Recommendation re long lead time projects 59194949

W
Shared by: HC121001035142
Categories
Tags
-
Stats
views:
0
posted:
9/30/2012
language:
English
pages:
8
Document Sample
scope of work template
							      Recommendations re:
    Long-Lead Time Programs
• Summary of Issues (ComEd)
• Proposed Solutions (Ameren Illinois)
  – Prescriptive / Standard
  – Custom, New Construction, and Retro-
    Commissioning
• Benefits and Summary (DCEO)
            Summary of Issues
• Energy efficiency project work flow does not
  exactly map to annual budget cycles
• Strict adherence to individual program years has led
  to suboptimal program approach
• The statute as currently interpreted creates a
  significant barrier to larger, multi-year projects
• Larger projects, that are often the most cost-
  effective, generally have long lead times (6 to 12
  months or more) involving
   – design
   – material ordering and delivery
   – installation
                            Illustration of Issues
                                             PY1                                                            PY2
           June 1           Sept 1           Dec 1             Mar 1              June 1           Sept 1             Dec 1

 STEPS
              •Customers submit Pre Applications                                      •Customers submit Pre Applications
Recruiting    •Contract with suppliers           “Dead     Zone”                      •Contract with suppliers
              •Allocate funding to project                                            •Allocate funding

 Begin                          •Reservation letter received                                  •Reservation letter received
                                •Order materials and labor                                    •Order materials and labor
EE Build                        •Begin construction                    “Dead Zone”            •Begin construction

Complete            “Dead                         •Projects Completed                      “Dead
                                                  •Final Applications submitted
 Project            Zone”                         •Incentive Checks processed              Zone”

  Existing Program Approach Create three “Dead Zones” of inactivity
  1.    Recruiting: The timeframe between having exceeded funding limits in one year
        and the start of the next program year (Currently Nov 1 to June1 for ComEd)
  2.    Begin EE Build: The timeframe between customers receiving reservation letters
        and the completion of their project (Example: Lighting projects typically take
        about 90 days to complete project and remain within the same funding year)
  3.    Complete Project: The time period before customers receive a reservation letter
        and begin their project
          Proposed Solutions
• kWh saved established upon receipt of Final
  Application
• We will honor reservation amounts through the
  reservation commitment timeframe
• Incentive payments outside a reservation timeframe
  is paid based on the rules and rates in the year the
  Final Application (payment request) is received
• Multi-year projects and very large projects (only a
  handful) can be parsed into multiple applications to
  match program years to align savings with
  completed milestones
Proposed Solutions for the Prescriptive /
          Standard Programs
• Begin reserving projects three months before the
  program year (i.e. March 1, 2009) beginning with
  the “Wait List” applications first
• Allow customers to begin projects (construction /
  build) three months before the program year starts
  (i.e. March 1, 2009)
• Provide reservations to meet the expected
  completion date for customers to contract / order
  equipment before a specific program year to
  accommodate long lead time projects (i.e. Chillers)
• Each entity (ComEd, Ameren Illinois, DCEO) will
  determine the appropriate % of Year 2&3 funds to
  reserve in year one
      Proposed Solutions for the
 Custom, New Construction, and Retro-
      Commissioning Programs
• Begin reserving projects for Program Year 2&3
  now
• Ability for customers to begin projects (ordering
  equipment, contracting, permitting) now
• Each entity (ComEd, Ameren Illinois, DCEO) will
  determine the appropriate % of Year 2&3 funds to
  reserve in year one
                       Benefits
• Provide continuity to customers and Trade Allies /
  Program Allies
   – Eliminate Start / Stop of program activities on June 1 /
     May 31
   – Reduce marketing costs
   – Increase cost effectiveness of program
• Provides a longer timeframe for project
  development activities
• Ability to fill the project pipeline for Program
  Year 2&3
• New approach would help spur activity for “big
  ticket” items and/or projects with long lead times
                  Summary
• New program approach will shrink the “Dead
  Zone” in area 1 by allowing customers to apply
  for year 2 funding on March 1.
• Allowing customers to begin ordering materials in
  advance and to begin construction on April 1 for
  Program Year 2 will shrink the “Dead Zone” in
  area 2
• Ability to provide reservations for Program Year 2
  and 3 will shrink the “Dead Zone” for area 3

						
Related docs
Other docs by HC121001035142
HARRIS COUNTY
Views: 1  |  Downloads: 0
Samba link
Views: 0  |  Downloads: 0
Pr�sentation PowerPoint - DM ou KDD
Views: 6  |  Downloads: 0
Virtuelne ma�ine - PowerPoint
Views: 7  |  Downloads: 0
North Orange County
Views: 3  |  Downloads: 0
COURSE COMPLETION REQUIREMENTS
Views: 0  |  Downloads: 0
Order Form for DH677, 09/07/11
Views: 0  |  Downloads: 0
Research Ethics Application Form
Views: 3  |  Downloads: 0
FACILITIES MANAGEMENT - DOC
Views: 2  |  Downloads: 0
Doc 5 Placement Learning Agreement Form
Views: 7  |  Downloads: 0