Modified Guaranteed Maximum Price (MGMP) Contracting For the Public Rental Housing Development At Eastern Harbour Crossing Site Phase 4
MGMP Contracting
Risk-reduced Model Developed from Private Sector’s Target Cost and Guaranteed Maximum Price (GMP) Contracting A contracting model which allows for:
Integration of contractor‟s expertise and innovation in design and construction at tender and post tender stage And in doing so, it embraces the feature of - a guaranteed maximum price at main contract award - shared savings during construction
MGMP Contract Procurement Route
DESIGN
Direct Works Design and Construction Information MGMP Works Packages / MGMP Sub-contract Works Tenderers Issue Tenders for MGMP Sub-contract Works Following HA‟s Tendering Procedures and Guidelines Tenderers Submit Technical Proposals Tender Price Award MGMP Contract Sum
TENDER
CONSTRUCTION
Design Development for GMP Sub-contract Works Based on Technical Proposals Main Contractor Carries Out Works Main Contractor Carries out Works under „Open Book‟ Accounting Arrangement Variations Valuation of Variations Shared Savings Final Account Resolve Disputes Through Adjudication Committee
MGMP at Various Stages of Procurement
Design Stage Tender Stage Construction Stage
Appendix A
Design Stage
DESIGN
Design and Construction Information
Direct Works
MGMP Works Packages / MGMP Sub-contract Works
Key features at design stage
• Employer identifies works packages that require integration of contractor‟s input in design, buildability, and procurement
TENDER
Tenderers Issue Tenders for MGMP Sub-contract Works Following HA‟s Tendering Procedures and Guidelines
Tenderers Submit Technical Proposals
Tender Price
•
Employer prepares basic scheme / outlined design and performance specification for works packages
Works Packages subject to detailed design development by the contractor
Award MGMP Contract Sum
CONSTRUCTION
Design Development for GMP Sub-contract Works Based on Technical Proposals
•
Main Contractor Carries Out Works
Main Contractor Carries out Works under „Open Book‟ Accounting Arrangement
Variations
Valuation of Variations
Shared Savings Final Account
Resolve Disputes Through Adjudication Committee
Appendix A
Tender Stages
DESIGN
Design and Construction Information
Direct Works
MGMP Works Packages / MGMP Sub-contract Works
Key features at tender invitation
TENDER
Tenderers Issue Tenders for MGMP Sub-contract Works Following HA’s Tendering Procedures and Guidelines
Earmarked for Premier League Contractors Corporate Strength Partnering Commitments Experience on GMP MGMP Sub-contract Packages Domestic sub-contracts Back to back contract documentation Follow HA‟s tendering guidelines MGMP sub-contract tender prices Ceiling price Part of the overall contract sum
CONSTRUCTION
Tenderers Submit Technical Proposals
Tender Price
Award MGMP Contract Sum
Design Development for GMP Sub-contract Works Based on Technical Proposals
Main Contractor Carries Out Works
Main Contractor Carries out Works under „Open Book‟ Accounting Arrangement
Variations
Valuation of Variations
Shared Savings Final Account
Resolve Disputes Through Adjudication Committee
Appendix A
Tender Stages
DESIGN
Design and Construction Information
Direct Works
MGMP Works Packages / MGMP Sub-contract Works
TENDER
Key features at tender evaluation and award
Tenderers Issue Tenders for MGMP Sub-contract Works Following HA’s Tendering Procedures and Guidelines
Tenderers Submit Technical Proposals
Tender Price
Contractors submit technical proposal for the MGMP Sub-contract works Technical and price evaluation in tender assessment Contract Sum and the technical proposals are binding to the contract
Award MGMP Contract Sum
CONSTRUCTION
Design Development for GMP Sub-contract Works Based on Technical Proposals
Main Contractor Carries Out Works
Main Contractor Carries out Works under „Open Book‟ Accounting Arrangement
Variations
Valuation of Variations
Shared Savings Final Account
Resolve Disputes Through Adjudication Committee
Appendix A
Construction Stage
DESIGN
Design and Construction Information
Direct Works
MGMP Works Packages / MGMP Sub-contract Works
Key features at Construction Stage
TENDER
Tenderers Issue Tenders for MGMP Sub-contract Works Following HA‟s Tendering Procedures and Guidelines
Tenderers Submit Technical Proposals
MGMP Subcontracts under “Open Book” accounting arrangement Further savings from improvements in buildability and use of materials would be shared Adjudication Committee to settle differences on MGMP design developments and variations
CONSTRUCTION
Tender Price
Award MGMP Contract Sum
Design Development for GMP Sub-contract Works Based on Technical Proposals
Main Contractor Carries Out Works
Main Contractor Carries out Works under ‘Open Book’ Accounting Arrangement
Variations
Valuation of Variations
Shared Savings Final Account
Resolve Disputes Through Adjudication Committee
Opportunities offered by EHC Site Phase 4
Project
Three site-specific domestic blocks Bus terminus and noise barrier Lift tower cum footbridge
Opportunities offered by EHC Site Phase 4
The Master Layout Plan
Integration of Contractor’s Expertise
Good potential GMP packages for site specific nature of project Proposed packages of works
Bus Stop Specialist External Works (Footbridge and Lift Tower, Covered Walkway, etc.) Plumbing and Drainage Fire Services and Water Pump Installation Electrical Services Installation
Superstructure
Moderation of Benefits and Risks
Opportunities
Integration between building services and reinforced concrete construction Optimization of precast construction Optimization of contractor‟s expertise in specialist design