							UK Cleanup Market Overview
A Strategic approach to Cleanup
& Hazard Reduction




Nov 2010


Marcus Mackay                 mercury stone
marcus@mercurystone.co.uk
 Purpose

• Provide an overview of the UK Civil Nuclear Estate

• Explore the UK Nuclear Decommissioning Authority (NDA)
  strategy which is driving UK cleanup and the market
  opportunity

• Describe the UK site restoration context & strategy




                                                        mercury stone
    UK Cleanup Overview

•

    The Nuclear Decommissioning
    Authority was established in 2005 with
    a remit to clean up the civil public
    sector nuclear legacy

•   Sites and facilities built from 1940s
    onwards

•   Annual funding of ~£2.8Bn ($4+Bn)

•   Head Office based in North West
    England

•   Total staffing circa 18,500 plus
    contractors
                                                         3

                                             mercury stone
The UK legacy - Sellafield




                                         4

                             mercury stone
The UK legacy – Magnox Reactors




                                      5

                          mercury stone
    The UK legacy - Research Facilities
           Dounreay




                                         Harwell




Dounreay
                                      Winfrith




                                                 6

                                mercury stone
   The NDA mission covers a diverse range
   of complex activities as well as cleanup
Demolition of towers at Chapelcross           Chapelcross begins          Trawsfynydd ILW store opens
                                              Reactor 3 defuelling




  New Sellafield product store
  under construction
                                                     Dounreay Puma Cell cleared out and cleaned up
                                 VRR back overseas




                                                                                      mercury stone
 Progress since 2005

• First UK-wide strategy 2006, five yearly review underway
• Understanding the nature of the legacy, the interactions and
  the scale of the Nuclear Liability Estimate (circa £70Bn)
• Changed the architecture of the industry, moving 18,000
  workforce under private sector management, replacing two
  monoliths with six Site Licensed Companies (SLCs)
• Successfully competed and sold sites, placing them under
  private sector management
• Real focus on high hazards & programme delivery




                                                     mercury stone
The NDA's Strategic Approach is
focussing effort on priority activities
NDA activities are grouped under six strategic themes that translate into key
programmes of work that must be delivered in the short to medium term.

Reduce               Ensure fuel            Implement            Deal with              Maximise
hazards and          from 1st and           storage and          plutonium and          commercial
liability across     2nd generation         disposal for         uranium in a           value from
our estate (eg       is reprocessed         LLW, ILW and         safe and               our assets
legacy ponds         and managed            HLW inc.             secure way
& silos)             in a safe and          Geological
                     secure way             Disposal
                                            Facility (GDF)


    SITE                 SPENT               WASTE                  NUCLEAR               BUSINESS
RESTORATION              FUELS             MANAGEMENT              MATERIALS            OPTIMISATION



                                       CRITICAL ENABLERS

  Build an effective industry (supply chain, skills, R&D, competition, socio-economic)


              The NDA Strategy was first published in 2006. Consultation on Strategy 2 started in Sept 2010,
              for further information: http://www.nda.gov.uk/strategy/


                                                                                          mercury stone
Current UK expenditure breakdown




                  Estate wide expenditure broken down by
                  strategic theme. This is indicative and based
                  on previous years.

                  53% of spend is on Sellafield




                                           mercury stone
    The NDA Business Plan 2010-13…
    a top level guide to priorities for delivery
•   Defines the NDA Strategic Objectives
•   Provides an overview of Costs & Funding
•   Maps Activities against Strategic Themes
    eg. Site Restoration - £863m in 2010/11
        Spent Fuels - £439m in 2010/11 etc…
•   Activities in some cases specific…
    eg. “Complete the asbestos stripping from 8 of 16
    heat exchangers at Chapelcross”
    … in some cases general…
    eg. “Continue Preparation of retrieval of legacy waste”
•   Further Detail are held in
    - Site Life Time Plans,
    - 3 year detailed Operating Plans
    - Procurement Plans
                              For more information download the NDA Business Plan 2010-13
                              www.nda.gov.uk/loader.cfm?csModule=security/getfile&pageid=38406

                                                                           mercury stone
Site Restoration - Context
Restoration of the UK’s nuclear legacy presents a major and time
critical challenge; in 2009/10 the discounted future cost estimate
amounts to £40.8 billion

    – Legacy plants dating from late 1940’s and 1950’s
    – Large quantities of old corroding radioactive waste
    – Degrading infrastructure
    – Contaminated ground and / or groundwater at every NDA site
      as a result of various land uses (not all nuclear)
    – Volume of ground estimated to be radioactively contaminated
      exceeds (~x4) current UK low level waste disposal capacity




                                                                     12

                                                        mercury stone
Site Restoration - Context
•   Site Restoration covers three key activities required to deliver a
    site or facility through to a planned Site End State

     – Decommissioning and Clean-Up
       Cleaning out, dismantling and demolishing redundant facilities (from
       cessation of operations to demolition)
     – Land Quality Management
       Managing contaminated ground and groundwater
     – Site End States
       Providing credible objectives for the restoration of each site; defining
       the physical condition of a site when NDA has completed its mission

•   Takes account of Non NDA Liabilities located on NDA sites



                                                                                  13

                                                                 mercury stone
Site Restoration - Context




                                                                            Site End States
Operations          Decommissioning and Clean-up

                                                                                               Land & Property
                                                                                                Management

Land Quality Management                                                                         Dedesignate


                                                                                                   Divest


     Interim States                                                                           Next societal use


(Site Restoration is the driving strategy that other strategies (inc. Integrated Waste Management) support)



                                                                                                                  14

                                                                                                   mercury stone
        Site Restoration
          Site Restoration Objective:
     To restore NDA designated sites and
          release them for other uses

•   Focus on reducing risks to people and the              •
    environment, while restoring each site as soon as
    reasonably practicable to a condition suitable for its
    next planned use
•   Site restoration is considered on a case-specific
    basis, taking account of a range of relevant factors
•   Intolerable risks – the NDA will take urgent
    continuous action to reduce them to at least a
    tolerable level
•   Less significant risks – the NDA will take greater
    account of other factors
•   Act proportionately to ensure net level of risk does
    not increase in the long-term
•   Consider full lifecycle impacts on people &
    environment to avoid compromising future
    generations – ie. Adopt sustainable solutions

                                                               mercury stone
Key Messages

•   The UK nuclear landscape has transformed over the last 5 years, with
    Nuclear New Build providing new challenges & end-state possibilities

•   Joined up Strategy and Business Plans are key to:
    - Quantifying the liability
    - Demonstrating Credibility & Securing Funding
    - Enabling effective prioritisation

•   The focus on High Hazards requires flexible approach, including
    deferred decommissioning and cleanup of lower risk facilities




                                                                       16

                                                          mercury stone
   Close any questions




Marcus Mackay
marcus@mercurystone.co.uk
                                       17

                            mercury stone

						