									Mechanical FDISV Schedule & Status               5/23/2011 ISO/TC20/SC14/WG1

             Status & Schedule - 10785 Bellows
Date: 23 May 2011
FDIS/V: Start date on 2011-06-??
       Close date on 2011-??-??
Ukraine’s comments resulted in a negative vote because of definition
issues about terminology, so FDISs are required for 10785 and 10786.
DIS Comments about 10785 from France resolved by M. Ikeuchi and
P. Blanchard in Brazil WG1, had been confirmed with PL, M. Watanabe.
Ukraine had agreed the DIS comment resolutions by PL.
PL had resolved DIS/V comments and answered on 18/April/2011,
including all questions from ISO/SC14.
FDIS will start soon
SC14 informed PL that FDIS is being processed at ISO Central Secretariat.



                                                                            1
Mechanical FDISV Schedule & Status                  5/23/2011 ISO/TC20/SC14/WG1

             Status & Schedule - 10785 Bellows
    Initial concept proposed at 23th Meeting in France – May/2005
    NWIP with outline of standard presented at 24th WG1 in Germany
                                                        – Nov/2005
    Modified NWIP presented at 26th Meeting in France – Oct/2006
    Vote pass / Approved as NWI                       – Nov/2006
    Assigned to 14N434/AWI 10785 as WD                – Apr/2007
    WD distributed to countries concerned for review – May/2007
    CD/C registered                                   – April/2008
    CD/V pass                                          – Oct/2009
     DIS registered                                    – April/2010
    DIS/V pass                                          – October/2010
    FDIS registered                                     – Jun/2011?


                                                                             2
Mechanical FDISV Schedule & Status        5/23/2011 ISO/TC20/SC14/WG1

            Status & Schedule - 10786 Structure
 Date: 23 May 2011
 FDIS/V: Start date on 2011-04-08
        Close date on 2011-06-08
 PL had resolved DIS/V comments and answered, including
 all questions from ISO/SC14.
 PL asks P-members affirmative voting before the date.

 Recommendation to other Mechanical Standards
 About terminology changes for other standards, every
 structure document can be reconciled together at the moment
 of each SR.
 It will be discussed in the agenda for overview of Mechanical
 SR.

                                                                   3
Mechanical FDISV Schedule & Status                     5/23/2011 ISO/TC20/SC14/WG1

            Status & Schedule - 10786 Structure
  Date: 23 May 2011
           NWIP circulation           Aug 9, 2006
           Voting closed             Oct 25, 2006
           NWI voting report           Jan 2, 2007
           AWI / WD                   April 9, 2007
           CD                         April 9, 2008
           CD/C                       August 1, 2008 (by SC14)
                                     (July, ECSS recommendation)
           CD/V                       May 13, 2009 <- Oct 9, 2008
           DIS registration           Mar 17, 2009
           DIS/V                      June, 2010 – November, 2010
           FDIS/V                     April, 2011 – June, 2011
           IS target date             From 2011-01-02 to 2011-08-31
                                      (Extended target date)