Docstoc

PacifiCorp 20022003 IRP Presentation Oregon Public Utility

Document Sample
PacifiCorp 20022003 IRP Presentation Oregon Public Utility Powered By Docstoc
					Overview
»History of IRP
                           Power Supply Adequacy Forum
»PacifiCorp’s Position
»Key IRP Assumptions     Roundtable Discussion on IRP
»Reviewing Assumptions
»Studies & Issues




                                   May 2003
History of PacifiCorp’s IRP
History of IRP:
                                   Dec. ‘01              Mar. ‘02               Jun. ‘02           Sep. ‘02
»   Used Henwood                      to                   to                     to                  to
    models (ProSym and            Feb. ‘02              May ‘02                Aug. ‘02           Jan. ‘03
    MarketSym) to
    perform analysis
»   Risk was introduced
    as an important
    factor in this IRP
    process
                            Began public input                           Held technical    Produced final set
                                                  Evaluated risk
»   Required to file an     meetings              models                  workshops          of IRP Results
    IRP every two years     Selected IRP model Consolidated             Finalized risk    Developed Action
»   Ten Public Input                                                      model              Plan
                            Gathered and input models and verified
    Meetings were held      model data and      preliminary results       Ran portfolios    Prepared IRP Draft
    between December        assumptions                                   through models     Report
                                                Updated inputs and
    2001 and February                             assumptions             Processed data    Communicated IRP
    2003                                          Selected initial new   and produced       findings and issued
                                                                          preliminary        Draft Report
»   Eleven Public                                 resources for
                                                                          results
    Technical Workshops                           portfolios                                 Modified Draft
                                                  Completed initial      Refined           Report based on
    were held with
                                                                          portfolios based   public input
    participants                                  model runs
                                                                          on findings, ran
                                                                                             Filed IRP with all
»   The IRP was filed in                                                  new portfolios
                                                                                             State Public Service
    all states on January                                                                    Commissions
    24, 2003                                                                                           2
Analysis of Current Position
Results of Analysis:        » PacifiCorp’s current position reveals a substantial need for new
»   Both deterministic        resources
    and stochastic
    analysis were
                            » Anticipate need of about 4,000 additional megawatts of
    performed on top          capacity over the next 10 years
    portfolios
                            » The 15% Planning Margin accounted for ~1,700 MW of the
»   Thirteen stress tests
    were also performed
                              4,000 MW in the least-cost, low risk portfolio
    on top portfolios
                                 12,000
»   Least-Cost Portfolio                   Peak System Requirement + 15% Planning Margin

    included:
                                 10,000                                              Resource Deficit - "The Gap"
     •   1,400 MW
         Renewables
                                   8,000
     •   1,200 MW
                                MW's




         Peakers
                                   6,000
     •   2,100 MW Base
         Load                                            Nameplate Capacity of Existing Resources
                                   4,000
     •   450 MWa DSM
     •   700 MW Shaped             2,000
         Products
                                       0
                                       2004    2005   2006    2007   2008    2009   2010    2011    2012    2013    2014
                                                                        Calendar Year
                                                                                                                           3
IRP Planning Margin Assumption
Base Case Assumptions:
»   Average hydro
                            » Decision Criteria used in filed IRP
»   Average loads                 • Limit initial net short energy position to less than 5% of the
                                      hours in any year
»   No Capacity credit
    for wind                      • Build portfolios to meet 15% capacity planning margin for the
»   Market sales and                  system by fiscal year 2007
    purchases were                       Planning Margin = {Load +(LT Sales - LT Purchases)} x 0.15
    limited to 500 MW for
    each control area                    This is mid-way between 12%-18% mentioned in SMD*
                                          discussions
                                         Reserve peakers were built to cover planning margin

                            » Issues with Decision Criteria
                                  • 5% criteria seemed arbitrary to third parties
                                  • FERC's SMD White Paper issued on April 28, 2003 specifically
                                      said it would not require a minimum level of resource adequacy
                                         FERC indicated that resource adequacy will be left up to the states
                                          and/or regions


                                                                                                      4
                            *Note:FERC’s Standard Market Design - Notice of Proposed Rulemaking
    Review of Planning Margin Assumption
Planning Margin Analysis:
                              » PacifiCorp’s view is planning margin needs to reflect the
»   Planning margin was
                                operating requirements
    used to provide
    sufficient resources to      • Operating Reserves (vary by control area)
    cover unplanned                     Obligated by WECC to carry operating reserves above firm
    outages, provide                     load at any time plus additional as seemed appropriate by
    operating reserves,                  operators
    regulatory margin,
    and demand growth
                                        One measure of operating reserves is 5% of hydro and 7%
    uncertainty                          of thermal generation being used to serve load at that time
                                  • Generator Unplanned Outages
                                        Historical and future unplanned outages between 10 - 12%

                              » Appropriate amount of planning margin for each control
                                area is still under review
                                  • PacifiCorp has transmission constraints on the East side of
                                     its system that may mandate a higher planning margin
                                     requirement
                                  • More flexibility on West side of PacifiCorp system


                                                                                                5
Next Steps - Studies & Issues
Goals of IRP
                             » Studies Under Review:
»   Plan for new resources
    to provide reliable         • Demand-elasticity in our load forecast
    service
                                • Reliability and economic risk associated with varying
»   Gain key stakeholder             planning margin levels
    involvement and
    commitment                   •   Capacity contributions associated with wind plants
»   Comply with PUC              •   Different planning margin requirements for transmission
    requirements                     constrained areas
»   Gain PUC
    acknowledgement of the   » Issues
    Action Plan                 • Appropriate trade-off between risk and cost is a
»   Foundation for future            policy/regulatory issue
    investment and long
    term business planning       •   Building reserves is expensive - production cost models
                                     should always choose less reserves unless extreme
                                     assumptions are made for market prices & penalties




                                                                                               6

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:3
posted:10/16/2012
language:English
pages:6