SLAC National Accelerator Laboratory
Conventional Facilities Status
LCLS Conventional Facilities
Introduction
Key Elements
Staff
Schedule
Construction Status
Remaining Issues
December 2, 2008 Jess Albino
1
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
LCLS Installation and Commissioning Time-Line
Install Undulators
First Light in FEH
First Light in FEE
CD-4 (7/31/2010)
X-Rays in NEH
FEE/NEH Install
PEP-II run ends
LTU/Und Install
FEH Hutch BO
now
J F MA M J J A S ON D J F M AM J J A S OND J F MAM J J
2008 Down
PPS 2009 Down?
2010
LTU/Und NEH Ops &
Linac/BC2
Comm. Commissioning
Commissioning
Re-establish FEL/FEE
e- to SL2 Commissioning Nov. 3, 2008
December 2, 2008 Jess Albino
2
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Substantial Completion Dates
Central Utility Plant
Undulator NOV 08
Beam Hall
Transfer NOV 08 Near Experimental Hall
NOV 08 NOV 08
Beam Dump
NOV 08
Front End Enclosure
NOV 08 Xray/Diagnostics
NOV 08
Far Experimental Hall
NOV 08
December 2, 2008 Jess Albino
3
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
December 2, 2008 Jess Albino
4
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
December 2, 2008 Jess Albino
5
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Equipment Warranties
Equipment Testing Reports
Mark up Drawings and Specifications
Subcontractor Financial Records
Final Acceptance Records
December 2, 2008 Jess Albino
6
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
December 2, 2008 Jess Albino
7
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
TCCo —> LCLS CF
Commiss. Final
Status e-beam System Install. Dwgs of Test Final Punch accepta
(thru e–DUMP) compl. Record reports List nce CF Recip.
Building/Housing shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz
AC Pwr √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla
Ch. W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
Hot W. √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
LCW √ shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
HVAC √ shop dwgs √ 15-Nov-08 30-Nov-08 Saenz
C. Air √ shop dwgs √ 15-Nov-08 30-Nov-08 Sevilla
Fire
System
s √ shop dwgs 31-Oct-08 15-Nov-08 30-Nov-08 Saenz
Sump 30-Nov shop dwgs √ 15-Nov-08 30-Nov-08 Baclit/Sevilla
Radio n/a n/a n/a n/a n/a n/a
Phones √ shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz
Magnets n/a n/a n/a n/a n/a n/a
Vacuum n/a n/a n/a n/a n/a n/a
Mag. Power spl n/a n/a n/a n/a n/a n/a
Controls n/a n/a n/a n/a n/a n/a
December 2, 2008 Jess Albino
8
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Beam Transport Hall
December 2, 2008 Jess Albino
9
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Undulator Hall
December 2, 2008 Jess Albino
10
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Electron Beam Dump Area
December 2, 2008 Jess Albino
11
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
December 2, 2008 Jess Albino
12
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Access Tunnel
December 2, 2008 Jess Albino
13
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
20 ITEMS REMAINING
December 2, 2008 Jess Albino
14
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
CF Construction Organization
Project Director
John Galayda
Deputy Proj. Director
Mark Reichanadter
Project Controls and
SLAC Services Support
Support Office
Exec. CF Committee
Associate Project Director
R. Claus, J. Jobe Turner
– Civil Construction
B. Miller Bill Jangraw
Jess Albino
M. Reichanadter Project Executive
Change Processing
Cost / Schedule
Jim Dee
Anita Malahowski
John Azevedo
CF System Manager
David Saenz
Administrative Support
SLAC ES&H Subject
Lee Anne De Wan
Concepcion Zelaya Matter Experts (SME)
Site Manager Engineering Group University Technical CM/GC – Turner
Jacobs Facilities, Inc Leader Rep – Group Leader Mike Owens – Sr. PM
Dave McDonough Javier Sevilla Jesse Saldivar Matt Zybura -APM
General Turner Procurement –
JE Design PM Structural Electrical UTR – Electrical UTR – CM
JE Walnut Creek Superintendent Pre-purchased
Cypress Ken Yang Lori Shewchuk Lori Shewchuk Dumitru Ciorbea
Nick Tyler Equipment
Mechanical Engineer Electrical Engineer UTR – Structural UTR – CM C.M. Tunnels
JE Portland JE Boston Turner Project Office
Ray Baclit Khalid Ahmed Ken Yang Richard Maggi Eric Alward - HMM
Rutherford /Chekene UTR – Mechanical Site Safety Rep
Sub Contractors
Gyimah Kasali Javier Sevilla Andrew Leone
December 2, 2008 Jess Albino
15
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
Summary
Substantial Completion has been achieved.
Punch list items are currently being addressed.
Installation tasks were successfully supported with
Beneficial Occupancy and logistics under CF direction.
All systems accepted and ready for transfer to
installation or laboratory service groups.
Plans are in place for the beam commissioning
program.
December 2, 2008 Jess Albino
16
Accelerator Readiness Review albino@SLAC.Stanford.edu
SLAC National Accelerator Laboratory
End of presentation
December 2, 2008 Jess Albino
17