					PMP Exam Preparation                                                    Frank Reveles, PMP
                                                                           March 11th, 2005


Study Session

Exercise 1. You are the project manager for a project with the following network
diagram

                    Task            Estimate in
                                    weeks
                        Start-A           2
                        Start-B           1
                         A-C              3
                         B-C           Dummy
                         C-D              4
                         B-E              1
                         D-F              4
                          E-F             2
                        F-End             1
                        E-End             5

1. What type of network diagram is this?


2. Draw the network diagram




3. Calculate all of the paths in this network diagram




4. What is the duration of the critical path of this network diagram?