           use on the environment and the promotion of a wider use of renewable energy sources
    be addressed [2.1]
                                           within regulatory frameworks and supportive public policies regarding the development
                                           and use of renewable energy.

                                           In general, there seems to be room for the private sector to increase its involvement to
                                           manage, construct and operate, and maintain major facilities. Moreover, PPPs can support
                                           an approach to enhancing the economic development impact of remittances is to develop
                                           ways to utilize some of the remittance proceeds for development purposes, notably
                                           through Development of Community-based Programs that help to leverage remittance
                                           flows for Long-term Investment. There is also need for private public sector partnerships in
                                           waste management activities that should be guided by a system of incentives and
                                           disincentives, rules, regulations and agreements. The governments have contracted
                                           private enterprises primarily to collect and transport waste in the OECS and Barbados.



    How does the Action                    To the extent that PPPs are hampered by the lack of a favourable regulatory
    contribute to address the              framework, the present work will create better conditions for PPPs on the basis of a
    problems identified?                   study of investment potential in the area.

                                           Success will hinge on governments’ willingness to adopt measures and build stronger
    Assumptions and Risks [2.7]            institutional setup


    To what extent is the                  The Action involves the preparation of a report on the country identifying its potential for
                                           PPPs and equipping for project preparation. Hence, it is likely that existing government
    intervention likely to lead to
                                           bodies will use the knowledge acquired to prepare PPPs and financiers, such EIB, to be
    follow-up activities? [2.8]
                                           sensitized about the potential.

    Is the intervention Consistent,        The Action is consistent, coherent and complementary notably to actions undertaken by
    Coherent and Complementary             the European Union, the World Bank and other donors.


3
     “Target groups” are the groups/entities who will be directly positively affected by the project at the project
     purpose level.
4
     “Final beneficiaries” are those who will benefit from the project in the long term at the level of the society or
     sector at large




ACP Business Climate Facility (BizClim)                                                              Manual of Procedures
10 ACP RPR 015                                                                    Activity Implementation Proposal (AIP)
                                                                                                                 Page | 3
 with other interventions? [2.8]
                                          The project will interact with the E-Government for Regional Integration Program (EGRIP)
                                          implemented by the World Bank which aim is to promote the efficiency, quality, and
                                          transparency of public services through the delivery of regionally integrated e-government
                                          applications that take advantage of economies of scale. The project will interact with the
                                          EGRIP first at the level of design and implementation of the EGRIP considering an action
                                          plan for pooled procurement in the OECS foresees the assessment of options for a PPP
                                          framework for e-procurement. Second, once the EGRIP is operational, to ensure the
                                          instrument can be used to forecast OECS public procurements, including those which
                                          cover PPPs options.

                                          A Report of a Special Meeting on the OECS construction sector held in St. Vincent and the
                                          Grenadines in March 2009 and requested by the Joint OECS Authority and ECCB
                                          Monetary Council Meeting, concluded that the construction sector had a vital role to play in
                                          the recovery effort and that creative strategies should be developed to ensure the
                                          continued growth of this sector. It was also recommended that there be focused attention
                                          over the medium term to the greater use of Public Private Partnerships (PPPs) for the
                                          delivery of public services, in a bid to increase cost effectiveness of delivery, generate
                                          more private sector activity and free up public resources for redeployment in other priority
                                          service areas and, to that end, engage the Caribbean Development Bank (CDB) as a
                                          partner in the development of a fiscally prudent approach to the use of PPPs in public
                                          expenditure programmes.

                                          The Caribbean Business Leaders meeting that took place in Trinidad & Tobago in March
                                          2009 ahead of the Commonwealth Heads of Government Meeting (CHOGM) in November
                                          2009 identified a number of priority sectors for investment.

 Is there a strong support to             Interest will be gauged early on in the implementation of the present assignment.
 the intervention from key
 stakeholders? [2.8]



     CONTEXT OF THE ACTION                Intervention Background

 Describe what previous                   The lack of PPPs in the region have raised the questions about the potential for PPPs in
 actions, contacts, projects led          the region and what is needed for the creation of a better related environment. Also,
 to the Action concept [2.9]              limited experience is some countries, notably Barbados, indicate a need for stronger
                                          efforts in the area
 Indicate if this action is
 inspired from a “success
 story” (i.e. a similar action
 was successfully implemented
 elsewhere) [2.9]

 Where the action is the
 continuation of a previous
 action, explain how the action
 is intended to build on the
 results of this previous action
 [2.9]

 Where the action is part of a            See above complementarities of actions
 larger programme, explain
 how it fits or is coordinated
 with this programme. Please
 specify the potential synergies



ACP Business Climate Facility (BizClim)                                                            Manual of Procedures
10 ACP RPR 015                                                                  Activity Implementation Proposal (AIP)
                                                                                                               Page | 4
 with other initiatives, in
 particular from the EC [2.9]



     SUSTAINABILITY                       Financial, Institutional, Policy Level

 How will activities be financed          Capacity building is a permanent activity depending on the sector of interest. Other
 when the assistance ends?                resources can be sought for strengthening the capacity of Member states
 [2.10]

 Will structures allowing the             The capacity building itself is designed for member states in their effort for promoting
 activities to continue be in place       investment.
 at the end of the action? Will
 there be local "ownership" of
 action outcomes? [2.10]

 What structural impact will the          The impact will reflected through policy and institutional reforms.
 action have - e.g. will it lead to
 improved legislation, codes of
 conduct, methods, etc? [2.10]




ACP Business Climate Facility (BizClim)                                                             Manual of Procedures
10 ACP RPR 015                                                                   Activity Implementation Proposal (AIP)
                                                                                                                Page | 5
                                LOGFRAME (max 2 pages)

 G L O B A L O B J E C T I V E [ 2. 2]                   Describe the high level objective to which the Action contributes


 To promote reforms in macroeconomic policy, improve legislation, the institutional setup and financial measures (the rules of the game)
 relating to the enabling environment of the private sector in ACP countries and/or regions.

                             Indicators are meant to show to what extent the global
                                                                                                          SOURCES OF
 INDICATORS                  objective has been reached - See impact and
                                                                                                          VERIFICATION
                             sustainability indicators

  Businesses, investors and stakeholders reporting a more favourable perception of business              Benchmarking and country ratings
   climate in BizClim’s areas of intervention                                                             Survey of stakeholders, private
  Number draft Laws, recommendations, strategies, roadmaps and other official relevant                   sector key investors and
   documents adopted                                                                                      businesses (e.g. Regulatory
  Number of follow-up actions (e.g. financing of projects formulated, incorporated in RIPs and           Compliance Cost)
   NIPs) taken.                                                                                           Reports and files, press book of
                                                                                                          media appearances



 S P E C I F I C O B J E C T I V E (S) [2.2]             Describe the specific objectives to be achieved by the Action

 Key stakeholders empowered (in terms of knowledge, capacities and analysis) in undertaking business environment reforms and creating
 more favourable business and investment conditions. More specifically, the project aims at studying the potential of PPPs in the OECS and
 Barbados.

                                                                                                         SOURCES OF
 INDICATORS                   See effectiveness indicators
                                                                                                         VERIFICATION

    Number of studies, surveys and ratings                                                              BizClim database of reports
    Number of policy documents (draft Laws, recommendations, strategies, roadmaps) realised in          Media appearances and press
     participatory approach                                                                              books
    Number of participants from RECs, governments and the private sector in workshops,                  Lists of participants and presence
     conferences, specific training and consultation sessions                                            sheets in workshops and trainings
    Quality of training sessions and workshops, with prospects for greater reach out (e.g.              Fiches for quality evaluation and
     dissemination, training of peers)                                                                   auto-assessment on the transfer of
    Relevance, applicability and accessibility of studies and consultations                             competences filled by the
                                                                                                         participants at the end of the
                                                                                                         session
                                                                                                         Official correspondence with
                                                                                                         regional and national authorities
                                                                                                         Workshop reports and minutes
                                                                                                         Reporting by implementing



 EXPECTED OUTCOMES /RESULTS                              Describe the results expected by the implementation of the
 [2 .3 ]                                                 activities

    The contribution of key stakeholders is ensured through the organization of a meeting
    Study on PPP potential in OECS and Barbados and the relevant structures of PPPs




ACP Business Climate Facility (BizClim)                                                                     Manual of Procedures
10 ACP RPR 015                                                                           Activity Implementation Proposal (AIP)
                                                                                                                        Page | 6
       Assessment of the investment climate (related to PPPs), identification of bottlenecks and corresponding measures to address them
       Roadmap for further project preparations (improvement of the investment climate for PPPs through policy and regulatory reforms)
        prepared and presented to a debriefing meeting

                                 Indicators are meant to describe and quantify the
                                                                                                                SOURCES OF
    INDICATORS                   outcomes of the activities - See effectiveness and
                                                                                                                VERIFICATION
                                 efficiency indicators


                                                                                                                Final report
        Report validated by key stakeholders
                                                                                                                Summary of proceedings
        Report on concerned countries identifying their potential for PPPs and equipping for project            List of participants (targeted
        preparation                                                                                             audience)
                                                                                                                Assessment of the quality of the
                                                                                                                validation workshop by participant




                                                               What activities are planned to achieve the above mentioned
        ACTIVITIES
                                                               results?

    Methods of implementation                                  The project will involve a study on the PPP potential and the required measures for
    (e.g. workshops, short term experts…)                      the creation of a more conducive environment. The study will be presented and
    and reasons for the proposed                               validated at regional workshop.
    methodology [2.5.1]

    Title, and as much as possible, detailed                   1- Draft an inception report on the basis of the methodology proposed and
    description of each activity to be                            the coordination meeting with the EIB in Luxembourg and with relevant
    undertaken to produce the results,                            stakeholders. Prepare the stakeholders meeting in St Lucia
    justifying the choice of the activities
    and specifying where applicable the role
                                                                  (identification of stakeholders able to contribute to the study)
    of each partner (or associates or                          2- Hold a 2-day stakeholders meeting in Castries, St Lucia5 (around 20
    subcontractors) in the activities. [2.5.2]
                                                                  persons, 2 days)
                                                               3- Undertake a study on the potential for PPPs in the OECS and Barbados
                                                                  (in terms of sectors and types of PPPs required)
                                                               4- Assess the investment climate in OECS and Barbados, identify major
                                                                  bottlenecks for the use of PPPs and prepare a draft road map for policy
                                                                  and regulatory reforms
                                                               5- Circulate the study on the potential for PPPs, the assessment of the
                                                                  investment climate and the roadmap for policy & regulatory reforms
                                                                  among key stakeholders
                                                               6- Finalize the study on the potential for PPPs and the corresponding
                                                                  roadmap (including publication once approved) on the basis of the feed-
                                                                  back received from key stakeholders (final report)
                                                               7- Prepare and hold a 1-day Debriefing meeting in Brussels (ACP
                                                                  Secretariat) or in Luxembourg
                                                               A validation meeting with key stakeholders and potential investors may be
                                                               organised as follow-up action if the study has the power to trigger sufficient
                                                               interest and momentum.

5   Where the Secretariat of the OECS is based




ACP Business Climate Facility (BizClim)                                                                           Manual of Procedures
10 ACP RPR 015                                                                                 Activity Implementation Proposal (AIP)
                                                                                                                              Page | 7
 LIST MEANS, INPUTS AND TIME LEADS [2.5.3]

    Means, inputs and time leads               Team Leader (60 working days)
    In line with international and
     standard costs and timeframes              PPP expert (50 working days)
                                                Event coordinator (18 working days)



 Ro l es & Re s po n s ib i li t ie s            How the applicant and its partner(s) is intended to contribute to the
 [2 .6 ]                                         intervention?

 Applicant:                                      Will be responsible for all coordination, guidance and advice.

 Partner 1:


 Partner 2:


 Partner 3:




 PMU ACTIONS                              What PMU actions are needed to put in place and follow-up the Action

 Start-up Phase                           May 1st, 2011

 Implementation phase

 Closing phase

 Other



 COMMENTS & REMARKS                       In case the applicant has made any comments and remarks regarding the
 OF THE APPLICANT                         intervention, indicate it here
 [2.11]




ACP Business Climate Facility (BizClim)                                                            Manual of Procedures
10 ACP RPR 015                                                                  Activity Implementation Proposal (AIP)
                                                                                                               Page | 8
                                                           TIMETABLE


                                                             Month      1   2    3     4      5     6      7     8
     Activity

     Draft an inception report on the basis of the methodology
     proposed and the coordination meeting with the EIB in
     Luxembourg and with relevant stakeholders. Prepare the
     stakeholders meeting in St Lucia (identification of stakeholders
     able to contribute to the study)

     Hold a 2-day stakeholders meeting in Castries, St Lucia6
     (around 20 persons, 2 days)



     Undertake a study on the potential for PPPs in the OECS
     and Barbados (in terms of sectors and types of PPPs
     required)

     Assess the investment climate in OECS and Barbados,
     identify major bottlenecks for the use of PPPs and prepare a
     draft road map for policy and regulatory reforms

     Circulate the study on the potential for PPPs, the assessment of
     the investment climate and the roadmap for policy & regulatory
     reforms among key stakeholders

     Finalize the study on the potential for PPPs and the
     corresponding roadmap (including publication once approved)
     on the basis of the feed-back received from key stakeholders

     Prepare and hold a 1-day Debriefing meeting in Brussels (ACP
     Secretariat) or in Luxembourg (final report)




6   Where the Secretariat of the OECS is based




ACP Business Climate Facility (BizClim)                                                            Manual of Procedures
10 ACP RPR 015                                                                  Activity Implementation Proposal (AIP)
                                                                                                               Page | 9
                                                      BUDGET
               Capacity building program to enhance public officials’ capacity to design and implement PPP
                               projects in infrastructure, both at regional and country level.

                                             1.a. TEAM COMPOSITION AND FEES IN €

                                                                                                    Number of
                      Name of the expert                   Cat. (1)          Unit price              working    TOTAL PRICE
                                                                                                      days

         Key Expert 1: Team Leader                            S.              1.000 €                  60             60.000 €
         Key Expert 2: PPP expert                             S.              1.000 €                  50             50.000 €
         Expert in administration & logistic s                S.               600 €                   18             10.800 €
         (1)
             Two c ategories: S., Senior, > 10 years of relevant experienc e ; J., Junior, < 3 years
                                                                                                                    120.800 €
         relevant experienc e

                 1.b. OTHER COSTS IN € (to be included in fees in the budget presented by the tenderer)

                                                                      Quantity    Unit Price                TOTAL PRICE
         Organisation of ad hoc meetings, offic e c osts                 1              1.000 €                           1.000 €

         Travel of experts from their plac e of residenc e to the        0              1.500 €                               0€
         loc ation of the assignment

         Per diem for experts in the loc ation of the assignment         0                243 €                               0€


         TOTAL OF OTHER COSTS                                                                                         1.000 €

         TOTAL OF FEES and OTHER COSTS (1.a+1.b)                                                                    121.800 €

                                  2. REIMBURSABLE COSTS IN € - INCIDENTAL EXPENDITURE

                                                                      Quantity    Unit Price                TOTAL PRICE
         Travel costs of Experts
         International travel                                             8             2.000 €                       16.000 €
         Regional travel                                                  6               500 €                        3.000 €
         Max. Per diem (average based on per diem for St Luc ia)         46               214 €                        9.844 €

         Production & publication of reports
         Translation, Public ation & dissemination of the study          1              5.000 €                           5.000 €
         and roadmap

         Stakeholders workshop (2 day, 20 participants)
         Conferenc e Room & equipment (inc luding rec ording of          2              1.300 €                           2.600 €
         disc ussions)
         Conferenc e kit & Sensitization material                       20                 20   €                           400   €
         Regional travel for partic ipants                              10                500   €                         5.000   €
         Per diem partic ipants                                         20                214   €                         4.280   €
         Loc al staff for the workshop (hostesses, administrative        1              1.000   €                         1.000   €
         assistanc e, c ommunic ation expert, designer, etc .)

         Lunc h (for partic ipants not entitled to a per diem) &         1              1.520 €                           1.520 €
         c oc ktail


         Stakeholders workshop (1/2 day, 30 participants)
         Conferenc e Room                                                1                500 €                             500 €
         Conferenc e kit                                                20                 20 €                             400 €
         Loc al staff for the workshop (hostesses, administrative        1              1.000 €                           1.000 €
         assistanc e, c ommunic ation expert, designer, etc .)

         Coc ktail                                                       1              1.000 €                           1.000 €


         TOTAL OF REIMBURSABLE COSTS (3)                                                                             51.544 €

         EXPENDITURE VERIFICATION                                                                                     1.500 €

         GRAND TOTAL                                                                                                174.844 €




ACP Business Climate Facility (BizClim)                                                               Manual of Procedures
10 ACP RPR 015                                                                     Activity Implementation Proposal (AIP)
                                                                                                                 Page | 10

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:6
posted:1/2/2013
language:Unknown
pages:12