					Bicycle Pedestrian Element


                 F. BICYCLE PEDESTRIAN ELEMENT
                                 Updated March 14, 2006
The MPO has defined its role in long range bicycle and pedestrian planning as limited to two
activities, so as not to duplicate or conflict with local governments’ bicycle and pedestrian
planning efforts. One is to identify bicycle and pedestrian facility improvements that are needed
along state highways and to adopt a financially feasible plan for retrofitting bicycle and
pedestrian improvements along state highways were no highway improvement projects are
planned. The other is to review local governments’ bicycle and pedestrian facility plans and
identify any inconsistencies or discontinuities that should be corrected at their borders or where
county roads penetrate cities.

Table F-1, pages F-2 to F-3, lists the bicycle and pedestrian improvement projects on state
highways where no highway improvement projects are called for in the 2030 highway element
that are included in the 2030 Bicycle Pedestrian Element. It also identifies which of the projects
are financially feasible by 2030 and which are designated contingent upon additional funding.
The locations of the projects are shown on the map provided as Figure F-1, page F-4.

The available revenue forecast includes the funds already set aside in FYs 2007/08-2009/10 in
FDOT’s work program, for which no projects have yet been programmed through FY 2009/10,
in addition to the $18,456,550 (in 2005 dollars) that will become available from FY 2010/11
through FY 2029/30 by continuing to set aside $1.5 million annually, as recommended in the
2030 financially feasible highway element. Deflated to 2005 dollars, the total amount available
through 2030 is $22,866,506. The estimated cost of implementing all the projects in Table F-1
amounts to $33,090,826, leaving a shortfall of $10,818,345.

It should be noted that while the first 14 projects in Table F-1 are ranked according to the 2005
Bicycle/Pedestrian Box Priorities that were adopted by the MPO on August 24th, after project #
21 the rest are not in any specific order.

The projects shown shaded in Table F-1 are projects that were included in the 2020 bicycle
pedestrian element. The projects in the unshaded rows (located on page two of Table F-1) are
new projects that were identified during the development of the 2030 bicycle pedestrian needs
assessment.

The remaining needed bicycle and pedestrian improvements along state highways that are
recommended for construction when state highway improvement projects identified as
financially feasible in the 2030 highway element are undertaken are identified in Table F-2.
(page F-5). The locations of these projects are also shown on the map in Figure F-1.

    Lee County Metropolitan Planning Organization   F-1-       2030 Long Range Transportation Plan
     December 7, 2005
                                                                                         Table F-1
                                    2030 BICYCLE/PEDESTRIAN RETROFIT NEEDS IDENTIFIED WHERE HIGHWAY IMPROVEMENTS ARE NOT PLANNED OR PROGRAMMED
                                                                                   Updated March 14, 2006

                                                                                                                                                          Project                                                                                                                    Cost of Feasible
                                                                                                              Fa- cility                      Length (in                                                                                Cost Estimate (in
          ID No.          Road Segment                        From                            To                               Side   #                  Length (in                                Notes                                                     Financial Feasibility       Projects
                                                                                                               Type                             miles)                                                                                      2005 $s)
                                                                                                                                                           miles)                                                                                                                      (in 2005 $s)

            1                                 College Pkwy                   Edinburgh Dr                     SW           W              1        0.22       0.22                                                                                 $51,766    Feasible by 2030                  $51,766
            2                                 Peck Ave                       Bayside Dr                       SW           W              1        0.08       0.08                                                                                 $98,024    Feasible by 2030                  $98,024
            3                                 Travers Ln                     Dean Way                         SW           W              1        0.33       0.33                                                                               $404,349     Feasible by 2030                $404,349
                    McGregor Blvd (SR 867)
            4                                 200' N of College Pkwy         Wilson Ave                       SW           E              1        0.57       0.57                                                                               $134,121     Feasible by 2030                $134,121
            5                                 Royal Palm Square Blvd         Colonial Blvd                    SW           E              1        0.25       0.25                                                                               $504,325     Feasible by 2030                $504,325
            6                                 Argyle Dr                      Georgetown/Davis Dr              SW           E              1        0.43       0.43                                                                               $867,439     Feasible by 2030                $867,439
                                                                                                                                                                   Should the interchange project at US 41 and Daniels Pkwy
            7                                 Daniels Pkwy                   College Pkwy                     BP           B              2        0.75       1.50 become financially feasible, this project should be shortened                 $619,028     Feasible by 2030                $619,028
                                                                                                                                                                   accordingly.

                                                                                                                                                                      This segment should be built with the interchange project at US
            8       US 41 (SR 45)             500' S of Daniels Pkwy         Daniels Pkwy                     SW           E              1        0.10       0.10                                                                                 $23,530    Feasible by 2030                  $23,530
                                                                                                                                                                      41 and Daniels Pkwy should it become financially feasible.

            9                                 College Pkwy                   Palm Dr                          BP           B              2        1.04       2.08                                                                               $858,385     Feasible by 2030                $858,385
           10                                 0.4 m N of Littleton Rd        Business US 41                   SW           W              1        0.82       0.82                                                                               $192,946     Feasible by 2030                $192,946
           11                                 Business US 41                 500' S of Del Prado Blvd         BP           W              1        0.81       0.81                                                                               $334,275     Feasible by 2030                $334,275
           12       Palm Beach Blvd (SR 80)   0.5 m E of Orange River Blvd   SR 31                            BP           N              1        1.96       1.96                                                                               $282,360     Feasible by 2030                $282,360
                                                                                                                                                                      This segment should be built as part of the 6 laning project
           13       Palm Beach Blvd (SR 80)   SR 31                          Buckingham Rd                    BP           N              1        2.51       2.51                                                                              $2,071,679    Feasible by 2030               $2,071,679
                                                                                                                                                                      should it be funded with SIS funds.
           14       SR 78 (Bayshore Rd)       Business US 41                 Hart Rd                          SW           S              1        1.10       1.10                                                                               $258,830     Feasible by 2030                $258,830
           15                                 500' S of Del Prado Blvd       Del Prado Blvd                   BP           E              1        0.81       0.81                                                                                 $28,143    Feasible by 2030                  $28,143
           16                                 Business US 41                 500' S of Del Prado Blvd         BP           E              1        0.81       0.81                                                                               $334,275     Feasible by 2030                $334,275
           17                                 0.4 m N of Littleton Rd        Business US 41                   SW           E              1        0.82       0.82                                                                               $192,946     Feasible by 2030                $192,946
                    US 41 (SR 45)
           18                                 Stockton Rd                    0.4 m N of Littleton Rd          SW           E              1        1.06       1.06                                                                               $258,830     Feasible by 2030                $258,830
           19                                 360' N of Pine Island Rd       Stockton Rd                      SW           E              1        0.35       0.35                                                                                 $88,590    Feasible by 2030                  $88,590
           20                                 Pine Island Rd                 300' N of Pine Island Rd         SW           E              1        0.09       0.09                                                                                 $21,177    Feasible by 2030                  $21,177
                                                                                                                                                                      Should the Colonial express lanes project prove financially
           21       Colonial Blvd (SR 884)    500' E of Metro                to existing Bike Path            SW           N              1        0.11       0.11                                                                                 $25,833    Feasible by 2030                  $25,833
                                                                                                                                                                      feasible, this project should be included in it.




A-2
           22       Palm Beach Blvd (SR 80)   Buckingham Rd                  Werner Rd                        BP           B              2        2.07       4.14                                                                              $1,708,516    Feasible by 2030               $1,708,516
           23                                 Pondella Rd                    US 41                            BP           N              1        2.35       2.35                                                                              $6,676,781   Not Feasible by 2030
                    Pine Island Rd (SR 78)
           24                                 Pondella Rd                    US 41                            SW           S              1        2.35       2.35                                                                               $756,745     Feasible by 2030                $756,745
                                                                                                                                                                      The I 75 interchange project should build 1/2 mile of the bike
           25       Palm Beach Blvd (SR 80)   Morse Plaza                    Orange River Blvd                BP           N              1        0.51       0.51                                                                              $1,047,149    Feasible by 2030               $1,047,149
                                                                                                                                                                      path.
           26       Palm Beach Blvd (SR 80)   Orange River Blvd              0.5 m E of Orange River Blvd     BP           N              1        0.50       0.50                                                                              $1,047,149    Feasible by 2030               $1,047,149
           27       McGregor Blvd             Winkler Rd                     Cleburne Dr                      SW           E              1        0.82       0.82                                                                               $192,946     Feasible by 2030                $192,946
           28       Metro Pkwy (SR 739)       US 41                          Six Mile Cypress Pkwy            SW           E              1        2.77       2.77                                                                               $282,360     Feasible by 2030                $282,360
           29                                 Chiquita Blvd                  Skyline Blvd                     BP           N              1        0.83       0.83                                                                               $685,692     Feasible by 2030                $685,692
           30                                 Chiquita Blvd                  Skyline Blvd                     SW           S              1        0.83       0.83                                                                              $1,047,149    Feasible by 2030               $1,047,149
                    Pine Island Rd (SR 78)
           31                                 Del Prado Blvd                 Pondella Rd                      BP           N              1        0.31       0.31                                                                              $1,047,149    Feasible by 2030               $1,047,149
           32                                 Del Prado Blvd                 Pondella Rd                      SW           S              1        0.31       0.31                                                                               $192,946     Feasible by 2030                $192,946
           33       Pine Island Rd (SR 78)    Skyline Blvd                   300' W of Santa Barbara Blvd     BP           N              1        1.40       2.80                                                                               $336,759     Feasible by 2030                $336,759
           34                                 300' W of Santa Barbara Blvd   Cultural Park Blvd               BP           N              1        2.40       2.40                                                                               $577,301     Feasible by 2030                $577,301
                    Pine Island Rd (SR 78)
           35                                 300' W of Santa Barbara Blvd   Cultural Park Blvd               SW           S              1        2.40       2.40                                                                               $434,400     Feasible by 2030                $434,400
           36       Fowler St (SR 739)        Hanson St                      Dr Martin Luther King, Jr Blvd   SW           E              1        1.26       1.26                                                                               $747,875     Feasible by 2030                $747,875
           37                                 Michigan Link                  Ortiz Ave                        SW           N              1        0.85       0.85                                                                               $595,490    Not Feasible by 2030
                                                                                                                                                                   These projects should be implemented with the 6-laning from
           38       SR 82/MLK Blvd            Ortiz Ave                      Park 82 Dr                       SW           B              2        0.27       0.54 Michigan Link to Park 82 Dr, should it be added to SIS plan                     $97,740    Feasible by 2030                  $97,740

           39                                 Ortiz Ave                      Park 82 Dr                       BL           B              2        0.27       0.54                                                                               $171,423     Feasible by 2030                $171,423
           41                                 Wallace Ave                    Owen Ave                         SW           N              1        0.70       0.70                                                                               $126,700    Not Feasible by 2030
                    SR 82/Immokalee Rd
           42                                 Owen Ave                       Vernon                           BP           N              1        0.66       0.66                                                                               $158,758    Not Feasible by 2030
           43       Vernon Ave                SR 82                          Meadow Rd                        BP           N              1        0.06       0.06 No road exists, but new bike path proposed.                                    $39,777    Not Feasible by 2030


      Shaded rows are projects from the 2020 Transportation Plan bicycle pedestrian element.
                                                                      Table F-1 -page two
                     2030 BICYCLE/PEDESTRIAN RETROFIT NEEDS IDENTIFIED WHERE HIGHWAY IMPROVEMENTS ARE NOT PLANNED OR PROGRAMMED

                                                                                                                                                       Project                                                                                                                 Cost of Feasible
                                                                                                           Fa- cility                      Length (in                                                                              Cost Estimate (in
          ID No.          Road Segment                       From                            To                             Side   #                  Length (in                              Notes                                                             100                Projects
                                                                                                            Type                             miles)                                                                                    2005 $s)
                                                                                                                                                        miles)                                                                                                                   (in 2005 $s)
                                                                                                                                                                   This project may be implemented with 6-laning from Teter Rd
           44                                 Vernon Ave                    40th St SW                     SW           N              1        3.13       3.13                                                                             $566,530    Not Feasible by 2030
                                                                                                                                                                   to Hendry County line if added to SIS plan
           45                                 Wallace Ave                   40th St SW                     SW           S              1        4.50       4.50                                                                             $814,500    Not Feasible by 2030
           46       SR 82/Immokalee Rd        Harcourt Ave                  Jaguar Blvd                    SW           N              1        4.25       4.25                                                                             $769,250    Not Feasible by 2030
           47                                 Alabama Rd                    Jaguar Blvd                    SW           S              1        2.05       2.05                                                                             $371,050    Not Feasible by 2030
           48                                 Jaguar Blvd                   Hedgewood St                   BP           N              1        0.17       0.17                                                                               $40,892   Not Feasible by 2030
           49                                 Hedgewood St                  Naples Ave S                   SW           N              1        4.51       4.51                                                                             $816,310    Not Feasible by 2030
           50       Naples Ave S              Meadow Rd                     SR 82/Immokalee Rd             BP           N              1        0.06       0.06 No road exists, but new bike path proposed.                                   $50,000   Not Feasible by 2030
                                                                                                                                                                This project may be implemented with 6-laning from Teter Rd
           51       SR 82/Immokalee Rd        Wildcat Dr                    Hendry County Line             SW           S              1        1.05       1.05                                                                             $190,050    Not Feasible by 2030
                                                                                                                                                                to Hendry County line if added to SIS plan
           52                                 AW Bulb Rd                    Cypress Lake Dr                SW           B              2        0.67       1.34                                                                             $242,540     Feasible by 2030               $242,540
                    McGregor Blvd
           53                                 Cypress Lake Dr               College Pkwy                   SW           B              2        0.81       1.62                                                                             $293,220     Feasible by 2030               $293,220




A-4
           54                                 Summerlin Rd                  500' S of Gladiolus Dr         BP           E              1        1.41       1.41                                                                             $339,164     Feasible by 2030               $339,164
                    San Carlos Blvd
           55                                 Summerlin Rd                  500' S of Gladiolus Dr         BP           W              1        1.41       1.41 Replace off-road sidewalk with new 12' bike path                            $339,164     Feasible by 2030               $339,164
           56                                 E of I 75                     Nalle Rd                       SW           B              2        0.55       1.10                                                                             $398,200     Feasible by 2030               $398,200
                    SR 78 (Bayshore Rd)
           57                                 E of I 75                     Nalle Rd                       BL           B              2        0.55       1.10                                                                             $698,390     Feasible by 2030               $698,390
           58       SR 739                    1800' N of Winkler Ave        Hanson St                      SW           B              2        0.81       1.62                                                                             $293,220     Feasible by 2030               $293,220
           59                                 Del Prado Blvd                Verano Drive/Durden Pkwy Ext   BP           B              2        1.40       2.80                                                                             $673,518     Feasible by 2030               $673,518
           60       US 41 (SR 45)             Pondella Rd                   Del Prado Blvd                 SW           B          2            4.32       8.64                                                                             $112,220     Feasible by 2030               $112,220
           61                                 Verano Dr/Durden Pkwy Ext.    Charlotte County Line          BP           B          2            2.02       4.04                                                                             $485,895     Feasible by 2030               $485,895
           62                                 Cultural Park Blvd            Del Prado Blvd                 BP           N          1            1.35       1.35                                                                             $324,732     Feasible by 2030               $324,732
                    Pine Island Rd (SR 78)
           63                                 Cultural Park Blvd            Del Prado Blvd                 SW           S          1            1.35       1.35                                                                             $244,350     Feasible by 2030               $244,350
                                                                                                                                                                                                Total Project Costs (in 2005 $s)         $33,684,851                                 $22,468,763

      Shaded rows are projects from the 2020 Transportation Plan bicycle pedestrian element.                                                                                          Available Funds (in 2005 $s) through 2030           22,866,506                                  22,866,506
                                                                                                                                                                                         Remaining Balance or (Underfunding)             (10,818,345)                                    397,743
Table D -2 (Continued)
                                                                                               Table F-2
                                                  BICYCLE/PEDESTRIAN IMPROVEMENTS TO BE BUILT AS PART OF FINANCIALLY FEASIBLE STATE HIGHWAY PROJECTS

                                                                                                                                      Facility          Length    Project Length   Width
                          ID No             Road Segment                               From                          To                          Side                                      Comments
                                                                                                                                       Type              (mile)        (mile)       (ft)
                           67     SR 78 (Pine Island Rd)                Burnt Store Rd                W of Chiquita Blvd                BP        N      2.05          2.05         10
                           68     SR 78 (Pine Island Rd)                Burnt Store Rd                W of Chiquita Blvd                SW        S      2.05          2.05         5
                           72     SR 739 (Metro Pkwy)                   US 41 (South Tamiami Trail)   Six Mile Cypress Pkwy             BP        W      2.77          2.77         8
                           73     SR 739 (Metro Pkwy)                   Six Mile Cypress Pkwy         Daniels Pkwy                      SW        B      1.25          2.5          5
                           74     SR 739 (Metro Pkwy)                   Six Mile Cypress Pkwy         Daniels Pkwy                      BL        B      1.25          2.5          4
                           75     SR 739 (Metro Pkwy)                   Daniels Pkwy                  1800' N of Winkler Ave            SW        B      4.56          9.12         5
                           76     SR 739 (Metro Pkwy)                   Daniels Pkwy                  1800' N of Winkler Ave            BL        B      4.56          9.12         10
                           77     Fowler St-Metro Pkwy crossover        1800' N of Winkler Ave        Fowler St & Evans Ave             SW        B      1.06          2.12         5
                           81     Kennesaw connector                    Fowler St                     Evans Ave                         SW        B      0.22          0.44         6
                           82     Kennesaw connector                    Fowler St                     Evans Ave                         BL        B      0.22          0.44         5
                           110    SR 82 (Martin Luther King, Jr Blvd)   Park 82 Dr                    Teter Rd                          SW        S      0.60          0.60         5
                           91     SR 82 (Martin Luther King, Jr Blvd)   Teter Rd                      Wallace Ave                       BP        N      0.81          0.81         10
                           92     SR 82 (Martin Luther King, Jr Blvd)   Teter Rd                      Wallace Ave                       SW        S      0.81          0.81          5
                           100    US 41 (South Tamiami Trail)           Corkscrew Rd                  Broadway                          BL        B      0.74          1.48          4
                           101    US 41 (South Tamiami Trail)           Corkscrew Rd                  Broadway                          SW        B      0.74          1.48          6
                           102    US 41 (South Tamiami Trail)           Broadway                      San Carlos Blvd                   SW        B      1.71          3.42          5
                           103    US 41 (South Tamiami Trail)           Broadway                      San Carlos Blvd                   PS        B      1.71          3.42          5
                           104    US 41 (North Cleveland Ave)           Caloosahatchee River          500' S of Hancock Bridge Pkwy     SW        W      0.49          0.49         10
                           111    US 41 (North Cleveland Ave)           Hancock Bridge Pkwy           330' S of Brown Rd                SW        W      1.23          1.23          5




Table D - 2 (Continued)
                           112    US 41 (North Cleveland Ave)           Brown Rd                      SR 78 (Pine Island Rd)            SW        W      0.28          0.28          5
                           113    US 41 (North Cleveland Ave)           SR 78 (Pine Island Rd)        Stockton St                       SW        W      0.35          0.35          5
                           114    US 41 (North Cleveland Ave)           Hancock Bridge Pkwy           Marianna Ave                      SW        E      1.29          1.29          5
                           115    US 41 (North Cleveland Ave)           Brown Rd                      SR 78 (Pine Island Rd)            SW        E      0.15          0.15          5


                                  BL= 5' wide Bike Lane                 BP= 10' wide Bike Path
                                  PS= 5' wide Paved Shoulder            SW=5' wide Sidewalk
                                  Shaded rows are newly proposed projects.
Bicycle Pedestrian Element


The MPO noted that projects might be moved between Table F-1 and Table F-2 if it made any
changes to the state highway projects that are designated financially feasible in the 2030 highway
element.

The MPO approved Table F-1 and Table F-2 initially with a reduction of the annual set-aside
for bicycle and pedestrian improvements of $1,117,000 to balance the highway element.

This left a balance of $2,725,207 which the MPO directed staff to finance the following
additional projects in Table F-1:

   •    [21] Colonial Blvd (SR 884) from 500' E of Metro Pkwy to the existing bike path (bike
        Path, north side);

   •    [28] Metro Pkwy (SR 739) from US 41 to Six Mile Cypress Pkwy (sidewalks, east
        side);[37] SR 82 (Dr. Martin Luther King Blvd) from Michigan Link to Ortiz Ave
        (sidewalks, north side);

   •    [38] SR 82 (Dr. Martin Luther King Blvd) from Ortiz Ave to Park Eighty Two Drive
        (sidewalks, both sides);

   •    [39] SR 82 (Dr. Martin Luther King Blvd) from Ortiz Ave to Park Eighty Two Drive
        (bike Lanes, both sides);

   •    [58] SR 739 (Metro Pkwy) from 1800' north of Winkler Ave to Hanson St (sidewalks,
        both sides).

The following projects had to be moved from Table F-2 to Table F-1 as a result in the changes
in the financially feasible highway element due to the slippage of programmed projects to after
FY 2009/10 in FDOT’s Draft Tentative Work Plan:

   •    [61] US 41 (North Cleveland Avenue) from Verano Dr (Durden Parkway extension) to
        the Charlotte County Line (bike paths, both sides);

   •    [62, 63] Pine Island Rd (SR 78) from Cultural Park Blvd to Del Prado Blvd (bike path on
        north side and sidewalk on south side).

On the other hand, the sidewalk projects along US 41 (North Cleveland Avenue) from the
Caloosahatchee River to Stockton Street were moved from Table F-1 to Table F-2 because the


    Lee County Metropolitan Planning Organization   F-6-        2030 Long Range Transportation Plan
     December 7, 2005
Bicycle Pedestrian Element


highway improvements between the river and Diplomat Parkway were indeed financially
feasible if combined with the bridge widening and financed as a package with toll revenues.

The following projects also were added to Table F-2 as a result of the slippage of the
corresponding highway projects in FDOT’s Draft Tentative Work program:

        •   [72] SR 739 (Metro Parkway) from US 41 to Six Mile Cypress Parkway (bike path,
            west side);

        •   [73, 74] SR 739 (Metro Parkway) from Six Mile Cypress Parkway to Daniels
            Parkway (bike lanes and sidewalks on both sides);

        •   [100, 101] US 41 (South Tamiami Trail) from to Corkscrew Rd to Broadway (bike
            lanes and sidewalks on both sides);

        •   [102, 103] US 41 (South Tamiami Trail) from Broadway to San Carlos Blvd
            (sidewalks and paved shoulders on both sides).

The annual bicycle pedestrian set-aside was eventually restored to $1.5 million because one of
the state highway projects that had been included in the financially feasible highway element (on
Evans Avenue) was in fact already programmed this year and thus should not have been
included. These changes made it possible to add the following additional financially feasible
projects to Table F-1:

   •    [25] Palm Beach Blvd (SR 80) from Morse Plaza to Orange River Blvd (bike path, north
        side);

   •    [26] Palm Beach Blvd (SR 80) from Orange River Blvd to 0.5 miles east of Orange River
        Blvd (bike path, north side);

   •    [27] McGregor Blvd from Winkler Rd to Cleburne Dr (sidewalk, east side);

   •    [30] Pine Island Rd (SR 78) from Chiquita Blvd to Skyline Blvd (sidewalk, south side);

   •    [31] Pine Island Rd (SR 78) from Del Prado Blvd to Pondella Rd (bikepath, north side);

   •    [32] Pine Island Rd (SR 78) from Del Prado Blvd to Pondella Rd (sidewalk, south side);



    Lee County Metropolitan Planning Organization   F-7-       2030 Long Range Transportation Plan
     December 7, 2005
Bicycle Pedestrian Element


   •    [33] Pine Island Rd (SR 78) from Skyline Blvd to 300' west of Santa Barbara Blvd (bike
        path, north side);

   •    [34] Pine Island Rd (SR 78) from 300' west of Santa Barbara Blvd to Cultural Park Blvd
        (bike path, north side);

   •    [35] Pine Island Rd (SR 78) from 300' west of Santa Barbara Blvd to Cultural Park Blvd
        (sidewalk, south side);

   •    [52] McGregor Blvd from A.W. Bulb Rd to Cypress Lake Dr (sidewalk, both sides);

   •    [53] McGregor Blvd from Cypress Lake Dr to College Pkwy (sidewalk, both sides);

   •    [54] San Carlos Blvd from Summerlin Rd to 500' south of Gladiolus Dr (bike path, east
        side);

   •    [55] San Carlos Blvd from Summerlin Rd to 500' south of Gladiolus Dr (bike path, west
        side);

   •    [56, 57] SR 78 (Bayshore Rd) from east of I-75 to Nalle Rd (bike lanes and sidewalks,
        both sides);

   •    [58] SR 739 from 1800' north of Winkler Ave to Hanson St (sidewalk, both sides);

   •    [59] US 41 (SR 45) from Del Prado Blvd to Verano Dr/Durden Pkwy Ext (bike path,
        both sides);

   •    [60] US 41 (SR 45) from Pondella Rd to Del Prado Blvd (sidewalk, both sides);

   •    [61] US 41 (SR 45) from Verano Dr/Durden Pkwy Ext to Charlotte County Line (bike
        path, both sides);

   •    [62] Pine Island Rd (SR 78) from Cultural Park Blvd to Del Prado Blvd (bike path, north
        side);

   •    [63] Pine Island Rd (SR 78) from Cultural Park Blvd to Del Prado Blvd (sidewalk, south
        side);



    Lee County Metropolitan Planning Organization   F-8-      2030 Long Range Transportation Plan
     December 7, 2005
Bicycle Pedestrian Element


   •    [36] Fowler St (SR 739) from Hanson St to Dr. Martin Luther King, Jr Blvd (sidewalk,
        east side).

Consistency of interjurisdictional connections          Staff reviewed the local jurisdictions’
comprehensive plans and worked closely with the Lee County DOT, Hendry County
Consultants, Collier County MPO, and the local cities’ staffs to check for discontinuities and
inconsistencies between adjoining jurisdictions’ long range bicycle pedestrian plans. Only a few
such inconsistencies were found, which are listed in Table F-3, page F-10.

The following new policy statements on consistency of interjurisdictional connections have been
included in bicycle pedestrian element:

   •    All local governments should review the consistency of their long range bicycle
        pedestrian plans with the Lee County Greenways Master Plan upon its adoption.

   •    Lee County and each municipality should take advantage of every opportunity to
        implement the bicycle and pedestrian improvements identified as needed in the MPO’s
        bicycle pedestrian element when approving development abutting state highways, and
        each municipality should also take advantage of every opportunity to implement the
        bicycle and pedestrian improvements called for in The Lee Plan when approving
        development abutting county roads.

Pathway Issues from the Joint multimodal transportation plan: So as not to duplicate or
conflict with local governments’ established bicycle pedestrian planning programs, this MPO has
restricted the scope of its bicycle pedestrian element to two components: a plan for retrofitting
bicycle and pedestrian facilities along state highways, and a review of the continuity of local
governments’ bicycle pedestrian plans across jurisdictional boundaries or where the
jurisdictional responsibility for a road changes. In Collier County, however, the MPO is
responsible for countywide bicycle and pedestrian pathway planning, including the development
of a countywide trails and greenways plan, which in Lee County is the responsibility of the
county Department of Parks and Recreation. Both the Collier MPO and the Lee County
Department of Parks and Recreation are proposing the development of an off-road trail along a
new FP&L power line that will run from Buckingham past Lehigh Acres and Immokalee to the
Orangetree area on Immokalee Road in Collier County in their respective trails and greenways
plans, although neither plan has yet been adopted. Since this trail would cross the county line, it
is included in the joint regional multimodal transportation plan.




    Lee County Metropolitan Planning Organization   F-9-        2030 Long Range Transportation Plan
     December 7, 2005
                                                      Table F-3
                                DISCONTINUITIES IN PLANNED BICYCLE AND PEDESTRIAN
                                     FACILITIES AT JURISDICTIONAL BOUNDARIES

                          ID       Road                                                                  Proposed                   Width
                                                        Location                Jurisdiction                                 Side
                          No.     Segment                                                              Improvement                   (ft)
                          116                   W of Oritz Ave             City of Fort Myers       None                      -       -
                              Luckett Rd
                          117                   E of Ortiz Ave             Lee County               Sidewalk                  N       5
                                                                                                    Sidewalk          Bike    B       6
                          118                   S of Lee County line       Collier County
                                                                                                    Lane                      B       4
                                Livingston Rd
                          119                   N of Collier County line   City of Bonita Springs   None                      -       -
                          120                   W of Collier County line   Lee County               Paved shoulders           B
                              Corkscrew Rd
                          121                   E of Lee County line       Collier County           None                      -       -
                                                                                                    Sidewalk          Bike    B       5
                          122                   S of Lee County line       Collier County
                                                                                                    Lane                      B       4




Table D - 2 (Continued)
                                Vanderbilt Dr
                          123                   N of Collier County line   City of Bonita Springs   None                      -       -

                          124                   S of Lee County line       Collier County           None                      -       -
                                Old 41 Rd                                                           Sidewalks and paved
                          125                   N of Collier County line   City of Bonita Springs                                     5
                                                                                                    shoulders/bike lanes
Bicycle Pedestrian Element


This project is not explicitly included in the recommended 2030 bicycle pedestrian element,
since for the most part it would not be on a state highway. However, the proposed Lee County
Trails and Greenways Master Plan was consulted and considered during the development of the
bicycle pedestrian element, which incorporates some segments of proposed trails where they
would need to follow state highways for continuity where off-road alignments are not available.
This project was also included in the interjurisdictional continuity review, since it crosses the
county line, but it is not among the discontinuities mentioned in the bicycle pedestrian element
(Table F-3) because there is no inconsistency between the two counties with respect to it. The
most specific reference in the bicycle pedestrian element to this and other proposed trails and
greenways is the policy statement calling upon all Lee County local governments to review their
bicycle pedestrian plans for consistency with the Lee County Trails and Greenways Master Plan
following its adoption, which is expected in January.

Thus, the MPO considers the pathways component of the recommended joint regional
multimodal transportation plan element to be appropriately addressed in the bicycle pedestrian
element.

.




    Lee County Metropolitan Planning Organization   F - 11 -   2030 Long Range Transportation Plan
     December 7, 2005

				