Installation Guidelines - NCMA
Document Sample


Recommended Installation Guidelines
Recommended Installation Guidelines
NCMA
Segmental Retaining
Wall Installation
Guide (2010)
Recommended Installation Guidelines
Construction Planning
Excavation
Preparing the Leveling Pad
Place Drainage Pipe
Installing Base Course
Installing Facing Units
Installing Gravel Fill
Place Infill Soil
Compaction
Installing Geosynthetic Reinforcement
Capping and Grading
Recommended Installation Guidelines
Recommended Installation Guidelines
Granular
Compacted to 95%
(ASTM D-698)
Minimum size:
6” Thick
6” Wider than
base each way
Cover drain
Recommended Installation Guidelines
Recommended Installation Guidelines
Important to address subsurface water
PVC, ABS or corrugated pipe
4” minimum
Correct side up
Geotextile wrap
Slope to drain
Daylight drain
Tie into stormwater
Recommended Installation Guidelines
Most important course in the wall
Determines trueness of the finished wall
Uniform bearing on leveling pad is essential
Recommended Installation Guidelines
Must be level in both directions
Use string line and level for alignment
Use string line to achieve smooth radii
Use on molded face only (not split face)
Recommended Installation Guidelines
Recommended Installation Guidelines
Fill voids with gravel fill
Compact with hand-operated plate vibrator (250 lb. minimum)
3 feet from back of wall
95% ASTM D-698
Recommended Installation Guidelines
Recommended Installation Guidelines
Tolerance for completed wall
+/- 1.25” over 10’ distance
Both vertical and horizontal
Recommended Installation Guidelines
Recommended Installation Guidelines
• Place & compact infill soil behind aggregate
• Compact carefully
• 95% ASTM D-698
Recommended Installation Guidelines
Recommended Installation Guidelines
Ensure aggregate & infill soil are level
Cut to length plus facing unit depth
Clean debris off top of unit
DO NOT OVERLAP!!!
Recommended Installation Guidelines
Recommended Installation Guidelines
6” of backfill before
using vehicles
No turning of
vehicles
No sudden breaking
or sharp turns
Keep heavy
equipment no closer
than 3’ of wall
Recommended Installation Guidelines
Recommended Installation Guidelines
Concave corners and radii
Recommended Installation Guidelines
Convex corners and radii:
3” of Soil between overlap
Optionally, skip courses
Recommended Installation Guidelines
Install cap blocks
with adhesive
Ensure drainage
away from SRW
system
Grade drainage
swale
Minimum 8” low
permeable soil
Vegetate slopes
Recommended Installation Guidelines
Detailing
Get documents about "