B-7 Project Information
Project owner                 Brushy Creek Regional Utility Authority, TX                    Project name             Raw and Treated Water Pipeline Program
General description of project
SJL constructed 24,069 lf of 78” steel water main and associated appurtenances and 330 lf of 102” tunnels for the raw water program and 7,598 lf of 78” steel water main and associated
appurtenances and 1,395 lf of 102” tunnels for the treated water program. (See attached Project Information Appendix 6 for more information)
Project Budget and Schedule Performance
                              Budget history                                                                                 Schedule performance
                                                                  % of Bid
                                            Amount                                                                                                                     Date              Days
                                                                  Amount
Bid                                 $27,506,079                N/A             Notice to Proceed                                                                10/19/2009             N/A
Change orders                       $510,824                   1.86%           Contract Substantial Completion date at Notice to Proceed                        7/11/2011              630
Owner enhancements                  $153,444                   0.56%           Contract final completion date at Notice to Proceed                              10/19/2011             730
Unforeseen conditions               $357,379                   1.30%           Change Order authorized Substantial Completion date                              9/22/2011              703
Design issues                       $0                         NA              Change Order authorized final completion date                                    2/20/2012              854
Total                              $510,824                  1.86%           Actual / estimated Substantial Completion date                                 9/22/2011               703
Final cost                         $28,016,903               101.86%         Actual / estimated final completion date                                       2/1/2012                835
Key Project Personnel
                                                                                                                Project
                                                                                 Project Manager                                           Safety Manager          Quality Control Manager
                                                                                                             Superintendent
Name                                                                         David Dickerson             Ken Glover                  Kyle Duke                    Sam Montoya
Percentage of time devoted to the Project.                                   50%                         100%                        20%                          50%
Proposed for this Project.                                                   Yes                         No                          Yes                          No
Did Individual start and complete the project?                               Yes                         No                          Yes                          Yes
If not, who started or completed the Project in their place.                 N/A                         Ken Menebroker              N/A                          N/A
                                                                                                         Local Staff Became
Reason for change.                                                           N/A                         Available to Complete       N/A                          N/A
                                                                                                         Project.
Reference Contact Information (listing names indicates approval to contacting the names individuals as a reference)
                                       Name                   Title/ position                 Organization             Telephone                          E-mail
Owner                        Mike Thuss                   Project Manager            BCRUA                      512-215-9151                mthus@bcrua.org
Designer                     Glenn Bridges                Project Engineer           Jacobs Engineering         512-314-3100                glenn.a.bridges@jacobs.com
Construction Manager         N/A
Surety                       Garnett Elliot               Assistant Secretary        Liberty Mutual             610-832-8240                garnett.elliot@libertymutual.com
Issues / disputes resolved or pending resolution by arbitration, litigation or dispute review boards
Number of issues                Total amount involved in                                Number of issues            Total amount involved in
                      0                                           $0                                       0                                           $0
resolved:                       resolved issues:                                        pending:                    resolved Issues:

Statement of Qualifications Outlines and Forms
CMD11269 – Ward County Pipeline – Contracts A & B                                                                                                                             00450a-9
                                                     Attachment B




Statement of Qualifications Outlines and Forms
CMD11269 – Ward County Pipeline – Contracts A & B   00450a-9

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:8
posted:12/5/2012
language:Unknown
pages:2