Presentation for the International Transport Forum
Shared by: zMNeoq10
-
Stats
- views:
- 7
- posted:
- 11/8/2012
- language:
- Unknown
- pages:
- 12
Document Sample


Presentation for the International
Transport Forum
Jean Shaoul, Anne
Stafford and
Pam Stapleton
Who bears risks in practice?
Transport projects in the UK in rail, roads and air
traffic control (and other sectors) examining the
financial costs and rewards to various stakeholders.
Evidence base is financial statements of the
partners, official reports, statistical sources research
literature and the press.
Significant proportion of UK transport projects by
capital value have collapsed / been terminated or
been re-negotiated - £35bn of £91bn.
London Underground
General assumption – Investment scaled back –
commercial expertise will slow and over budget
ensure viable projects Subsidies 5x previous
Size – significant – expected Guarantees on debt
to provide £30bn investment Letter of comfort
over 30 years
Contractual incentives
Intention was 30% savings limited impact
on costs
Metronet companies
Terminate subsidies bankrupt and TfL ownership
Taxpayers / users bore the
cost
National Railways - Three rounds of
franchises
Purpose of privatisation Renegotiation of
Competitive forces – 25 franchises – several
franchises to11 cos. rounds
Outcomes History of over
– Reduction in competition optimistic bids –
– Subsidies doubled assumptions of 10%
– Dividends paid out of growth without
subsidy precedent
– Poor performance Ability to hand back the
against targets that were keys with limited liability
no more challenging
Role of the regulator
RAB model Metronet – suffered
– Deals with time- as the regulator
inconsistency found it had not
problem been efficient
– Guarantees return
Rail – regulator has
for investors if they
operate efficiently not ensured good
outcomes for
customers/ taxpayer
Are PPPs a new phenomena?
What is different about PPP?
Our focus is on
– Use of the private sector as a financial intermediary – and
the associated increase in the cost of finance
– Complex and opaque organisational structures – designed
to ring fence each individual project – reducing the senior
debt lenders’ risk exposure
– Increasing proportions of public money spent outside the
direct control of government together with lack of
transparency of financial reporting
Cost of finance debate 1
Costs of public borrowing < private finance
Taxpayer as holder of equity risk
– EIB Helm (2010) 3 elements to equity risk
bankruptcy / CAPEX / political and regulatory risk.
– Factoring in equity risk private finance is costlier.
– Risks vary between private sector and taxpayer -
contractor being ‘on time’ and the non-cash cost
to taxpayers of a late bridge
Cost of finance debate 2
Post financial crisis the gap is widening in
countries like the UK but many of the risks of
the specific projects are no greater than
previously
Small differences in cost can represent very
large absolute amounts
Efficiency, innovation and the
‘only game in town’
Only game in town – reduces competition /
provides perverse incentives to bias bids –
PPP almost always better than PSC
Independent evidence on efficiency is mixed
and on innovation is limited
Efficiency often equated with ‘on time and
budget’ but without consideration of actual
total time taken or cost incurred
Risk transfer
Risk transfer is absolutely central to the PPP rationale –
argument is this off-sets the higher costs of finance.
IMF – warning about overpricing of risk adding cost to PPP
In practice:
– Difficult to find optimal allocations of risk (a/c rules tend to >
inappropriate risk transfer)
– Demand risk very problematical
– Evidence on RT in practice is mixed
– Low penalties relative to total payment
– Inability or reluctance to enforce penalties
– Legally or practically difficult to terminate partnerships
Conclusions 1
Experience of the UK’s transport PPPs:
– Rail projects failed to deliver the outputs despite receiving
more subsidy than under public ownership
– Using the private sector as financial intermediary adds cost
/ complexity / bureaucracy and risk
– Partnerships have a higher cost of finance than
conventional public procurement
– Risk transfer is supposedly from the state to the private
sector but in practice is from the consortia to subcontractors
and their work forces and to the public as users / tax payers.
Conclusions 2
Internationally the capital intensive nature of
transport means it is very difficult to achieve a return
attractive to private sector – especially in a
geographically comprehensive service
Higher cost of finance is especially important in
capital intensive projects
Transport projects have wide ranging benefits that
are greater than the benefits to users and investors –
underinvestment by private sector classic case for
public funding and financing – in the public interest.
Related docs
Other docs by zMNeoq10
The following files were incorrectly listed on the respective Public Notice PN Dates
Views: 0 | Downloads: 0
Get documents about "