scope of work template
							                              Cabinet Member Report
                     Date:    8 January 2010

                  Subject:    Q132 Scheme and Estimate Approval for Phase 5 of
                              Queens Park Structural Repairs and void refurbishment


Summary
CityWest Homes, on behalf of Westminster City Council, wishes to undertake
Refurbishment Works to the following Void properties:

       18 Enbrook Street
       23 Galton Street
       57 Kilravock Street
       30 Second Avenue
       14 Oliphant Street

The total cost of this contract is £354,264 inclusive of professional fees and
contingencies and will be met from Westminster Community Homes Ltd.


Recommendations

That in accordance with the requirements of Financial Regulation B8 the Cabinet
Member for Housing approves of the total expenditure of £354,264 inclusive of
contingencies and professional fees.
                            Cabinet Member
City of Westminster         Report
      Cabinet Member:       Cabinet Member for Housing


                   Date:    8 January 2010


         Classification:    For General Release


         Title of Report:   Q132 Scheme and Estimate Approval for Phase 5 of
                            Queens Park Structural Repairs and void
                            refurbishment


              Report of:    Chief Executive, CityWest Homes


       Wards involved:      Queens Park


         Policy context:    Housing Service Aim 1 – To deliver and maintain
                            Decent Homes, improve energy efficiency and invest
                            in ‘beyond Decent Homes’.

    Financial summary:      The total cost of this contract is £354,264 inclusive of
                            professional fees and contingencies will be met from
                            Westminster Community Homes Ltd.

         Report Author:     Max Hills


        Contact details     Tel: 020 7245 2254
                            Email: mhills@cwh.org.uk
1.    Background Information
1.1   Queens Park phase 4 is currently on site and completing; phase 5 will contain
      similar work types. All previous schemes complied with statutory legislation such
      as compliance with current Building Regulations, the Health & Safety at Work
      Act and CDM regulations.


                             Date                      Weekly      Rent Loss to
          Properties                     Bedspace
                             Void                      Rent        Date(22-11-09)
          18 Enbrook
                             16:02:09    3 Bed         £118.96     £4,679.38
          Street
          23 Galton
                             06:04:09    2 Bed         £110.18     £3,588.99
          Street
          57 Kilravock
                             06:04:09     2 Bed        £110.18     £3,588.99
          Street
          30 Second
                             19:10:09    2 Bed         £106.40     £532.00
          Avenue
          14 Oliphant
                             27:04:09     2 Bed        £112.98     £3,353.40
          Street

1.2   The 5 properties are all late Victorian terraced within the conservation area of
      Queens Park. The front elevations have decorative porches with pitched roofs
      which are shared between two properties. They have the usual rear projection,
      which is shared with the adjacent house. The houses have cut timber roofs and
      timber floors spanning onto load bearing masonry walls. They also have very
      shallow spread foundations bearing on crushed brick on highly shrinkable
      London Clay.

1.3   The constructors will be selected using CompeteFor procurement system.

1.4   Works will be procured in agreement with CityWest Homes Supply Chain.


2.    Detail
2.1   The five properties will require extensive refurbishment and some structural
      repairs.

      The Works will comprise the following:-

      Asbestos removal
      Full electrical rewire
      Installation of gas central heating
      Renewal of lath and plaster ceiling
      Lime Plastering
      Extensive plastering, crack repair and redecoration
      New kitchen and bathroom
      Repair and renewal to timberwork – floorboards & joists
      Repair/renewal to sash and casement windows
      Drain surveys
      Helibeam masonry repairs
      Underpinning and concrete ties
      DPC works
      Loft insulation

2.2   All works will comply with Conservation Area guide lines.

2.3   The following programme is proposed

       Scheme & Estimate Contracts Board              17th December 2009
       Approval
       Section 20 Notice of Intention                                 N/A
       Scheme & Estimate Cabinet Member                     February 2010
       Approval
       Tenders Issued                                      February 2010
       Tender Return                                          March 2010
       Tender Acceptance Contracts Board                       April 2010
       Tender Acceptance Cabinet Member                               N/A
       Section 20 Notice of Estimate                                  N/A
       Contract Let                                            May 2010
       Start on Site                                           May 2010
       Monitoring report Contract Board                               N/A
       Practical Completion                               September 2010
       Final Account                                      November 2010
       End of Defects                                     September 2011


3.    Financial Implications
3.1   The cost of the work is estimated at £354,264 inclusive of professional fees. The
      detailed financial break down and spend profile is attached at Appendix 1.

3.2   The funding for this scheme will initially come from the HRA Capital Voids
      Budget for 2010/2011. At a later date the funding will be transferred by WCC
      from the Westminster Community Homes budget.

3.3   Funding for this scheme has been approved.

3.4   The on-going maintenance will relate to the central heating boilers and any
      electrical testing that is required as part of our PPM regime. This will be funded
      from the subsequent year’s revenue budget.

3.5   CityWest Homes will ensure Value for Money (VMF) has been achieved by
      carrying out VFM reviews at all key stages of the Scheme and Estimate
      development. Historical data from previous schemes has been used to build up
      costs
3.6   Works will be procured using CWH CompleteFor or the Frameworx procurement
      system and the JCT Intermediate form of contract. Value for money will be
      checked at the tender acceptance stage with submitted rates from bidders
      compared between themselves and to previously tendered rates.

4.    Legal Implications
4.1   There are no legal implications arising from this report.

5.    Outstanding Issues
5.1   There are no outstanding issues arising from this report.


6.    Lessee Implications
6.1   There are no Lessee implications arising from this report as works are to void
      properties only.

7.    Consultation
7.1   All residents within the immediate local will receive a news letter informing them
      of:

          Works time scales/duration of works
          Contractor
          Out of hours emergency number
          Working hours
          Schedule of condition surveys

7.2   Where applicable party wall notices will be served.

7.3   Resident consultation is outlined in the table below:

                                                  Resident
             Date             Type                                   Actions
                                                 comments
          March 2010       News letter
           May 2010        News letter


7.4   This scheme is in the Queens Park Ward. Ward Members have been consulted
      on this scheme.

7.5   Cllr Paul Dimoldenberg strongly supports the proposed works.
8.       Health and Safety Issues
8.1      Works will fall under the Construction (Design and Management) Regulations
         2007 (CDM regulations) the consultant will appoint a CDM Co-ordinator to
         ensure that all CDM and Health and Safety issues have been addressed.

8.2     Possible health and safety risks:
           Asbestos
           Excavation support
           Removal of waste, cuts from materials
           Skin and eye damage when removing materials, such as glazing
           Ingestion – dust, grit, chemicals etc
           General manual handling hazards
           Working with sewage pipes
           Falling from height
           Site access and egress

         These will be covered in the construction phase Health and Safety plan.


9.       Risk Appraisals & Management
9.1     All risks and risk management will be coved by CDM regulations and the
        constructors Health and Safety Plan.

10.     Crime and Disorder Act 1998 Implications
10.1    There are no Crime and Disorder implication arising from this report.


11.      Disability Discrimination Act (DDA) 2005 Considerations
11.1    There are no DDA considerations arising from this report.


12.      Environmental Matters
12.1 All properties will be fitted with energy efficient boiler, draft proofing to windows
     and 250mm loft insulation.

13.      Reason for Decision
13.1 The works highlighted in this report are deemed to be necessary in order to
     bring these void properties up to the Decent Homes Standard.


        If you have any queries about this report or wish to inspect one of the
      background papers please contact Max Hills on 020 7245 2254, fax number
                       020 7245 2260, email mhills@cwh.org.uk
Background Papers

None


Appendices

Appendix 1 – Financial Breakdown tables
Appendix 1 – Financial Breakdown tables
Works Elements – Constructor only

Full electrical rewire                                                            21,000
Installation of gas central heating                                               20,000
Partitions                                                                         4,000
Renewal of lath and plaster ceilings                                              19,900
Extensive plastering, crack repair                                                36,500
Complete redecoration                                                             23,500
New bathrooms                                                                     17,500
New Kitchens                                                                      22,500
Repair and renewal to timber work, floor boards and joists                        22,500
Repair/renewal to sash and casement windows                                       23,750
Drain surveys                                                                      1,760
Drainage works                                                                     5,000
Helifix ties                                                                      13,750
DPC works                                                                         12,500
Loft insulation                                                                    1,450
TV aerial                                                                          4,000
Total Works Elements                                                             249,610
Risk Register
Work Elements – Constructor Only
For Example: (please remove or add where appropriate)
Asbestos removal                                                                   3,000
Underpinning                                                                       7,000
Structural surveys                                                                 3,500
Dry rot                                                                            5,500
Installation of gas/electrical meters                                              6,000

Total Risk Register                                                               25,000
TOTAL WORKS ELEMENTS & RISK REGISTER                                             274,610
Other Costs
Site specific overheads
Sub Total - Contract Works + Risk Register + Site Specific O/H                   274,610
Contractors prelims are anticipated to be 10%                                     27,461
Constructor O/H – x% (Included in work costs)                    x%
subtotal                                                                         302,071
Constructor Profit – x%                                               5%          15,104
Total Constructor Costs                                                          317,175
Design – Electrical                                                        N/A
Design - Mechanical                                                        N/A
Lead Design                                                                           -
Contract Admin, Lead Design and CDM Coordinator                       6%          19,031
Health and safety audit                                                               -
CWH Project Fees (includes PM, CoW, RCO)                              5%          15,859
CWH Central On-cost                                                                   -
Audit Fees                                                                         1,200
Legal fees                                                                         1,000
Procurement fees (CompeteFor/Cyntra)
Party wall surveyors                                             N/A
Provider Fees (covering Resident Consultation)                   N/A                  -
TOTAL S&E / AMP                                                                  354,264
     2009/2010 Forecast spend                                   -
     Feb 2010 - consultant 20% of fee                   3,806   -
                                                                -
     2010/2011 Forecast spend                                   -
     June 2010 - Contractor valuation 1                56,974   -
     June 2010 - Consultant upto valuation 1            3,045   -
     July 2010 - Contractor valuation 2                56,974   -
     July 2010 - Consultant upto valuation 2            3,045   -
     August 2010 - Contractor valuation 3              56,974   -
     August 2010 - Consultant upto valuation 3          3,045   -
     September 2010 - Contractor valuation 4           56,974   -
     September 2010 - Consultant upto valuation 4       3,045   -
     October 2010 - Contractor valuation 5             56,974   -
     October 2010 - Consultant upto valuation 5         3,045   -
     October 2010 - Audit, Legal, CWH project fee's    18,059
     2011/2012 Forcast send
      September 2011Retention                           7,304   -
RISK REGISTER                                          25,000   -

TOTAL                                                 354,265   -
For completion by the Cabinet Member for Housing


Declaration of Interest

   I have no interest to declare in respect of this report

    Signed ……………………………. Date ………………………………
    NAME: Cllr Philippa Roe, Cabinet Member for Housing

   I have to declare an interest

    State nature of interest ……..……………………………………………

    ………………………………………………………………………………..

    Signed ……………………………. Date …………………………………
    NAME: Cllr Philippa Roe, Cabinet Member for Housing

(N.B: If you have an interest you should seek advice as to whether it is appropriate to
make a decision in relation to this matter.)


For the reasons set out above, I agree the recommendations in the report entitled
Q132 Scheme and Estimate Approval for Phase 5 of Queens Park Structural
Repairs and void refurbishment and reject any alternative options which are referred
to but not recommended.

Signed ………………………………………………

Cabinet Member for Housing

Date …………………………………………………


    For Ward Specific Reports Only (Delete if report affects more than one
    Ward)

    In reaching this decision I have given due regard to any representations made
    by relevant Ward Members.


    Signed ………………………………………………

    Cabinet Member for Housing

    Date …………………………………………………
If you have any additional comment which you would want actioned in connection with
your decision you should discuss this with the report author and then set out your
comment below before the report and this pro-forma is returned to the Secretariat for
processing.

Additional comment: …………………………………………………………………

………………………………………………………………………………………….

………………………………………………………………………………………….


NOTE: If you do not wish to approve the recommendations, or wish to make an
alternative decision, it is important that you consult the report author, the Head of Legal
Services, the Director of Finance and, if there are staffing implications, the Director of
Human Resources (or their representatives) so that (1) you can be made aware of any
further relevant considerations that you should take into account before making the
decision and (2) your reasons for the decision can be properly identified and recorded,
as required by law.

Note to Cabinet Member: Your decision will now be published and copied to the
Members of the relevant Policy & Scrutiny Committee. If the decision falls within
the criteria for call-in, it will not be implemented until five working days have
elapsed for any call-in request to be received.

						
Other docs by IT4921X
NIAC 4 ISC
Views: 6  |  Downloads: 0
CV andrew cutts
Views: 1  |  Downloads: 0
Responding to our request
Views: 0  |  Downloads: 0
PowerPoint Presentation
Views: 0  |  Downloads: 0
schools smcps org
Views: 0  |  Downloads: 0
Age of Reforms Economic Philosophers
Views: 12  |  Downloads: 0
Profit Registration Form for Welcome 2012 1
Views: 1  |  Downloads: 0