projects
Document Sample


On going projects in MPT
Progress of work of various Plan Schemes during the month of July, 2011 is indicated below:
Sanctioned Date of
Cost Commence Scheduled
Sr. % of
Name of Scheme Original/ ment Completion/ Remarks
No. Progress
Revised(Rs Revised
. in lakhs) Completion
1 2 3 4 5 6 7
1 a) Construction of four lane 8000.00 Jun-98 May-04 68% Completed stretch from 0 to
road from Mormugao to 13.10 km from Verna to
Verna junction of NH -17B Varunapuri junction and was
thrown open to traffic in May,
2004.
b) Balance 5.2 km of NH 17B 12000.00 Oct-09 Oct-11 9% M/s. K.M.C Constructions Ltd.,
from Varunapuri Junction to Hyderabad has been awarded
Sada flyover from Gate No. 9 the work of construction of
to NH-17B. remaining 5.20 km. road from
Varunapuri junction to Sada
including Fly-over connectivity to
Gate No. 9 of the Port from NH-
17B. The progress of work is
very slow. Govt. of Goa filed
Special Leave petition in Hon'ble
Supreme Court challenging
Hon'bleHigh Court order to
hand over balance strench of
land by 30.06.2011. Goa
Rehabilitation Board, Govt . of
Goa has initiated the allotment
of housing units at Joshi Bhatt
and at Sada. The coastal Zone
Management Authority Govt. of
Goa has withdrawn the CRZ
approval granted vide
GCZMA/S/331/283
dtd.13/6/2011.
2 Construction of a 7.2 MMTPA 72100 1))Only one party submitted
Iron Ore Export Handling RFP document and Security
Terminal at West of clearance of the party have
Breakwater(WOB) been received from the Ministry.
2)Goa Pollution control Board
(GSPCB) has returned the
documents along with the
amount and directed to conduct
comprehensive EIA study which
is in progress at WAPCOS,
Gurgaon. 3)Application for CRZ
Clearance resubmitted to
GCZMA. (4) CCI approval is
awaited (5) Comprehenssive
hydrodynamic study report
submitted to GCZMA.
Sanctioned Date of
Cost Commence Scheduled
Sr. % of
Name of Scheme Original/ ment Completion/ Remarks
No. Progress
Revised(Rs Revised
. in lakhs) Completion
1 2 3 4 5 6 7
3 Construction of two Additional 12000.00 M/s. Tran System USA, in
Berths at Vasco Bay. consortium with M/s. MIR
Projects consultants Pvt. Ltd.,
Cochin, appointment as
consultant for preparation of
feasibility report. Preliminary
report received and is being
scrutinized and the consultant
has been informed to submit the
Draft final report. The project will
start only on relocation of the
fishing Jetty and rehabilitation
of encroachers from the project
site at Khariwada.
4 Remodelling and upgradation 608.00 Oct-06 Dec-08 16% The sanctioned amount or Rs.
of existing railway yards at 6.08 crores includes
harbour including other allied Construction of Roads &
works. Realignment of Compound Wall
has been completed.
5000.00 The following works are now
proposed to be taken under the
scheme.
i) Augmentation of Railway
Network at Mormugao Port -
Work order is being issued to
lowest tenderer M/s. Vyshnavi
Infrastructure and Concrete
Products with completion time
as fourteen (14) months.
ii) Construction of internal roads,
drains and cable trench Draft
tender is being prepared.
iii) Relocation of existing MOHP
structures - Estimate approved
work to be kept in abeyance
temporarily.
5 Construction of berth 4652 Feb-10 Mar-12 65% The progress has been
alongside of breakwater hampered due to bad weather.
65% work complete.
6 Construction of RCC Piled 1002 Jul-10 Dec-11 56% 56% work complete.
Retaining Structure Alongwith
Reclamation of the Area to be
taken over from SWPL at
East of Berth No. 4.
Sanctioned Date of
Cost Commence Scheduled
Sr. % of
Name of Scheme Original/ ment Completion/ Remarks
No. Progress
Revised(Rs Revised
. in lakhs) Completion
1 2 3 4 5 6 7
7 Development of 4 MMTPA 35530 - - - 1) Approval obtained from the
Coal Import Terminal at Berth Board vide Resolution No .7 of
No. 11. 18.06.2010 to executed as PPP
project.
2) Board has approved all 13
RFQ applications based on the
scrutiny report submitted by the
Transaction Advisor.
3) Upfront tariff notified by
TAMP.
4) Financial Viability Report
received from Transaction
Advisor,
5)PPPAC Memo sent to Ministry
of Shipping.
11 Modernisation of MOHP 60700 Jun-08 Apr-14 2% M/s. HOWE India Pvt. Ltd., Delhi
have submitted the DPR for the
modernisation of MOHP and the
same has been accepted by the
Port on 22.12.2009. PIB memo
submitted to the Ministry on
18.10.2010. The project has
been recommended by the PIB
for the approval of the CCI. The
project will be executed by
International Competitive
12 Replacement of 3 no. stackers 2780 Apr-07 Mar-10 20% Supply of 95% material for the
Oct-12 1st stacker has been completed.
Manufacturing of materials for
balance 2 no. stackers is in
progress. Work order for
modification of the stacker has
been placed on M/s. Sandvik
vide
no.CME/XEM(PW)/STK/3703 dt.
29/09/2010. Modificastion work
on all the 3 stackers is
scheduled for completion by
Get documents about "