auditorium by xuyuzhu

VIEWS: 4 PAGES: 14

									Seattle Pacific University

AUDITORIUM / CHAPEL



    LMN ARCHITECTS
                MISSION

•   Determine Site Feasibility
•   Explore Design Character & Image
•   Estimate Cost
•   Outline Schedule
          SITE FEASIBILITY
•   Highly visible site
•   Landmark qualities
•   Campus gateway
•   Adequate area
•   Restricted building height
           SITE PLANNING

•   Relationship to street
•   Relationship to campus
•   Entry plaza
•   Lobby-Auditorium concept
               PROGRAM
•   SPU
•   Concerts
•   Chapel
•   Speakers

• Local orchestras & performers
            ARCHITECTURE
• ACOUSTICS                • ROOM SHAPE

•   Instrumental music     • Proportions
•   Choral music           • Seating layout
•   Organ music            • Character
•   Congregation singing
•   Spoken word
          COST ESTIMATE
• Construction cost   $23,000,000
• Soft costs            7,500,000

• Project cost        $30,500,000

• Escalation          $33,500,000 year 2003
           SCHEDULE
           3 1/2 to 4 years

• Design………………...One year

• Permitting……………..Six - 12 months

• Construction…………..Two years

								