					  December 2012

Continued Closure of Gilbert Street                                                                   Duration of work
                                                                                                       Gilbert Street will be
As part of the work to build the new Crossrail western ticket hall at                                   closed until December ,
Bond Street, our contractor Costain Skanska Joint Venture (CSJV)                                        2013
will be maintaining the closure of Gilbert Street between Weighhouse                                   Site shut down during
Street and St Anselms Place from the 21 December 2012.                                                  Christmas between the
                                                                                                        22 December to 2
The purpose of this closure is to provide temporary welfare facilities                                  January 2013
on the worksite for the increased workforce as we continue to
                                                                                                       Core working hours
excavate the ticket hall down to platform level. It is important to be                                  Mon-Fri 8am until 6pm,
able to provide nearby facilities for those operatives working under                                    Sat 8am until 1pm.
the ground floor slab to remove the excavated material.
                                                                                                       From January 2013
Gilbert Street will remain closed subject to consent and conditions                                     extended working
                                                                                                        hours for excavation
until late December 2013. To maintain safety, hoarding will remain
                                                                                                        will be Mon - Fri 6pm to
along the western kerb line of Gilbert Street and vehicle marshals will                                 8pm, Sat 1pm to 6pm.
be present at all times to allow for deliveries into the site through the
                                                                                                       One hour start up and
north western site entrance.                                                                            shut down periods are
                                                                                                        also permitted.
Vehicular access to properties in St Anselm’s Place will be provided
from Brook Street with Gilbert Street being made two-way between                                      What to expect
Brook Street and St Anselms Place. Pedestrian access will be
                                                                                                       Continued closure of
maintained along Gilbert Street as the footpath will be kept open.
                                                                                                        Gilbert St between St
The temporary welfare accommodation will be two stories high. While                                     Anselms Place and
                                                                                                        Weighhouse Street
it will be visible over the hoarding any windows facing the residential
flats will be obscured.                                                                                Extended working
                                                                                                        hours for excavation
Where possible we will assist with special access/delivery needs
while this closure is in place and we encourage you to call us in                                     What we will do
advance of these works so that we can discuss any necessary                                            Continued traffic
arrangements.                                                                                           diversions in place
                                                                                                       Two-way operation for
 From January we will also be using extedned working hours on the
                                                                                                        Gilbert St between
 western ticket hall for excavation works only (including supporting                                    Brook Street and St
 surface equipment) under the newly laid ground floor slab.                                             Anselms Place
We apologise in advance for any inconvenient caused as a result of                                     Monitor noise,
our works. If you have any queries, please contact the Crossrail 24-                                    vibration and dust and
                                                                                                        keep within permitted
public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk                                      levels
                                                                                                       Traffic marshals on site
                                                                                                        to help with traffic and
                                                                                                        vehicle access
 We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
 Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
 Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
 Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
 Crossrail services will commence through the central tunnelled section in late 2018
 followed by a phased introduction of services along the rest of the Crossrail route.         C411-XRL-Z-XBU-C125_WS086-50043
About Crossrail
 Crossrail is the new high frequency, convenient and
 accessible railway for London and the South East.

 When the service opens Crossrail trains will travel
 from Maidenhead and Heathrow in the west to
 Shenfield and Abbey Wood in the east via new twin
 tunnels under central London. It will link Heathrow
 Airport, the West End, the City of London and
 Canary Wharf.

 Travelling on Crossrail will dramatically reduce
 journey times:

                                                        With
 Example journey times in minutes          Now
                                                      Crossrail

 Slough – Tottenham Court Road              55            32

 Romford – Bond Street                      43            35

 Whitechapel – Abbey Wood                   49            15

 Ealing Broadway – Farringdon               38            17

 Heathrow – Liverpool Street                55            32

 Heathrow – Canary Wharf                    71            40

 Maidenhead – Liverpool Street              71            46

 Paddington - Canary Wharf                  30            16


Drop in to our Visitor Information Centres

West End 16-18 St Giles High Street, WC2H 8LN,
Open Tuesdays and Thursdays 11.00 to 19.00

 Whitechapel Idea Store, 321 Whitechapel Road, E1
1BU Open Mondays and Wednesdays 11.00 to 19.00

Bond Street Community Liaison Panel
Crossrail run a community liaison panel for each
central London Station to keep local community
representatives informed of progress & plans. If you
would like further information please contact
crossrailliaisonpanels@crossrail.co.uk


                    QR Code
                    Scan with your mobile device to be taken to
                    the ‘Near You’ section of our website



   We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
   Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
   Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
   Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
   Crossrail services will commence through the central tunnelled section in late 2018
   followed by a phased introduction of services along the rest of the Crossrail route.         C411-XRL-Z-XBU-C125_WS086-50043

				