Request for Certification and Release of Funds Form
ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE
PROJECT NAME KRONOS- A SHARE INTEGRATED TIME COLLECTION SOLUTION
PROJECT NUMBER DATE
LEAD AGENCY DEPARTMENT OF HEALTH AGENCY CODE 665
OTHER AGENCIES DEPARTMENT OF FINANCE AND PROJECT PHASE Implementation
ADMINISTRATION
EXECUTIVE SPONSOR ANITA WESTBROOK, DIRECTOR OF OFFICE OF FACILITIES MANAGEMENT
PROJECT MANAGER TAMMY JO MONTOYA
AGENCY HEAD DR. ALFREDO VIGIL
AGENCY CIO/IT LEAD ROBERT MAYER
PROJECT DESCRIPTION (PROVIDE A BRIEF DESCRIPTION AND PURPOSE FOR THIS PROJECT)
Kronos solution SHARE integrated automated time collection solution will support DOH facilities
in efficiently managing employees’ work schedules and accurately tracking work hours.
The purpose of the project is to provide DOH 24/7 Healthcare facilities the ability to manage
workforce staff to provide for adequate staffing that meet necessary ratios as mandated by
Federal and State Agencies. This will include workforce planning activities to ensure proper
acuity (Patient to Staff Ratio) rates to maintain patient safety. Office of Facilities Management
(OFM) will standardize procedures and policy across the facilities for using Kronos time
keeper software.
In 1998, the New Mexico Behavioral Health Institute implemented Kronos and then
successfully integrated Kronos with SHARE in 2006. Sequoyah Adolescent Treatment Center
is currently using Kronos in a limited capacity without integration with SHARE.
This project will build upon NMBHI’s successful use of Kronos. Kronos will be upgraded at
NMBHI and Sequoyah and expanded into the other five facilities. Additional functionality
will be to fully integrate Kronos into the SHARE system.
Planned Start Date April 2008 Planned End date June 2009
Amount Requested this Certification $ 730,000
Amount Previously Certified $ 70,000
Remaining Appropriation not Certified $0
Total Appropriated Amount (include any new funds) $ 800,000
This is a controlled document, refer to the document control index for the latest revision
Revision: 2/14/08 Page 1
Implementation
Request for Certification and Release of Funds Form
ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE
CERTIFICATION HISTORY (INCLUDE ANY PREVIOUS PROJECT OR PHASE CERTIFICATIONS)
Date Amount Funding Source(s) (use specific citations to laws, grants, etc.)
April 10, 2008 $800,000 LAW OF 2008, CHAPTER 3, SECTION 7, SUBSECTION 10
PROPOSED CERTIFICATION SCHEDULE FOR CURRENT FISCAL YEAR (AGENCY TO COMPLETE FOR ALL PHASES)
Phases Amount Major Deliverable(s) / Performance Measure(s) Due
Requested Dates
Initiation: $70,000 IV & V contract and plan, Project Management plan March
2008
Planning: $0 Design Document, OFM Policy and Procedures, July 2008
Application Support Plan, IV & V periodic reports
Implementation: $730,000 Kronos contract – software and hardware purchased, Sept 2008
installed, tested, user acceptance, transition to OPS
document, IV &V periodic reports
Closeout: $0 DoIT Closure Report, Project Closure Archive, IV June 15,
&V Close out report 2009
APPROPRIATION HISTORY (INCLUDE ALL FUNDING SOURCES, E.G. FEDERAL, STATE, COUNTY, MUNICIPAL LAWS OR GRANTS)
Fiscal Year Amount Funding Source(s)
FY09 $800,000 LAW OF 2008, CHAPTER 3, SECTION 7, SUBSECTION 10
BUDGET
Comments:
Description FY07 & Prior FY08 FY09 FY10 FY11
Staff -
Internal
Consulting SHARE technical $343,000
Services resource
IVV Consultant
Implementation
Training
Hardware $150,000
Software Kronos Licenses $307,000
SAS
This is a controlled document, refer to the document control index for the latest revision
Revision: 2/14/08 Page 2
Implementation
Request for Certification and Release of Funds Form
ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE
$800,000
TOTAL
IT SYSTEM ANALYSIS
On this document, or as an attachment, provide a summary response, including changes, to
the following IT infrastructure topics relating to this project:
DOH will subscribe to Kronos’ through Software as a Service (SaaS). By subscribing to Kronos’ SaaS,
DOH will be provided with server and application administration, automatic update and patch
management along with application upgrade management. Kronos’ SaaS will be reliable and will allow
DOH to control costs.
Employees will swipe in and out several times a day using a time clock terminal located at the facility.
These terminals collect the data and transmit small bits of data to Kronos. It may be real time or batch
communication and will be determined during the implementation phase. NMBHI has been successful
with integrating Kronos into SHARE.
Kronos is a web-enabled solution and will not have an impact on DOH’s infrastructure hardware.
There will be bandwidth usage over the state’s network as data transfers occur from the facilities to
Kronos’ site and from Kronos’ site to SHARE.
Discussion with Maynard Salazar occurred on March 26, 2008. He recommended we have a
benchmark of traffic generated from DOH over the state’s WAN. More information about the network
bandwidth utilization will be discovered and discussed with DoIT.
BUSINESS CONTINUITY STRATEGY
On this document, or as an attachment, provide a summary response, including changes, of
your business Continuity Strategy.
Kronos will provide weekly full and daily incremental backups of the database and kept online for the
most recent 28 days. Data is stored at the primary data center. In the event Kronos is unavailable,
employees who use web entry will be required to submit paper timesheets. Kronos timeclocks will
hold up to 7 days of data. In the event the timeclocks can not communicate with the database,
employees will be required to go to paper timesheets. HR personnel will be required to enter in
summary time into SHARE.
SECURITY STRATEGY (APPLICATION AND DATA SECURITY PROCESS, PLAN, OR STANDARD)
Application and data security are maintained through standard methods appropriate for different
components of the implemented system. Interaction with the servers from workstations is
accomplished using IE 6.0 and SSL (secure socket layer) with all connections authenticated against the
local set of users and groups on the host servers.
This is a controlled document, refer to the document control index for the latest revision
Revision: 2/14/08 Page 3
Implementation
Request for Certification and Release of Funds Form
ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE
INDEPENDENT VERIFICATION & VALIDATION (INCLUDE SUMMARY OF THE LATEST IV & V REPORT)
The IV&V contract is in place with Fox Systems and the IVV plan complete. The initial risk
assessment has been received.
SIGNIFICANT RISKS AND MITIGATION STRATEGY
RISK 1: Network performance at NMBHI may not handle the addition of Kronos.
MITIGATION 1: DOH ITSD is working with DoIT and Qwest to get a DS3 line installed at
NMBHI to stabilize network operations. NMBHI will be the last of Facilities for the Kronos
implementation in order that DS3 circuit is operational.
RISK 2: Network performance at Fort Bayard may not handle the addition of Kronos.
MITIGATION 2: Monitor network performance once Kronos is implemented. Engage DOH’s PSB
to address issues.
RECORD RETENTION POLICY (DESCRIBE THE AGENCY’S RECORDS RETENTION REQUIREMENTS FOR THIS PROJECT)
Kronos retention decisions would also be based on the New Mexico Administrative Code (NMAC) and
other governing policies.
MAINTENANCE STRATEGY (DESCRIBE HOW THE AGENCY PLANS TO MAINTAIN THIS PROJECT AFTER DEPLOYMENT)
DOH will execute a support and maintenance agreement with Kronos. This agreement will detail the
maintenance strategy with Kronos having the lead role in maintaining the application since Kronos’
SaaS will provide all required maintenance. DOH will work closely with Kronos to support and
maintain the application and hardware. The SHARE team will play a role with maintaining the
interface between Kronos and SHARE.
INTEROPERABILITY (DESCRIBE HOW THIS PROJECT INTERFACES WITH EXISTING SYSTEMS/APPLICATIONS WITHIN THE AGENCY)
Kronos will interface with the SHARE system to provide time and leave balances for Facilities
employees. The SHARE Project Director and Manager are members of the project team. DFA and
DOH have signed a JPA. DFA personnel from the SHARE Project are members of the steering
committee and will be part of the technical team.
This is a controlled document, refer to the document control index for the latest revision
Revision: 2/14/08 Page 4