Period Covered in Report

Document Sample
Period Covered in Report Powered By Docstoc
					   Period Covered in Report
August 01, 2012 to August 31, 2012
                           Table of Contents



Report of Construction Engineer                                 3

Projects Completed - Final Estimate Not Processed               4

Projects Under Construction                                    41

Contracts Awarded - NTP Not Processed                        113

ODOT Residency Directory                                     117




                              Construction Status Report   Page 2
                               Activity for Month of August 2012
                                                  Number of
                                                  Contracts                  Contract Amount      Amount Paid

Contracts Finaled                                       34                    48,630,285.65      51,159,881.43

Contracts Completed                                     26                    35,192,593.95      34,349,257.43

NTP Issued                                              32                    70,634,206.95                0.00

Contracts Awarded                                       35                    41,210,866.73                0.00

Contracts Let                                           35                    44,705,198.19                0.00




             Status of Construction Projects as of August 31, 2012
                                                  Number of
                                                  Contracts                  Contract Amount      Amount Paid

Contracts Completed, Final Estimate Not Paid          322                   1,243,312,018.25   1,253,062,894.16

Contracts Under Construction                          376                   1,462,074,697.91   1,015,962,153.91

Contracts Awarded, NTP Not Processed                    43                    56,362,078.03                0.00

Active Contracts                                      741                   2,761,748,794.19   2,269,025,048.07




                                               Construction Status Report                              Page 3
County:          Adair                                       Commissioner District:                               1
 Contracts Completed - Final Estimate Not Processed


 23105(08)     Contract: 110230     US-59       Residency:        01200       0.00 MI. US-59/BRIDGE WATER
                                                                              PROOF SEAL;SH-31/SH-82; AT
 BRFY-101C(097)                                 SALLISAW
                                                                              VARIOUS LOCATIONS IN DIV. I.
 Contractor:          GARY A. CRAIN, INC.
 Engineer:            Edwards, Carl
 Contract Amount:     $39,997.50                                              Completion Date:               01/10/2012
 Letting Date:        04/14/2011                                              Final Est Sub:

 24229(04)     Contract: 090608     US-59       Residency:        01200       2.680 MI. GRADING, DRAIN &
                                                                              SURFACE US-59 BEGIN AT THE
 STPY-101A(072)                                 SALLISAW
                                                                              DELAWARE COUNTY LINE & EXTEND
 Contractor:          FORSGREN INC.                                           SOUTH.
 Engineer:            Edwards, Carl
 Contract Amount:     $9,155,608.77                                           Completion Date:               02/23/2012
 Letting Date:        10/15/2009                                              Final Est Sub:

 18258(04)     Contract: 090514     US-59       Residency:        01200       1.302 MI. US-59;GRADE,DRAIN    &
                                                                              SURFACE;BEGIN 1.3 MI. S. OF
 STPY-101A(037)SS                               SALLISAW
                                                                              US-412, EXTEND NORTH.
 Contractor:          APAC-CENTRAL, INC.
 Engineer:            Edwards, Carl
 Contract Amount:     $4,942,919.10                                           Completion Date:               10/12/2011
 Letting Date:        08/20/2009                                              Final Est Sub:

 20883(05)     Contract: 100056     US-59   Residency:     01002              0.00 MI. US-59;BRIDGE REHAB-
                                                                              ILITATION/US-64 AT VARIOUS
 BHFY-101A(060)                              TETRA TECH
                                                                              LO-CATIONS IN DIV. 1.
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC
 Engineer:            TETR
 Contract Amount:     $1,112,270.07                                           Completion Date:               11/23/2011
 Letting Date:        07/22/2010                                              Final Est Sub:




County:          Alfalfa                                     Commissioner District:                               6
 Contracts Completed - Final Estimate Not Processed


 20937(04)     Contract: 110183    SH-45      Residency:    06700             0.00 MI. SH-45 OVER EAGLE CREEK,
                                                                              1.2 MI. EAST OF WOODS C/L
 BRFY-NBIP(387)                               DIV. 6 BRIDGE
 Contractor:          TARPON INDUSTRIAL, INC.
 Engineer:            Roesner, Wayne
 Contract Amount:     $159,720.00                                             Completion Date:               05/01/2012
 Letting Date:        09/15/2011                                              Final Est Sub:

 26922(04)     Contract: 100019     SH-8    Residency:       06100            6.940 MI.;SH8/RESURFACE
                                                                              (ASPHALT)FROM THE SH-11 JUNC-
 STP-JOBS(080)3R                             BUFFALO
                                                                              TION W. OF BURLINGTON, EX-
 Contractor:          VENTURE CORPORATION DBA V. C. O. PAVING                 TEND N. TO THE KANSAS STATE LI
 Engineer:            Burke, David
 Contract Amount:     $1,858,043.16                                           Completion Date:               10/05/2011
 Letting Date:        04/01/2010                                              Final Est Sub:                 07/24/2012

 26826(04)     Contract: 100205     SH-8     Residency:      06100         *STPY-176B(190)/0.00 MI. SH
                                                                           -8/US-281; BRIDGE REHAB.;OVER
 STPY-102C(168)(169)*                         BUFFALO
                                                                           MULE CR.,& SH-8 OVER W. CLAY CR.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           & SALT FORK OF THE ARKANSA
 Engineer:            Burke, David
 Contract Amount:     $2,005,469.28                                        Completion Date:             08/31/2011
 Letting Date:        05/20/2010                                           Final Est Sub:



                                            Construction Status Report                                Page 4
 24070(04)     Contract: 100154     US64      Residency:            06100       0.383 MI.;US-64/GRADE,DRAIN,
                                                                                SURFACE & BRIDGE.OVER TWIN
 SSP-102C(109)SS                              BUFFALO
                                                                                SPRINGS CR.,1.6 MI. EAST OF THE
 Contractor:          L & M CONTRACTORS, INC.                                   SH-58 JUNCTION.
 Engineer:            Burke, David
 Contract Amount:     $1,920,007.33                                            Completion Date:               08/22/2012
 Letting Date:        08/19/2010                                               Final Est Sub:




County:          Atoka                                         Commissioner District:                               2
 Contracts Completed - Final Estimate Not Processed


 23144(09)     Contract: 120151     SH-7          Residency:        02200       0.00 MI. SH-7:BRIDGE WATER
                                                                                -PROOF
 BRFY-203C(003)                                   HEAVENER
                                                                                SEAL/US-59/US-79/US-270/SH-37/SH-
 Contractor:          GARY A. CRAIN, INC.                                       82. AT VARIOUS    LOCATIONS IN
 Engineer:            Huddleston, David                                         DIV. II.
 Contract Amount:     $160,145.20                                              Completion Date:               07/19/2012
 Letting Date:        04/19/2012                                               Final Est Sub:




County:          Beaver                                        Commissioner District:                               6
 Contracts Completed - Final Estimate Not Processed


 27005(04)     Contract: 110471    US-83       Residency:           06100       0.00 MI.
                                                                                US-83/US-183/US-281/US-412/SH-23/
 STPG-147B(171)                                BUFFALO
                                                                                SH-34 AT VARIOUS LOCATIONS IN
 Contractor:          ACTION SAFETY SUPPLY CO.                                  DIVISION 6.
 Engineer:            Burke, David
 Contract Amount:     $232,960.31                                              Completion Date:               05/08/2012
 Letting Date:        09/15/2011                                               Final Est Sub:




County:          Beckham                                       Commissioner District:                               5
 Contracts Completed - Final Estimate Not Processed


 28960(04)     Contract: 110499    I-40           Residency:        05100       0.00 MI. I-40B: FLASHING BEACONS
                                                                                FROM 2ND STREET TO WADE STREET
 HSIP-105C(205)TR                                 CLINTON
                                                                                IN THE CITY OF SAYRE
 Contractor:          TRAFFIC SIGNALS, INC.
 Engineer:            Greer, Randy
 Contract Amount:     $17,704.80                                               Completion Date:               03/12/2012
 Letting Date:        10/20/2011                                               Final Est Sub:                 08/20/2012

 24871(05)     Contract: 100420     IS-40    Residency:      05100         0.00 MI.BRIDGE REDECKING/IS
                                                                           -40;REHAB. OVER I-40B & FARM-
 STPY-105N(160)                               CLINTON
                                                                           RAIL CORP. R/R, 4.5 MI. E. OF THE
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           SH-30 JCT.
 Engineer:            Greer, Randy
 Contract Amount:     $1,964,846.55                                        Completion Date:               10/31/2011
 Letting Date:        07/22/2010                                           Final Est Sub:

 20800(04)     Contract: 100060     IS-40B  Residency:              05100       1.809 MI. IS-40B;WIDEN &
                                                                                RESURFACE(ASPHALT)FROM 0.25
 STPY-105A(080)                             CLINTON
                                                                                MIW. OF PIONEER ST. IN ELK
 Contractor:          WITTWER CONSTRUCTION CO., INC.                            CITY, EXTEND EAST.
 Engineer:            Greer, Randy
 Contract Amount:     $5,532,756.64                                            Completion Date:               08/01/2011
 Letting Date:        11/18/2010                                               Final Est Sub:




                                              Construction Status Report                               Page 5
County:          Blaine                                         Commissioner District:                            5
 Contracts Completed - Final Estimate Not Processed


 25453(05)     Contract: 100464   CO.RD.    Residency:     05005             0.436 MI. CO.RD.;BRIDGE &
                                                                             APPROACHES;AT MULTIPLE COUNTY
 ERSTP-106C(92)(110)(99)ER                   CIRCUIT ENGR. DISTR. # 7
                                                                             BRDG. LOCATIONS IN DIV. V.
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY
 Engineer:            CED7
 Contract Amount:     $960,560.57                                            Completion Date:              05/29/2012
 Letting Date:        07/22/2010                                             Final Est Sub:

 27200(04)     Contract: 100063    SH-51      Residency:             05100   *(461)PT.3EH/ 0.822 MI. SH-
                                                                             51/SH-58;PEDESTRIAN IMPROV.
 STP-STIM(461)EH/STP-STIM*                    CLINTON
                                                                             FROM GRANT ST. EXTEND E.,   &
 Contractor:          K & K CONTRACTING, INC.                                SH-58 FROM PK. ST.
 Engineer:            Greer, Randy
 Contract Amount:     $626,582.20                                            Completion Date:              02/27/2012
 Letting Date:        04/15/2010                                             Final Est Sub:                07/30/2012




County:          Bryan                                          Commissioner District:                            2
 Contracts Completed - Final Estimate Not Processed


 07092(07)     Contract: 110231       SH-78  Residency:              02300   0.00 MI. SH-78/RIGHT-OF-   WAY
                                                                             CLEARANCE;FROM 0.25 MI. NORTH
 STPY-107C(174)RW                             MADILL
                                                                             OF THE US-69 JCT,    EXTEND
 Contractor:          SCHIRALLI CONSTRUCTION CORP.                           NORTH.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $118,700.00                                            Completion Date:              06/08/2012
 Letting Date:        08/18/2011                                             Final Est Sub:

 26295(06)     Contract: 090151      US-69  Residency:      02400       8.00 MI. US-69:RESURFACE
                                                                        (CONC.)FROM 1.07 MI. N.E. OF     THE
 NHY-013N(147)3P                             MCALESTER
                                                                        SH-78 JCT, EXTEND NORTH.
 Contractor:          DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
 Engineer:            Plymate, Larry
 Contract Amount:     $4,747,640.36                                     Completion Date:                   12/12/2011
 Letting Date:        01/20/2011                                        Final Est Sub:

 28128(50)     Contract: 120059       US-69   Residency:             02300   33.25 MI. US-69;SAFETY IM-
                                                                             PROVEMENTS(FIBER OPTIC CABLE)
 BTOP-207N(001)                               MADILL
                                                                             FROM THE CITY OF DURANT TO THE
 Contractor:          TRANS-TEL CENTRAL, INC.                                CITY OF ATOKA.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $2,663,361.71                                          Completion Date:              07/31/2012
 Letting Date:        01/19/2012                                             Final Est Sub:

 26148(04)     Contract: 100064       US-69B       Residency:        02300   1.254 MI. US-69B;GRADE,DRAIN
                                                                             ,SURFACE, & BRIDGE.;AT THE US-69
 SSP-107B(148)SS                                   MADILL
                                                                             JUNCTION IN DURANT.
 Contractor:          OBC, INC.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $5,390,236.53                                          Completion Date:              11/16/2011
 Letting Date:        02/18/2010                                             Final Est Sub:

 23417(04)     Contract: 100368       US-70        Residency:        02300   0.505 MI. US-70;BRIDGE &
                                                                             APPROACHES;OVER UNION PACIFIC
 HPPY-022N(163)HP                                  MADILL
                                                                             R/R,2.0 MI. EAST OF THE US- 69 JCT
 Contractor:          L & N BRIDGE, LLC                                      IN THE CITY OF DURANT.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $4,684,898.34                                          Completion Date:              01/12/2012
 Letting Date:        07/22/2010                                             Final Est Sub:



                                               Construction Status Report                            Page 6
 18847(06)     Contract: 090564       US-70       Residency:        02300   2.032 MI. US-70 BYPASS;     FROM
                                                                            3.04 MI. S.E. OF US-70, EXTEND
 SAP-022N(089)                                    MADILL
                                                                            EAST TO SH-78.
 Contractor:          OBC, INC.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $13,232,378.18                                        Completion Date:               05/15/2012
 Letting Date:        10/15/2009                                            Final Est Sub:

 18847(04)     Contract: 090401       US-70       Residency:        02300   2.738 MI. GRD., DRN., BR. &
                                                                            EROSION CNTRL. US-70 BYPASS
 ACNHY-022N(87)(88)GB                             MADILL
                                                                            FROM US-70 (EW-208) EXT. S.; FROM
 Contractor:          L & N BRIDGE, LLC                                     1.64 MI. S. US-70 EXT. S.E.
 Engineer:            Eldridge, Jerry
 Contract Amount:     $24,231,482.43                                        Completion Date:               12/04/2011
 Letting Date:        05/14/2009                                            Final Est Sub:




County:          Caddo                                         Commissioner District:                             7
 Contracts Completed - Final Estimate Not Processed


 27424(04)     Contract: 110232     CO.RD         Residency:        07300   1.717 MI. CO.RD.;GRADE,DRAIN &
                                                                            SURFACE/FROM 3.2 MI. EAST OFTHE
 CIRB-108C(282)RB                                 ANADARKO
                                                                            SH-146 JCT, EXTEND EAST.
 Contractor:          SEWELL BROS., INC.
 Engineer:            Knight, Reese
 Contract Amount:     $1,295,447.95                                         Completion Date:               08/08/2012
 Letting Date:        04/14/2011                                            Final Est Sub:

 26867(04)     Contract: 110373     CORD          Residency:        07300   0.160 MI. CO.RD./BRIDGE &
                                                                            APPROACHES;OVER CEDAR CR.,6.0
 BRF-108C(277)CI                                  ANADARKO
                                                                            MI. SOUTH OF THE SH-8/SH- 152
 Contractor:          SEWELL BROS., INC.                                    JUNCTION IN BINGER.
 Engineer:            Knight, Reese
 Contract Amount:     $339,055.62                                           Completion Date:               06/21/2012
 Letting Date:        08/18/2011                                            Final Est Sub:

 24073(04)     Contract: 090565      I-40   Residency:              05200   *(078)087ER/0.153 MI. GRADE,
                                                                            DRAIN & BRIDGE IMPROVEMENT I-40
 BHFY-108C(163)/ERIM-40-3*                   ALTUS
                                                                            FRONTAGE RD. 0.85 MI. & 1.30 MI. E.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                        OF THE CUSTER C/L.
 Engineer:            Nedbalek, Will
 Contract Amount:     $1,435,216.20                                         Completion Date:               07/19/2010
 Letting Date:        09/17/2009                                            Final Est Sub:

 28749(04)     Contract: 110407     PKRD    Residency:              07300   3.100 MI. PK.RD.:RESURFACE
                                                                            (ASPHALT)AT VARIOUS LOCATIONS
 SAP-108D(303)(304)(305)                    ANADARKO
                                                                            AT FT. COBB ST. PARK.
 Contractor:          MARKWELL PAVING COMPANY, INC.
 Engineer:            Knight, Reese
 Contract Amount:     $558,930.00                                           Completion Date:               12/23/2011
 Letting Date:        07/21/2011                                            Final Est Sub:                 06/14/2012

 21713(09)     Contract: 080303     SH-19      Residency:           07300   2.841 MI. GRADE, DRAIN & SURFACE
                                                                            SH-19 FROM 5.5 MI. EAST OF JCT.
 BRFY-108C(140)                                ANADARKO
                                                                            US-62 EXTEND EAST.
 Contractor:          T & G CONSTRUCTION, INC.
 Engineer:            Knight, Reese
 Contract Amount:     $5,629,322.71                                         Completion Date:               07/12/2012
 Letting Date:        01/22/2009                                            Final Est Sub:

 27228(04)     Contract: 100054     SH-37    Residency:    07300            *(280)PT.2/ 6.76 MI. SH-37;
                                                                            RESURFACE (ASPHALT)BEGIN JUST
 MC-108C(281)PT.1/MC-108C*                   ANADARKO
                                                                            EAST OF US-281 JCT, AND
 Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.                EXTEND EAST.
 Engineer:            Knight, Reese
 Contract Amount:     $365,144.60                                           Completion Date:               07/08/2011
 Letting Date:        02/18/2010                                            Final Est Sub:                 09/27/2011


                                              Construction Status Report                             Page 7
 28565(04)     Contract: 110281     SH-37   Residency:             07300       5.99 MI. SH-37:RESURFACE
                                                                               (ASPHALT)FROM THE SH-152
 MC-108C(298) PART 1 & 2                     ANADARKO
                                                                               JUNC-TION, EXTEND NORTH.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Knight, Reese
 Contract Amount:     $856,408.70                                              Completion Date:             01/11/2012
 Letting Date:        06/16/2011                                               Final Est Sub:               07/18/2012




County:          Canadian                                     Commissioner District:                              4
 Contracts Completed - Final Estimate Not Processed


 26646(04)     Contract: 110509      CORD        Residency:        04200       1.006 MI. CO.RD./GRADE,DRAIN &
                                                                               SURFACE;FROM THE KINGFISHER
 STP-109C(159)CI                                 EL RENO
                                                                               C/L., EXTEND SOUTH.
 Contractor:          ATLAS PAVING COMPANY
 Engineer:            Vonfeldt, Cole
 Contract Amount:     $1,023,031.08                                            Completion Date:             05/15/2012
 Letting Date:        11/17/2011                                               Final Est Sub:

 20539(04)     Contract: 090321      I-40   Residency:      04200       *STIM(15)/IMG-40-4(421)TR 7.39 MI.
                                                                        RECONSTRUCT (ADDED LANE),
 IMY-040-4(396)128SS/IM-*                    EL RENO
                                                                        BRIDGE & SAFTEY IMPROVEMENT
 Contractor:          DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
                                                                        I-40 FROM M.M. 124 TO M.M. 136.
 Engineer:            Vonfeldt, Cole
 Contract Amount:     $59,384,562.21                                    Completion Date:              10/25/2011
 Letting Date:        03/19/2009                                        Final Est Sub:

 26224(04)     Contract: 110397    IS-40       Residency:     04010            9.03 MI. IS-40 SAFETY IMPRO
                                                                               -VEMENT (CABLE BARRIER)FROM 8
 IMG-0040-4(424)111TR                          ATKINS (AKA - PBS & J)
                                                                               MILES WEST OF THE US-270 JCT,
 Contractor:          ACTION SAFETY SUPPLY CO.                                 EXTEND EAST.
 Engineer:            ATKINS (AKA - PBSJ)
 Contract Amount:     $984,788.73                                              Completion Date:             04/13/2012
 Letting Date:        06/30/2011                                               Final Est Sub:

 18257(04)     Contract: 090078     US-281  Residency:             04300       3.30 MI. GRADE, DRAIN & SURFACE
                                                                               US-281 FROM NEW US-281 SPUR
 SEC1702Y-130N(130)HP                        ENID
                                                                               EXTEND NORTH.
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $6,715,437.15                                            Completion Date:             10/31/2011
 Letting Date:        02/19/2009                                               Final Est Sub:

 20227(04)     Contract: 090029     US-81    Residency:      07300         1.278 MI. GRADE, DRAIN, SURFACE &
                                                                           BRIDGE US-81 OVER SOUTH
 BRFY-011N(053)                               ANADARKO
                                                                           CANADIAN RIVER NORTH OF THE
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           CITY OF MINCO.
 Engineer:            Knight, Reese
 Contract Amount:     $7,435,339.82                                        Completion Date:              08/22/2011
 Letting Date:        05/14/2009                                           Final Est Sub:                05/23/2012

 05173(12)     Contract: 090016      US-81  Residency:             04200       3.902 MI. GRADE, DRAIN & SURFACE
                                                                               US-81 BEGIN AT THE SH-152 JCT. &
 NHY-011N(008)                               EL RENO
                                                                               EXTEND NORTH.
 Contractor:          DUIT CONSTRUCTION COMPANY, INC.
 Engineer:            Vonfeldt, Cole
 Contract Amount:     $7,978,265.75                                            Completion Date:             06/07/2010
 Letting Date:        01/22/2009                                               Final Est Sub:




County:          Carter                                       Commissioner District:                              7
 Contracts Completed - Final Estimate Not Processed



                                             Construction Status Report                               Page 8
24103(04)     Contract: 090597    I-35    Residency:             07200   2.473 MI. GRADE, DRAIN, SURFACE &
                                                                         BRIDGE I-35 FROM 4.1 MILES NORTH
IMY-0035-1(145)029                         ARDMORE
                                                                         OF THE LOVE COUNTY LINE AND
Contractor:          DOBSON BROTHERS CONSTRUCTION CO.                    EXTEND NORTH.
Engineer:            Earp, Jay
Contract Amount:     $21,601,135.43                                      Completion Date:              11/02/2010
Letting Date:        10/15/2009                                          Final Est Sub:                05/22/2012

27987(04)     Contract: 110398     IS-35   Residency:            07200   8.20 MI. IS-35:SAFETY IMPRO
                                                                         -VEMENT(CABLE BARRIER)FROM
IMG-0035-1(158)027TR                       ARDMORE
                                                                         2.56 MI. NORTH OF THE LOVE C/L.,
Contractor:          FULSOM CONSTRUCTION COMPANY, INC.                   EXTEND NORTH.
Engineer:            Earp, Jay
Contract Amount:     $1,155,791.14                                       Completion Date:              08/17/2012
Letting Date:        06/30/2011                                          Final Est Sub:

12665(04)     Contract: 020039    IS-35      Residency:          07200   7.04 MI. RESURFACE (CONCRETE)
                                                                         I-35 FROM 7.0 MI. N. OF US-70
IMY-35-1(101)038IR                           ARDMORE
                                                                         EXTEND N. TO MURRAY COUNTY LINE.
Contractor:          KECK CONSTRUCTION, INC.
Engineer:            Earp, Jay
Contract Amount:     $10,106,331.30                                      Completion Date:              04/30/2008
Letting Date:        08/22/2002                                          Final Est Sub:                12/15/2011

19739(04)     Contract: 020131    SH-53       Residency:         07200   0.00 M. BR. PAINT SH-53: BR. OVER
                                                                         SPRING, HICKORY &       HENRY
MC-110C(93)                                    ARDMORE
                                                                         HORSE CREEKS, EAST OF
Contractor:          KERRVILLE PAINTING CO., INC.                        SH-53/SH-76.
Engineer:            Earp, Jay
Contract Amount:     $64,300.00                                          Completion Date:              12/13/2002
Letting Date:        03/21/2002                                          Final Est Sub:                02/24/2005

28095(04)     Contract: 110178    SH-53A    Residency:    07200          1.00 MI. SH-53A;RESURFACE
                                                                         (ASPHALT)FROM 1.00 MI. S. OF THE
MC-110C(231)                                ARDMORE
                                                                         SH-53 JCT., EXTEND NORTH.
Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.
Engineer:            Earp, Jay
Contract Amount:     $149,230.00                                         Completion Date:              05/31/2012
Letting Date:        03/17/2011                                          Final Est Sub:                06/22/2012

09247(14)     Contract: 090279     US-70    Residency:    07200          3.367 MI. GRD., DRN., SURF., & BR.
                                                                         US-70 BEG. AT JEFFERSON C/L EXT.
STP-STIM(038)(040)                          ARDMORE
                                                                         E./OVER RED OAK CRK. 1.8 MI. E. OF
Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.              JEFFERSON C/L.
Engineer:            Earp, Jay
Contract Amount:     $7,352,000.00                                       Completion Date:              08/15/2012
Letting Date:        03/19/2009                                          Final Est Sub:

09247(04)     Contract: 080258     US-70       Residency:        07200   1.929 MI. GRADE, DRAIN & SURFACE
                                                                         US-70 BEGIN 2.1 MI. W. OF JCT.
STPY-010B(302)                                 ARDMORE
                                                                         US-70/SH-76 & EXTEND EAST.
Contractor:          OVERLAND CORPORATION
Engineer:            Earp, Jay
Contract Amount:     $5,739,555.91                                       Completion Date:              12/16/2011
Letting Date:        11/20/2008                                          Final Est Sub:                08/27/2012

09477(04)     Contract: 090613     US-70       Residency:        07200   *(207)SB / 0.804 MI. US-70
                                                                         ;GRADE,DRAIN,SURFACE, BRIDGE.
SAP-10B(304)/SBR-110B*                         ARDMORE
                                                                         OVER COTTON WOOD CR. 8.5    MI.
Contractor:          OBC, INC.                                           WEST OF IS-35.
Engineer:            Earp, Jay
Contract Amount:     $3,489,259.82                                       Completion Date:              07/11/2011
Letting Date:        10/15/2009                                          Final Est Sub:                04/13/2012

28159(04)     Contract: 120083   US70          Residency:        07200   0.780 MI. US-70;RESURFACE
                                                                         (ASPHALT)FROM IS-35, EXTEND
NHY-022N(203)3P                                ARDMORE
                                                                         EAST.
Contractor:          OVERLAND CORPORATION
Engineer:            Earp, Jay
Contract Amount:     $607,907.14                                         Completion Date:              08/23/2012
Letting Date:        02/16/2012                                          Final Est Sub:

                                           Construction Status Report                             Page 9
County:         Cherokee                                       Commissioner District:                            1
 Contracts Completed - Final Estimate Not Processed


 28760(04)     Contract: 110460      SH-51        Residency:        01100    0.00 MI. SH-51 AT THE
                                                                             INTERSECTION OF W 4TH STREET IN
 HSIP-111A(136)TR                                 MUSKOGEE
                                                                             CITY OF TAHLEQUAH.
 Contractor:          TRAFFIC SIGNALS, INC.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $121,929.50                                            Completion Date:             05/14/2012
 Letting Date:        09/15/2011                                             Final Est Sub:

 27303(04)     Contract: 100211   SH-51     Residency:     01011             0.00 MI. SH-51;BRIDGE REHAB.
                                                                             ;OVER DOUBLE SPRING CR.,6.9
 STPY-111B(127)                              GARVER, LLC.
                                                                             MIEAST OF THE WAGONER COUNTY
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC               LINE.
 Engineer:            GARV
 Contract Amount:     $574,517.60                                            Completion Date:             09/30/2011
 Letting Date:        07/22/2010                                             Final Est Sub:

 23108(04)     Contract: 090332     SH-82    Residency:      01200         0.90 MI.;SH-82;BRIDGE &
                                                                           APPROACHES/OVER TERRAPIN CR.,
 SSP-111C(087)SS                              SALLISAW
                                                                           3.6 MI. N. OF SEQUOYAH
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)LINE.
                                                                           COUNTY
 Engineer:            Edwards, Carl
 Contract Amount:     $3,818,345.34                                        Completion Date:           08/03/2011
 Letting Date:        05/14/2009                                           Final Est Sub:




County:         Choctaw                                        Commissioner District:                            2
 Contracts Completed - Final Estimate Not Processed


 20920(04)     Contract: 110138     SH-2          Residency:        02200    0.00 MI.;SH-2 JOINT SEAL/
                                                                             REPAIR:SH-93/SH-113:AT MULTI- PLE
 BHFY-164F(164)                                   HEAVENER
                                                                             LOCATIONS IN DIV. II
 Contractor:          PBX CORPORATION
 Engineer:            Huddleston, David
 Contract Amount:     $247,851.00                                            Completion Date:             07/01/2012
 Letting Date:        01/20/2011                                             Final Est Sub:

 28462(04)     Contract: 120129    US-271         Residency:        02100    0.244 MI. US-271/ INTERSEC TION
                                                                             ODIFICATION:AT COX ROAD IN THE
 HSIPY-112A(097)TR                                ANTLERS
                                                                             CITY OF GRANT.
 Contractor:          L & N BRIDGE, LLC
 Engineer:            Moy, Ryan
 Contract Amount:     $388,196.92                                            Completion Date:             08/08/2012
 Letting Date:        03/15/2012                                             Final Est Sub:

 16745(04)     Contract: 980376     US070         Residency:        02100    5.26700 MIS. WIDEN & RESURF. ON
                                                                             US-70 BEG. APPROX. 0.75 MI. E. OF
 CIP-112N(10)IP                                   ANTLERS
                                                                             THE JCT. OF US-70/SH-109 & EXT.
 Contractor:          PAVERS, INC.                                           EAST.
 Engineer:            Moy, Ryan
 Contract Amount:     $2,367,601.65                                          Completion Date:             08/04/2000
 Letting Date:        06/25/1998                                             Final Est Sub:               01/11/2002




County:         Cimarron                                       Commissioner District:                            6
 Contracts Completed - Final Estimate Not Processed




                                              Construction Status Report                            Page 10
 13337(16)     Contract: 090518      US-287 Residency:            06200      2.979 MI. GRADE, DRAIN, SURFACE &
                                                                             BRIDGE US-287 NORTH      SECTION
 NCIPY-017N(190)NI                          GUYMON
                                                                             OF BOISE CITY BYPASS.
 Contractor:          DOBSON BROTHERS CONSTRUCTION CO.
 Engineer:            Michael, Charles
 Contract Amount:     $7,612,874.65                                          Completion Date:              09/18/2011
 Letting Date:        08/20/2009                                             Final Est Sub:

 29248(04)     Contract: 120155      US-385 Residency:            06200      7.00 MI. US-385;RESURFACE
                                                                             (ASPHALT)FROM THE TX. STATE
 MC-213C(002)                                GUYMON
                                                                             LINE, EXTEND NORTH
 Contractor:          HIGHWAY CONTRACTORS, INC.
 Engineer:            Michael, Charles
 Contract Amount:     $530,654.60                                            Completion Date:              08/15/2012
 Letting Date:        04/19/2012                                             Final Est Sub:




County:         Cleveland                                    Commissioner District:                              3
 Contracts Completed - Final Estimate Not Processed


 24611(04)     Contract: 110464     CORD    Residency:            03200      .014 MI. CORD(EW-132) OVER
                                                                             SPRING CREEK, 4.5 MI. W OF POTT.
 BRO-114D(202)CO                             PURCELL
                                                                             COUNTY LINE.
 Contractor:          KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:            Riemer, Caleb
 Contract Amount:     $157,039.70                                            Completion Date:              03/29/2012
 Letting Date:        09/15/2011                                             Final Est Sub:                08/15/2012

 14391(04)     Contract: 070429     CT. ST. Residency:            03002      1.920 MI GRD, DRN, SURF, & BR
                                                                             (TRAFF SIG) CITY ST (TECUMSEH RD)
 STPY-014B(378)                              TETRA TECH
                                                                             BEG APPROX 0.3 MI E OF 12TH AVE
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                         NW & EXT E IN NORMAN.
 Engineer:            TETR
 Contract Amount:     $7,039,963.90                                          Completion Date:              08/31/2009
 Letting Date:        11/15/2007                                             Final Est Sub:                07/20/2011

 09034(05)     Contract: 080461     I-35    Residency:            03200      4.594 MI. GRADE, DRAIN, SURFACE &
                                                                             BRIDGE I-35 FROM 0.5 MI. N. OF
 SEC1702Y-114A(191)HP                        PURCELL
                                                                             MAIN ST. & EXTEND NORTH.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Riemer, Caleb
 Contract Amount:     $35,304,952.60                                         Completion Date:              09/30/2010
 Letting Date:        12/18/2008                                             Final Est Sub:

 20997(15)     Contract: 110086     US-77    Residency:           03200      0.00 MI. US-77:RIGHT-OF- WAY
                                                                             CLEARANCE FROM 6.05 MI. NORTH
 STPY-114C(293)RW                            PURCELL
                                                                             OF SH-39 JCT, EXTEND NORTH.
 Contractor:          MIDWEST WRECKING, INC.
 Engineer:            Riemer, Caleb
 Contract Amount:     $41,210.00                                             Completion Date:              10/13/2011
 Letting Date:        02/17/2011                                             Final Est Sub:                08/13/2012




County:         Comanche                                     Commissioner District:                              7
 Contracts Completed - Final Estimate Not Processed


 23411(04)     Contract: 080435     CT.ST.  Residency:      07004       1.027 MI. GRADE, DRAIN, SURFACE,
                                                                        BRIDGE & SIGNALS CITY ST. (N.W.
 STP-116B(138)MS                             JACOBS (AKA - CARTER-BURGESS)
                                                                        67TH ST.) FROM CACHE RD. TO
 Contractor:          DUIT CONSTRUCTION COMPANY, INC.                   ROGERS LN. IN LAWTON.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $4,889,495.46                                     Completion Date:              10/31/2010
 Letting Date:        09/18/2008                                        Final Est Sub:



                                            Construction Status Report                               Page 11
27048(04)     Contract: 100429      CTST      Residency:         07100   0.383 MI. CT.ST./GRADE,DRAIN ,AND
                                                                         SURFACE;US-62 AT FT.SILL BLVD.
NHY-020N(30)(32)                              DUNCAN
                                                                         INTERCHANGE,AND @ SHERI -DAN
Contractor:          T & G CONSTRUCTION, INC.                            RD. IN LAWTON.
Engineer:            Harwell, Jerry M.
Contract Amount:     $1,307,942.52                                       Completion Date:                02/29/2012
Letting Date:        09/16/2010                                          Final Est Sub:

20299(04)     Contract: 080135      I-44       Residency:        07100   0.376 MI. BRIDGE & APPROACHES
                                                                         I-44 BRIDGES AT MEDICINE BLUFF
BRIY-0044-1(069)043                            DUNCAN
                                                                         CRK. APPROX. 2.0 MI. N. OF US-62.
Contractor:          SEWELL BROS., INC.
Engineer:            Harwell, Jerry M.
Contract Amount:     $4,794,148.08                                       Completion Date:                04/08/2010
Letting Date:        03/20/2008                                          Final Est Sub:                  08/04/2011

20951(05)     Contract: 100374   IS-35         Residency:     07001      0.00 MI. IS-35/I-44/SH-5;    JOINT
                                                                         SEAL/REPR.;AT MULTIPLE
BRFY-116C(191)                                 ENGR. SERV. & TESTING
                                                                         LOCATIONS IN DIV. VII.
Contractor:          PBX CORPORATION
Engineer:            EST
Contract Amount:     $456,760.00                                         Completion Date:                02/08/2012
Letting Date:        06/17/2010                                          Final Est Sub:                  08/09/2012

25027(04)     Contract: 090117      IS-44     Residency:         07100   *21N(52)3P / 3.85 MI. IS-44 /BEGIN
                                                                         2.5 MI. N. OF US-281B, EXTEND N.
IMY-44-1(120)12 3P/NHY-*                      DUNCAN
                                                                         SH-7 FROM THE IS -44 JCT,EXTEND
Contractor:          T & G CONSTRUCTION, INC.                            EAST.
Engineer:            Harwell, Jerry M.
Contract Amount:     $1,247,960.80                                       Completion Date:                08/23/2011
Letting Date:        02/17/2011                                          Final Est Sub:

28592(04)     Contract: 110375    IS-44       Residency:     07001       0.00 MI. IS-44:BRIDGE PAINT- ING;
                                                                         1.7 MI. NORTH OF US-62.
BRFY-NBIP(446)3B                              ENGR. SERV. & TESTING
Contractor:          K.V.K. CONTRACTING, INC.
Engineer:            EST
Contract Amount:     $410,599.00                                         Completion Date:                03/15/2012
Letting Date:        08/18/2011                                          Final Est Sub:                  08/15/2012

27052(04)     Contract: 100570      IS-44 Residency:             07100   *-1(114)42TR/NHIY-3N(01)/ 8. 782
                                                                         MI. IS-44;RESURFACE(ASPHALT)&
IMG-44-1(115)37TR/IMG-44*                  DUNCAN
                                                                         SAFETY IMPR.(CABLE BARR- IER)
Contractor:          DOBSON BROTHERS CONSTRUCTION CO.                    FROM US-281B JCT,EXT.NE
Engineer:            Harwell, Jerry M.
Contract Amount:     $4,537,111.50                                       Completion Date:                06/04/2012
Letting Date:        10/21/2010                                          Final Est Sub:

28592(05)     Contract: 110376      IS-44   Residency:           07100   0.00 MI. IS-44;JOINT SEAL/
                                                                         REPR.;AT VARIOUS LOCATIONS IN
BRFY-116N(207)3B                             DUNCAN
                                                                         DIV. VII.
Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.
Engineer:            Harwell, Jerry M.
Contract Amount:     $84,170.00                                          Completion Date:                06/06/2012
Letting Date:        11/17/2011                                          Final Est Sub:

27478(04)     Contract: 100516     SH-115 Residency:             07300   2.85 MI. SH-115;GRADE,DRAIN, AND
                                                                         SURFACE;FROM THE US-62
STP-116C(194)SS                            ANADARKO
                                                                         JUNCTION,EXTEND N. TO THE
Contractor:          DOBSON BROTHERS CONSTRUCTION CO.                    WICHITA MTS. WILDLIFE REFUGE P
Engineer:            Knight, Reese
Contract Amount:     $2,196,092.10                                       Completion Date:                08/14/2012
Letting Date:        10/21/2010                                          Final Est Sub:

28482(04)     Contract: 110364      SH-281A Residency:           07100   0.00 MI. SH-281A/SCHOOL ZONE
                                                                         :FROM THE SH-277 JUNCTION IN
STPY-116C(203)TR                            DUNCAN
                                                                         GERONIMO, EXTEND EAST.
Contractor:          MIDSTATE TRAFFIC CONTROL, INC.
Engineer:            Harwell, Jerry M.
Contract Amount:     $14,615.50                                          Completion Date:                09/16/2011
Letting Date:        06/16/2011                                          Final Est Sub:

                                           Construction Status Report                                Page 12
 10439(07)     Contract: 090311      SH-7    Residency:      07100         0.381 MI. GRADE, DRAIN, SURFACE &
                                                                           BRIDGE SH-7 OVER BEAVER CRK.
 STP-STIM(037)                                DUNCAN
                                                                           2.44 MI. W. OF COMANCHE /
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) COUNTY LINE.
                                                                           STEPHENS
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $2,359,697.73                                        Completion Date:              12/31/2010
 Letting Date:        03/19/2009                                           Final Est Sub:




County:          Cotton                                       Commissioner District:                              7
 Contracts Completed - Final Estimate Not Processed


 24114(08)     Contract: 110239      SH-36     Residency:     07100            0.00 MI. SH-36: RIGHT-OF-WAY
                                                                               CLEARANCE;FROM THE IS-44 JCT,
 STPY-117C(089)RW                               DUNCAN
                                                                               EXTEND NORTH.
 Contractor:          K & M DIRT SERVICES, LLC DBA K & M WRECKING
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $39,850.00                                               Completion Date:             05/31/2012
 Letting Date:        04/14/2011                                               Final Est Sub:

 27210(04)     Contract: 100072      SH65      Residency:          07100       *(471)PT.3EH / 0.719 MI. SH
                                                                               -65;PEDESTRIAN IMPROV./RESUR-
 STP-STIM(471)EH/STP-STIM*                     DUNCAN
                                                                               FACE(ASPHALT)FROM OREGON ST.
 Contractor:          T & G CONSTRUCTION, INC.                                 ,EXTEND S. TO OKLA. ST. IN TEM
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $463,962.76                                              Completion Date:             03/18/2011
 Letting Date:        04/15/2010                                               Final Est Sub:




County:          Craig                                        Commissioner District:                              8
 Contracts Completed - Final Estimate Not Processed


 23418(04)     Contract: 110106    CORD          Residency:   08003            0.610 MI. CO.RD.:BRIDGE &
                                                                               APPROACHES:OVER BIG CABIN
 BRF-118C(070)CI                                 COBB ENGINEERING CO., INC.
                                                                               CR.,2.3 MI. W. OF THE SH-2
 Contractor:          BELK BRIDGE, INC.                                        JUNCTION.
 Engineer:            COBB
 Contract Amount:     $969,552.50                                              Completion Date:             03/15/2012
 Letting Date:        01/20/2011                                               Final Est Sub:

 23419(04)     Contract: 100553     CORD         Residency:        08012       0.388 MI. CO.RD.;BRIDGE &
                                                                               APPROACHES;OVER PAW PAW CR.,
 CIRB-118D(071)RB                                PSA-DEWBERRY
                                                                               5.0 MI. W. OF THE SH-2
 Contractor:          BELK BRIDGE, INC.                                        JUNCTION.
 Engineer:            PSAD
 Contract Amount:     $1,052,145.67                                            Completion Date:             10/31/2011
 Letting Date:        10/21/2010                                               Final Est Sub:               08/24/2012

 21906(04)     Contract: 110395     US-60      Residency:    08300        0.364 MI. US-60/BRIDGE &
                                                                          APPROACHES:OVER SL & SF RAIL-
 NHY-018N(057)                                 CLAREMORE
                                                                          ROAD, 0.60 MI. NW OF THE  SH-66
 Contractor:                                                               (JV)
                      OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLCJUNCTION.
 Engineer:            Bray, Timothy
 Contract Amount:     $2,284,073.57                                       Completion Date:             06/27/2012
 Letting Date:        08/18/2011                                          Final Est Sub:

 16229(04)     Contract: 090036     US-60     Residency:           08300       0.59 MI. GRADE, DRAIN, SURFACE &
                                                                               BRIDGE US-60 OVER BULL CRK. 0.5
 BRFY-018N(009)DC                             CLAREMORE
                                                                               MI. E. OF JCT. SH-2.
 Contractor:          BECCO CONTRACTORS, INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $5,381,584.57                                            Completion Date:             05/25/2010
 Letting Date:        01/22/2009                                               Final Est Sub:



                                             Construction Status Report                                Page 13
 20886(04)     Contract: 100482     US-60   Residency:            08300       0.529 MI. US-60;BRIDGE &
                                                                              APPROACHES.OVER LEGION CABIN
 SSP-118B(038)SS                             CLAREMORE
                                                                              CR.,2.6 MI. EAST OF THE  SH-2
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY                         JUNCTION.
 Engineer:            Bray, Timothy
 Contract Amount:     $2,836,834.48                                           Completion Date:              09/30/2011
 Letting Date:        08/19/2010                                              Final Est Sub:

 27781(05)     Contract: 100619   US-69       Residency:     08001            0.00 MI. US-69/US-75/SH-
                                                                              28/SH-48/JOINT SEAL/REPAIR;AT
 BPMY-172F(500)3B                             ENGR. SERV. & TESTING
                                                                              VARIOUS LOCATIONS IN DIV.   VIII.
 Contractor:          KEYSTONE SERVICES, INC.
 Engineer:            EST
 Contract Amount:     $347,344.70                                             Completion Date:              08/28/2012
 Letting Date:        11/18/2010                                              Final Est Sub:




County:          Creek                                       Commissioner District:                               8
 Contracts Completed - Final Estimate Not Processed


 22145(04)     Contract: 080056     CO. RD.   Residency:   08400              1.254 MI. GRADE, DRAIN, SURFACE &
                                                                              BRIDGE CO. RD. (S. 49TH W. AVE.)
 STP-119C(122)IG                              SAND SPRINGS
                                                                              FROM CREEK TURNPIKE EXTEND N.
 Contractor:          BECCO CONTRACTORS, INC.                                 TO 91ST ST. S.
 Engineer:            Williams, Mark J.
 Contract Amount:     $4,372,114.25                                           Completion Date:              03/31/2010
 Letting Date:        01/17/2008                                              Final Est Sub:

 22350(04)     Contract: 100028     CO.RD.    Residency:          08002       0.862 MI. CO.RD.;GRADE,DRAIN &
                                                                              SURFACE;(W. 81ST. ST.)FROM
 STP-STIM(275)IG                              TETRA TECH
                                                                              FRANKHOMA RD., EXTEND EAST.
 Contractor:          BECCO CONTRACTORS, INC.
 Engineer:            TETR
 Contract Amount:     $1,640,579.05                                           Completion Date:              11/07/2011
 Letting Date:        04/15/2010                                              Final Est Sub:

 18168(04)     Contract: 110008     CORD     Residency:   08400               0.207 MI. CO.RD.:BRIDGE &
                                                                              APPROACHES:OVER BUCKEYE CR.,
 BRO-119D(044)CO                             SAND SPRINGS
                                                                              4.7 MI. EAST OF THE SH-99
 Contractor:          BRIDGECO CONTRACTORS, INC.                              JUNCTION.
 Engineer:            Williams, Mark J.
 Contract Amount:     $736,531.95                                             Completion Date:              07/26/2012
 Letting Date:        01/20/2011                                              Final Est Sub:

 25446(04)     Contract: 110049     SH-117    Residency:   08400              5.45 MI. SH-117:RESURFACE
                                                                              (ASPHALT)FROM THE US-75A JCT,
 SSR-119B(175)(210)SR                         SAND SPRINGS
                                                                              EXTEND E. SH-117A:FROM THE
 Contractor:          BECCO CONTRACTORS, INC.                                 SH-117 JCT, EXTEND NORTH.
 Engineer:            Williams, Mark J.
 Contract Amount:     $1,152,073.59                                           Completion Date:              09/15/2011
 Letting Date:        01/20/2011                                              Final Est Sub:                08/14/2012

 20889(04)     Contract: 090522     SH-16    Residency:      08400         0.151 MI. SH-16;GRADE,DRAIN,
                                                                           SURFACE, & BRIDGE;OVER BROWNS
 BRFY-119C(099)DC                             SAND SPRINGS
                                                                           CR. 1.7 MI. W. OF OKMULGEE CL.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Williams, Mark J.
 Contract Amount:     $1,296,236.93                                        Completion Date:             07/30/2011
 Letting Date:        08/20/2009                                           Final Est Sub:               09/14/2011

 27621(04)     Contract: 110050     SH-33       Residency:        08400       13.14 MI. SH-33:RESURFACE
                                                                              (ASPHALT)FROM 3.0 MI. W. OF
 STPY-119B(207)(208)3P                          SAND SPRINGS
                                                                              SH-48 JCT, EXTEND EAST.
 Contractor:          THE QUAPAW COMPANY
 Engineer:            Williams, Mark J.
 Contract Amount:     $3,293,426.20                                           Completion Date:              02/12/2012
 Letting Date:        02/17/2011                                              Final Est Sub:                07/02/2012


                                            Construction Status Report                                Page 14
 27625(04)     Contract: 110052     SH-66   Residency:    08400              0.00 MI. SH-66; BRIDGE REHAB.
                                                                             OVER LITLE POLECAT CR., 13.4 MI.
 SBR-119C(209)SB                             SAND SPRINGS
                                                                             N.E. OF THE SH-48 JCT.
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY
 Engineer:            Williams, Mark J.
 Contract Amount:     $885,773.73                                            Completion Date:              03/13/2012
 Letting Date:        01/20/2011                                             Final Est Sub:

 10157(04)     Contract: 070338     SH-66     Residency:   08400             1.461 MI. GRADE, DRAIN, BRIDGE,
                                                                             SIGNALS, EROSION CONTROL &
 STPY-019A(314)BF                             SAND SPRINGS
                                                                             SURFACE SH-66 FROM SH-117 ON W.
 Contractor:          BECCO CONTRACTORS, INC.                                EDGE OF SAPULPA & EXTEND E.
 Engineer:            Williams, Mark J.
 Contract Amount:     $8,991,481.69                                          Completion Date:              01/27/2010
 Letting Date:        10/18/2007                                             Final Est Sub:




County:         Custer                                        Commissioner District:                             5
 Contracts Completed - Final Estimate Not Processed


 27036(04)     Contract: 100461     I-40         Residency:        05100     10.899 MI.;IS-40/SAFETY
                                                                             IMPROVEMENT (CABLE BARRIER)
 IMG-0040-2(141)049SS                            CLINTON
                                                                             FROM MILE MARKER 49, EXTEND
 Contractor:          JLT CONTRACTING, LLC                                   EAST TO MILE MARKER 61.
 Engineer:            Greer, Randy
 Contract Amount:     $1,815,949.15                                          Completion Date:              08/22/2011
 Letting Date:        07/22/2010                                             Final Est Sub:                07/09/2012

 26035(04)     Contract: 110284      SH-33     Residency:    05200        0.00 MI. SH-33:BRIDGE REHA-
                                                                          BILITATION/OVER THE WASHITA
 SBR-120C(168)SB                               ALTUS
                                                                          RIVER OVERFLOW,5.3 MI. EAST OF
 Contractor:                                                               (JV)
                      OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLCTHE SH-34 JCT.
 Engineer:            Nedbalek, Will
 Contract Amount:     $1,519,752.04                                       Completion Date:            02/02/2012
 Letting Date:        06/16/2011                                          Final Est Sub:              07/09/2012

 24377(04)     Contract: 110240    SH-33     Residency:            05100     0.00 MI.SH-33/BRIDGE WATER
                                                                             PROOF SEAL;SH-30/SH-9/US-183/
 BRFY-120C(139)                               CLINTON
                                                                             IS-40;AT VARIOUS LOCATIONS IN
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.                  DIV. V.
 Engineer:            Greer, Randy
 Contract Amount:     $47,554.20                                             Completion Date:              12/16/2011
 Letting Date:        04/14/2011                                             Final Est Sub:

 18779(09)     Contract: 090042     SH-34   Residency:             05100     7.237 MI. GRADE, DRAIN, SURFACE,
                                                                             SIGNING & STRIPING SH-34 BEGIN
 SSP-120B(076)SS                             CLINTON
                                                                             JUST NORTH OF SH-47 & EXTEND
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.                     SOUTH.
 Engineer:            Greer, Randy
 Contract Amount:     $6,915,164.51                                          Completion Date:              08/31/2011
 Letting Date:        06/18/2009                                             Final Est Sub:

 02077(04)     Contract: 070178     US-183  Residency:             05100     0.888 MI. GRADE, DRAIN, SURFACE &
                                                                             BRIDGE US-183 BEGIN @ I-40
 NHY-009N(008)                              CLINTON
                                                                             EXTEND N. TO I-40B IN CLINTON.
 Contractor:          WITTWER CONSTRUCTION CO., INC.
 Engineer:            Greer, Randy
 Contract Amount:     $9,472,045.00                                          Completion Date:              09/30/2009
 Letting Date:        05/17/2007                                             Final Est Sub:                04/30/2012




County:         Delaware                                      Commissioner District:                             8
 Contracts Completed - Final Estimate Not Processed



                                             Construction Status Report                              Page 15
 25900(04)     Contract: 100352     CORD    Residency:     08300            0.40 MI. CO.RD.; BRIDGE &
                                                                            APPROACHES;OVER HOG CR., 4.3
 BRF-121C(121)CO                             CLAREMORE
                                                                            MI. S. OF THE SH-20/SH-43
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC              JUNCTION.
 Engineer:            Bray, Timothy
 Contract Amount:     $409,302.55                                           Completion Date:                  08/18/2011
 Letting Date:        05/20/2010                                            Final Est Sub:

 26456(04)     Contract: 110061     CORD    Residency:            08300     0.08 MI. CO.RD./BRIDGE &
                                                                            APPROACHES;OVER CHEROKEE CR.,
 BRF-121C(133)CO                             CLAREMORE
                                                                            0.9 MI. N. OF SH-116 E.
 Contractor:          BEACHNER CONSTRUCTION CO., INC.                       JUNCTION.
 Engineer:            Bray, Timothy
 Contract Amount:     $402,783.90                                           Completion Date:                  03/15/2012
 Letting Date:        02/17/2011                                            Final Est Sub:

 26228(04)     Contract: 090606     SH-10      Residency:         08300     0.0 MI. SAFETY IMPROVEMENT
                                                                            (CABLE BARRIER & GUARDRAIL)
 HSIPG-121A(136)                               CLAREMORE
                                                                            SH-10/SH-20/US-59 AT VARIOUS
 Contractor:          ACTION SAFETY SUPPLY CO.                              LOCATIONS IN DIVISION 8.
 Engineer:            Bray, Timothy
 Contract Amount:     $1,042,485.60                                         Completion Date:                  08/09/2010
 Letting Date:        12/17/2009                                            Final Est Sub:                    03/16/2012

 27607(04)     Contract: 110056     SH-20    Residency:    08300       9.18 MI. SH-20:RESURFACE
                                                                       (ASPHALT)FROM 10.0 MI. E. OF       THE
 SSR-121C(144)(149)SR                        CLAREMORE
                                                                       SH-10 JCT, EXTEND N.
 Contractor:          HUTCHENS ASPHALT PAVING CO. DBA HUTCHENS CONSTRUCTION CO. THE ADAIR C/L.
                                                                       SH-10,FROM
 Engineer:            Bray, Timothy
 Contract Amount:     $1,116,502.54                                    Completion Date:                       10/07/2011
 Letting Date:        01/20/2011                                       Final Est Sub:

 15015(04)     Contract: 080002     US-59   Residency:    08300             4.66 KM WIDEN & RESURFACE US-59
                                                                            FROM 1.48 MI. N.W. OF THE
 STPY-021B(273)                             CLAREMORE
                                                                            US-59/SH-25 JCT. IN GROVE &
 Contractor:          KOSS CONSTRUCTION COMPANY & SUBSIDIARY                EXTEND N.W.
 Engineer:            Bray, Timothy
 Contract Amount:     $17,356,640.46                                        Completion Date:                  04/16/2010
 Letting Date:        07/24/2008                                            Final Est Sub:

 27613(04)     Contract: 110060     US-59     Residency:          08300     1.71 MI. US-59:RESURFACE
                                                                            (ASPHALT)FROM THE SH-20 WEST
 STPY-121B(148)3P                             CLAREMORE
                                                                            JUNCTION, EXTEND NORTH.
 Contractor:          GLOVER & ASSOCIATES, INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $711,099.56                                           Completion Date:                  11/01/2011
 Letting Date:        01/20/2011                                            Final Est Sub:

 27609(04)     Contract: 110057     US-59     Residency:          08300     17.24 MI. US-59:RESURFACE
                                                                            (ASPHALT)FROM THE US-412A
 SSR-121B(145)(146)(147)SR                    CLAREMORE
                                                                            JCT,EXTEND NORTH.
 Contractor:          GLOVER & ASSOCIATES, INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $2,082,725.80                                         Completion Date:                  10/27/2011
 Letting Date:        01/20/2011                                            Final Est Sub:                    05/30/2012

 15015(14)     Contract: 110330     US-59       Residency:        08300     4.27 MI. US-59 1.0 MI. N OR THE
                                                                            SH-10 EAST JCT. EXTEND NORTH
 STPY-121A(143)                                 CLAREMORE
 Contractor:          APAC-CENTRAL, INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $634,081.97                                           Completion Date:                  05/10/2012
 Letting Date:        09/15/2011                                            Final Est Sub:




County:         Dewey                                        Commissioner District:                                5
 Contracts Completed - Final Estimate Not Processed



                                            Construction Status Report                               Page 16
 26653(04)     Contract: 110481   CORD      Residency:     05005                .123 MI. CORD:BRIDGE &
                                                                                APPROACHES; OVER WEST SEILING
 BRO-122D(069)CI                             CIRCUIT ENGR. DISTR. # 7
                                                                                CREEK 1.4 MI. E OF US-183 AND .5
 Contractor:          KLAVER CONSTRUCTION COMPANY, INC.                         MI. N OF SH-51 IN SEILING.
 Engineer:            CED7
 Contract Amount:     $324,194.90                                              Completion Date:               08/24/2012
 Letting Date:        10/20/2011                                               Final Est Sub:




County:          Ellis                                        Commissioner District:                               6
 Contracts Completed - Final Estimate Not Processed


 26544(04)     Contract: 100290    CORD          Residency:        06100        0.103 MI. CO.RD,;BRIDGE &
                                                                                APPROACHES;OVER IVANHOE CR.,
 BHF-123C(073)CO                                 BUFFALO
                                                                                2.0 MI. N. & 4.6 MI. W.  OF
 Contractor:          SEWELL BROS., INC.                                        SHATTUCK.
 Engineer:            Burke, David
 Contract Amount:     $364,867.36                                              Completion Date:               11/09/2011
 Letting Date:        04/15/2010                                               Final Est Sub:                 08/28/2012

 20943(07)     Contract: 090312     US-283   Residency:      06100         0.692 MI. GRADE, DRAIN, SURFACE &
                                                                           BRIDGE US-283 OVER TWENTY-FIVE
 STP-STIM(034)                                BUFFALO
                                                                           MILE CRK. 0.5 MI. N. OF SH-15 JCT.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Burke, David
 Contract Amount:     $3,655,118.69                                        Completion Date:               11/10/2011
 Letting Date:        03/19/2009                                           Final Est Sub:




County:          Garfield                                     Commissioner District:                               4
 Contracts Completed - Final Estimate Not Processed


 23086(04)     Contract: 110172     CTST      Residency:           04002        0.338 MI. CT. ST.:GRADE,DRAIN
                                                                                ,SURFACE & TRAFFICE SIGNAL;
 STP-124B(079)UR                              TETRA TECH
                                                                                (OAKWOOD RD.) AT THE INTER-
 Contractor:          TOM HUDSON PAVING, INC.                                   SECTION OF WILLOW RD. IN ENID.
 Engineer:            TETR
 Contract Amount:     $1,458,678.76                                            Completion Date:               07/01/2012
 Letting Date:        02/17/2011                                               Final Est Sub:

 20855(04)     Contract: 080402     SH-15    Residency:      04100         *(204)/ 1.04 MI. GRD, DRN, SURF, BR
                                                                           & ERSN CNTRL SH-15 7.8 MI N OF
 BRFY-124C(045)/BRFY-052C*                    PERRY
                                                                           US-64/SH-15 2.8 MI E OF GARFIELD
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)LINE.
                                                                           COUNTY
 Engineer:            Zachary, Ted
 Contract Amount:     $7,176,188.58                                        Completion Date:               08/17/2011
 Letting Date:        08/21/2008                                           Final Est Sub:

 28250(04)     Contract: 110402     US-60   Residency:             04300        4.13 MI. US-60/US-412:RE-
                                                                                SURFACE(ASPHALT)FROM SH-132
 NHY-019N(129)3P                             ENID
                                                                                EXTEND EAST.
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $1,750,671.05                                            Completion Date:               01/20/2012
 Letting Date:        06/30/2011                                               Final Est Sub:




County:          Garvin                                       Commissioner District:                               3
 Contracts Completed - Final Estimate Not Processed




                                             Construction Status Report                                 Page 17
 24762(04)     Contract: 100032     SH-29       Residency:        03200   0.053 MI. SH-29;BRIDGE RE-
                                                                          HAB.:OVER W. ROCK CR., 8.9 MI.E.
 BHFY-125B(158)                                 PURCELL
                                                                          OF THE STEPHENS C/L.
 Contractor:          PBX CORPORATION
 Engineer:            Riemer, Caleb
 Contract Amount:     $482,673.00                                         Completion Date:                05/16/2011
 Letting Date:        10/21/2010                                          Final Est Sub:

 28158(04)     Contract: 110063     SH-7     Residency:    07200          4.02 MI. SH-7:RESURFACE
                                                                          (ASPHALT)FROM THE MURRAY C/L,
 NHY-021N(055)3P                             ARDMORE
                                                                          EXTEND EAST.
 Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.
 Engineer:            Earp, Jay
 Contract Amount:     $1,165,524.55                                       Completion Date:                11/30/2011
 Letting Date:        02/17/2011                                          Final Est Sub:                  04/13/2012

 28208(04)     Contract: 110065     SH-74    Residency:    03200          8.0 MI. SH-74;RESURFACE
                                                                          (ASPHALT)FROM THE SH-29 JCT,
 STPY-125C(205)3P                            PURCELL
                                                                          EXTEND NORTH.
 Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.
 Engineer:            Riemer, Caleb
 Contract Amount:     $1,212,614.70                                       Completion Date:                06/21/2012
 Letting Date:        02/17/2011                                          Final Est Sub:

 28212(04)     Contract: 110097     US-77   Residency:            03200   *(204)3P / 19.57 MI. US-77
                                                                          :RESURFACE (ASPHALT)FROM THE
 STPY-125C(202)(203)*                        PURCELL
                                                                          MURRAY C/L, EXTEND NORTH.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Riemer, Caleb
 Contract Amount:     $3,660,026.68                                       Completion Date:                09/21/2011
 Letting Date:        02/17/2011                                          Final Est Sub:                  07/05/2012




County:         Grady                                        Commissioner District:                               7
 Contracts Completed - Final Estimate Not Processed


 23136(04)     Contract: 100580     CORD        Residency:        07300   0.245 MI. CO.RD.:BRIDGE &
                                                                          APPROACHES/OVER LITTLE
 BRF-126C(108)CI                                ANADARKO
                                                                          WASHITACR., 3.5 MI. S. OF THE
 Contractor:          SEWELL BROS., INC.                                  US-277 JUNTION.
 Engineer:            Knight, Reese
 Contract Amount:     $791,822.83                                         Completion Date:                01/11/2012
 Letting Date:        11/18/2010                                          Final Est Sub:

 22215(04)     Contract: 100382     CORD        Residency:        07300   0.207 MI. CO.RD.;BRIDGE &
                                                                          APPROACHES;OVER OTTER CR.,
 BRO-126D(102)CO                                ANADARKO
                                                                          1.2MI. NORTH OF THE SH-9/US-       62
 Contractor:          D. M. DOZERS, INC.                                  JUNCTION.
 Engineer:            Knight, Reese
 Contract Amount:     $380,799.45                                         Completion Date:                02/23/2012
 Letting Date:        06/17/2010                                          Final Est Sub:                  07/25/2012

 28089(04)     Contract: 110098     SH-17      Residency:         07300   *(188)3P/NHY-11N(90)3P / 6. 60 MI.
                                                                          SH-17:RESURFACE(ASPHALT)FROM
 STPY-126C(185)/STPY-126C*                     ANADARKO
                                                                          1.02 MI. W. OF US-81, EXTEND E.
 Contractor:          T & G CONSTRUCTION, INC.
 Engineer:            Knight, Reese
 Contract Amount:     $1,834,143.36                                       Completion Date:                11/10/2011
 Letting Date:        02/17/2011                                          Final Est Sub:                  06/08/2012

 20959(04)     Contract: 090402     SH-19   Residency:            07300   0.189 MI. SH-19;GRADE,DRAIN
                                                                          ,SURFACE & BRIDGE;OVER
 BRFY-126C(079)                              ANADARKO
                                                                          ROARINGCR., 1.7 MI. W. OF
 Contractor:          MUNOZ CONSTRUCTION CO., INC.                        BRADLEY.
 Engineer:            Knight, Reese
 Contract Amount:     $1,589,481.50                                       Completion Date:                07/13/2011
 Letting Date:        05/14/2009                                          Final Est Sub:                  06/09/2012


                                            Construction Status Report                             Page 18
 20961(04)     Contract: 100264     SH-37        Residency:     07004       0.766 MI. SH-37;GRADE,DRAIN
                                                                            ,SURFACE, & BRIDGE;OVER BUGGY
 BRFY-126C(085)                                  JACOBS (AKA - CARTER-BURGESS)
                                                                               CREEK 6.5 MI. WEST OF US-    81
 Contractor:          SEWELL BROS., INC.                                       JCT.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $2,947,895.13                                           Completion Date:               05/31/2012
 Letting Date:        05/20/2010                                              Final Est Sub:

 28001(04)     Contract: 110332     SH-4    Residency:             07300       .08 MI. SH-4 FROM 2.0 MI. NORTH OF
                                                                               SH-37 JCT. EXTEND NORTH.
 SSP-126C(184)SS                            ANADARKO
 Contractor:          MARKWELL PAVING COMPANY, INC.
 Engineer:            Knight, Reese
 Contract Amount:     $56,219.31                                              Completion Date:               04/06/2012
 Letting Date:        09/15/2011                                              Final Est Sub:                 07/28/2012

 24515(04)     Contract: 080465     US-81    Residency:      07001             0.180 MI. BRIDGE REDECKING &
                                                                               REHABILITATION US-81 OVER
 SSP-126N(120)(121)SS                         ENGR. SERV. & TESTING
                                                                               LITTLE WASHITA RVR. 1.0 MI. S. OF
 Contractor:          PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC               SH-19 (N.& S.BOUND LANES).
 Engineer:            EST
 Contract Amount:     $2,739,899.48                                           Completion Date:               06/30/2011
 Letting Date:        09/18/2008                                              Final Est Sub:                 02/13/2012

 26225(04)     Contract: 100173     US-81     Residency:           07300       1.967 MI. US-81; PAVEMENT
                                                                               REHAB.(PC PAVEMENT)FROM 2.0 MI.
 SSP-126N(174)SS                               ANADARKO
                                                                               S. OF THE SH-19 JCT,   EXTEND
 Contractor:          SCHWARZ PAVING CO., INC.                                 NORTH.
 Engineer:            Knight, Reese
 Contract Amount:     $4,210,116.53                                           Completion Date:               08/19/2011
 Letting Date:        05/20/2010                                              Final Est Sub:

 27035(04)     Contract: 110069     US-81     Residency:           07300       0.79 MI. US-81:WIDEN & RESUR
                                                                               -FACE (ASPHALT)FROM 1.5 MI. N.OF
 SSP-126N(177)SS                               ANADARKO
                                                                               SH-19E, EXTEND NORTH.
 Contractor:          SCHWARZ PAVING CO., INC.
 Engineer:            Knight, Reese
 Contract Amount:     $789,461.60                                             Completion Date:               03/01/2012
 Letting Date:        01/20/2011                                              Final Est Sub:




County:         Grant                                         Commissioner District:                                4
 Contracts Completed - Final Estimate Not Processed


 25586(04)     Contract: 110379    CORD          Residency:    04009           .113 MI. CO.RD.(EW-12) OVER DEER
                                                                               CREEK, 3.0 MI. WEST OF KAY
 BRO-127D(146)CI                                 CIRCUIT ENGR. DISTR. # 8
                                                                               COUNTY LINE.
 Contractor:          K & R BUILDERS, INC.
 Engineer:            CED8
 Contract Amount:     $418,872.10                                             Completion Date:               08/17/2012
 Letting Date:        09/15/2011                                              Final Est Sub:

 28232(04)     Contract: 120123     SH-74    Residency:     04300              8.00 MI. SH-74/RESURFACE
                                                                               (ASPHALT)FROM US-60, EXTEND
 STPY-127C(180)3P                            ENID
                                                                               NORTH.
 Contractor:          EVANS & ASSOCIATES CONSTRUCTION CO., INC.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $1,643,759.20                                           Completion Date:               08/30/2012
 Letting Date:        02/16/2012                                              Final Est Sub:

 21850(04)     Contract: 070218     US-64    Residency:   04300                0.731 MI. GRADE, DRAIN,
                                                                               SURFACING, BRIDGE & APPROACHES
 BRFY-127C(061)BF                             ENID
                                                                               US-64 OVER UNNAMED CRK. 1.1 MI.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC               E. OF THE ALFALFA COUNTY LINE.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $3,459,978.04                                           Completion Date:               09/28/2009
 Letting Date:        08/16/2007                                              Final Est Sub:                 08/03/2012


                                             Construction Status Report                                 Page 19
County:         Greer                                       Commissioner District:                             5
 Contracts Completed - Final Estimate Not Processed


 26718(04)     Contract: 110472   CORD      Residency:     05005          .709 MI. CO.RD. (EW-151) OVER
                                                                          UNNAMED CREEK, 2.0 MI. WEST
 BRO-128D(080)CI                             CIRCUIT ENGR. DISTR. # 7
                                                                          OFUS-283 JCT.
 Contractor:          KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:            CED7
 Contract Amount:     $209,010.55                                         Completion Date:                08/21/2012
 Letting Date:        09/15/2011                                          Final Est Sub:

 29259(04)     Contract: 120138      SH-6   Residency:           05200    5.00 MI. SH-6/RESURFACE
                                                                          (UTBWC)BEGIN 2.0 MI. N. OF
 STPY-228B(003)3P                            ALTUS
                                                                          THEJACKSON C/L. EXTEND NORTH.
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:            Nedbalek, Will
 Contract Amount:     $1,561,086.63                                       Completion Date:                06/26/2012
 Letting Date:        03/15/2012                                          Final Est Sub:                  08/07/2012

 10100(07)     Contract: 100602      SH-6   Residency:    05200           3.56 MI.
                                                                          SH-6;SURFACE(ASPHALT)FROM 1.0
 STPY-128B(004)                             ALTUS
                                                                          MI. N. OFTHE SH-9 JUNCTION,
 Contractor:          KOSS CONSTRUCTION COMPANY & SUBSIDIARY              EXTEND NORTH.
 Engineer:            Nedbalek, Will
 Contract Amount:     $3,760,594.93                                       Completion Date:                07/31/2012
 Letting Date:        11/18/2010                                          Final Est Sub:




County:         Harmon                                      Commissioner District:                             5
 Contracts Completed - Final Estimate Not Processed


 27517(04)     Contract: 110027      US-62  Residency:           05200    8.00 MI. US-62:RESURFACE
                                                                          (ASPHALT)FROM 1.0 MI. E. OF THE
 NHY-020N(036)3P                             ALTUS
                                                                          SH-30 JUNCTION, EXTEND EAST.
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:            Nedbalek, Will
 Contract Amount:     $1,765,814.51                                       Completion Date:                02/29/2012
 Letting Date:        01/20/2011                                          Final Est Sub:                  08/06/2012




County:         Harper                                      Commissioner District:                             6
 Contracts Completed - Final Estimate Not Processed


 25914(04)     Contract: 110403     CORD       Residency:    06009        9.316 MI. CO.RD.:RESURFACE
                                                                          (ASPHALT)FROM THE BEAVER C/L
 STP-130C(136)(137)CI                          CIRCUIT ENGR. DISTR. # 8
                                                                          EXT E. ON EW-22 FROM US-283 EXT.
 Contractor:          J & R SAND COMPANY, INC.                            WEST, THEN NORTH ON NS-17
 Engineer:            CED8
 Contract Amount:     $2,225,101.69                                       Completion Date:                10/31/2011
 Letting Date:        06/30/2011                                          Final Est Sub:

 22323(08)     Contract: 100435     CORD       Residency:        06100    6.051 MI. CO.RD.;GRADE,DRAIN , &
                                                                          SURFACE;FROM 4.0 MI. NORTHOF THE
 CIRB-130C(124)RB                              BUFFALO
                                                                          US-64/US-283 JUNCTION ,EXTEND
 Contractor:          J & R SAND COMPANY, INC.                            NORTH.
 Engineer:            Burke, David
 Contract Amount:     $2,886,458.85                                       Completion Date:                10/20/2011
 Letting Date:        07/22/2010                                          Final Est Sub:




                                           Construction Status Report                             Page 20
County:         Haskell                                       Commissioner District:                           1
 Contracts Completed - Final Estimate Not Processed


 25334(04)     Contract: 100556      CORD        Residency:        01100   0.141 MI. CO.RD.:BRIDGE &
                                                                           APPROACHES:OVER UNNAMED CR.,
 BRO-131D(088)CI                                 MUSKOGEE
                                                                           3.0 MI. WEST OF THE SH-2
 Contractor:          K & R BUILDERS, INC.                                 JUNCTION.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $358,200.40                                          Completion Date:               05/18/2012
 Letting Date:        04/14/2011                                           Final Est Sub:

 28082(04)     Contract: 110125     SH-31     Residency:           01200   *(110)(111)3P / 10.08 MI. SH
                                                                           -31;PAVEMET REHAB. &
 STPY-131C(109)/STPY-131B*                    SALLISAW
                                                                           RESURFACE(ASPHALT)AT THE SH-2
 Contractor:          GLOVER & ASSOCIATES, INC.                            JCT IN KINTA. SH-2 .
 Engineer:            Edwards, Carl
 Contract Amount:     $2,145,997.22                                        Completion Date:               03/07/2012
 Letting Date:        02/17/2011                                           Final Est Sub:




County:         Hughes                                        Commissioner District:                           3
 Contracts Completed - Final Estimate Not Processed


 21775(04)     Contract: 110352      CORD    Residency:            03300   0.198 MI. CO.RD./BRIDGE &
                                                                           APPROACHES:OVER UNNAMED CR.,
 BRF-132C(076)CI                             WEWOKA
                                                                           3.7 MI. WEST OF THE SH-27
 Contractor:          BRIDGECO CONTRACTORS, INC.                           JUNCTION.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $250,530.00                                          Completion Date:               05/16/2012
 Letting Date:        08/18/2011                                           Final Est Sub:                 06/27/2012

 29035(04)     Contract: 120094     US-75   Residency:             03200   7.76 MI. US-75;RESURFACE
                                                                           (ASPHALT)FROM SH-9, EXTEND
 STPY-232B(001)3P                            PURCELL
                                                                           NORTH.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Riemer, Caleb
 Contract Amount:     $1,494,918.70                                        Completion Date:               08/08/2012
 Letting Date:        02/16/2012                                           Final Est Sub:




County:         Jefferson                                     Commissioner District:                           7
 Contracts Completed - Final Estimate Not Processed


 29193(04)     Contract: 120014      SH-5      Residency:          07100   1.87 MI. SH-5;RESURFACE
                                                                           (ASPHALT)BEGIN AT COTTON C/L
 MC-234C(003)                                  DUNCAN
                                                                           AND EXTEND EAST.
 Contractor:          T & G CONSTRUCTION, INC.
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $202,465.08                                          Completion Date:               04/25/2012
 Letting Date:        01/19/2012                                           Final Est Sub:

 23231(04)     Contract: 070397      SH-5        Residency:        07100   1.242 MI. GRADE, DRAIN, SURFACE,
                                                                           BRIDGE & EROSION CONTROL SH-5
 BRFY-134C(058)BF                                DUNCAN
                                                                           OVER BEAVER CRK. APPROX. 5.6 MI.
 Contractor:          OVERLAND CORPORATION                                 E. OF COTTON CO. LN.
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $3,798,079.87                                        Completion Date:               03/31/2010
 Letting Date:        09/20/2007                                           Final Est Sub:




                                             Construction Status Report                           Page 21
County:         Johnston                                    Commissioner District:                          3
 Contracts Completed - Final Estimate Not Processed


 08931(04)     Contract: 100584      SH-78     Residency:        03100   0.854 MI. SH-78;BRIDGE &
                                                                         APPROACHES/OVER BRUSHY CR.,
 BRFY-035C(190)                                ADA
                                                                         JUST S. OF THE TOWN OF
 Contractor:          OVERLAND CORPORATION                               MILBURN.
 Engineer:            Russell, Julie
 Contract Amount:     $2,344,652.84                                      Completion Date:              12/30/2011
 Letting Date:        11/18/2010                                         Final Est Sub:                07/25/2012

 21784(04)     Contract: 100438      SH-99  Residency:           03100   0.088 MI. SH-99;BRIDGE &
                                                                         APPROACHES;OVER LITTLE BLUE
 BRFY-135B(061)                             ADA
                                                                         CREEK, 1.30 MI. SOUTH OF  THE
 Contractor:          WITTWER CONSTRUCTION CO., INC.                     PONTOTOC C/L.
 Engineer:            Russell, Julie
 Contract Amount:     $1,204,242.73                                      Completion Date:              05/12/2011
 Letting Date:        07/22/2010                                         Final Est Sub:

 28606(05)     Contract: 110427   US-75      Residency:      03001       0.00 MI. US-75/SH-3E/SH-7/SH-22
                                                                         /CO.RD. AT VARIOUS LOCATIONSIN
 BRFY-135F(136)3B                             ENGR. SERV. & TESTING
                                                                         DIVISION 3.
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.
 Engineer:            EST
 Contract Amount:     $320,373.75                                        Completion Date:              07/10/2012
 Letting Date:        09/15/2011                                         Final Est Sub:




County:         Kay                                         Commissioner District:                          4
 Contracts Completed - Final Estimate Not Processed


 25645(05)     Contract: 100557    CORD     Residency:           04100   0.117 MI. CO.RD.;BRIDGE &
                                                                         APPROACHES/OVER CANADIAN CR.,
 BRO-136D(178)CI                             PERRY
                                                                         12.7 MI. E. & 0.4 MI. N. OF THE
 Contractor:          BEACHNER CONSTRUCTION CO., INC.                    TOWN OF NEWKIRK.
 Engineer:            Zachary, Ted
 Contract Amount:     $289,144.45                                        Completion Date:              05/17/2012
 Letting Date:        10/21/2010                                         Final Est Sub:

 24432(07)     Contract: 090314    I-35     Residency:    04100          4.918 MI. GRADE, DRAIN, SURFACE,
                                                                         BRIDGE & CABLE BARRIER I-35
 IM-STIM(019)                               PERRY
                                                                         BEGIN AT M.M. 224.43 & EXTENDN.
 Contractor:          KOSS CONSTRUCTION COMPANY & SUBSIDIARY             TO M.M. 229.33.
 Engineer:            Zachary, Ted
 Contract Amount:     $23,984,922.13                                     Completion Date:              08/15/2011
 Letting Date:        03/19/2009                                         Final Est Sub:

 24140(04)     Contract: 080183     I-35       Residency:        04300   0.00 MI. I-35/SAFETY IMPROV.
                                                                         (CABLE BARRIER);BEGIN AT MILE
 IMG-0035-4(214)209TR                          ENID
                                                                         MARKER 209 & EXTEND NORTH     TO
 Contractor:          ACTION SAFETY SUPPLY CO.                           MILE MARKER 214.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $798,610.07                                        Completion Date:              05/12/2010
 Letting Date:        04/17/2008                                         Final Est Sub:

 12302(04)     Contract: 100384     SH-156  Residency:           04100   0.340 MI. SH-156;GRADE,DRAIN
                                                                         ,SURFACE & BRIDGE;OVER A SALT
 BRFY-036C(267)                              PERRY
                                                                         FORK OF THE ARKANSAS RIVER,
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY                    1.10 MI. N. OF NOBLE C/L.
 Engineer:            Zachary, Ted
 Contract Amount:     $2,144,561.13                                      Completion Date:              11/18/2011
 Letting Date:        09/16/2010                                         Final Est Sub:



                                           Construction Status Report                            Page 22
 27533(04)     Contract: 100520    US-177   Residency:            04100       *(56)SB/ 0.118 MI. US-177/
                                                                              US-60:BRIDGE REHAB. OVER
 SBR-136C(201)SB/SBR-18N*                   PERRY
                                                                              STINKCR., 3.2 MI. N. OF US-60
 Contractor:          WITTWER CONSTRUCTION CO., INC.                          JCT.US-60:OVER UNNAMED CR.
 Engineer:            Zachary, Ted
 Contract Amount:     $340,640.14                                             Completion Date:                10/06/2011
 Letting Date:        09/16/2010                                              Final Est Sub:

 23216(04)     Contract: 080373     US-177   Residency:      04100         1.563 MI GRD, DRN, SURF & BR
                                                                           US-177 DRY CRK & DRY CRK O'FLOW
 BRFY-136C(124)(123)                          PERRY
                                                                           12.4 MI N US-60 & UNNAMED CRK
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) 16.2 MI N US-60.
                                                                           13.1 MI &
 Engineer:            Zachary, Ted
 Contract Amount:     $5,384,031.40                                        Completion Date:             10/06/2011
 Letting Date:        11/20/2008                                           Final Est Sub:

 27120(04)     Contract: 100519    US-77    Residency:            04100       0.057 MI. US-77;BRIDGE RE-
                                                                              HAB.:OVER CHILOCCO CR.,2.2 MI.S.
 SBR-136C(203)SB                            PERRY
                                                                              OF THE OK STATE LINE.
 Contractor:          WITTWER CONSTRUCTION CO., INC.
 Engineer:            Zachary, Ted
 Contract Amount:     $568,950.00                                             Completion Date:                11/21/2011
 Letting Date:        09/16/2010                                              Final Est Sub:

 28587(04)     Contract: 110452    US77       Residency:     04001            0.00 MI. US-77:BRIDGE
                                                                              PAINTING;OVER CHILOCCO CREEK
 BRFY-NBIP(442)3B                             ENGR. SERV. & TESTING
                                                                              2.0 MI. SOF THE KANSAS STATE LINE
 Contractor:          PACIFIC PAINTING COMPANY, INC.
 Engineer:            EST
 Contract Amount:     $99,000.00                                              Completion Date:                04/30/2012
 Letting Date:        10/20/2011                                              Final Est Sub:                  08/27/2012




County:          Kingfisher                                  Commissioner District:                                4
 Contracts Completed - Final Estimate Not Processed


 28243(04)     Contract: 110084     SH-51   Residency:            04300       7.65 MI. SH-51;RESURFACE
                                                                              (ASPHALT)FROM THE BLAINE
 STPY-137C(101)3P                            ENID
                                                                              COUNTY LINE, EXTEND EAST.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $1,071,109.00                                           Completion Date:                11/03/2011
 Letting Date:        02/17/2011                                              Final Est Sub:                  08/24/2012

 28083(04)     Contract: 110404     US-81    Residency:           04300       0.290 MI. US-81:PAVEMENT
                                                                              REHAB.(P.C. CONCRETE)FROM THE
 STPY-137C(096)                              ENID
                                                                              SH-33 JUNCTION, EXTEND NORTH IN
 Contractor:          REDLANDS CONTRACTING, LLC                               KINGFISHER.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $735,867.50                                             Completion Date:                01/06/2012
 Letting Date:        06/30/2011                                              Final Est Sub:

 27193(04)     Contract: 100162     US-81   Residency:            04300       *(454)PT.3EH / 1.433 MI. US
                                                                              -81;PEDESTRIAN IMPROV./RESUR-
 STP-STIM(454)EH/STP-STIM*                  ENID
                                                                              FACE (ASPHALT)FROM 7TH ST.,
 Contractor:          TMC CONSTRUCTION COMPANY                                EXTEND N. IN HENNESSEY.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $814,376.50                                             Completion Date:                11/07/2011
 Letting Date:        04/15/2010                                              Final Est Sub:                  08/08/2012

 24886(04)     Contract: 110294     US-81   Residency:            04300       1.38 MI. US-81;RESURFACE
                                                                              (ASPHALT)BEGIN 2.0 MI. SOUTH OF
 SSR-137N(098)SR                             ENID
                                                                              SH-51, EXTEND NORTH IN
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                          HENNESSEY.
 Engineer:            Crowl, Kenny (Act.)
 Contract Amount:     $618,152.00                                             Completion Date:                06/27/2012
 Letting Date:        01/19/2012                                              Final Est Sub:


                                            Construction Status Report                                 Page 23
County:          Kiowa                                       Commissioner District:                              5
 Contracts Completed - Final Estimate Not Processed


 28145(04)     Contract: 110088      SH-54  Residency:            05200       15.00 MI. SH-54;RESURFACE
                                                                              (ASPHALT)BEGIN AT SH-9 JCT,
 STPY-138C(184)(185)3P                       ALTUS
                                                                              EXTEND SOUTH.
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:            Nedbalek, Will
 Contract Amount:     $2,501,667.84                                           Completion Date:              02/22/2012
 Letting Date:        02/17/2011                                              Final Est Sub:

 28321(04)     Contract: 110161      SH-54  Residency:            05200       *-175C(128)3R / 15.36 MI.
                                                                              SH-54:RESURFACE(ASPHALT)FROM
 STPY-138C(186)3P/STPY-*                     ALTUS
                                                                              THE SH-9 JUNCTION,EXTEND
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.                      NORTH.
 Engineer:            Nedbalek, Will
 Contract Amount:     $2,415,188.26                                           Completion Date:              02/22/2012
 Letting Date:        01/20/2011                                              Final Est Sub:

 16063(28)     Contract: 100522      US-183 Residency:            05200       1.572 MI.,US-183;GRADE,DRAIN , &
                                                                              SURFACE:FROM 0.2 MI. S. OFTHE
 NHY-009N(055)                               ALTUS
                                                                              SH-9 JUNCTION,EXTEND     NORTH.
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:            Nedbalek, Will
 Contract Amount:     $4,048,982.70                                           Completion Date:              02/21/2012
 Letting Date:        09/16/2010                                              Final Est Sub:

 28134(04)     Contract: 110296      US-183 Residency:            05200       7.25 MI. US-183;RESURFACE
                                                                              (ASPHALT)BEGIN 0.75 MI. SOUTH OF
 SSR-138A(182)SR                             ALTUS
                                                                              SH-19, EXTEND NORTH.
 Contractor:          CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:            Nedbalek, Will
 Contract Amount:     $2,059,335.56                                           Completion Date:              07/19/2012
 Letting Date:        01/19/2012                                              Final Est Sub:




County:          Latimer                                     Commissioner District:                              2
 Contracts Completed - Final Estimate Not Processed


 23194(04)     Contract: 100487     SH-82    Residency:      02200         1.102 MI. SH-82;GRADE,DRAIN,
                                                                           SURFACE & BRIDGE;OVER FOURCHE
 STPY-139C(070)SS                             HEAVENER
                                                                           MALINE CR., 5.0 MI. W. OF THE
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) C/L.
                                                                           LATIMER
 Engineer:            Huddleston, David
 Contract Amount:     $2,390,981.83                                        Completion Date:             03/30/2012
 Letting Date:        10/21/2010                                           Final Est Sub:

 26396(04)     Contract: 110297     US-270    Residency:          02200       2.30 MI. US-270;RESURFACE
                                                                              (ASPHALT)BEGIN 4.3 MI. EAST
 SSR-139B(114)SR                              HEAVENER
                                                                              OFSH-2, EXTEND EAST.
 Contractor:          JOB CONSTRUCTION CO., INC.
 Engineer:            Huddleston, David
 Contract Amount:     $962,368.80                                             Completion Date:              05/31/2012
 Letting Date:        01/19/2012                                              Final Est Sub:

 28189(04)     Contract: 110405     US-270    Residency:          02200       1.140 MI. US-270:RESURFACE
                                                                              (ASPHALT)FROM THE SH-2 JCT,
 STPY-139B(113)3P                             HEAVENER
                                                                              EXTEND EAST.
 Contractor:          GLOVER & ASSOCIATES, INC.
 Engineer:            Huddleston, David
 Contract Amount:     $490,035.50                                             Completion Date:              12/22/2011
 Letting Date:        06/30/2011                                              Final Est Sub:



                                            Construction Status Report                                Page 24
County:          Le Flore                                     Commissioner District:                                 2
 Contracts Completed - Final Estimate Not Processed


 22885(04)     Contract: 110531     CORD     Residency:    02013               0.392 MI. CO.RD.;BRIDGE &
                                                                               APPROACHES/OVER BLACKFORTH
 CIRB-140C(135)RB                            CIRCUIT ENGR. DISTRICT # 3
                                                                               CR.0.5 MI. E. OF US-59 IN
 Contractor:          HUB CONSTRUCTION, INC.                                   HODGENS.
 Engineer:            CED3
 Contract Amount:     $1,561,013.58                                            Completion Date:                 08/31/2012
 Letting Date:        11/17/2011                                               Final Est Sub:

 28567(04)     Contract: 120099     SH-1         Residency:        02200       11.00 MI. SH-1;CHIP SEAL/FROM 2.5
                                                                               MI. EAST OF THE US-259 JCT, EXTEND
 FH-140C(213)                                    HEAVENER
                                                                               EAST TO THE ARKANSAS STATE LINE.
 Contractor:          VANCE BROTHERS, INC.
 Engineer:            Huddleston, David
 Contract Amount:     $329,501.14                                              Completion Date:                 05/30/2012
 Letting Date:        02/16/2012                                               Final Est Sub:

 17127(05)     Contract: 090406     US-59   Residency:    02200                8.006 KM GRADE, DRAIN, SURFACE &
                                                                               BRIDGE US-59 FROM SH-9    EXTEND
 NH-STIM(169)                               HEAVENER
                                                                               NORTH.
 Contractor:          KOSS CONSTRUCTION COMPANY & SUBSIDIARY
 Engineer:            Huddleston, David
 Contract Amount:     $20,696,687.21                                           Completion Date:                 11/17/2011
 Letting Date:        04/23/2009                                               Final Est Sub:




County:          Lincoln                                      Commissioner District:                                 3
 Contracts Completed - Final Estimate Not Processed


 26064(04)     Contract: 110354    CORD          Residency:     03004       0.387 MI. CO.RD.:BRIDGE &
                                                                            APPROACHES:OVER CHUCKAHO
 BRO-141D(202)CI                                 JACOBS (AKA - CARTER-BURGESS)
                                                                               CREEK, 0.6 MI. SOUTH OF SH-66.
 Contractor:          BELK BRIDGE, INC.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $600,000.00                                              Completion Date:                 04/30/2012
 Letting Date:        07/21/2011                                               Final Est Sub:                   08/21/2012

 29330(04)     Contract: 120244   CORD      Residency:    03003                1.902 MI. CO.RD.:GRADING/    FROM
                                                                               3.5 MI. EAST OF US-177, EXTEND
 CIRB-241C(004)RB                            COBB ENGINEERING CO., INC.
                                                                               EAST.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            COBB
 Contract Amount:     $133,870.05                                              Completion Date:                 08/21/2012
 Letting Date:        05/17/2012                                               Final Est Sub:

 17226(17)     Contract: 110431    SH-66       Residency:    03003        .136 MI. SH-66 OVER CHUCKAHO
                                                                          CREEK, 3.8 MI. E OF SH-18 JCT.
 BRFY-141C(049)                                COBB ENGINEERING CO., INC.
 Contractor:          OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
 Engineer:            COBB
 Contract Amount:     $775,774.35                                         Completion Date:               08/01/2012
 Letting Date:        09/15/2011                                          Final Est Sub:

 28219(04)     Contract: 120100      SH-66B Residency:             03300       1.410 MI. SH-66B;RESURFACE
                                                                               (ASPHALT)FROM 1.41 MI. NORTH-
 STPY-141C(227)3P                           WEWOKA
                                                                               WEST OF US-66, EXTEND
 Contractor:          MARKWELL PAVING COMPANY, INC.                            SOUTHWEST.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $217,246.02                                              Completion Date:                 05/29/2012
 Letting Date:        02/16/2012                                               Final Est Sub:



                                             Construction Status Report                                Page 25
County:          Love                                        Commissioner District:                                 7
 Contracts Completed - Final Estimate Not Processed


 19576(04)     Contract: 040436    I-35     Residency:            07200       *-1(133)(134)008 / 8.13 MI. GRADE,
                                                                              DRAIN, SURFACE & BRIDGE I-35
 IMY-35-1(125)000/BRIY-35*                   ARDMORE
                                                                              SEVERAL LOCATIONS ALONG I-35 IN
 Contractor:          DUIT CONSTRUCTION COMPANY, INC.                         LOVE COUNTY.
 Engineer:            Earp, Jay
 Contract Amount:     $24,831,744.31                                          Completion Date:                 10/01/2007
 Letting Date:        11/18/2004                                              Final Est Sub:                   10/06/2011

 24141(04)     Contract: 070407     IS-35    Residency:           07200       0.00 MI. SAFETY IMPROVEMENT
                                                                              (CABLE BARRIER PROJECT) I-35
 IMG-0035-1(146)013TR                        ARDMORE
                                                                              BEGIN AT THE TX. ST. LINE &
 Contractor:          JIM COOLEY CONSTRUCTION, INC.                           EXTEND N. TO MM 12.5 (4 LOCS.)
 Engineer:            Earp, Jay
 Contract Amount:     $1,364,152.19                                           Completion Date:                 01/25/2010
 Letting Date:        11/15/2007                                              Final Est Sub:                   08/27/2012

 22161(10)     Contract: 080445     IS-35       Residency:        07200       0.88 MI. GRADE, DRAIN & SURFACE
                                                                              ROGERS RD. FROM JCT. I-35 / US-77
 SEC1702Y-143N(072)HP                           ARDMORE
                                                                              EXTEND EAST.
 Contractor:          OVERLAND CORPORATION
 Engineer:            Earp, Jay
 Contract Amount:     $2,476,542.95                                           Completion Date:                 04/13/2012
 Letting Date:        10/16/2008                                              Final Est Sub:                   06/21/2012

 27990(04)     Contract: 110336   IS-35      Residency:           07200       0.00 MI. IS-35:TRAFFIC
                                                                              SIGNALS:AT THE MILE 1 INTER-
 IMG-35-1(160)001TR                          ARDMORE
                                                                              CHANGE IN THE CITY OF
 Contractor:          MIDSTATE TRAFFIC CONTROL, INC.                          THACKERVILLE
 Engineer:            Earp, Jay
 Contract Amount:     $195,190.92                                             Completion Date:                 07/17/2012
 Letting Date:        07/21/2011                                              Final Est Sub:

 20264(04)     Contract: 070007     SH-32       Residency:        07200       1.470 MI. BRIDGE & APPROACHES
                                                                              SH-32 OVER WALNUT BAYOU
 BRFY-143C(046)                                 ARDMORE
                                                                              APPROX. 14.7 MI. E. OF THE
 Contractor:          OBC, INC.                                               JEFFERSON COUNTY LINE.
 Engineer:            Earp, Jay
 Contract Amount:     $6,059,419.07                                           Completion Date:                 01/20/2010
 Letting Date:        01/18/2007                                              Final Est Sub:                   05/21/2012

 20963(04)     Contract: 080231     SH-32    Residency:      07200         0.662 MI. BRIDGE & APPROACHES
                                                                           SH-32 OVER ROCK CRK. APPROX.
 BRFY-143C(057)                               ARDMORE
                                                                           4.7 MI. W. OF MARRIETTA.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Earp, Jay
 Contract Amount:     $3,199,999.99                                        Completion Date:             10/12/2010
 Letting Date:        05/15/2008                                           Final Est Sub:               02/14/2011




County:          Major                                       Commissioner District:                                 6
 Contracts Completed - Final Estimate Not Processed


 22875(04)     Contract: 100390     CORD     Residency:      06100         0.980 MI. CO.RD.;GRADE,DRAIN
                                                                           ,SURFACE & BRIDGE/FROM 1.0
 CIRB-147D(103)RB                             BUFFALO
                                                                           MI.WEST OF THE SH-58 JUNCTION,
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           EXTEND EAST.
 Engineer:            Burke, David
 Contract Amount:     $1,173,455.08                                        Completion Date:             08/31/2011
 Letting Date:        06/17/2010                                           Final Est Sub:               06/04/2012



                                            Construction Status Report                                 Page 26
 24793(04)     Contract: 090492     SH-8        Residency:        06100       0.09 MI. BR. REHAB. SH-8 OVER DEEP
                                                                              CRK. 2 MI. N. OF BLAINE C/L. SH-58
 SBR-147C(131)(140)SB                           BUFFALO
                                                                              OVER INDIAN CRK. JUST S. OF
 Contractor:          SEWELL BROS., INC.                                      US-60 IN RINGWOOD.
 Engineer:            Burke, David
 Contract Amount:     $1,113,263.60                                          Completion Date:                09/28/2011
 Letting Date:        07/23/2009                                             Final Est Sub:                  08/30/2012

 27572(04)     Contract: 110302     US-60      Residency:         06100       13.00 MI. US-60;RESURFACE
                                                                              (ASPHALT)BEGIN AT THE US-281
 SSR-147C(164)(165)SR                          BUFFALO
                                                                              JCT, EXTEND EAST.
 Contractor:          J & R SAND COMPANY, INC.
 Engineer:            Burke, David
 Contract Amount:     $1,507,031.00                                          Completion Date:                08/02/2012
 Letting Date:        01/19/2012                                             Final Est Sub:




County:         Mayes                                        Commissioner District:                                8
 Contracts Completed - Final Estimate Not Processed


 25639(04)     Contract: 110011   CORD        Residency:   08012              0.190 MI. CO.RD.;BRIDGE &
                                                                              APPROACHES;OVER SALT CR.,1.50
 BRO-NBIL(129)CO                              PSA-DEWBERRY
                                                                              MI. NORTH OF THE SH-20
 Contractor:          BECCO CONTRACTORS, INC.                                 JUNCTION.
 Engineer:            PSAD
 Contract Amount:     $533,112.80                                            Completion Date:                04/18/2012
 Letting Date:        04/14/2011                                             Final Est Sub:

 20230(04)     Contract: 100010     SH-28       Residency:     08004       1.55 MI. SH-28;BRIDGE &
                                                                           APPROACHES;OVER OSAGE CREEK,
 SSP-149C(059)SS                                JACOBS (AKA - CARTER-BURGESS)
                                                                              4.9 MI. PRYOR CR. RELIEF    ,5.1
 Contractor:          OBC, INC.                                               MI., BITTER CR.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $6,706,958.94                                          Completion Date:                08/31/2012
 Letting Date:        05/20/2010                                             Final Est Sub:

 29091(04)     Contract: 120103     US-69       Residency:        08300       5.22 MI. US-69;RESURFACE
                                                                              (ASPHALT)FROM 8.3 MI. NORTH
 NHY-013N(158)3P                                CLAREMORE
                                                                              OFTHE WAGONER C/L, EXTEND
 Contractor:          APAC-CENTRAL, INC.                                      NORTH (SOUTHBOUND ONLY).
 Engineer:            Bray, Timothy
 Contract Amount:     $886,252.05                                            Completion Date:                08/23/2012
 Letting Date:        02/16/2012                                             Final Est Sub:




County:         McClain                                      Commissioner District:                                3
 Contracts Completed - Final Estimate Not Processed


 20999(06)     Contract: 100266     IS-35   Residency:      03001             6.772 MI. IS-35;PAVEMENT RE- HAB.
                                                                              (ASPHALT)FROM 2.5 MI. S. OF THE
 IMY-0035-2(311)088                          ENGR. SERV. & TESTING
                                                                              SH-74 JUNCTION, EXT. NORTH.
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:            EST
 Contract Amount:     $8,483,906.12                                          Completion Date:                09/15/2011
 Letting Date:        05/20/2010                                             Final Est Sub:

 19314(08)     Contract: 090623     SH-9W    Residency:      03200         0.23 MI. SH-9W;GRADE,DRAIN,
                                                                           SURFACE & BRIDGE;OVER I-35
 SEC 1702Y-144A(124)HP                        PURCELL
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Riemer, Caleb
 Contract Amount:     $4,285,993.25                                        Completion Date:            11/03/2011
 Letting Date:        12/17/2009                                           Final Est Sub:



                                            Construction Status Report                                   Page 27
 13574(04)     Contract: 060279     US-62   Residency:           03200    1.694 MI. GRADE, DRAIN, SURFACE &
                                                                          BRIDGE US-62 FROM GRADY
 STPY-044B(319)                              PURCELL
                                                                          COUNTY LINE EXTEND N. THRU
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                      BLANCHARD.
 Engineer:            Riemer, Caleb
 Contract Amount:     $9,459,984.70                                       Completion Date:               03/10/2010
 Letting Date:        05/17/2007                                          Final Est Sub:




County:         McIntosh                                    Commissioner District:                             1
 Contracts Completed - Final Estimate Not Processed


 25102(04)     Contract: 110383   CORD       Residency:   01003           0.965 MI. CO.RD./BRIDGE RE-
                                                                          HAB.:OVER LAKE EUFAULA, 3.0 MI.
 CIRB-146C(100)RB                            COBB ENGINEERING CO., INC.
                                                                          SO. OF SH-9 IN VIVIAN & 6.5 MI. W.
 Contractor:          C-GAWF CONSTRUCTION, INC.                           OF US-69.
 Engineer:            COBB
 Contract Amount:     $948,053.27                                         Completion Date:               07/12/2012
 Letting Date:        08/18/2011                                          Final Est Sub:

 22223(04)     Contract: 110486   CORD       Residency:   01003           .188 MI. CO.RD.:BRIDGE AND
                                                                          APPROACHES OVER TRIB TO MILL
 BRF-146C(073)CI                             COBB ENGINEERING CO., INC.
                                                                          CREEK 1.0 MI. N AND 8.0 MI. E OF
 Contractor:          C-GAWF CONSTRUCTION, INC.                           HANNA
 Engineer:            COBB
 Contract Amount:     $234,928.30                                         Completion Date:               07/12/2012
 Letting Date:        10/20/2011                                          Final Est Sub:

 20291(04)     Contract: 090472      US-266   Residency:         01100    0.495 MI. GRADE, DRAIN & SURFACE
                                                                          US-266 BEGIN 0.3 MILES WEST OF
 SSP-146C(049)SS                              MUSKOGEE
                                                                          US-69 AND EXTEND EAST.
 Contractor:          GLOVER & ASSOCIATES, INC.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $5,647,930.93                                       Completion Date:               08/29/2011
 Letting Date:        07/23/2009                                          Final Est Sub:




County:         Murray                                      Commissioner District:                             7
 Contracts Completed - Final Estimate Not Processed


 16352(04)     Contract: 010235    US-77       Residency:        07200    0.00 M. BR. PAINTING ON US-77;
                                                                          BRIDGE OVER TURKEY CREEK, 8.52
 BRFY-NBIP(87)                                  ARDMORE
                                                                          MILES N. OF DAVIS.
 Contractor:          KERRVILLE PAINTING CO., INC.
 Engineer:            Earp, Jay
 Contract Amount:     $50,600.00                                          Completion Date:               12/12/2001
 Letting Date:        06/21/2001                                          Final Est Sub:                 02/25/2005

 20965(04)     Contract: 110498   US77      Residency:     07200          0.00 MI. US-77:BRIDGE REHAB OVER
                                                                          TURKEY/GARNER CREEK .3 MI. S OF
 SBR-150C(053)SB                             ARDMORE
                                                                          GARVIN COUNTY LINE
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC
 Engineer:            Earp, Jay
 Contract Amount:     $699,932.84                                         Completion Date:               07/27/2012
 Letting Date:        10/20/2011                                          Final Est Sub:




County:         Muskogee                                    Commissioner District:                             1
 Contracts Completed - Final Estimate Not Processed




                                           Construction Status Report                              Page 28
22164(06)     Contract: 090574     I-40    Residency:             01200    */BRFY-151C(209)MS/BRFY-151B
                                                                           (210)MS;0.00 MI. IS-40/US-62/
BRFY-040-6(366)290MS*                       SALLISAW
                                                                           US-64;BRIDGE IMPROV.(PIER
Contractor:          JENSEN CONSTRUCTION COMPANY                           PROTECTION)MULTIPLE LOCATIONS
Engineer:            Edwards, Carl
Contract Amount:     $7,910,832.00                                         Completion Date:                07/02/2012
Letting Date:        06/17/2010                                            Final Est Sub:

20900(05)     Contract: 090323     I-40    Residency:      01200       4.998 MI. PAVEMENT
                                                                       REHABILITATION & BRIDGE I-40
IM-STIM(001)                                SALLISAW
                                                                       FROM MILE MARKER 281.67 TO
Contractor:          DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
                                                                       288.22.
Engineer:            Edwards, Carl
Contract Amount:     $33,928,747.73                                    Completion Date:             03/30/2012
Letting Date:        03/19/2009                                        Final Est Sub:

29020(04)     Contract: 120104      IS-40     Residency:          01200    1.30 MI. IS-40/RESURFACE
                                                                           (ASPHALT)FROM 1.0 MI. EAST OF
IMY-0040-6(376)288 3P                         SALLISAW
                                                                           SH-100, EXTEND EAST.
Contractor:           GLOVER & ASSOCIATES, INC.
Engineer:             Edwards, Carl
Contract Amount:      $991,037.10                                          Completion Date:                05/25/2012
Letting Date:         02/16/2012                                           Final Est Sub:

28585(05)     Contract: 110385      IS-40       Residency:        01100    0.00 MI. IS-40:JOINT SEAL/
                                                                           REPAIR:OVER COUNTY RD., 2.8 MI.
BRFY-151N(239)3B                                MUSKOGEE
                                                                           EAST OF THE MCINTOSH       C/L.
Contractor:          PBX CORPORATION
Engineer:            Ivy, Steve (Act.)
Contract Amount:     $85,439.00                                            Completion Date:                05/15/2012
Letting Date:        08/18/2011                                            Final Est Sub:

28585(04)     Contract: 110384   IS-40       Residency:     01001          0.00 MI. IS-40:BRIDGE PAINT
                                                                           -ING:OVER COUNTY RD., 2.8 MI.
BRFY-NBIP(440)3B                             ENGR. SERV. & TESTING
                                                                           EAST OF THE MCINTOSH C/L.
Contractor:          TARPON INDUSTRIAL, INC.
Engineer:            EST
Contract Amount:     $196,715.00                                           Completion Date:                03/30/2012
Letting Date:        08/18/2011                                            Final Est Sub:                  08/13/2012

27994(04)     Contract: 110103      US-62  Residency:             01100    0.00 MI. US-62;BRIDGE REHAB.
                                                                           ;OVER THE MK&T R/R, 3.2 MI. E.OF
SBR-151A(229)SB                             MUSKOGEE
                                                                           THE US-69 JUNCTION.
Contractor:          MANHATTAN ROAD & BRIDGE COMPANY
Engineer:            Ivy, Steve (Act.)
Contract Amount:     $1,379,192.95                                         Completion Date:                05/23/2012
Letting Date:        03/17/2011                                            Final Est Sub:

14994(10)     Contract: 070189      US-64  Residency:             01100    1.849 MI. GRADE, DRAIN, BRIDGE &
                                                                           SURFACE US-64 FROM 11.3 MI. S. OF
STPY-151C(004)                              MUSKOGEE
                                                                           SH-165 EXT. S. (5 LANE)(DIRTY CRK.
Contractor:          DUIT CONSTRUCTION COMPANY, INC.                       & OVERFLOW).
Engineer:            Ivy, Steve (Act.)
Contract Amount:     $9,168,998.59                                         Completion Date:                08/04/2010
Letting Date:        05/17/2007                                            Final Est Sub:

29021(04)     Contract: 120105     US-64     Residency:           01200    7.03 MI. US-64/RESURFACE
                                                                           (ASPHALT)FROM SH-2, EXTEND
STPY-151C(247)3P                             SALLISAW
                                                                           EAST.
Contractor:          GLOVER & ASSOCIATES, INC.
Engineer:            Edwards, Carl
Contract Amount:     $1,206,926.67                                         Completion Date:                07/20/2012
Letting Date:        02/16/2012                                            Final Est Sub:

28295(04)     Contract: 110171      US-69    Residency:           01100    16.45 MI. US-69/RESURFACE
                                                                           (ASPHALT)FROM THE MCINTOSH
NHY-013N(149)(151)3P                         MUSKOGEE
                                                                           C/L, EXTEND NORTH FROM 0.5 MI.
Contractor:          GLOVER & ASSOCIATES, INC.                             N. OF US-64, EXTEND N.
Engineer:            Ivy, Steve (Act.)
Contract Amount:     $3,036,841.00                                         Completion Date:                05/17/2012
Letting Date:        02/17/2011                                            Final Est Sub:

                                            Construction Status Report                              Page 29
County:          Noble                                        Commissioner District:                                  4
 Contracts Completed - Final Estimate Not Processed


 22352(04)     Contract: 110195    CORD          Residency:    04009            0.236 MI. CO.RD. BRIDGE &
                                                                                APPROACHES;OVER EAST WARREN
 BRF-152C(093)CI                                 CIRCUIT ENGR. DISTR. # 8
                                                                                CR., 0.60 MI. NORTH OF THE
 Contractor:          K & R BUILDERS, INC.                                      SH-164 JUNCTION.
 Engineer:            CED8
 Contract Amount:     $412,917.89                                              Completion Date:                  01/20/2012
 Letting Date:        04/14/2011                                               Final Est Sub:

 12317(04)     Contract: 070333     US-77    Residency:      04100         *(111)BF / 1.52 MI. GRD, DRN, SURF
                                                                           & BR US-77 RED ROCKCRK OVRFLW
 SAB-52C(194)BF/SAB-152C*                     PERRY
                                                                           1.1 MI S OF SH-15/SH-15 UNNAMED
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) E US-77.
                                                                           CRK 0.7 MI
 Engineer:            Zachary, Ted
 Contract Amount:     $7,055,993.43                                        Completion Date:               04/08/2011
 Letting Date:        07/19/2007                                           Final Est Sub:




County:          Nowata                                       Commissioner District:                                  8
 Contracts Completed - Final Estimate Not Processed


 27057(04)     Contract: 100607     US-169       Residency:        08300        6.00 MI. US-169;PAVEMENT RE-
                                                                                HAB(ASPHALT);FROM 6.0 MI. S. OF
 NHY-030N(068)                                   CLAREMORE
                                                                                THE KANSAS STATE LINE,   EXTEND
 Contractor:          APAC-CENTRAL, INC.                                        SOUTH.
 Engineer:            Bray, Timothy
 Contract Amount:     $2,665,265.99                                            Completion Date:                  12/15/2011
 Letting Date:        11/18/2010                                               Final Est Sub:

 27025(04)     Contract: 100272     US-169    Residency:           08300        4.817 MI. US-169:RESURFACE
                                                                                (ASPHALT)FROM THE ROGERS/
 NHY-030N(067)                                CLAREMORE
                                                                                NOWATA COUNTY LINE, EXTEND
 Contractor:          BECCO CONTRACTORS, INC.                                   NORTH.
 Engineer:            Bray, Timothy
 Contract Amount:     $3,750,716.40                                            Completion Date:                  08/01/2012
 Letting Date:        05/20/2010                                               Final Est Sub:




County:          Okfuskee                                     Commissioner District:                                  3
 Contracts Completed - Final Estimate Not Processed


 26268(04)     Contract: 090169     IS-40      Residency:   03003               0.00 MI. IS-40;SAFETY IMPRO.
                                                                                (CABLE BARRIER)FROM MILE
 HSIPIG-0040-5(406)216TR                       COBB ENGINEERING CO., INC.
                                                                                MARKER 230.
 Contractor:          ACTION SAFETY SUPPLY CO.
 Engineer:            COBB
 Contract Amount:     $2,334,968.32                                            Completion Date:                  06/29/2012
 Letting Date:        10/21/2010                                               Final Est Sub:

 27568(04)     Contract: 110339      IS-40  Residency:      03300               0.00 MI. IS-40:BRIDGE RE-
                                                                                HAB.:OVER NS-375, 7.4 MI.      EAST
 SBR-154N(161)SB                             WEWOKA
                                                                                OF THE SEMINOLE C/L.
 Contractor:          WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $783,537.00                                              Completion Date:                  01/25/2012
 Letting Date:        07/21/2011                                               Final Est Sub:




                                             Construction Status Report                                  Page 30
County:          Oklahoma                                     Commissioner District:                               4
 Contracts Completed - Final Estimate Not Processed


 22924(04)     Contract: 100301     CORD    Residency:             04400      0.512 MI. CO.RD.;GRADE,DRAIN , &
                                                                              SURFACE(HOGBACK RD.)AT THEI-44
 SEC115-0H17(011)SG                         EDMOND
                                                                              (TURNER TURNPIKE) INTER- CHANGE.
 Contractor:          MARKWELL PAVING COMPANY, INC.
 Engineer:            Hubbard, Tom
 Contract Amount:     $4,224,611.42                                           Completion Date:                03/30/2012
 Letting Date:        04/15/2010                                              Final Est Sub:

 22129(04)     Contract: 090336     CORD     Residency:      04600         0.535 MI. CO.RD.;BRIDGE &
                                                                           APPROACHES(BRITTON RD.)OVER
 CIRB-155C(474)(475)RB                        OKLAHOMA CITY
                                                                           ANUNNAMED CR. & THE N. CANA-
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           DIAN RIVER.
 Engineer:            Howell, Terry
 Contract Amount:     $2,155,875.12                                        Completion Date:             11/06/2010
 Letting Date:        05/14/2009                                           Final Est Sub:

 25011(04)     Contract: 110469    CORD          Residency:        04400      .112 MI. CO.RD. SORGHUM MILL RD
                                                                              (EW-90) OVER CHISHOLM CREEK AT
 BRO-155D(638)CI                                 EDMOND
                                                                              WESTER AVE IN EDMOND.
 Contractor:          K & R BUILDERS, INC.
 Engineer:            Hubbard, Tom
 Contract Amount:     $631,562.77                                             Completion Date:                07/16/2012
 Letting Date:        09/15/2011                                              Final Est Sub:

 22321(05)     Contract: 090419     CT.ST.    Residency:     04600            0.00 MI. CT.ST.;SAFETY IM- PROV.
                                                                              (TRAFFIC SIGNALS)AT VAR- IOUS
 STPG-155F(671)AG                              OKLAHOMA CITY
                                                                              LOCATIONS IN THE OKC      METRO
 Contractor:          TRAFFIC & LIGHTING SYSTEMS, LLC                         AREA.
 Engineer:            Howell, Terry
 Contract Amount:     $202,702.75                                             Completion Date:                08/01/2010
 Letting Date:        06/18/2009                                              Final Est Sub:

 28044(04)     Contract: 120025    CTST     Residency:             04400      1.01 MI. CT.ST.(MAY AVE.)
                                                                              RESURFACE(ASPHALT)FROM
 STP-155B(812)AG                             EDMOND
                                                                              BRITTONRD. TO HEFNER RD., IN THE
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                          CITY OF THE VILLAGE.
 Engineer:            Hubbard, Tom
 Contract Amount:     $473,439.21                                             Completion Date:                06/06/2012
 Letting Date:        01/19/2012                                              Final Est Sub:

 27854(04)     Contract: 110305    CTST       Residency:           04400      0.00 MI. CT.ST.:STRIPING &
                                                                              PAVEMENT MARKING:AT VARIOUS
 STPG-155B(803)AG                             EDMOND
                                                                              LOCATIONS IN THE CITY OF
 Contractor:          DIRECT TRAFFIC CONTROL INC.                             EDMOND.
 Engineer:            Hubbard, Tom
 Contract Amount:     $497,707.32                                             Completion Date:                02/03/2012
 Letting Date:        06/16/2011                                              Final Est Sub:

 28105(04)     Contract: 110014     CTST    Residency:             04002      5.28 MI. CT.ST.;GRADE,DRAIN, &
                                                                              SURFACE(HEFNER RD.)FROM THE
 STP-155B(813)AG                             TETRA TECH
                                                                              BROADWAY EXTENSION,EXTEND      E.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                          IN OKC.
 Engineer:            TETR
 Contract Amount:     $1,967,951.20                                           Completion Date:                02/01/2012
 Letting Date:        01/20/2011                                              Final Est Sub:

 22321(06)     Contract: 100564     CTST      Residency:    04600             0.00 MI. CT.ST.;SAFETY IMPRO.
                                                                              (TRAFFIC SIGNALS)AT VARIOUS
 STPG-155F(722)AG                             OKLAHOMA CITY
                                                                              LOCATIONS IN THE OKC AREA.
 Contractor:          DAVIS H. ELLIOT CONSTRUCTION COMPANY, INC.
 Engineer:            Howell, Terry
 Contract Amount:     $148,808.00                                             Completion Date:                03/21/2012
 Letting Date:        10/21/2010                                              Final Est Sub:


                                             Construction Status Report                               Page 31
28223(04)     Contract: 110306     CTST    Residency:    04600                0.50 MI. CT.ST.(NE 23RD)
                                                                              PAVEMENT REHAB.(PC CONC.)
MC-155D(836)                               OKLAHOMA CITY
                                                                              FROMWALNUT STREET, EXTEND EAST.
Contractor:          RUDY CONSTRUCTION CO.
Engineer:            Howell, Terry
Contract Amount:     $824,622.00                                              Completion Date:                08/31/2012
Letting Date:        08/18/2011                                               Final Est Sub:

17428(75)     Contract: 090645     I-40     Residency:     04600        0.195 MI. GRADE, DRAIN, SURFACE &
                                                                        BRIDGE I-40 FROM 0.25 MI. EAST OF
OKCY-XTWN(065)SG                             OKLAHOMA CITY
                                                                        AGNEW AVE. EXTEND EAST IN
Contractor:          SHERWOOD CONST. , ALLEN CONTR. & MANHATTAN RD. & BR. (JV)
                                                                        OKLAHOMA CITY.
Engineer:            Howell, Terry
Contract Amount:     $22,514,185.55                                     Completion Date:              08/10/2011
Letting Date:        10/15/2009                                         Final Est Sub:

17428(26)     Contract: 080120     I-40   Residency:    04600                 *WN(008)HP/2.649 MI. GRADE,
                                                                              DRAIN SURFACE, BRIDGE &
OKCY-XTWN(007)TI/OKCY-XT*                 OKLAHOMA CITY
                                                                              RAILROAD I-40 E. OF PENN. AVE.
Contractor:          SHERWOOD CONSTRUCTION CO., INC.                          EXT. E. / FROM SHARTEL AVE. EXT.
Engineer:            Howell, Terry                                            W.
Contract Amount:     $40,574,036.60                                           Completion Date:                02/22/2010
Letting Date:        08/21/2008                                               Final Est Sub:

17428(30)     Contract: 090105     I-40      Residency:           04400       0.773 MI. GRADE, DRAIN, SURFACE &
                                                                              BRIDGE I-40 FOM MAY AVE. EXTEND
OKCY-XTWN(011)HP                             EDMOND
                                                                              E. 0.9 MI. TO AGNEW AVE. IN OKC.
Contractor:          ALLEN CONTRACTING, INC.
Engineer:            Hubbard, Tom
Contract Amount:     $8,926,771.72                                            Completion Date:                01/24/2011
Letting Date:        06/18/2009                                               Final Est Sub:

19693(04)     Contract: 020183     IS-40     Residency:    04600              0.00 M. BRIDGE PAINTING I-40:
                                                                              OVER NORTH CANADIAN RIVER       IN
IMY-NBIP(281)                                OKLAHOMA CITY
                                                                              WEST OKC.
Contractor:          J & N INTERNATIONAL COATINGS, INC.
Engineer:            Howell, Terry
Contract Amount:     $378,000.00                                              Completion Date:                08/31/2012
Letting Date:        05/23/2002                                               Final Est Sub:

24883(05)     Contract: 110114    IS-44         Residency:   04003            0.00 MI. IS-44:BRIDGE REHAB.
                                                                              OVER SH-3A(BELLE ISLE BRDG.) 5.7
SBR-155N(786)SB                                 COBB ENGINEERING CO., INC.
                                                                              MI. N.E. OF THE IS-40  JCT IN OKC.
Contractor:          RESTEK, INC.
Engineer:            COBB
Contract Amount:     $440,789.00                                              Completion Date:                04/22/2012
Letting Date:        03/17/2011                                               Final Est Sub:

25000(04)     Contract: 080360     IS-44    Residency:    04600               *SAP-141A(201)/IMG-044-2
                                                                              (471)223 TR; 0.00 MI. IS-44, SAFETY
IMG-0035-3(297)138 TR*                      OKLAHOMA CITY
                                                                              IMPROVEMENT(MESSAGE
Contractor:          MIDSTATE TRAFFIC CONTROL, INC.                           SIGN)LOCATIONS DIV. 3,4,5.
Engineer:            Howell, Terry
Contract Amount:     $1,837,942.75                                            Completion Date:                11/03/2010
Letting Date:        11/20/2008                                               Final Est Sub:                  08/30/2012

24883(04)     Contract: 100193   IS-44          Residency:   04003            0.00 ,MI. IS-44;BRIDGE REHAB.
                                                                              (BELLE ISLE BRIDGE) OVER
SBR-155N(634)SB                                 COBB ENGINEERING CO., INC.
                                                                              NORTH-WEST EXPRESSWAY.
Contractor:          PBX CORPORATION
Engineer:            COBB
Contract Amount:     $648,625.00                                              Completion Date:                04/16/2011
Letting Date:        03/18/2010                                               Final Est Sub:

17271(04)     Contract: 080093    US-77      Residency:   04400            1.506 KM GRADE, DRAIN, SURFACE &
                                                                           BRIDGE US-77 (BROADWAY
NHY-024N(004)                                EDMOND
                                                                           EXTENSION) AT MEMORIAL ROAD
Contractor:          ALLEN CONTRACTING, INC./MUSKOGEE BRIDGE CO., INC. (J V)
                                                                           INTERCHANGE.
Engineer:            Hubbard, Tom
Contract Amount:     $27,947,058.47                                       Completion Date:              11/15/2010
Letting Date:        02/21/2008                                           Final Est Sub:

                                            Construction Status Report                                 Page 32
County:          Okmulgee                                     Commissioner District:                              1
 Contracts Completed - Final Estimate Not Processed


 25642(04)     Contract: 110307   CORD      Residency:     02100                0.169 MI.CO.RD./BRIDGE &
                                                                                APPROACHES;OVER SNAKE CREEK,
 BRO-156D(160)CI                             ANTLERS
                                                                                0.5 MI. NORTH OF THE SH-16
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC                  JUNCTION.
 Engineer:            Moy, Ryan
 Contract Amount:     $331,800.81                                              Completion Date:             04/30/2012
 Letting Date:        06/16/2011                                               Final Est Sub:

 22026(04)     Contract: 110463    CT-ST      Residency:      01004       .041 MI. CT.ST. (4TH STREET) OVER
                                                                          COAL CREEK .2 MI. SOUTH OFI-40, IN
 STP-156C(102)UR                               JACOBS (AKA - CARTER-BURGESS)
                                                                          HENRYETTA.
 Contractor:          B & B BRIDGE COMPANY, LLC
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $433,809.02                                         Completion Date:               06/30/2012
 Letting Date:        09/15/2011                                          Final Est Sub:

 23106(04)     Contract: 100608      SH-16   Residency:      01100         B0.445 MI. SH-16;BRIDGE &
                                                                           APPROACHES/OVER SALT CR.,4.2 MI.
 BRFY-156C(120)                               MUSKOGEE
                                                                           EAST OF CREEK COUNTY      LINE.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $2,032,848.13                                        Completion Date:               05/10/2012
 Letting Date:        10/21/2010                                           Final Est Sub:

 29056(04)     Contract: 120107     SH-16        Residency:     01004       6.920 MI. SH-16;RESURFACE
                                                                            (ASPHALT)FROM THE CREEK C/L,
 CIP-256C(003)SR                                 JACOBS (AKA - CARTER-BURGESS)
                                                                                EXTEND EAST.
 Contractor:          APAC-CENTRAL, INC.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $1,263,902.87                                            Completion Date:             06/30/2012
 Letting Date:        02/16/2012                                               Final Est Sub:

 24271(04)     Contract: 100345      US-75    Residency:           01100        5.611 MI. US-75;INTERSEC-  TION
                                                                                MOD.& SAFETY IMPROV.    (CABLE
 NHY-014N(079)(082)                           MUSKOGEE
                                                                                BARRIER)FROM 6.3 MI. & 13.3 MI.
 Contractor:          BECCO CONTRACTORS, INC.                                   N. OF US-62.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $4,944,602.43                                            Completion Date:             08/24/2011
 Letting Date:        05/20/2010                                               Final Est Sub:




County:          Osage                                        Commissioner District:                              8
 Contracts Completed - Final Estimate Not Processed


 23987(04)     Contract: 110386    CORD          Residency:    08007            0.204 MI. CO.RD./BRIDGE &
                                                                                APPROACHES:OVER CLEAR CREEK,
 BRO-157D(094)CO                                 CRAIG & KEITHLINE, INC.
                                                                                1.0 MI. SOUTH OF THE US-60
 Contractor:          BELK BRIDGE, INC.                                         JUNCTION.
 Engineer:            C&KI
 Contract Amount:     $643,520.30                                              Completion Date:             06/19/2012
 Letting Date:        08/18/2011                                               Final Est Sub:

 12311(04)     Contract: 100013     SH-11   Residency:   08400                  0.216 MI. SH-11;BRIDGE &
                                                                                APPROACHES;OVER MUD CR.,2.33
 SSP-057C(335)SS                            SAND SPRINGS
                                                                                MI. EAST OF THE KAY COUNTY
 Contractor:          WITTWER CONSTRUCTION CO., INC.                            LINE.
 Engineer:            Williams, Mark J.
 Contract Amount:     $755,115.00                                              Completion Date:             03/16/2011
 Letting Date:        01/28/2010                                               Final Est Sub:               05/05/2011



                                             Construction Status Report                                Page 33
 28259(04)     Contract: 110119     SH-20     Residency:   08400          0.00 MI. SH-20 BRIDGE REHAB.;
                                                                          OVER QUAPAW CR., 3.8 MI. WEST OF
 SBR-157A(177)SB                              SAND SPRINGS
                                                                          THE TULSA COUNTY LINE.
 Contractor:          BECCO CONTRACTORS, INC.
 Engineer:            Williams, Mark J.
 Contract Amount:     $720,251.57                                         Completion Date:               02/17/2012
 Letting Date:        04/14/2011                                          Final Est Sub:

 28270(04)     Contract: 110122     US-60       Residency:        08400   6.63 MI. US-60:RESURFACE
                                                                          (ASPHALT)FROM THE SH-18 JCT,
 NHY-018N(060)3P                                SAND SPRINGS
                                                                          EXTEND EAST.
 Contractor:          APAC-CENTRAL, INC.
 Engineer:            Williams, Mark J.
 Contract Amount:     $1,880,569.24                                       Completion Date:               04/30/2012
 Letting Date:        02/17/2011                                          Final Est Sub:




County:         Ottawa                                       Commissioner District:                           8
 Contracts Completed - Final Estimate Not Processed


 22896(04)     Contract: 090033     CO.RD.    Residency:          08300   0.264 MI. CO.RD.; BRIDGE &
                                                                          APPROACHES;OVER NEOSHO RIVER,
 CIRB-158D(101)RB                             CLAREMORE
                                                                          3.4 MI. NO. & 2.0 MI. EAST OF THE
 Contractor:          M.J. LEE CONSTRUCTION COMPANY                       SH-125/US-60 JCT.
 Engineer:            Bray, Timothy
 Contract Amount:     $4,175,684.50                                       Completion Date:               07/02/2010
 Letting Date:        01/22/2009                                          Final Est Sub:

 27242(04)     Contract: 110308   CORD      Residency:     08003          0.126 MI.CO.RD.;BRIDGE &
                                                                          APPROACHES:OVER BEE CREEK,
 BRO-158D(172)CO                             COBB ENGINEERING CO., INC.
                                                                          2.8 MI. SOUTH OF THE US- 60
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC            JUNCTION.
 Engineer:            COBB
 Contract Amount:     $423,651.45                                         Completion Date:               06/06/2012
 Letting Date:        06/16/2011                                          Final Est Sub:

 22188(04)     Contract: 100536     CORD    Residency:            08300   0.163 MI. CO.RD.; BRIDGE &
                                                                          APPROACHES/OVER BEAVER CR.,
 BRO-158D(086)CO                             CLAREMORE
                                                                          0.50 MI. N. OF THE I-44
 Contractor:          BEACHNER CONSTRUCTION CO., INC.                     JUNCTION.
 Engineer:            Bray, Timothy
 Contract Amount:     $479,618.20                                         Completion Date:               02/28/2012
 Letting Date:        09/16/2010                                          Final Est Sub:

 08932(07)     Contract: 090666     SH-10     Residency:          08300   0.00 MI. SH-10;RIGHT-OF-WAY
                                                                          CLEARANCE/AT LITTLE ELM CR. &
 BRFY-158C(170)RW                             CLAREMORE
                                                                          UNNAMED CR., 0.5 MI. EAST OF THE
 Contractor:          K & K CONTRACTING, INC.                             WILL ROGERS TRNPIKE.
 Engineer:            Bray, Timothy
 Contract Amount:     $105,555.55                                         Completion Date:               04/27/2010
 Letting Date:        12/17/2009                                          Final Est Sub:

 26609(04)     Contract: 090607     SH-10   Residency:            08300   0.00 MI. SH-10;SAFETY IMPRO-
                                                                          VEMENT(CABLE BARRIER &
 HSIPG-158C(168)                            CLAREMORE
                                                                          GUARD-RAIL) AT VARIOUS
 Contractor:          FULSOM CONSTRUCTION COMPANY, INC.                   LOCATIONS IN DIV. VIII.
 Engineer:            Bray, Timothy
 Contract Amount:     $979,785.00                                         Completion Date:               10/05/2010
 Letting Date:        12/17/2009                                          Final Est Sub:

 20894(04)     Contract: 110017     US-59   Residency:            08300   0.400 MI. US-59/BRIDGE &
                                                                          APPROACHES:OVER TH BNSF RAIL-
 BRFY-158B(055)                              CLAREMORE
                                                                          ROAD,2.6 MI. N. OF THE
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY                     DELAWARE C/L.
 Engineer:            Bray, Timothy
 Contract Amount:     $4,944,607.36                                       Completion Date:               06/27/2012
 Letting Date:        01/20/2011                                          Final Est Sub:


                                            Construction Status Report                            Page 34
 28271(04)     Contract: 110124     US-69     Residency:          08300   -158A(189)3P / 14.40 MI. US
                                                                          -69A;RESURFACE(ASPHALT)FROM
 STPY-158B(188)3P/STPY*                       CLAREMORE
                                                                          THE US-69 JCT,EXTEND EAST.
 Contractor:          GLOVER & ASSOCIATES, INC.                           US-69 FROM THE SH-10E.
 Engineer:            Bray, Timothy
 Contract Amount:     $3,074,815.02                                       Completion Date:               07/11/2012
 Letting Date:        02/17/2011                                          Final Est Sub:

 27085(04)     Contract: 110199     US60     Residency:      08001        0.00 MI. US-60: OVER NEOSHO RIVER
                                                                          JUST W OF SH-137 JCT. AND OVER
 BRFY-NBIP(434)(435)                          ENGR. SERV. & TESTING
                                                                          SPRING RIVER JUST E OF SH-137 JCT.
 Contractor:          SPARTAN CONTRACTING, LLC
 Engineer:            EST
 Contract Amount:     $1,347,000.00                                       Completion Date:               06/07/2012
 Letting Date:        09/15/2011                                          Final Est Sub:




County:         Pawnee                                       Commissioner District:                            8
 Contracts Completed - Final Estimate Not Processed


 24721(04)     Contract: 110342     CORD    Residency:    08400           0.047 MI. CO. RD.:BRIDGE &
                                                                          APPROACHES:OVER UNNAMED
 BRO-159D(084)CO                             SAND SPRINGS
                                                                          CREEK,2.3 MI. WEST OF THE SJ-99.
 Contractor:          KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:            Williams, Mark J.
 Contract Amount:     $176,897.25                                         Completion Date:               07/23/2012
 Letting Date:        07/21/2011                                          Final Est Sub:

 24086(04)     Contract: 070317     US-64      Residency:         08100   *NHG-019N(107)(108)SS; 0.00 MI.
                                                                          CABLE BARRIER PROJECT
 STPG-159A(069)SS/*                            TULSA
                                                                          US-64/US-412 BEGIN AT SH-48
 Contractor:          ACTION SAFETY SUPPLY CO.                            EXTEND E. TO I-244 IN TULSA.
 Engineer:            Arnold, Bruce
 Contract Amount:     $2,920,742.77                                       Completion Date:               08/27/2009
 Letting Date:        07/19/2007                                          Final Est Sub:




County:         Payne                                        Commissioner District:                            4
 Contracts Completed - Final Estimate Not Processed


 23656(04)     Contract: 110520     CORD        Residency:        04500   0.312 MI. CO.RD.;BRIDGE &
                                                                          APPROACHES:OVER COUNCIL CR.,
 BRO-160D(160)CI                                STILLWATER
                                                                          2.0 MI. S. OF SH-51
 Contractor:          BELK BRIDGE, INC.
 Engineer:            Arps, Jonathan
 Contract Amount:     $731,991.33                                         Completion Date:               07/17/2012
 Letting Date:        11/17/2011                                          Final Est Sub:

 28224(04)     Contract: 110309     SH-51       Residency:        04500   3.79 MI. SH-51;RESURFACE
                                                                          (ASPHALT)FROM THE CREEK C/L,
 SSR-160B(205)SR                                STILLWATER
                                                                          EXTEND WEST TO YALE.
 Contractor:          APAC-CENTRAL, INC.
 Engineer:            Arps, Jonathan
 Contract Amount:     $724,541.30                                         Completion Date:               05/29/2012
 Letting Date:        01/19/2012                                          Final Est Sub:




County:         Pittsburg                                    Commissioner District:                            2
 Contracts Completed - Final Estimate Not Processed




                                            Construction Status Report                            Page 35
 25471(04)     Contract: 100538      CO.RD.  Residency:            02400     0.297 MI. CO.RD.;BRIDGE &
                                                                             APPROACHES;OVER COAL CR., 2.5
 CIRB-161C(215)RB                            MCALESTER
                                                                             MI. N. OF THE US-270 JUNC- TION.
 Contractor:          C-GAWF CONSTRUCTION, INC.
 Engineer:            Plymate, Larry
 Contract Amount:     $1,352,747.49                                          Completion Date:               04/19/2012
 Letting Date:        09/16/2010                                             Final Est Sub:

 29030(04)     Contract: 120042      US-270   Residency:           02400     0.44 MI. US-270;RESURFACE
                                                                             (ASPHALT) BEGIN 1.3 MI. WEST OF
 SSR-261B(001)SR                              MCALESTER
                                                                             SH-1, EXTEND EAST.
 Contractor:          JOB CONSTRUCTION CO., INC.
 Engineer:            Plymate, Larry
 Contract Amount:     $100,564.20                                            Completion Date:               06/07/2012
 Letting Date:        01/19/2012                                             Final Est Sub:

 28685(04)     Contract: 120029      US-69    Residency:           02400     3.70 MI. US-69;RESURFACE
                                                                             (UTBWC)BEGIN 0.4 MI. NORTH OF
 NHY-013N(152)3P                              MCALESTER
                                                                             US-270, EXTEND NORTH(SOUTH
 Contractor:          JOB CONSTRUCTION CO., INC.                             -BOUND LANES ONLY).
 Engineer:            Plymate, Larry
 Contract Amount:     $461,560.00                                            Completion Date:               05/22/2012
 Letting Date:        02/16/2012                                             Final Est Sub:                 08/27/2012

 26296(07)     Contract: 090126      US-69  Residency:      02400       2.76 MI. US-69:PAVEMENT RE-
                                                                        HAB(P.C. CONC.)FROM 6.30 MI. N.
 NHY-013N(131)3P                             MCALESTER
                                                                        OF THE SH-63 JCT, EXTEND NORTH.
 Contractor:          DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
 Engineer:            Plymate, Larry
 Contract Amount:     $1,973,820.40                                     Completion Date:              04/27/2012
 Letting Date:        01/20/2011                                        Final Est Sub:




County:          Pontotoc                                     Commissioner District:                               3
 Contracts Completed - Final Estimate Not Processed


 23496(04)     Contract: 110363      CORD        Residency:        03100     *162C(202)CI /0.415 MI. CO.
                                                                             RD.;BRIDGE & APPROACHES:OVER
 BRO-162D(154)CI/BRF-*                           ADA
                                                                             WEST DAYS CR. 2.8 MI. S. & 1.2 MI.
 Contractor:          K & R BUILDERS, INC.                                   W. OF SH-19.
 Engineer:            Russell, Julie
 Contract Amount:     $740,383.55                                            Completion Date:               06/06/2012
 Letting Date:        07/21/2011                                             Final Est Sub:

 28169(04)     Contract: 110210      SH-1        Residency:        03100     *(218)SB / 0.00 MI. SH-1:   BRIDGE
                                                                             REHAB.:OVER SH-3, 1.0 MI. S. OF
 SBR-162A(217)SB/SBR-162B*                       ADA
                                                                             ADA. SH-3W;OVER      SH-19, 1.5 MI.
 Contractor:          OBC, INC.                                              E. OF SH-1.
 Engineer:            Russell, Julie
 Contract Amount:     $1,437,855.45                                          Completion Date:               04/20/2012
 Letting Date:        02/17/2011                                             Final Est Sub:

 28199(04)     Contract: 120030      SH-1   Residency:             03100     7.33 MI. SH-1; RESURFACE
                                                                             (ASPHALT) FROM HUGHES COUNTY
 SSR-162B(221)SR                             ADA
                                                                             LINE, EXTEND WEST.
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.                     NORTH OF JUMBO.
 Engineer:            Russell, Julie
 Contract Amount:     $2,977,352.79                                          Completion Date:               07/15/2012
 Letting Date:        01/19/2012                                             Final Est Sub:




County:          Pottawatomie                                 Commissioner District:                               3
 Contracts Completed - Final Estimate Not Processed



                                             Construction Status Report                               Page 36
 28464(04)     Contract: 110343     IS-40    Residency:     03004       0.00 MI. IS-40:SAFETY IMPRO-
                                                                        VEMENT(GUARDRAIL)FROM THE SH-
 HSIPIG-40-5(418)186TR                       JACOBS (AKA - CARTER-BURGESS)
                                                                        18 JUNCTION, EXTEND EAST.
 Contractor:          MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $1,000,590.50                                     Completion Date:             06/14/2012
 Letting Date:        07/21/2011                                        Final Est Sub:

 28206(04)     Contract: 110132      SH-18  Residency:           03300      4.610 MI. SH-18:RESURFACE
                                                                            (ASPHALT)FROM THE US-270B
 STPY-163A(355)3P                            WEWOKA
                                                                            JUNCTION, EXTEND EAST.
 Contractor:          HASKELL LEMON CONSTRUCTION CO.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $962,817.60                                           Completion Date:                09/02/2011
 Letting Date:        01/20/2011                                            Final Est Sub:

 28041(04)     Contract: 110362      SH-9   Residency:           03300      0.72 MI. SH-9:INTERSECTION
                                                                            MODIFICATION/AT MALONE RD. & AT
 STPY-163B(357)SG                            WEWOKA
                                                                            ROCK CREEK RD., IN THE   CITY OF
 Contractor:          HASKELL LEMON CONSTRUCTION CO.                        TECUMSEH.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $1,233,668.50                                         Completion Date:                06/15/2012
 Letting Date:        07/21/2011                                            Final Est Sub:




County:         Pushmataha                                  Commissioner District:                               2
 Contracts Completed - Final Estimate Not Processed


 20395(04)     Contract: 110493   CORD      Residency:     02013            0.28 MI. CO.RD.: BRIDGE AND
                                                                            APPROACHES;OVER CLOUDY CREEK
 CIRB-164C(051)RB                            CIRCUIT ENGR. DISTRICT # 3
                                                                            .7 MI. N AND .4 MI. E OF CLOUDY.
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC
 Engineer:            CED3
 Contract Amount:     $998,530.60                                           Completion Date:                08/08/2012
 Letting Date:        10/20/2011                                            Final Est Sub:

 28586(05)     Contract: 110388     SH-259   Residency:          02200      0.00 MI. US-259:JOINT SEAL/
                                                                            REPAIR: SH-3/SH-98/SH-112. AT
 BRFY-164A(166)3B                             HEAVENER
                                                                            VARIOUS LOCATIONS IN DIV. II.
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.
 Engineer:            Huddleston, David
 Contract Amount:     $215,951.43                                           Completion Date:                03/30/2012
 Letting Date:        08/18/2011                                            Final Est Sub:

 23201(04)     Contract: 090307     US-271   Residency:          02200      0.946 MI. BRIDGE AND APPROACHES
                                                                            US-271 OVER WALNUT CREEK 4.6
 SSP-164C(097)SS                             HEAVENER
                                                                            MILES SOUTHWEST OF THE LEFLORE
 Contractor:          HUB CONSTRUCTION, INC.                                COUNTY LINE.
 Engineer:            Huddleston, David
 Contract Amount:     $3,015,634.35                                         Completion Date:                04/19/2011
 Letting Date:        04/23/2009                                            Final Est Sub:

 23144(08)     Contract: 110250     US-69    Residency:          02200      0.00 MI. US-69;BRIDGE WATER
                                                                            PROOF SEAL/US-70/US-271/SH-1/
 BHFY-164C(165)                               HEAVENER
                                                                            SH-3/SH-37 AT MULTIPLE LO-
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.                 CATIONS IN DIV. II.
 Engineer:            Huddleston, David
 Contract Amount:     $83,455.40                                            Completion Date:                01/30/2012
 Letting Date:        04/14/2011                                            Final Est Sub:




County:         Roger Mills                                 Commissioner District:                               5
 Contracts Completed - Final Estimate Not Processed



                                           Construction Status Report                               Page 37
 28023(04)     Contract: 110389   CORD           Residency:    05005           0.101 MI. CO.RD./BRIDGE &
                                                                               APPROACHES:OVER CAMP HOLLOW
 BRO-165D(118)CI                                 CIRCUIT ENGR. DISTR. # 7
                                                                               CR., 4.0 MI. NORTH OF SH-47.
 Contractor:          SEWELL BROS., INC.
 Engineer:            CED7
 Contract Amount:     $184,803.50                                              Completion Date:               03/22/2012
 Letting Date:        08/18/2011                                               Final Est Sub:

 26034(04)     Contract: 100414     SH-47    Residency:      05100         0.00 MI. SH-47;BRIDGE REHAB.
                                                                           :OVER CROTEN CR. 5.9 MI. EAST OF
 STPY-165C(104)(110)                          CLINTON
                                                                           THE SH-30 JT, & OVER SER- GENT
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) 13.2 MI. E. OF
                                                                           MAJOR CR.
 Engineer:            Greer, Randy
 Contract Amount:     $1,544,594.87                                        Completion Date:              07/21/2011
 Letting Date:        07/22/2010                                           Final Est Sub:                06/20/2012




County:          Rogers                                       Commissioner District:                               8
 Contracts Completed - Final Estimate Not Processed


 25427(04)     Contract: 100498     CORD    Residency:     08300               0.226 MI. CO.RD.;BRIDGE &
                                                                               APPROACHES/OVER ELM CR., 2.4 MI.
 STP-166C(210)CO                             CLAREMORE
                                                                               S. OF SH-20 & 1.0 MI. E. OF TULSA
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC                 C/L.
 Engineer:            Bray, Timothy
 Contract Amount:     $1,261,809.40                                            Completion Date:               09/13/2011
 Letting Date:        09/16/2010                                               Final Est Sub:

 21490(04)     Contract: 110392    CORD       Residency:      08004       0.198 MI. CO.RD./BRIDGE &
                                                                          APPROACHES:OVER PANTHER CR.,
 BRO-166D(139)CI                               JACOBS (AKA - CARTER-BURGESS)
                                                                          3.2 MI. EAST OF IS-44.
 Contractor:          B & B BRIDGE COMPANY, LLC
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $456,119.71                                         Completion Date:           08/15/2012
 Letting Date:        08/18/2011                                          Final Est Sub:

 20315(08)     Contract: 090581     I-44    Residency:             08002       0.336 MI. BRIDGE & APPROACHES
                                                                               I-44 OVER NORTH 163RD EAST
 IMY-0044-2(476)238HP                        TETRA TECH
                                                                               AVENUE.
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY
 Engineer:            TETR
 Contract Amount:     $6,836,178.02                                            Completion Date:               05/19/2011
 Letting Date:        09/17/2009                                               Final Est Sub:

 19983(08)     Contract: 100496     SH-412P Residency:             08300       1.421 MI. SH-412P;GRADE,
                                                                               DRAIN,SURFACE & BRIDGE;US-412
 SEC1702Y-166A(194)SS                       CLAREMORE
                                                                               CT.ST.;FROM 3 MI. W. OF  305TH
 Contractor:          SHERWOOD CONSTRUCTION CO., INC.                          AVE. EXT.E., SH-412P.
 Engineer:            Bray, Timothy
 Contract Amount:     $7,818,098.00                                            Completion Date:               04/03/2012
 Letting Date:        08/19/2010                                               Final Est Sub:

 28578(04)     Contract: 120235     SH-66    Residency:            08300       0.016 MI.:SH-66/BRIDGE REPR.
                                                                               OVER THE VERDIGRIS RIVER.
 MC-266C(008)                                 CLAREMORE
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $173,240.00                                              Completion Date:               08/20/2012
 Letting Date:        05/17/2012                                               Final Est Sub:

 20899(04)     Contract: 110209     SH-66   Residency:             08300       0.22 MI. SH-66:BRIDGE &
                                                                               APPROACHES:SOUTHBOUND OVER
 BRFY-166C(130)SS                            CLAREMORE
                                                                               BIRD CR., & RD. UNDER 3.68 MI.
 Contractor:          MANHATTAN ROAD & BRIDGE COMPANY                          N.E. OF THE IS-44 JCT.
 Engineer:            Bray, Timothy
 Contract Amount:     $5,316,072.19                                            Completion Date:               04/17/2012
 Letting Date:        04/14/2011                                               Final Est Sub:


                                             Construction Status Report                                Page 38
 18887(05)     Contract: 090580     SH-88     Residency:           08300        4.616 MI. SH-88; GRADE,DRAIN
                                                                                ,SURFACE & BRIDGE. FROM 3.5
 STPY-166C(072)                               CLAREMORE
                                                                                MINORTHWEST OF US-412, EXTEND
 Contractor:          BECCO CONTRACTORS, INC.                                   NORTH.
 Engineer:            Bray, Timothy
 Contract Amount:     $8,993,188.75                                             Completion Date:             04/03/2012
 Letting Date:        10/15/2009                                                Final Est Sub:

 18887(04)     Contract: 050537     SH-88   Residency:             08300        3.49 MI. GRADE, DRAIN, SURFACE &
                                                                                BRIDGE SH-88 BEGIN @ US-412 &
 STPY-166C(71)                              CLAREMORE
                                                                                EXTEND NORTH.
 Contractor:          WITTWER CONSTRUCTION CO., INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $11,449,145.00                                            Completion Date:             04/30/2009
 Letting Date:        06/15/2006                                                Final Est Sub:               02/15/2012




County:          Seminole                                     Commissioner District:                               3
 Contracts Completed - Final Estimate Not Processed


 13626(07)     Contract: 100253      IS-40  Residency:      03300       *-40-5(405)203TR/ 6.016 MI.
                                                                        IS-40;PAVEMENT REHAB. & CABLE
 IMY-40-5(415)206/HSIPIG*                    WEWOKA
                                                                        BARRIER;FROM MILE MARKER 203,
 Contractor:                                                            EXTEND JV
                      DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC E. TO MILE MARKER 213.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $24,933,232.28                                    Completion Date:               04/30/2012
 Letting Date:        08/19/2010                                        Final Est Sub:

 21005(04)     Contract: 100198      SH-9    Residency:      03300         0.205 MI. SH-9;BRIDGE &
                                                                           APPROACHES;OVER CARTER
 BRFY-167C(088)                               WEWOKA
                                                                           CR.,1.4MI. EAST OF SH-99 JCT.
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $1,051,623.18                                        Completion Date:                  06/13/2011
 Letting Date:        07/22/2010                                           Final Est Sub:

 13020(04)     Contract: 070445      SH-99  Residency:             03300        8.665 KM GRADE, DRAIN &
                                                                                SURFACING SH-99 BEGIN N. OF I-40
 NHY-012N(019)                               WEWOKA
                                                                                & EXTEND N. TO PRAGUE.
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $11,884,548.98                                            Completion Date:             03/24/2011
 Letting Date:        11/15/2007                                                Final Est Sub:

 28463(04)     Contract: 110344    SH-99A   Residency:     03004       0.00 MI. SH-99A FROM
                                                                       POTTAWATOMIE COUNTY LINE,
 HSIPG-167C(187)TR                          JACOBS (AKA - CARTER-BURGESS)
                                                                       EXTEND EAST.
 Contractor:          FULSOM CONSTRUCTION COMPANY, INC.
 Engineer:            JACOBS (AKA - C-B)
 Contract Amount:     $484,513.75                                      Completion Date:                      06/30/2012
 Letting Date:        09/15/2011                                       Final Est Sub:

 28553(04)     Contract: 110311      US-270 Residency:             03300        0.850 MI. US-270:INTERSEC- TION
                                                                                MODIFICATION:FROM 4.5 MI.EAST OF
 SEC117-167B(189)SG                          WEWOKA
                                                                                THE SH-99 JUNCTION, EXTEND
 Contractor:          THE CUMMINS CONSTRUCTION CO., INC.                        EAST.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $997,641.45                                               Completion Date:             01/06/2012
 Letting Date:        06/16/2011                                                Final Est Sub:

 12313(04)     Contract: 110448      US-270B Residency:            03300        .159 MI. US-270B OVER UNNAMED
                                                                                CREEK, .6 MI. W OF SH-56 JCT.
 BRFY-067C(245)                              WEWOKA
 Contractor:          C-GAWF CONSTRUCTION, INC.
 Engineer:            Moore, Archie (Act.)
 Contract Amount:     $1,172,111.19                                             Completion Date:             08/07/2012
 Letting Date:        09/15/2011                                                Final Est Sub:


                                             Construction Status Report                                 Page 39
County:          Sequoyah                                    Commissioner District:                                1
 Contracts Completed - Final Estimate Not Processed


 22524(04)     Contract: 100539     CORD        Residency:   01003            0.340 MI. CO.RD.;BRIDGE/
                                                                              APPROACHES:OVER LITTLE
 CIRB-168D(147)RB                               COBB ENGINEERING CO., INC.
                                                                              SALLISAW CR., 0.20 MI.      S. OF
 Contractor:          OBC, INC.                                               THE IS-40 JCT.
 Engineer:            COBB
 Contract Amount:     $945,558.03                                             Completion Date:               05/10/2012
 Letting Date:        11/18/2010                                              Final Est Sub:

 28028(04)     Contract: 110174     I-40      Residency:          01200       7.67 MI. IS-40:RESURFACE
                                                                              (ASPHALT)FROM DWIGHT MISSION
 IMY-0040-6(372)303                           SALLISAW
                                                                              RD., EXTEND E. IN SALLISAW.
 Contractor:          JOB CONSTRUCTION CO., INC.
 Engineer:            Edwards, Carl
 Contract Amount:     $2,562,619.50                                           Completion Date:               03/19/2012
 Letting Date:        02/17/2011                                              Final Est Sub:

 28099(04)     Contract: 110345     I-40     Residency:           01200       3.0 MI. I-40 FROM MM 322, EXTEND
                                                                              EAST TO MM 325.
 IMG-0040-6(371)322TR                        SALLISAW
 Contractor:          MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:            Edwards, Carl
 Contract Amount:     $480,212.30                                             Completion Date:               06/06/2012
 Letting Date:        09/15/2011                                              Final Est Sub:

 26270(04)     Contract: 090163     IS-40      Residency:         01200       9.131 MI. IS-40;SAFETY IMPR.
                                                                              (CABLE BARRIER)FROM THE US-59
 HSIPIG-0040-6(359)299TR                       SALLISAW
                                                                              JUNCTION IN THE CITY OF
 Contractor:          ACTION SAFETY SUPPLY CO.                                SALLISAW,EXTEND WEST.
 Engineer:            Edwards, Carl
 Contract Amount:     $1,383,157.00                                           Completion Date:               08/19/2011
 Letting Date:        10/21/2010                                              Final Est Sub:

 27993(04)     Contract: 110449     SH-10   Residency:      01200             0.00 MI. SH-10 OVER THE ILLINOIS
                                                                              RIVER AND DEEP BRANCH CREEK1.9
 SBR-168C(210)SB                             SALLISAW
                                                                              AND 2.2 MI. EAST OF MUSKOGEE CO.
 Contractor:          WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES           LINE.
 Engineer:            Edwards, Carl
 Contract Amount:     $2,489,577.54                                           Completion Date:               04/18/2012
 Letting Date:        09/15/2011                                              Final Est Sub:

 12309(04)     Contract: 100451     SH-101   Residency:      01200         0.643 MI. SH-101;BRIDGE &
                                                                           APPROACHES/OVER BIG LEE CR. &
 SSP-068C(235)SS                              SALLISAW
                                                                           MISSION BR. CR.,0.5 MI. W. OF THE
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) SHORT.
                                                                           TOWN OF
 Engineer:            Edwards, Carl
 Contract Amount:     $2,898,689.84                                        Completion Date:             06/15/2012
 Letting Date:        07/22/2010                                           Final Est Sub:

 08900(04)     Contract: 090473     SH-82     Residency:          01200       *(127)/ 2.75 MI. SH-82;GRADE
                                                                              ,DRAIN,SURFACE & BRIDGE;BEGIN
 BRFY-68C(229)/STPY-168C*                     SALLISAW
                                                                              7.1 MI. NORTH OF THE US-64/ SH-82
 Contractor:          GLOVER & ASSOCIATES, INC.                               JCT, EXTEND NORTH.
 Engineer:            Edwards, Carl
 Contract Amount:     $5,082,984.23                                           Completion Date:               03/07/2012
 Letting Date:        09/17/2009                                              Final Est Sub:

 16952(04)     Contract: 050224     US-59   Residency:            01200       1.70 MI. GRADE, DRAIN & SURFACE
                                                                              US-59 FROM THE ARKANSAS RVR.
 ACSTPY-168A(023)GB                          SALLISAW
                                                                              EXTEND N. TO THE SH-141 JCT. IN
 Contractor:          GLOVER CONSTRUCTION CO., INC.                           SEQUOYAH CO.
 Engineer:            Edwards, Carl
 Contract Amount:     $5,289,626.58                                           Completion Date:               07/11/2008
 Letting Date:        08/18/2005                                              Final Est Sub:


                                            Construction Status Report                                   Page 40
 17670(05)     Contract: 080139     US-59   Residency:             01200   2.968 MI. SURFACE US-59 BEGIN 2.7
                                                                           MI. S. OF I-40 & EXTEND S.
 NHY-033N(012)                               SALLISAW
 Contractor:          DUIT CONSTRUCTION COMPANY, INC.
 Engineer:            Edwards, Carl
 Contract Amount:     $7,688,456.48                                        Completion Date:                02/12/2010
 Letting Date:        03/20/2008                                           Final Est Sub:

 28292(04)     Contract: 110167     US-59     Residency:           01200   *168C(217)3P / 8.28 MI. US
                                                                           -59:RESURFACE(ASPHALT)FROM
 STPY-168A(216)3P/STPY-*                      SALLISAW
                                                                           THESH-101 JCT,EXTEND N. SH-101
 Contractor:          JOB CONSTRUCTION CO., INC.                           FROM THE US-59 JCT,EXTEND E.
 Engineer:            Edwards, Carl
 Contract Amount:     $1,599,833.00                                        Completion Date:                10/06/2011
 Letting Date:        01/20/2011                                           Final Est Sub:




County:          Stephens                                     Commissioner District:                            7
 Contracts Completed - Final Estimate Not Processed


 25482(04)     Contract: 100363      CORD        Residency:        07100   0.431 MI. CO.RD.L BRIDGE &
                                                                           APPROACHES;OVER WILD HORSE
 CIRB-169C(152)RB                                DUNCAN
                                                                           CR., 1.5 MI. N. OF THE SH-7
 Contractor:          OBC, INC.                                            JUNCTION.
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $923,541.82                                          Completion Date:                07/19/2011
 Letting Date:        05/20/2010                                           Final Est Sub:

 22980(04)     Contract: 080371      CT.ST.    Residency:          07100   *SSP-169A(129)SS/ 1.20 MI.
                                                                           CT.ST.; GRADE,DRAIN,SURFACE
 STP-169B(117)UR*                              DUNCAN
                                                                           TRAFFIC SIGNALS;FROM THE
 Contractor:          T & G CONSTRUCTION, INC.                             DUNCAN BYPASS TO CHISHOLM TRAI
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $2,724,129.58                                        Completion Date:                12/14/2010
 Letting Date:        11/20/2008                                           Final Est Sub:

 23125(08)     Contract: 110252   IS-35      Residency:            07200   0.00 MI. IS-35:BRIDGE WATER
                                                                           PROOF SEAL:IS-44/US-70/US-81/
 BRFY-169C(189)                               ARDMORE
                                                                           SH-19/BOIS D'ARC AVE. AT
 Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.                MULTIPLE LOC. IN DIV. VII.
 Engineer:            Earp, Jay
 Contract Amount:     $98,607.85                                           Completion Date:                11/15/2011
 Letting Date:        04/14/2011                                           Final Est Sub:                  08/15/2012

 26332(04)     Contract: 110175      SH-7        Residency:        07100   0.00 MI. SH-7:BRIDGE REHAB.
                                                                           OVER LITTLE BEAVER CR., 5.45 MI.
 SBR-169N(159)SB                                 DUNCAN
                                                                           E. OF THE COMANCHE C/L.
 Contractor:          K & R BUILDERS, INC.
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $870,509.04                                          Completion Date:                11/03/2011
 Letting Date:        02/17/2011                                           Final Est Sub:

 20952(04)     Contract: 110327    US-70       Residency:     07001        0.00 MI. US-70/US-281/SH-7
                                                                           SH-76:BRIDGE PAINTING AT
 BRFY-NBIP(439)                                ENGR. SERV. & TESTING
                                                                           VARIOUS LOCATIONS IN DIV.    VII.
 Contractor:          K.V.K. CONTRACTING, INC.
 Engineer:            EST
 Contract Amount:     $396,990.00                                          Completion Date:                03/15/2012
 Letting Date:        06/16/2011                                           Final Est Sub:                  08/15/2012

 20316(18)     Contract: 090317      US-81       Residency:        07100   0.441 MI. GRADE, DRAIN, SURFACE &
                                                                           BRIDGE US-81 BYPASS AT AT BOIS
 NH-STIM(039)                                    DUNCAN
                                                                           D'ARC AVE. 1.5 MI. W. OF US-81.
 Contractor:          OBC, INC.
 Engineer:            Harwell, Jerry M.
 Contract Amount:     $5,504,958.27                                        Completion Date:                06/15/2011
 Letting Date:        03/19/2009                                           Final Est Sub:


                                             Construction Status Report                            Page 41
County:          Texas                                        Commissioner District:                           6
 Contracts Completed - Final Estimate Not Processed


 20312(07)     Contract: 090470      US-54     Residency:          06200   3.427 MI. GRADE, DRAIN, SURFACE &
                                                                           BRIDGE US-54 FROM 0.1 MI. N. OF
 NHY-008N(057)HP                               GUYMON
                                                                           US-64 & EXTEND NORTH.
 Contractor:          J & R SAND COMPANY, INC.
 Engineer:            Michael, Charles
 Contract Amount:     $6,298,630.23                                        Completion Date:               11/18/2010
 Letting Date:        10/15/2009                                           Final Est Sub:                 08/06/2012




County:          Tulsa                                        Commissioner District:                           8
 Contracts Completed - Final Estimate Not Processed


 26701(04)     Contract: 090648     CT. ST.   Residency:   08003           1.126 MI. PAVEMENT
                                                                           REHABILITATION CITY ST. (YALE
 STP-STIM(282)IG                              COBB ENGINEERING CO., INC.
                                                                           AVE.) FROM FROM ADMIRAL PL. TO
 Contractor:          BECCO CONTRACTORS, INC.                              PINE ST. IN THE CITY OF TULSA.
 Engineer:            COBB
 Contract Amount:     $2,121,387.22                                        Completion Date:               02/28/2011
 Letting Date:        11/19/2009                                           Final Est Sub:                 04/05/2012

 26703(04)     Contract: 090644     CT. ST.   Residency:     08001         2.926 MI. PAVEMENT
                                                                           REHABILITATION CITY ST.
 STP-STIM(284)(286)(482)IG                    ENGR. SERV. & TESTING
                                                                           (SHERICAN RD.) FROM ADMIRAL
 Contractor:          BECCO CONTRACTORS, INC.                              BLVD. EXTEND SOUTH.
 Engineer:            EST
 Contract Amount:     $4,374,893.50                                        Completion Date:               10/24/2011
 Letting Date:        11/19/2009                                           Final Est Sub:

 18429(06)     Contract: 090024     CT.ST.    Residency:           08100   STPG-172B(444)(446)IG/0.794 M I
                                                                           GRD, DRN, SURF & TRAFFIC SIG
 STP-172B(443)(445)IG*                        TULSA
                                                                           ELM ST/121 ST/MAIN ST/NOGALES
 Contractor:          BECCO CONTRACTORS, INC.                              AVE IN THE CITY OF JENKS.
 Engineer:            Arnold, Bruce
 Contract Amount:     $2,126,549.74                                        Completion Date:               02/25/2010
 Letting Date:        01/22/2009                                           Final Est Sub:                 10/27/2011

 26684(04)     Contract: 090647     CT.ST.       Residency:        08002   1.6820 MI. CT.ST.;(ELM PLACE
                                                                           )RESURFACE (ASPHALT)CT.STS.
 STP-STIM(264)(265)(268)IG                       TETRA TECH
                                                                           9TH/NEW ORLEANS/FLORENCE/
 Contractor:          APAC-CENTRAL, INC.                                   HOUSTON) IN BROKEN ARROW.
 Engineer:            TETR
 Contract Amount:     $1,245,715.28                                        Completion Date:               11/30/2010
 Letting Date:        11/19/2009                                           Final Est Sub:                 07/26/2012

 19690(04)     Contract: 080048     CT.ST.  Residency:             08100   2.087 MI. GRADE, DRAIN & SURFACE
                                                                           GILCREASE EXPRESSWAY L.L.
 STP-172A(210)IG                             TULSA
                                                                           TISDALE PARKWAY TO NORTH LEWIS
 Contractor:          DUIT CONSTRUCTION COMPANY, INC.                      AVENUE.
 Engineer:            Arnold, Bruce
 Contract Amount:     $9,087,350.95                                        Completion Date:               01/09/2009
 Letting Date:        01/17/2008                                           Final Est Sub:

 17310(04)     Contract: 090385     CT.ST.  Residency:             08002   0.85 MI. CT.ST.;GRADE,DRAIN, &
                                                                           SURFACE;BEG. AT MAIN & DATE ST.
 STP-172B(074)IG                             TETRA TECH
                                                                           JCT,EXT. E. THEN N. ON CEDAR ST.
 Contractor:          PARAGON CONTRACTORS, LLC                             TO 'A" ST.
 Engineer:            TETR
 Contract Amount:     $2,991,711.11                                        Completion Date:               10/03/2011
 Letting Date:        05/14/2009                                           Final Est Sub:



                                             Construction Status Report                            Page 42
22148(04)     Contract: 100567     CTST    Residency:            08002    0.094 MI. CT.ST.;GRADE,DRAIN,
                                                                          SURFACE & BRIDGE/(96TH ST.)
STP-172B(276)IG                             TETRA TECH
                                                                          FROM ADAMS ST.,EXTEND E. IN THE
Contractor:          PARAGON CONTRACTORS, LLC                             CITY OF JENKS.
Engineer:            TETR
Contract Amount:     $1,202,202.00                                        Completion Date:              01/11/2012
Letting Date:        10/21/2010                                           Final Est Sub:

27430(04)     Contract: 100407   CTST          Residency:        08011    0.307 MI. CT.ST.;INTERSEC- TION
                                                                          MODIFICATION & TRAFFIC
STP-STIM(518)IG                                GARVER, LLC.
                                                                          SIGNALS(GARNETT RD.);AT THE
Contractor:          APAC-CENTRAL, INC.                                   INTERSECTION OF ADMIRAL PL. IN
Engineer:            GARV
Contract Amount:     $566,985.91                                          Completion Date:              03/09/2012
Letting Date:        06/17/2010                                           Final Est Sub:                08/20/2012

27381(04)     Contract: 100196   CTST          Residency:        08002    0.898 MI. CT.ST.;RESURFACE
                                                                          (ASPHALT)(HOUSTON ST.)FROM S.
STP-STIM(505)IG                                TETRA TECH
                                                                          ASPEN AVE, EXTEND EAST IN  THE
Contractor:          APAC-CENTRAL, INC.                                   CITY OF BROKEN ARROW.
Engineer:            TETR
Contract Amount:     $448,562.09                                          Completion Date:              04/06/2011
Letting Date:        03/18/2010                                           Final Est Sub:

27403(04)     Contract: 100405     CTST   Residency:   08003              1.00 MI. CT.ST.;PAVEMENT RE- HAB.
                                                                          (ASPHALT)(LEWIS AVE.)FROM 21ST
STP-STIM(514)IG                           COBB ENGINEERING CO., INC.
                                                                          ST.,EXTEND S. TO 31ST ST. IN
Contractor:          SHERWOOD CONSTRUCTION CO., INC.                      TULSA.
Engineer:            COBB
Contract Amount:     $2,066,653.10                                        Completion Date:              06/27/2012
Letting Date:        06/17/2010                                           Final Est Sub:

27387(04)     Contract: 100403     CTST      Residency:     08001         0.907 MI. CT.ST.(61ST ST.)
                                                                          PAVEMENT REHAB.(P.C.
STP-STIM(510)IG                              ENGR. SERV. & TESTING
                                                                          CONCRETE)FROM YALE AVE,EXTEND
Contractor:          KEYSTONE SERVICES, INC.                              E. TO SHERIDA RD. IN TULSA.
Engineer:            EST
Contract Amount:     $1,227,009.89                                        Completion Date:              12/23/2011
Letting Date:        06/17/2010                                           Final Est Sub:

26683(04)     Contract: 100310     CTST      Residency:   08003           0.40 MI. CT.ST.;GRADE,DRAIN , &
                                                                          SURFACE (E. 131ST ST.)BE- GIN 0.15
STP-STIM(263)IG                              COBB ENGINEERING CO., INC.
                                                                          MI. W. OF MEMORIAL DR., EXTEND
Contractor:          BECCO CONTRACTORS, INC.                              EAST.
Engineer:            COBB
Contract Amount:     $1,070,372.65                                        Completion Date:              05/27/2011
Letting Date:        04/15/2010                                           Final Est Sub:

27388(04)     Contract: 100404   CTST        Residency:   08003           0.1500 MI. CT.ST.PAVEMENT
                                                                          REHAB.(P.C. CONCRETE)(RIVER-
STP-STIM(511)IG                              COBB ENGINEERING CO., INC.
                                                                          SIDE DR.)FROM 68TH ST.,EX- TEND
Contractor:          KEYSTONE SERVICES, INC.                              S. TO 71ST. ST. IN TULSA.
Engineer:            COBB
Contract Amount:     $373,341.05                                          Completion Date:              07/15/2011
Letting Date:        06/17/2010                                           Final Est Sub:

24583(04)     Contract: 080443     I-244       Residency:        08100    0.027 MI. BRIDGE REHABILITATION
                                                                          I-244 ENTRANCE RAMP OVER 1ST
BHIY-0244-2(472) 096                           TULSA
                                                                          STREET.
Contractor:          PBX CORPORATION
Engineer:            Arnold, Bruce
Contract Amount:     $807,534.75                                          Completion Date:              12/21/2009
Letting Date:        09/18/2008                                           Final Est Sub:                04/08/2011

06374(68)     Contract: 080454      I-44   Residency:            08100    1.309 MI GRADE, DRAIN, SURFACE,
                                                                          BRIDGE & UTILITIES I-44 N.
IMY-0044-2(473)225 NI                      TULSA
                                                                          FRONTAGE RD. FROM THE ARKANSAS
Contractor:           SHERWOOD CONSTRUCTION CO., INC.                     RVR. EXT. E. (PERRYMAN DITCH)
Engineer:             Arnold, Bruce
Contract Amount:      $42,395,254.70                                      Completion Date:              10/26/2010
Letting Date:         10/16/2008                                          Final Est Sub:

                                           Construction Status Report                             Page 43
06374(50)     Contract: 090586     I-44   Residency:            08100   1.532 MI. GRADE, DRAIN, SURFACE &
                                                                        BRIDGE I-44 BEGIN AT EAST 51ST
IMY-0044-2(402)227                        TULSA
                                                                        STREET & EXTEND EAST.
Contractor:          SHERWOOD CONSTRUCTION CO., INC.
Engineer:            Arnold, Bruce
Contract Amount:     $47,963,887.85                                     Completion Date:               06/17/2012
Letting Date:        10/15/2009                                         Final Est Sub:

06374(08)     Contract: 090604     I-44   Residency:            08100   0.606 MI. GRADE, DRAIN, SURFACE
                                                                        AND BRIDGE I-44 FROM DARLINGTON
IM-NHIY-0044-2(371)229                    TULSA
                                                                        AVENUE EXTEND NORTHEAST IN THE
Contractor:          SHERWOOD CONSTRUCTION CO., INC.                    CITY OF TULSA.
Engineer:            Arnold, Bruce
Contract Amount:     $10,981,091.55                                     Completion Date:               06/30/2011
Letting Date:        09/17/2009                                         Final Est Sub:

26304(05)     Contract: 100543     IS-244  Residency:           08100   0.170 MI.IS-244 BRIDGE REHAB. AT
                                                                        THE EXIT RAMP TO 1ST ST. INTHE
BHIY-0244-2(484)005                         TULSA
                                                                        CITY OF TULSA.
Contractor:          MANHATTAN ROAD & BRIDGE COMPANY
Engineer:            Arnold, Bruce
Contract Amount:     $1,141,465.31                                      Completion Date:               04/23/2012
Letting Date:        10/21/2010                                         Final Est Sub:

06374(82)     Contract: 100541     IS-44  Residency:            08100   0.454 MI. IS-44;GRADE,DRAIN
                                                                        ,SURFACE SIGNAL,SIGNING &
IM-NHIY-0044-2(494)229                    TULSA
                                                                        LIGH-TING.;FROM 41ST ST., EXTEND
Contractor:          SHERWOOD CONSTRUCTION CO., INC.                    NORTHEAST IN THE CITY OF TULSA
Engineer:            Arnold, Bruce
Contract Amount:     $11,762,121.05                                     Completion Date:               04/30/2012
Letting Date:        10/21/2010                                         Final Est Sub:

24959(04)     Contract: 110149     SH-11     Residency:         08100   0.00 MI. SH-11:BRIDGE REHAB.
                                                                        OVER EDISON RD. AT IS-244 JCT,IN
SBR-172A(390)SB                              TULSA
                                                                        TULSA.
Contractor:          KEYSTONE SERVICES, INC.
Engineer:            Arnold, Bruce
Contract Amount:     $423,422.00                                        Completion Date:               04/13/2012
Letting Date:        02/17/2011                                         Final Est Sub:

11143(07)     Contract: 100612     SH-51     Residency:   08400         5.95 MI. SH-51;PAVEMENT RE- HAB.
                                                                        (ASPHALT)/FROM 0.6 MI. E. OF THE
STPY-172C(509)                               SAND SPRINGS
                                                                        CREEK C/L, EXTEND    EAST.
Contractor:          BECCO CONTRACTORS, INC.
Engineer:            Williams, Mark J.
Contract Amount:     $7,979,606.92                                      Completion Date:               06/06/2012
Letting Date:        11/18/2010                                         Final Est Sub:

24110(04)     Contract: 080066     US-169     Residency:        08100   0.00 MI. US-169;SAFETY IM-
                                                                        PROVEMENT(CABLE BARRIER PRO-
NHG-030N(059)TR                               TULSA
                                                                        JECT) BEGIN AT E. 36TH ST.
Contractor:          ACTION SAFETY SUPPLY CO.                           EXTEND NO. TO BIRD CR. OVERFLO
Engineer:            Arnold, Bruce
Contract Amount:     $673,832.59                                        Completion Date:               03/12/2009
Letting Date:        02/21/2008                                         Final Est Sub:

20930(04)     Contract: 090646     US-169    Residency:         08100   5.055 MI. US-169; WIDEN,RE-
                                                                        SURFACE (ASPHALT), & BRIDGE.
SAP-30N(43)/SSP-30N(61)SS                    TULSA
                                                                        BEGIN @ IS-244 AND EXTEND
Contractor:          BECCO CONTRACTORS, INC.                            NORTH.
Engineer:            Arnold, Bruce
Contract Amount:     $16,358,949.00                                     Completion Date:               04/17/2012
Letting Date:        10/15/2009                                         Final Est Sub:

28593(04)     Contract: 110454   US-75     Residency:      08001        0.00 MI. US-75/I-244/US-64/UNION
                                                                        AVE. AT VARIOUS LOCATIONS IN
BRFY-NBIP(447)3B                            ENGR. SERV. & TESTING
                                                                        DIVISION 8
Contractor:          POSEIDON CONSTRUCTION, INC.
Engineer:            EST
Contract Amount:     $562,805.00                                        Completion Date:               05/10/2012
Letting Date:        09/15/2011                                         Final Est Sub:

                                          Construction Status Report                            Page 44
 27634(04)     Contract: 110319     US-75       Residency:        08400       0.00 MI. US-75: BRIDGE RE-
                                                                              HABILITATION:OVER NICKLE CR. 1.9
 SBR-172N(517)SB                                SAND SPRINGS
                                                                              MI. N. OF SH-117 IN    THE CITY OF
 Contractor:          PBX CORPORATION                                         JENKS.
 Engineer:            Williams, Mark J.
 Contract Amount:     $531,675.75                                            Completion Date:                03/05/2012
 Letting Date:        05/19/2011                                             Final Est Sub:




County:         Wagoner                                      Commissioner District:                                1
 Contracts Completed - Final Estimate Not Processed


 21259(04)     Contract: 100454   CORD       Residency:      01002         0.179 MI. CO.RD.;BRIDGE &
                                                                           APPROACHES:OVER SALT CR. TRI-
 BRF-173C(093)CO                              TETRA TECH
                                                                           BUTARY, 2.6 MI. S. OF THE
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)C/L.
                                                                           ROGERS
 Engineer:            TETR
 Contract Amount:     $244,332.27                                          Completion Date:            03/09/2012
 Letting Date:        07/22/2010                                           Final Est Sub:

 22156(04)     Contract: 100455    CORD         Residency:        01002       0.227 MI. CO.RD./BRIDGE &
                                                                              APPROACHES:OVER SPUNKY
 CIRB-173D(101)RB                               TETRA TECH
                                                                              CR.,1.0MI. EAST OF THE TULSA
 Contractor:          BELK BRIDGE, INC.                                       C/L.
 Engineer:            TETR
 Contract Amount:     $855,704.43                                            Completion Date:                06/28/2012
 Letting Date:        08/18/2011                                             Final Est Sub:

 20290(04)     Contract: 090407     I-44      Residency:          08300       0.722 MI. GRADE, DRAIN, SURFACE,
                                                                              SIGNS, LIGHTING, SIGNAL & BRIDGE
 IM-NHIY-0044-2(419)239HP                     CLAREMORE
                                                                              I-44 AT 193RD E. AVE. (SH-167) IN
 Contractor:          BECCO CONTRACTORS, INC.                                 THE CITY OF TULSA.
 Engineer:            Bray, Timothy
 Contract Amount:     $44,332,597.95                                         Completion Date:                12/13/2011
 Letting Date:        04/21/2009                                             Final Est Sub:

 19983(12)     Contract: 090669     SH-412P    Residency:         08300       0.00 MI. SH-412P: RIGHT-OF -WAY
                                                                              CLEARANCE:BEGIN WEST OF 305TH
 STPY-166A(245)RW                              CLAREMORE
                                                                              E. AVE., EXTEND EAST.
 Contractor:          D T SPECIALIZED SERVICES, INC.
 Engineer:            Bray, Timothy
 Contract Amount:     $72,777.00                                             Completion Date:                11/09/2010
 Letting Date:        12/17/2009                                             Final Est Sub:

 10004(12)     Contract: 100017      SH-51    Residency:          01100       0.492 MI. SH-51;BRIDGE &
                                                                              APPROACHES:OVER BILLY CR.,
 BRFY-173B(021)                               MUSKOGEE
                                                                              11.9 MI. EAST OF THE SH-  72 JCT.
 Contractor:          BECCO CONTRACTORS, INC.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $1,777,579.70                                          Completion Date:                08/24/2011
 Letting Date:        01/28/2010                                             Final Est Sub:

 10004(10)     Contract: 090541      SH-51  Residency:            01100       2.040 MI. SH-51;BRIDGE &
                                                                              APPROACHES: OVER THE
 STPY-173B(019)                              MUSKOGEE
                                                                              VERDIGRISRIVER, 7.5 MI. EAST OF
 Contractor:          JENSEN CONSTRUCTION COMPANY                             COWETA.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $8,762,873.67                                          Completion Date:                06/21/2011
 Letting Date:        10/15/2009                                             Final Est Sub:

 20914(04)     Contract: 080223      SH-72    Residency:          01100       0.155 MI. GRADE, DRAIN, SURFACE,
                                                                              BRIDGE & RAILROAD SH-72 OVER
 BRFY-173B(083)                               MUSKOGEE
                                                                              UNNAMED CRK. @ JCT. SH-51 IN
 Contractor:          M.J. LEE CONSTRUCTION COMPANY                           COWETA.
 Engineer:            Ivy, Steve (Act.)
 Contract Amount:     $7,973,218.60                                          Completion Date:                07/22/2010
 Letting Date:        09/18/2008                                             Final Est Sub:


                                            Construction Status Report                                Page 45
 24757(04)     Contract: 100261   SH-72     Residency:     01011            0.00 MI. SH-72;BRIDGE REHAB
                                                                            -ILITATION;OVER CONCHARTY
 STPY-173C(138)                              GARVER, LLC.
                                                                            CR.,1.8 MI. N. OF THE MUSKOGEE
 Contractor:          PARADIGM CONSTRUCTION & ENGINEERING, INC              C/L.
 Engineer:            GARV
 Contract Amount:     $588,506.34                                           Completion Date:                11/23/2011
 Letting Date:        07/22/2010                                            Final Est Sub:




County:         Washita                                     Commissioner District:                               5
 Contracts Completed - Final Estimate Not Processed


 17126(08)     Contract: 060288    US-183  Residency:            05100      2.867 MI. GRADE, DRAIN, SURFACE &
                                                                            BRIDGE US-183 BEGIN S. OF SH-152
 ACNHY-009N(082)GB                          CLINTON
                                                                            & EXTEND NORTH.
 Contractor:          DOBSON BROTHERS CONSTRUCTION CO.
 Engineer:            Greer, Randy
 Contract Amount:     $11,893,891.64                                        Completion Date:                06/11/2009
 Letting Date:        03/15/2007                                            Final Est Sub:                  03/07/2012




County:         Woods                                       Commissioner District:                               6
 Contracts Completed - Final Estimate Not Processed


 24113(04)     Contract: 100462     SH-50    Residency:      06100         0.190 MI. SH-50;BRIDGE &
                                                                           APPROACHES;OVER HOUSTON CR.,
 BRFY-176C(117)                               BUFFALO
                                                                           0.10 MI. S. OF THE US-64
 Contractor:          PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                           JUNCTION.
 Engineer:            Burke, David
 Contract Amount:     $1,304,200.77                                        Completion Date:          06/29/2012
 Letting Date:        07/22/2010                                           Final Est Sub:

 27433(04)     Contract: 110157    SH-50    Residency:           06100      0.00 MI. SH-50:BRIDGE REHAB.
                                                                            OVER THE CIMARRON RIVER, AT
 SBR-176C(174)SB                             BUFFALO
                                                                            WOODWARD C/L.
 Contractor:          LOGOS CONSTRUCTION CO., LLC
 Engineer:            Burke, David
 Contract Amount:     $327,802.00                                           Completion Date:                07/31/2012
 Letting Date:        02/17/2011                                            Final Est Sub:

 24634(04)     Contract: 100410    US-64    Residency:           06100      *(181)/1.800 MI. US-64/PAVE -MENT
                                                                            REHAB.(P.C. CONCRETE) FROM
 SSR-176A(140)/MC-176A*                     BUFFALO
                                                                            14TH ST.,EXTEND E. IN ALVA,FROM
 Contractor:          WITTWER CONSTRUCTION CO., INC.                        7TH ST. IN ALVA.
 Engineer:            Burke, David
 Contract Amount:     $664,008.00                                           Completion Date:                01/06/2012
 Letting Date:        06/17/2010                                            Final Est Sub:                  08/10/2012




County:         Woodward                                    Commissioner District:                               6
 Contracts Completed - Final Estimate Not Processed


 22895(04)     Contract: 110020     CORD       Residency:    06009          0.150 MI. CO.RD.:BRIDGE &
                                                                            APPROACHES:OVER HACKBERRY
 BRF-177C(072)CI                               CIRCUIT ENGR. DISTR. # 8
                                                                            CR.,4.4 MI. EAST OF THE SH-34
 Contractor:          OBC, INC.                                             JUNCTION.
 Engineer:            CED8
 Contract Amount:     $510,647.50                                           Completion Date:                08/24/2012
 Letting Date:        01/20/2011                                            Final Est Sub:




                                           Construction Status Report                               Page 46
20937(05)     Contract: 110184    SH-50     Residency:          06100   0.00 MI. SH-50 OVER SAND CREEK, .8
                                                                        MI. N OF US-183 AND OVER
BRFY-177C(120)                               BUFFALO
                                                                        CANADIAN RIVER OVERFLOW, 5.3 MI.
Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.              N OF US-183.
Engineer:            Burke, David
Contract Amount:     $51,266.00                                         Completion Date:               05/24/2012
Letting Date:        09/15/2011                                         Final Est Sub:

28591(04)     Contract: 110458   SH8         Residency:     06001       0.00 MI. SH-8/SH-34: BRIDGE
                                                                        PAINTING VARIOUS LOCATION IN
BRFY-NBIP(445)3B                             ENGR. SERV. & TESTING
                                                                        DIV6.
Contractor:          TARPON INDUSTRIAL, INC.
Engineer:            EST
Contract Amount:     $249,450.00                                        Completion Date:               05/01/2012
Letting Date:        10/20/2011                                         Final Est Sub:

27577(04)     Contract: 120113    US-183   Residency:           06100   5.400 MI. US-183;RESURFACE
                                                                        (UTWBC)FROM 8.3 MI. NORTH OF
NHY-017N(237)3P                             BUFFALO
                                                                        SH-15, EXTEND NORTH.
Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
Engineer:            Burke, David
Contract Amount:     $890,525.22                                        Completion Date:               07/16/2012
Letting Date:        02/16/2012                                         Final Est Sub:

17457(10)     Contract: 050646     US-183 Residency:            06100   4.536 MI. SURFACING US-270/183
                                                                        BEG. APPROX. 0.8 MI. S.E. OF SH-50
NHY-017N (053)                             BUFFALO
                                                                        EXTEND N.W.
Contractor:          DOBSON BROTHERS CONSTRUCTION CO.
Engineer:            Burke, David
Contract Amount:     $8,557,233.95                                      Completion Date:               12/12/2008
Letting Date:        01/19/2006                                         Final Est Sub:

27509(04)     Contract: 110159    US-183   Residency:           06100   3.71 MI. US-183;RESURFACE
                                                                        (ASPHALT)FROM THE SH-34 SOUTH
NHY-017N(240)3P                             BUFFALO
                                                                        JUNCTION, EXTEND NORTH.
Contractor:          THE CUMMINS CONSTRUCTION CO., INC.
Engineer:            Burke, David
Contract Amount:     $697,824.00                                        Completion Date:               09/20/2011
Letting Date:        01/20/2011                                         Final Est Sub:




                                          Construction Status Report                             Page 47
County:          Adair                                        Commissioner District:                                  1
Contracts Under Construction


 29283(04)     Contract: 120187     US-59    Residency:     01200        0.00 MI. US-59/US-64/US-69: STRIPING
 HSIPG-268F(001)TR                           SALLISAW                    & PAVEMENT MARKING. VARIOUS
                                                                         LOCATIONS IN DIV. 1.
 Contractor:   DIRECT TRAFFIC CONTROL INC.
 Engineer:     Edwards, Carl                Adjusted:
 Contract Amount:       $774,999.80        (        $774,999.80)
 Contract Time:         90                 (   90   )
 Letting Date:          05/17/2012
 Contract Date:         06/15/2012
 W/O Issued:            06/20/2012                                                               Adjusted:
 W/O Effective:         09/18/2012                                Amount Paid:              0 %(          0 %)
 Work Started:          08/28/2012                                Time Passed:              0 %(          0 %)


 25640(04)     Contract: 110476     CORD   Residency:     01200        0.237 MI. CO.RD. BRIDGE &
 BRF-101C(081)CI                           SALLISAW                    APPROACHES;OVER ROCK BR. CR. 6.0
                                                                       MI. E. OF SH-10 & 1.2  MI. S. OF THE
 Contractor:   PARADIGM CONSTRUCTION & ENGINEERING, INC                DELAWARE CL.
 Engineer:     Edwards, Carl              Adjusted:
 Contract Amount:       $453,606.00      (        $453,606.00)
 Contract Time:         90               (  157 )
 Letting Date:          11/17/2011
 Contract Date:         12/15/2011
 W/O Issued:            12/20/2011                                                             Adjusted:
 W/O Effective:         03/05/2012                              Amount Paid:             93 % (         93 %)
 Work Started:          03/05/2012                              Time Passed:            171 % (         98 %)




County:          Alfalfa                                      Commissioner District:                                  6
Contracts Under Construction


 25910(04)     Contract: 110411     CORD       Residency:       06009           0.27 MI.CORD(EW-030)BRIDGE &
 BRO-102D(136)CI                               CIRCUIT ENGR. DISTR. # 8         APPROACHES;OVER EAGLE CHIEF CREEK
                                                                                1.0 MI. N OF SH-45 AND 5.7 MI. W OF
 Contractor:   SEWELL BROS., INC.                                               SH-8,WEST OF CARMEN
 Engineer:     CED8                          Adjusted:
 Contract Amount:       $875,761.90         (        $875,761.90)
 Contract Time:         150                 (  156   )
 Letting Date:          10/20/2011
 Contract Date:         11/22/2011
 W/O Issued:            11/29/2011                                                                   Adjusted:
 W/O Effective:         02/06/2012                                        Amount Paid:          86 %(      86 %)
 Work Started:          01/23/2012                                        Time Passed:          93 % (     90 %)




                                             Construction Status Report                                   Page 48
 23272(04)     Contract: 110477     SH8        Residency:      06100           0.85 MI. SH-8 BRIDGE & APPROACHS
 BRFY-102C(093)                                BUFFALO                         OVER DRIFTWOOD CREEK 3.5 MINORTH
                                                                               OF US-64/SH-11
 Contractor:   SEWELL BROS., INC.
 Engineer:     Burke, David                  Adjusted:
 Contract Amount:       $3,737,877.60       (      $3,737,877.60)
 Contract Time:         200                 (  200 )
 Letting Date:          10/20/2011
 Contract Date:         11/22/2011
 W/O Issued:            11/29/2011                                                                  Adjusted:
 W/O Effective:         03/05/2012                                       Amount Paid:          45 % (     45 %)
 Work Started:          03/05/2012                                       Time Passed:          80 % (     80 %)


 24071(04)     Contract: 110051     US-64    Residency:     06100        1.18 MI. US-64:GRADE,DRAIN
 SSP-102C(112)SS                             BUFFALO                     ,SURFACE & BRIDGE,FROM 5.0 MI.E. OF
                                                                         WOODS C/L., EXTEND     EAST.
 Contractor:   VENTURE CORPORATION DBA V. C. O. PAVING
 Engineer:     Burke, David                Adjusted:
 Contract Amount:       $3,184,454.91     (       $3,275,837.60)
 Contract Time:         250               (   250 )
 Letting Date:          02/17/2011
 Contract Date:         03/22/2011
 W/O Issued:            04/14/2011                                                              Adjusted:
 W/O Effective:         07/05/2011                                Amount Paid:            98 % (        96 %)
 Work Started:          04/25/2011                                Time Passed:            96 % (        96 %)


 24062(04)     Contract: 120010     US-64      Residency:      06100           0.899 MI. US-64/SH-58 GRADE,
 SSP-102C(100)SS                               BUFFALO                         DRAIN,SURFACE & BRIDGE;FROM 0.5
                                                                               MI. W. OF SH-58,EXTEND EAST.FROM
 Contractor:   L & M CONTRACTORS, INC.                                         0.7 MI. SOUTH OF US-
 Engineer:     Burke, David                  Adjusted:
 Contract Amount:       $3,008,884.66       (      $3,008,884.66)
 Contract Time:         180                 (  180 )
 Letting Date:          02/16/2012
 Contract Date:         03/19/2012
 W/O Issued:            03/21/2012                                                                 Adjusted:
 W/O Effective:         07/02/2012                                       Amount Paid:          14 %(     14 %)
 Work Started:          07/02/2012                                       Time Passed:          25 %(     25 %)
 64

 23274(09)     Contract: 120179     US-60      Residency:      06100           0.00 MI./US-60/US-64/US-281 :BRIDGE
 SSP-202C(002)SS                               BUFFALO                         WATERPROOF SEAL.      VARIOUS
                                                                               LOCATIONS IN DIV. VI.
 Contractor:   GARY A. CRAIN, INC.
 Engineer:     Burke, David                  Adjusted:
 Contract Amount:       $106,422.75         (        $106,422.75)
 Contract Time:         30                  (   30   )
 Letting Date:          05/17/2012
 Contract Date:         06/19/2012
 W/O Issued:            06/21/2012                                                                 Adjusted:
 W/O Effective:         10/01/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                           Time Passed:           0 %(      0 %)




County:         Atoka                                        Commissioner District:                                  2
Contracts Under Construction




                                            Construction Status Report                                  Page 49
27370(04)     Contract: 120152     US-69   Residency:     02013        0.094 MI. US-69:BRIDGE &
ACBRF-103C(127)CI                          CIRCUIT ENGR. DISTRICT # 3 APPROACHES/OVER UNNAMED CREEK 1.0
                                                                       MI. WEST OF THE US-69    JUNCTION.
Contractor:   C-GAWF CONSTRUCTION, INC.
Engineer:     CED3                        Adjusted:
Contract Amount:       $434,146.30       (        $434,146.30)
Contract Time:         90                (   90   )
Letting Date:          04/19/2012
Contract Date:         05/22/2012
W/O Issued:            05/29/2012                                                              Adjusted:
W/O Effective:         08/06/2012                               Amount Paid:            18 % (         18 %)
Work Started:                                                   Time Passed:            11 % (         11 %)


28194(04)     Contract: 110505      US-69   Residency:     02100        0.207 MI. US-69/BRIDGE REHAB. :OVER
SBR-103N(137)SB                             ANTLERS                     N. BOOGY RIVER, 5.87 MI.N. OF THE
                                                                        SH-7 JCT.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     Moy, Ryan                    Adjusted:
Contract Amount:        $1,894,957.50     (      $1,901,657.10)
Contract Time:          150               (  150 )
Letting Date:           11/17/2011
Contract Date:          12/20/2011
W/O Issued:             12/29/2011                                                              Adjusted:
W/O Effective:          04/02/2012                               Amount Paid:            95 % (         95 %)
Work Started:           03/05/2012                               Time Passed:            91 % (         91 %)


29308(04)     Contract: 120245      US-69   Residency:     02100        0.00 MI. US-69;STRIPING &
HSIPG-203F(008)TR                           ANTLERS                     PAVEMENT
                                                                        MARKING/US-70/US-70B/US-271B:
Contractor:   DIRECT TRAFFIC CONTROL INC.                               MULTIPLE LOCATIONS IN DIV. II.
Engineer:     Moy, Ryan                    Adjusted:
Contract Amount:        $297,000.00       (        $297,000.00)
Contract Time:          45                (   45   )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                              Adjusted:
W/O Effective:          10/01/2012                               Amount Paid:              0 %(        0 %)
Work Started:                                                    Time Passed:              0 %(        0 %)


20306(04)     Contract: 090469     SH-3   Residency:      02100        5.07 MI. SH-3/GRADE,DRAIN, SURFACE
BRFY-103A(089)SS                          ANTLERS                      & BRIDGE.FROM THE    PUSHMATAHA
                                                                       C/L., EXTEND    WEST.
Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
Engineer:     Moy, Ryan                  Adjusted:
Contract Amount:        $12,723,126.56  (      $13,392,420.56)
Contract Time:          420             (   450 )
Letting Date:           08/18/2011
Contract Date:          09/20/2011
W/O Issued:             09/27/2011                                                            Adjusted:
W/O Effective:          01/02/2012                              Amount Paid:            25 %(        24 %)
Work Started:           01/16/2012                              Time Passed:            31 %(        29 %)




                                            Construction Status Report                            Page 50
 25859(04)     Contract: 120034     CORD   Residency:     02013        0.227 MI. CO. RD.;BRIDGE &
 BRO-103D(107)CI                           CIRCUIT ENGR. DISTRICT # 3 APPROACHES/OVER UNNAMED CR., 1.6
                                                                       MI. E. & O.3 MI. N. OF THE
 Contractor:   C-GAWF CONSTRUCTION, INC.                               US-69/SH-131 JCT.
 Engineer:     CED3                       Adjusted:
 Contract Amount:       $348,136.40      (        $348,136.40)
 Contract Time:         90               (   90   )
 Letting Date:          01/19/2012
 Contract Date:         02/24/2012
 W/O Issued:            03/01/2012                                                             Adjusted:
 W/O Effective:         05/07/2012                              Amount Paid:              88 % (     88 %)
 Work Started:          04/09/2012                              Time Passed:             104 % (    104 %)


 28128(45)     Contract: 120058      US-69     Residency:       02400           44.24 MI. US-69;SAFETY IM-
 BTOP-203N(001)                                MCALESTER                        PROVEMENTS(FIBER OPTIC CABLE) FROM
                                                                                THE CITY OF ATOKA TO    THE CITY OF
 Contractor:   B & H CONSTRUCTION, INC                                          MCALESTER.
 Engineer:     Plymate, Larry                 Adjusted:
 Contract Amount:        $2,887,691.00       (      $4,194,630.75)
 Contract Time:          125                 (  125 )
 Letting Date:           01/19/2012
 Contract Date:          02/13/2012
 W/O Issued:             02/29/2012                                                                 Adjusted:
 W/O Effective:          03/26/2012                                       Amount Paid:        126 % (     87 %)
 Work Started:           03/28/2012                                       Time Passed:        114 % (    114 %)


 28128(51)     Contract: 120069     US-75      Residency:       02011           45.12 MI. US-75;SAFETY IM-
 BTOP-203N(002)                                GARVER, LLC.                     PROVEMENTS(FIBER OPTIC CABLE)
                                                                                SH-3/SH-99;FROM THE CITY OF ADA TO
 Contractor:   ROHL NETWORKS, LP                                                THE CITY OF ATOKA.
 Engineer:     GARV                           Adjusted:
 Contract Amount:       $2,512,262.56        (      $2,695,297.56)
 Contract Time:         140                  (  145 )
 Letting Date:          01/19/2012
 Contract Date:         02/21/2012
 W/O Issued:            03/01/2012                                                                 Adjusted:
 W/O Effective:         03/26/2012                                        Amount Paid:        107 %(    100 %)
 Work Started:          03/29/2012                                        Time Passed:         92 %(     89 %)




County:          Beaver                                       Commissioner District:                                  6
Contracts Under Construction


 26980(04)     Contract: 120236      CORD      Residency:       06200           0.298 MI. CO. RD. BRIDGE &
 BRF-104C(068)CI                               GUYMON                           APPROACHES; OVER BEAVER RIVER 9.0
                                                                                MI. EAST & 11.9 MI. N. OF ELMWOOD.
 Contractor:   L & M CONTRACTORS, INC.
 Engineer:     Michael, Charles               Adjusted:
 Contract Amount:        $846,833.10         (        $846,833.10)
 Contract Time:          150                 (  150   )
 Letting Date:           05/17/2012
 Contract Date:          07/03/2012
 W/O Issued:             08/02/2012                                                                 Adjusted:
 W/O Effective:          09/04/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                            Time Passed:           0 %(      0 %)




                                             Construction Status Report                                  Page 51
 26981(04)     Contract: 110412      CORD   Residency:     06200        .26 MI.CORD(NS-133):BRIDGE &
 BRF-104C(069)CI                            GUYMON                      APPROACHES OVER SOUTH FORK OF
                                                                        CLEAR CREEK .9 MI. S OF SH-3, 6.0 MI.
 Contractor:   BEHNE CONSTRUCTION CO., INC.                             W OF ELMWOOD
 Engineer:     Michael, Charles            Adjusted:
 Contract Amount:        $521,501.00      (        $528,397.00)
 Contract Time:          120              (  120 )
 Letting Date:           10/20/2011
 Contract Date:          11/22/2011
 W/O Issued:             11/29/2011                                                             Adjusted:
 W/O Effective:          02/06/2012                              Amount Paid:            91 % (          90 %)
 Work Started:           01/03/2012                              Time Passed:          100 % (          100 %)


 27476(04)     Contract: 110031      SH-3      Residency:       06200           8.0 MI. SH-3:RESURFACE
 NHY-017N(234)3P                               GUYMON                           (ASPHALT)FROM 6.0 MI. W. OF THE
                                                                                TX/BEAVER C/L.,EXTEND    EAST.
 Contractor:   J & R SAND COMPANY, INC.
 Engineer:     Michael, Charles               Adjusted:
 Contract Amount:        $2,953,225.70       (      $3,113,972.77)
 Contract Time:          160                 (  327 )
 Letting Date:           02/17/2011
 Contract Date:          03/18/2011
 W/O Issued:             03/28/2011                                                                  Adjusted:
 W/O Effective:          06/06/2011                                       Amount Paid:         104 % (     99 %)
 Work Started:           06/06/2011                                       Time Passed:         206 % (    101 %)


 27576(04)     Contract: 120080      US-64     Residency:       06200           7.00 MI. US-64;RESURFACE
 STPY-104B(073)3P                              GUYMON                           (ASPHALT)FROM 5.0 MI. EAST OF US-83,
                                                                                EXTEND EAST.
 Contractor:   J & R SAND COMPANY, INC.
 Engineer:     Michael, Charles               Adjusted:
 Contract Amount:        $1,363,940.80       (      $1,370,408.80)
 Contract Time:          30                  (   30   )
 Letting Date:           02/16/2012
 Contract Date:          03/22/2012
 W/O Issued:             03/26/2012                                                                 Adjusted:
 W/O Effective:          06/04/2012                                       Amount Paid:          99 %(     99 %)
 Work Started:           05/14/2012                                       Time Passed:          73 %(     73 %)


 28534(04)     Contract: 110278      US-270   Residency:     06200        4.65 MI. US-270;RESURFACE
 SSR-104C(081)SR                              GUYMON                      (ASPHALT)FROM US-64, EXTEND SOUTH.

 Contractor:   J & R SAND COMPANY, INC.
 Engineer:     Michael, Charles              Adjusted:
 Contract Amount:        $581,138.00        (        $581,138.00)
 Contract Time:          30                 (   30   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/24/2012                                                              Adjusted:
 W/O Effective:          04/02/2012                                Amount Paid:            99 %(       99 %)
 Work Started:           03/27/2012                                Time Passed:           110 %(      110 %)




County:          Beckham                                      Commissioner District:                                   5
Contracts Under Construction




                                             Construction Status Report                                   Page 52
25822(04)     Contract: 110396      US-283   Residency:     05200        0.309 MI. US-283 BRIDGE &
BRFY-105B(169)                               ALTUS                       APPROACHES:OVER TIMBER CR., 0.50
                                                                         MI. SOUTH OF THE ROGER MILLS C/L.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     Nedbalek, Will                Adjusted:
Contract Amount:        $1,367,072.99      (      $1,371,350.99)
Contract Time:          180                (  224 )
Letting Date:           06/30/2011
Contract Date:          07/22/2011
W/O Issued:             07/29/2011                                                               Adjusted:
W/O Effective:          09/01/2011                                Amount Paid:             84 % (      84 %)
Work Started:           11/01/2011                                Time Passed:           136 % (      109 %)


26656(04)     Contract: 110055     CORD    Residency:    05005         0.114 MI. CO.RD.;BRIDGE &
BRO-105D(179)CI                            CIRCUIT ENGR. DISTR. # 7    APPROACHES:OVER SHORT CR., 2.3MI.
                                                                       W. OF THE IS-40 JCT.
Contractor:   MUNOZ CONSTRUCTION CO., INC.
Engineer:     CED7                       Adjusted:
Contract Amount:       $345,334.75      (        $348,334.75)
Contract Time:         120              (   129 )
Letting Date:          02/17/2011
Contract Date:         03/16/2011
W/O Issued:            03/18/2011                                                              Adjusted:
W/O Effective:         07/05/2011                                Amount Paid:            97 % (      96 %)
Work Started:          07/05/2011                               Time Passed:           113 % (      105 %)


26239(07)     Contract: 110414      IS-40   Residency:     05200        4.31 MI. IS-40;RESURFACE
IMY-0040-1(075)006                          ALTUS                       (ASPHALT)FROM MILE MARKER 3.50,
                                                                        EXTEND EAST.
Contractor:   CORNELL CONSTRUCTION COMPANY, INC.
Engineer:     Nedbalek, Will               Adjusted:
Contract Amount:        $4,781,940.44     (      $4,789,253.36)
Contract Time:          125               (  125 )
Letting Date:           02/16/2012
Contract Date:          03/22/2012
W/O Issued:             03/26/2012                                                              Adjusted:
W/O Effective:          07/02/2012                               Amount Paid:             74 %(       74 %)
Work Started:           05/09/2012                               Time Passed:             74 %(       74 %)


28132(04)     Contract: 110506      SH-34   Residency:     05200        0.112 MI. SH-34;BRIDGE REHAB. OVER
SBR-105C(198)SB                             ALTUS                       INDIAN CR., 0.70 MI. N. OF THE SH-152
                                                                        JCT.
Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
Engineer:     Nedbalek, Will               Adjusted:
Contract Amount:        $1,059,912.63     (      $1,061,308.91)
Contract Time:          85                (   85   )
Letting Date:           11/17/2011
Contract Date:          12/13/2011
W/O Issued:             12/19/2011                                                               Adjusted:
W/O Effective:          04/02/2012                               Amount Paid:             93  %(         93 %)
Work Started:           04/16/2012                               Time Passed:           108   %(        108 %)




                                            Construction Status Report                             Page 53
 29311(04)     Contract: 120246      IS-40   Residency:     05100        0.00 MI. IS-40:STRIPING &   PAVEMENT
 HSIPG-205F(014)TR                           CLINTON                     MARKING/US-62/US-183/US-270/US-283/
                                                                         SH-6/SH-3/     SH-33. MULTIPLE
 Contractor:   DIRECT TRAFFIC CONTROL INC.                               LOCATIONS IN D
 Engineer:     Greer, Randy                 Adjusted:
 Contract Amount:        $300,000.00       (        $300,000.00)
 Contract Time:          45                (   45   )
 Letting Date:           07/19/2012
 Contract Date:          08/21/2012
 W/O Issued:             08/24/2012                                                               Adjusted:
 W/O Effective:          09/24/2012                               Amount Paid:              0%(           0 %)
 Work Started:                                                    Time Passed:              0%(           0 %)
 IV. V.

 28902(04)     Contract: 120194     I-40      Residency:    05002        0.00 MI. FARMRAIL R/R BR.  /I-40.
 BRFY-NBIP(451)                               TETRA TECH                 BRIDGE PAINTING:OVER I-40 AT MILE
                                                                         MARKER 23.59.
 Contractor:   PACIFIC PAINTING COMPANY, INC.
 Engineer:     TETR                         Adjusted:
 Contract Amount:       $224,000.00        (        $224,000.00)
 Contract Time:         60                 (   60   )
 Letting Date:          05/17/2012
 Contract Date:         06/19/2012
 W/O Issued:            08/06/2012                                                               Adjusted:
 W/O Effective:         09/04/2012                                Amount Paid:              0%(            0 %)
 Work Started:                                                    Time Passed:              0%(            0 %)


 25909(05)     Contract: 100551     IS-40   Residency:     05014        1.355 MI. IS-40;GRADE,DRAIN
 SAP-105N(193)                                                          ,SURFACE & SITE
                                            SAIC (AKA - THE BENHAM COMPANIES, LLC) PLANS;TRUCK WEIGH
                                                                        STATION,1.75 MI. E.   OF THE TX STATE
 Contractor:                                                             JV
               DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCLINE.
 Engineer:     SAIC ( AKA - ZBCL)          Adjusted:
 Contract Amount:       $8,714,997.47     (      $8,872,171.39)
 Contract Time:         300               (  327 )
 Letting Date:          10/21/2010
 Contract Date:         11/16/2010
 W/O Issued:            11/23/2010                                                              Adjusted:
 W/O Effective:         03/07/2011                               Amount Paid:             97 %(          95 %)
 Work Started:          03/14/2011                               Time Passed:            121 %(        111 %)


 28031(04)     Contract: 120237     CORD       Residency:       05100           0.00 MI. CO.RD.:BRIDGE REPR. OVER
 SAP-205N(013)                                 CLINTON                          IS-40, 3.0 MI. EAST OF THE TEXAS
                                                                                STATE LINE.
 Contractor:   B & B CONSTRUCTION SERVICE   J.T., INC.
 Engineer:     Greer, Randy                  Adjusted:
 Contract Amount:        $23,550.00         (            $23,550.00)
 Contract Time:          10                 (     10   )
 Letting Date:           06/21/2012
 Contract Date:          07/17/2012
 W/O Issued:             07/18/2012                                                                 Adjusted:
 W/O Effective:          11/05/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                            Time Passed:           0 %(      0 %)




County:          Blaine                                       Commissioner District:                                5
Contracts Under Construction




                                             Construction Status Report                                   Page 54
20237(04)     Contract: 100549      US-270   Residency:     05100        2.215 MI. US-270;GRADE,DRAIN
NHY-010N(027)                                CLINTON                     ,SURFACE & BRIDGE;FROM 3.0 MI.S. OF
                                                                         THE SH-33 JUNCTION, EX- TEND NORTH.
Contractor:   HASKELL LEMON CONSTRUCTION CO.
Engineer:     Greer, Randy                  Adjusted:
Contract Amount:        $7,695,489.94      (      $7,783,472.23)
Contract Time:          360                (  419 )
Letting Date:           09/16/2010
Contract Date:          10/11/2010
W/O Issued:             10/14/2010                                                              Adjusted:
W/O Effective:          02/07/2011                                Amount Paid:           101 % (       100 %)
Work Started:           11/10/2010                                Time Passed:           116 % (       100 %)


21704(04)     Contract: 120081      SH-58   Residency:     05100        0.462 MI. SH-58;BRIDGE &
SSP-106C(061)SS                             CLINTON                     APPROACHES;OVER NINE MI. & UN-NAME
                                                                        CR., 8.6 & 9.2 MI.    NORTH OF US-270.
Contractor:   BRIDGES, INC. DBA SCUDDER BRIDGE CO.
Engineer:     Greer, Randy                 Adjusted:
Contract Amount:        $2,836,769.65     (      $2,836,769.65)
Contract Time:          180               (  180 )
Letting Date:           02/16/2012
Contract Date:          03/19/2012
W/O Issued:             04/09/2012                                                               Adjusted:
W/O Effective:          07/02/2012                               Amount Paid:              41 % (        41 %)
Work Started:           05/07/2012                               Time Passed:              56 % (        56 %)


24087(04)     Contract: 110507      US-270   Residency:     05100        0.255 MI. US-270:BRIDGE &
BRFY-017N(203)SS                             CLINTON                     APPROACHES;OVER THE
                                                                         N.CANADIANRIVER, 10.2 MI. EAST OF
Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) THE DEWEY C/L.
Engineer:     Greer, Randy                  Adjusted:
Contract Amount:        $2,445,565.14      (      $2,445,565.14)
Contract Time:          220                (  220 )
Letting Date:           11/17/2011
Contract Date:          12/13/2011
W/O Issued:             12/19/2011                                                               Adjusted:
W/O Effective:          04/02/2012                                Amount Paid:            68  %(         68 %)
Work Started:           04/02/2012                                Time Passed:            55  %(         55 %)


20237(08)     Contract: 110435      US-270   Residency:     05100        2.12 MI. US-270 FROM 5.2 MI. SOUTH OF
SSP-010N(032)SS                              CLINTON                     THE SH-33 JCT. EXTEND NORTH.

Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
Engineer:     Greer, Randy                  Adjusted:
Contract Amount:        $2,087,949.25      (      $2,087,949.25)
Contract Time:          240                (  240 )
Letting Date:           09/15/2011
Contract Date:          10/12/2011
W/O Issued:             10/17/2011                                                               Adjusted:
W/O Effective:          02/06/2012                                Amount Paid:             63 %(         63 %)
Work Started:           01/02/2012                                Time Passed:             82 %(         82 %)




                                            Construction Status Report                             Page 55
 26618(04)     Contract: 120238      CORD      Residency:       05005           0.217 MI. CO.RD.:BRIDGE &
 BRO-106D(116)CI                               CIRCUIT ENGR. DISTR. # 7         APPROACHES/OVER SALT CREEK,   4.7
                                                                                MI SOUTH OF SH-51.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     CED7                          Adjusted:
 Contract Amount:        $465,431.64        (        $465,431.64)
 Contract Time:          120                (  120 )
 Letting Date:           06/21/2012
 Contract Date:          07/20/2012
 W/O Issued:             07/24/2012                                                               Adjusted:
 W/O Effective:          11/05/2012                                       Amount Paid:          0%(      0 %)
 Work Started:                                                            Time Passed:          0%(      0 %)




County:          Bryan                                        Commissioner District:                                2
Contracts Under Construction


 21654(04)     Contract: 120153     CO.RD.   Residency:     02013        0.283 MI. CO.RD.:BRIDGE &
 BRO-107D(087)CI                             CIRCUIT ENGR. DISTRICT # 3 APPROACHES/OVER J-N CREEK, 2.5MI.
                                                                         NORTH OF US-70E.
 Contractor:   HUB CONSTRUCTION, INC.
 Engineer:     CED3                         Adjusted:
 Contract Amount:       $580,850.90        (        $580,850.90)
 Contract Time:         90                 (   90   )
 Letting Date:          04/19/2012
 Contract Date:         05/18/2012
 W/O Issued:            05/23/2012                                                               Adjusted:
 W/O Effective:         08/06/2012                                Amount Paid:              0%(         0 %)
 Work Started:                                                    Time Passed:              0%(         0 %)


 26295(08)     Contract: 120003      US-69   Residency:     02100        8.00 MI. US-69:PAVEMENT RE-
 NHY-013N(148)3P                             ANTLERS                     HABILITATION (UTBWC)BEGIN 1.07
                                                                         MI. NORTH OF SH-78,   EXTEND NORTH
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.                        (SOUTHBOUND LANE)
 Engineer:     Moy, Ryan                    Adjusted:
 Contract Amount:        $4,152,484.83     (      $4,152,484.83)
 Contract Time:          120               (  120 )
 Letting Date:           02/16/2012
 Contract Date:          03/14/2012
 W/O Issued:             03/21/2012                                                             Adjusted:
 W/O Effective:          07/02/2012                               Amount Paid:              9 %(        9 %)
 Work Started:           05/29/2012                               Time Passed:            52 % (       52 %)


 23191(04)     Contract: 120002       SH-199   Residency:     02300        1.280 MI. SH-199;BRIDGE &
 SSP-107C(111)SS                               MADILL                      APPROACHES/FROM 4.0 MI. W. OF SH-
                                                                           78, EXTEND W. OVER THE     WASHITA
 Contractor:   L & N BRIDGE, LLC                                           RIVER.
 Engineer:     Eldridge, Jerry                Adjusted:
 Contract Amount:         $6,741,856.52      (      $6,741,856.52)
 Contract Time:           240                (  240 )
 Letting Date:            01/19/2012
 Contract Date:           04/19/2012
 W/O Issued:              06/23/2012                                                              Adjusted:
 W/O Effective:           06/04/2012                                Amount Paid:            13  %(        13 %)
 Work Started:            06/04/2012                                Time Passed:            29  %(        29 %)




                                             Construction Status Report                                 Page 56
21732(04)     Contract: 110413       US-70   Residency:     02300        .725 MI. US-70 OVER CADDO CREEK,
BRFY-022N(154)SS                             MADILL                      10.5 MI. EAST OF US-69B JCT

Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
Engineer:     Eldridge, Jerry               Adjusted:
Contract Amount:         $3,447,006.66     (      $3,447,006.66)
Contract Time:           150               (  150 )
Letting Date:            09/15/2011
Contract Date:           10/12/2011
W/O Issued:              10/17/2011                                                              Adjusted:
W/O Effective:           02/06/2012                               Amount Paid:             66 % (       66 %)
Work Started:            02/06/2012                               Time Passed:           124 % (      124 %)


29079(04)     Contract: 120196       US-69   Residency:     02300        13.109 MI. US-69:SAFETY
HSIPG-013N(156)(157)TR                       MADILL                      IMPROVEMENT(CABLE BARRIER & INT.
                                                                         MODIFICATION)FROM JUST N. OF
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.                             COLBERT EXTEND N.
Engineer:     Eldridge, Jerry               Adjusted:
Contract Amount:         $2,115,063.70     (      $2,115,063.70)
Contract Time:           180               (  180 )
Letting Date:            07/19/2012
Contract Date:           08/21/2012
W/O Issued:              08/24/2012                                                              Adjusted:
W/O Effective:           11/05/2012                               Amount Paid:              0%(         0 %)
Work Started:                                                     Time Passed:              0%(         0 %)


21733(04)     Contract: 120247       US-70     Residency:       02300           0.738 MI. US-70/BRIDGE &
NHY-022N(157)                                  MADILL                           APPROACHES:OVER BLUE RIVER 7.7MI.
                                                                                EAST OF US-69B.
Contractor:   L & N BRIDGE, LLC
Engineer:     Eldridge, Jerry                 Adjusted:
Contract Amount:         $4,555,100.82       (      $4,555,100.82)
Contract Time:           200                 (  200 )
Letting Date:            07/19/2012
Contract Date:           08/21/2012
W/O Issued:              08/24/2012                                                                 Adjusted:
W/O Effective:           12/03/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                             Time Passed:           0 %(      0 %)


26231(04)     Contract: 120248       SH-69B   Residency:     02300        0.15 MI. SH-69B:BRIDGE &
BRFY-107B(151)                                MADILL                      APPROACHES:OVER MINERAL BAYOU CR.
                                                                          0.5 MI. SOUTH OF US-70.
Contractor:   L & N BRIDGE, LLC
Engineer:     Eldridge, Jerry                Adjusted:
Contract Amount:         $1,417,551.48      (      $1,417,551.48)
Contract Time:           150                (  150 )
Letting Date:            07/19/2012
Contract Date:           08/21/2012
W/O Issued:              08/24/2012                                                               Adjusted:
W/O Effective:           12/03/2012                                Amount Paid:              0 %(        0 %)
Work Started:                                                      Time Passed:              0 %(        0 %)




                                             Construction Status Report                                  Page 57
 18847(15)     Contract: 110348      US-70   Residency:     02300        4.502 MI. US-70;GRADE,DRAIN
 NHY-022N(195)(207)                          MADILL                      ,SURFACE & SIGNALS/DURANT BY-
                                                                         PASS:FROM THE US-JCT,EXTEND S.E. TO
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.                        THE SH-78 JCT.
 Engineer:     Eldridge, Jerry              Adjusted:
 Contract Amount:         $18,574,116.09   (     $18,574,116.09)
 Contract Time:           450              (  450 )
 Letting Date:            07/21/2011
 Contract Date:           08/18/2011
 W/O Issued:              08/24/2011                                                            Adjusted:
 W/O Effective:           12/05/2011                              Amount Paid:            28 % (       28 %)
 Work Started:            01/03/2012                              Time Passed:            46 % (       46 %)


 28101(04)     Contract: 110371       US-69   Residency:     02300        0.00 MI. US-69/SAFETY IMPROV. (CABLE
 NHG-013N(144)(145)TR                         MADILL                      BARRIER/GUARDRAIL)FROM THE
                                                                          OKLA./TEXAS S/L., EXTEND NORTH.
 Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:     Eldridge, Jerry               Adjusted:
 Contract Amount:         $2,001,222.50     (      $2,001,222.50)
 Contract Time:           160               (  160 )
 Letting Date:            08/18/2011
 Contract Date:           09/26/2011
 W/O Issued:              09/28/2011                                                              Adjusted:
 W/O Effective:           12/05/2011                               Amount Paid:            51 % (         51 %)
 Work Started:            12/06/2011                               Time Passed:           123 % (        123 %)




County:          Caddo                                        Commissioner District:                          7
Contracts Under Construction


 01817(04)     Contract: 120127     SH-152   Residency:     07004        2.105 MI. SH-152;GRADE,DRAIN, &
 STPY-008B(308)SS                                                        SURFACE;BEGIN 2.0 MI. E.OF SH-146,
                                             JACOBS (AKA - CARTER-BURGESS)
                                                                         EXTEND EAST.
 Contractor:   SCHWARZ PAVING CO., INC.
 Engineer:     JACOBS (AKA - C-B)           Adjusted:
 Contract Amount:       $6,558,995.07      (      $6,558,995.07)
 Contract Time:         285                (  285 )
 Letting Date:          03/15/2012
 Contract Date:         04/16/2012
 W/O Issued:            04/20/2012                                                               Adjusted:
 W/O Effective:         08/06/2012                                Amount Paid:             3 %(          3 %)
 Work Started:          08/08/2012                                Time Passed:             4%(           4 %)


 27439(04)     Contract: 110280      US-281   Residency:     07300        7.65 MI. US-281;RESURFACE
 SSR-108B(283)SR                              ANADARKO                    (ASPHALT)BEGIN 0.86 MI. N. OF US-62,
                                                                          EXTEND NORTH.
 Contractor:   T & G CONSTRUCTION, INC.
 Engineer:     Knight, Reese                 Adjusted:
 Contract Amount:        $1,396,224.90      (      $1,396,224.90)
 Contract Time:          30                 (   30   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/24/2012                                                               Adjusted:
 W/O Effective:          05/07/2012                                Amount Paid:            98 %(          98 %)
 Work Started:           05/01/2012                                Time Passed:            93 %(          93 %)




                                             Construction Status Report                             Page 58
 26488(04)     Contract: 110508      IS-40   Residency:     05100        2.058 MI. IS-40RESURFACE
 IMY-0040-4(430)102                          CLINTON                     (ASPHALT)FROM MILE MARKER 102 .2
                                                                         EXTEND EAST 2.06 MI.
 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Greer, Randy                 Adjusted:
 Contract Amount:        $4,682,467.35     (      $4,685,207.75)
 Contract Time:          120               (  120 )
 Letting Date:           11/17/2011
 Contract Date:          12/12/2011
 W/O Issued:             12/15/2011                                                             Adjusted:
 W/O Effective:          05/07/2012                               Amount Paid:           100 % (     100 %)
 Work Started:           02/06/2012                               Time Passed:           100 % (     100 %)


 24512(04)     Contract: 120302      US-281   Residency:     07300        0.000 MI. US-281/BRIDGE REPR. OVER
 SBR-108B(178)SB                              ANADARKO                    SUGAR CR.,0.4 MI. E. OF THE
                                                                          SH-8/SH-152 JCT IN THE CITY OF
 Contractor:   MERIDIAN CONTRACTING, INC.                                 BINGER.
 Engineer:     Knight, Reese                 Adjusted:
 Contract Amount:        $1,056,897.00      (      $1,056,897.00)
 Contract Time:          150                (  150 )
 Letting Date:           07/19/2012
 Contract Date:          08/17/2012
 W/O Issued:             08/22/2012                                                               Adjusted:
 W/O Effective:          12/03/2012                                Amount Paid:              0%(           0 %)
 Work Started:                                                     Time Passed:              0%(           0 %)




County:          Canadian                                     Commissioner District:                               4
Contracts Under Construction


 28313(04)     Contract: 110189     I-40      Residency:     04010          .075 MI. I-40:BRIDGE
 SBR-109N(181)SB                              ATKINS (AKA - PBS & J)        REHABILITATION;OVER MAYBERRY RD
                                                                            5.0 MI.WEST OF US-270
 Contractor:   C-P INTEGRATED SERVICES, INC.
 Engineer:     ATKINS (AKA - PBSJ)           Adjusted:
 Contract Amount:       $1,207,042.00      (       $1,207,042.00)
 Contract Time:         150                (   150 )
 Letting Date:          10/20/2011
 Contract Date:         11/23/2011
 W/O Issued:            12/07/2011                                                                 Adjusted:
 W/O Effective:         03/05/2012                                   Amount Paid:             36 %(      36 %)
 Work Started:          03/05/2012                                   Time Passed:            104 % (    104 %)


 21008(04)     Contract: 100511      I-40      Residency:       04200           *-40-4(433)139/ 2.037 MI.
 SEC1702Y-109A(130)HP/IMY*                     EL RENO                          IS-40:GRADE,DRAIN,SURFACE, &
                                                                                BRIDGE, AT MORGAN RD. INTER-
 Contractor:   ALLEN CONTRACTING, INC.                                          CHANGE IN OKC.
 Engineer:     Vonfeldt, Cole                Adjusted:
 Contract Amount:         $33,963,202.80    (     $34,075,771.00)
 Contract Time:           640               (  703 )
 Letting Date:            09/16/2010
 Contract Date:           10/15/2010
 W/O Issued:              10/21/2010                                                                Adjusted:
 W/O Effective:           02/07/2011                                      Amount Paid:          92 %(     92 %)
 Work Started:            02/14/2011                                      Time Passed:          85 %(     77 %)




                                             Construction Status Report                                  Page 59
 26457(04)     Contract: 120020     IS-40       Residency:       04003           0.00 MI. IS-40;PAVEMENT MARK -ING.
 IMG-0040-4(431)000                             COBB ENGINEERING CO., INC.       AT VARIOUS LOCATIONS IN THE OKC
                                                                                 METRO AREA.
 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     COBB                            Adjusted:
 Contract Amount:       $614,190.00           (        $614,190.00)
 Contract Time:         90                    (   90   )
 Letting Date:          01/19/2012
 Contract Date:         02/22/2012
 W/O Issued:            02/28/2012                                                                    Adjusted:
 W/O Effective:         06/04/2012                                         Amount Paid:          58 % (     58 %)
 Work Started:          06/04/2012                                         Time Passed:          76 % (     76 %)


 28012(04)     Contract: 110374       IS-40     Residency:       04200           *-11N(88)TR/14.150 MI. IS- 40
 IMG-40-4(434)120TR/NHG*                        EL RENO                          /SAFETY IMPROV.(CABLE
                                                                                 BARRIER)FROM 9.0 MI. W. OF THE
 Contractor:   JLT CONTRACTING, LLC                                              US-81 JCT. EXTEND E.
 Engineer:     Vonfeldt, Cole                  Adjusted:
 Contract Amount:         $2,574,390.20       (      $2,605,906.00)
 Contract Time:           160                 (  160 )
 Letting Date:            08/18/2011
 Contract Date:           10/03/2011
 W/O Issued:              10/07/2011                                                                  Adjusted:
 W/O Effective:           12/05/2011                                       Amount Paid:          62 % (     61 %)
 Work Started:            12/05/2011                                       Time Passed:         101 % (    101 %)




County:          Carter                                        Commissioner District:                                 7
Contracts Under Construction


 20231(04)     Contract: 100283     SH-199   Residency:     07200        3.45 MI.;SH-199;GRADE,DRAIN,
 STPY-110B(108)SS                            ARDMORE                     SURFACE & BRIDGE;FROM 4.8 MI. W. OF
                                                                         US-177, EXTEND EAST.
 Contractor:   OVERLAND CORPORATION
 Engineer:     Earp, Jay                    Adjusted:
 Contract Amount:        $11,231,158.14    (     $11,231,158.14)
 Contract Time:          330               (  654 )
 Letting Date:           08/19/2010
 Contract Date:          09/20/2010
 W/O Issued:             09/27/2010                                                             Adjusted:
 W/O Effective:          01/03/2011                               Amount Paid:            92 %(         92 %)
 Work Started:           10/18/2010                               Time Passed:           198 % (       100 %)


 09477(08)     Contract: 110022      US-70   Residency:     07200        *(232)/CIRB-110C(204)RB/SSP
 BRFY-110B(170)/STPY-110B*                   ARDMORE                     -110B(218)SS / 1.69 MI. US-70
                                                                         ;GRADE,DRAIN,SURFACE & BRIDGE
 Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.                    FROM MERIDAN RD. IN LONE GROVE
 Engineer:     Earp, Jay                    Adjusted:
 Contract Amount:        $6,498,225.78     (      $6,503,217.13)
 Contract Time:          180               (  180 )
 Letting Date:           02/17/2011
 Contract Date:          03/24/2011
 W/O Issued:             03/30/2011                                                               Adjusted:
 W/O Effective:          05/09/2011                               Amount Paid:             92 %(        92 %)
 Work Started:           04/12/2011                               Time Passed:             99 %(        99 %)
 .




                                              Construction Status Report                                   Page 60
20231(07)     Contract: 120128      SH-199   Residency:     07200        1.74 MI. SH-199:GRADE,DRAIN, &
STPY-110B(181)SS                             ARDMORE                     SURFACE/BEGIN 1.35 MI. W. OFUS-177
                                                                         EXTEND EAST.
Contractor:   OVERLAND CORPORATION
Engineer:     Earp, Jay                     Adjusted:
Contract Amount:        $6,196,358.20      (      $6,196,358.20)
Contract Time:          200                (  200 )
Letting Date:           03/15/2012
Contract Date:          04/12/2012
W/O Issued:             04/20/2012                                                              Adjusted:
W/O Effective:          05/23/2012                                Amount Paid:            26 % (        26 %)
Work Started:           05/23/2012                                Time Passed:            42 % (        42 %)


29176(04)     Contract: 120154      I-35      Residency:       07200           0.00 MI. IS-35:BRIDGE RE-
SBR-210N(004)SB                               ARDMORE                          HABILITION:OVER SH-142 &
                                                                               CO.RD(EW-189), 2.1 MI. & 7.2 MI.
Contractor:   GIBSON & ASSOCIATES, INC.                                        NORTH OF US-70
Engineer:     Earp, Jay                      Adjusted:
Contract Amount:        $526,159.58         (        $526,159.58)
Contract Time:          120                 (  120 )
Letting Date:           04/19/2012
Contract Date:          05/22/2012
W/O Issued:             06/19/2012                                                                  Adjusted:
W/O Effective:          09/04/2012                                       Amount Paid:             0%(      0 %)
Work Started:                                                            Time Passed:             0%(      0 %)


28128(15)     Contract: 110501     I-35      Residency:    07004         0.00 MI.
BTOP-116E(211)                                                           I-35/US-62/US-69/US-70/US-75/US-81 AT
                                             JACOBS (AKA - CARTER-BURGESS)
                                                                         VARIOUS LOCATIONS IN DIVISION 2 & 7.
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
Engineer:     JACOBS (AKA - C-B)           Adjusted:
Contract Amount:       $945,536.64        (        $945,536.64)
Contract Time:         150               (    150  )
Letting Date:          09/15/2011
Contract Date:         10/17/2011
W/O Issued:            10/22/2011                                                               Adjusted:
W/O Effective:         11/21/2011                                 Amount Paid:            86 %(         86 %)
Work Started:          03/12/2012                                 Time Passed:          118  %(        118 %)


28165(04)     Contract: 120001      US-77     Residency:       07200           2.25 MI. US-77;RESURFACE
SSR-110A(235)SR                               ARDMORE                          (ASPHALT)BEGIN 1.0 MI. N. OF US-70,
                                                                               EXTEND NORTH.
Contractor:   OVERLAND CORPORATION
Engineer:     Earp, Jay                      Adjusted:
Contract Amount:        $1,958,640.16       (      $2,004,945.16)
Contract Time:          60                  (   60   )
Letting Date:           01/19/2012
Contract Date:          02/15/2012
W/O Issued:             03/01/2012                                                                  Adjusted:
W/O Effective:          05/07/2012                                       Amount Paid:           86 %(     84 %)
Work Started:           05/07/2012                                       Time Passed:          122 %(    122 %)




                                            Construction Status Report                                     Page 61
 24373(04)     Contract: 120004      SH-53     Residency:       07200           0.576 MI. SH-53;GRADE,DRAIN &
 STPY-110C(198)HP                              ARDMORE                          SURFACE/BEGIN 7.05 MI. E. OFIS-35 AT
                                                                                THE W. ENTRANCE TO ARDMORE AIR
 Contractor:   OVERLAND CORPORATION                                             PARK.
 Engineer:     Earp, Jay                      Adjusted:
 Contract Amount:        $1,916,259.49       (      $1,918,224.25)
 Contract Time:          125                 (  125 )
 Letting Date:           01/19/2012
 Contract Date:          02/15/2012
 W/O Issued:             02/22/2012                                                                   Adjusted:
 W/O Effective:          06/04/2012                                       Amount Paid:           24 % (     23 %)
 Work Started:           04/23/2012                                       Time Passed:           58 % (     58 %)


 28164(04)     Contract: 110282      US-70     Residency:       07200           4.99 MI. US-70:RESURFACE
 SSR-110B(234)SR                               ARDMORE                          (ASPHALT)FROM SH-76N, EXTEND EAST.

 Contractor:   OVERLAND CORPORATION
 Engineer:     Earp, Jay                      Adjusted:
 Contract Amount:        $1,698,223.30       (      $1,698,223.30)
 Contract Time:          45                  (   45   )
 Letting Date:           06/21/2012
 Contract Date:          07/11/2012
 W/O Issued:             07/18/2012                                                                 Adjusted:
 W/O Effective:          08/06/2012                                       Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)


 28128(49)     Contract: 120064     IS-35      Residency:       07011           55.25 MI. IS-35/US-69/US-70 :SAFETY
 BTOP-210N(001)                                GARVER, LLC.                     IMPROVEMENTS(FIBER OPTIC
                                                                                CABLE)FROM THE CITY OF ARDMORE TO
 Contractor:   TELCO SUPPLY COMPANY                                             THE CITY OF DURANT.
 Engineer:     GARV                           Adjusted:
 Contract Amount:       $3,087,621.74        (      $3,298,552.49)
 Contract Time:         155                  (  155 )
 Letting Date:          01/19/2012
 Contract Date:         02/21/2012
 W/O Issued:            02/23/2012                                                                  Adjusted:
 W/O Effective:         03/19/2012                                        Amount Paid:         101 %(     94 %)
 Work Started:          03/19/2012                                        Time Passed:          87 %(     87 %)




County:          Cherokee                                     Commissioner District:                                   1
Contracts Under Construction


 10010(04)     Contract: 080046     SH-82   Residency:     01200        6.719 KM WIDEN & RESURFACE SH-82
 STPY-011C(341)SS                           SALLISAW                    BEGIN APPROX. 0.6 MI. N.W. OF SH-100
                                                                        & EXTEND N.W.
 Contractor:   SHERWOOD CONSTRUCTION CO., INC.
 Engineer:     Edwards, Carl               Adjusted:
 Contract Amount:       $9,279,334.90     (     $10,380,474.34)
 Contract Time:         400               ( 1,427 )
 Letting Date:          01/17/2008
 Contract Date:         04/16/2008
 W/O Issued:            04/25/2008                                                              Adjusted:
 W/O Effective:         08/04/2008                               Amount Paid:            99 %(          89 %)
 Work Started:          08/04/2008                               Time Passed:          357  %(         100 %)




                                             Construction Status Report                                    Page 62
County:          Choctaw                                      Commissioner District:                                  2
Contracts Under Construction


 21652(04)     Contract: 120048     CORD       Residency:       02013           0.32 MI. CO.RD.;BRIDGE &
 BRO-112D(058)CI                               CIRCUIT ENGR. DISTRICT # 3       APPROACHES/OVER SALT CR. 2.3 MI. N.
                                                                                & 0.7 MI. W. OF     THE US-70/SH-93
 Contractor:   HUB CONSTRUCTION, INC.                                           JCT.
 Engineer:     CED3                          Adjusted:
 Contract Amount:       $764,239.75         (        $764,239.75)
 Contract Time:         90                  (  104   )
 Letting Date:          01/19/2012
 Contract Date:         02/17/2012
 W/O Issued:            02/23/2012                                                                  Adjusted:
 W/O Effective:         05/07/2012                                        Amount Paid:          56 %(     56 %)
 Work Started:          05/21/2012                                        Time Passed:         108 %(     93 %)


 18850(04)     Contract: 100547     US-70   Residency:     02100        5.285 MI. US-70;GRADE,DRAIN,
 NHY-022N(071)                              ANTLERS                     SURFACE, & BRIDGE;FROM THE SH-147
                                                                        JUNCTION,EXTEND EAST.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Moy, Ryan                   Adjusted:
 Contract Amount:        $11,635,370.40   (     $11,635,370.40)
 Contract Time:          360              (  360 )
 Letting Date:           09/16/2010
 Contract Date:          10/21/2010
 W/O Issued:             10/26/2010                                                            Adjusted:
 W/O Effective:          02/07/2011                              Amount Paid:            86 % (       86 %)
 Work Started:           02/07/2011                              Time Passed:           114 % (      114 %)




County:          Cimarron                                     Commissioner District:                                  6
Contracts Under Construction


 13337(05)     Contract: 100614      US-287   Residency:     06200        3.139 MI. US-287;GRADE,DRAIN
 NHY-017N(238)                                GUYMON                      ,SURFACE & BRIDGE;FROM 6.9 MI.N. OF
                                                                          BOISE CITY, EXTEND    NORTH.
 Contractor:   DOBSON BROTHERS CONSTRUCTION CO.
 Engineer:     Michael, Charles              Adjusted:
 Contract Amount:        $8,619,401.99      (      $8,720,881.99)
 Contract Time:          200                (  452 )
 Letting Date:           11/18/2010
 Contract Date:          12/15/2010
 W/O Issued:             12/27/2010                                                              Adjusted:
 W/O Effective:          04/04/2011                                Amount Paid:            91 %(         90 %)
 Work Started:           04/04/2011                                Time Passed:           227 % (       100 %)




                                             Construction Status Report                                   Page 63
 13337(19)     Contract: 100477      US-287   Residency:     06200        2.215 MI. US-287;SURFACE/    FROM 1.0
 SEC1302Y-133N(050)HP                         GUYMON                      MI. S. OF THE SH-3/ US-64 JUNCTION.

 Contractor:   DOBSON BROTHERS CONSTRUCTION CO.
 Engineer:     Michael, Charles              Adjusted:
 Contract Amount:        $5,610,381.67      (      $5,934,340.85)
 Contract Time:          240                (  243 )
 Letting Date:           08/19/2010
 Contract Date:          09/16/2010
 W/O Issued:             09/21/2010                                                               Adjusted:
 W/O Effective:          01/03/2011                                Amount Paid:           100 % (         95 %)
 Work Started:           10/25/2010                                Time Passed:           101 % (        100 %)


 24823(04)     Contract: 120200      CORD   Residency:     06200        6.15 MI. CO.RD.:GRADE,DRAIN &
 CIRB-113C(058)RB                           GUYMON                      SURFACE.FROM THE US-287/ TEXAS
                                                                        STATE LINE JCT, EXTEND WEST.
 Contractor:   HIGHWAY CONTRACTORS, INC.
 Engineer:     Michael, Charles            Adjusted:
 Contract Amount:        $3,382,570.79    (      $3,382,570.79)
 Contract Time:          120              (  120 )
 Letting Date:           06/21/2012
 Contract Date:          07/18/2012
 W/O Issued:             07/20/2012                                                            Adjusted:
 W/O Effective:          08/13/2012                              Amount Paid:              0%(        0 %)
 Work Started:           08/09/2012                              Time Passed:              0%(        0 %)


 24612(04)     Contract: 100465      CORD   Residency:     06200        *-113D(56)CO/0.264 MI. CO. RD.;OVER
 BRO-113D(55)CO/ACBRO*                      GUYMON                      LANE CANYON/GALLINAS CANYON CR.,
                                                                        5.8 MI. & 4.25 MI. N. OF SH-325 JCT.
 Contractor:   KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:     Michael, Charles            Adjusted:
 Contract Amount:        $497,647.73      (        $497,647.73)
 Contract Time:          120              (  692   )
 Letting Date:           07/22/2010
 Contract Date:          08/24/2010
 W/O Issued:             10/06/2010                                                             Adjusted:
 W/O Effective:          11/01/2010                              Amount Paid:           93   %(          93 %)
 Work Started:           11/01/2010                              Time Passed:          533   %(          92 %)




County:          Cleveland                                    Commissioner District:                          3
Contracts Under Construction


 14392(04)     Contract: 110324     CTST   Residency:     03001        CT.ST.(60TH
 STPY-014B(377)MS                          ENGR. SERV. & TESTING       AVE):GRADE,DRAIN,SURFACE & BRIDGE
                                                                       FROM N OF TECUMSEH RD EXTEND N, IN
 Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.                  THE CITY OF NORMAN
 Engineer:     EST                        Adjusted:
 Contract Amount:       $5,728,854.37    (      $5,728,854.37)
 Contract Time:         210              (  210 )
 Letting Date:          10/20/2011
 Contract Date:         11/23/2011
 W/O Issued:            12/07/2011                                                           Adjusted:
 W/O Effective:         02/06/2012                               Amount Paid:          49 %(         49 %)
 Work Started:          02/06/2012                              Time Passed:           62 %(         62 %)




                                             Construction Status Report                             Page 64
22670(04)     Contract: 100042    CTST    Residency:     03002        *STIM(504)HP/0.333 MI. CT.ST.
TCSP-OH68(007)TC/STP-*                    TETRA TECH                  ;GRADE,DRAIN,SURFACE &
                                                                      BRIDGE;(ROBINSON ST.)DRAINAGE &
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                         PUMP STATION AT THE BNSF R/R
Engineer:     TETR                       Adjusted:
Contract Amount:       $12,207,431.52   (     $13,834,681.54)
Contract Time:         465              (  699 )
Letting Date:          02/18/2010
Contract Date:         03/09/2010
W/O Issued:            03/31/2010                                                             Adjusted:
W/O Effective:         08/02/2010                              Amount Paid:          100 % (         89 %)
Work Started:          06/14/2010                              Time Passed:          171 % (        114 %)


21925(04)     Contract: 120165     SH-9      Residency:       03001           0.00 MI. /SH-9/SH-37:BRIDGE
BRFY-NBIP(449)                               ENGR. SERV. & TESTING            PAINTING, AT VARIOUS LOCATIONSIN
                                                                              DIV. III.
Contractor:   MONOKO, LLC
Engineer:     EST                          Adjusted:
Contract Amount:       $483,426.00        (        $483,426.00)
Contract Time:         120                (  120 )
Letting Date:          04/19/2012
Contract Date:         05/21/2012
W/O Issued:            07/13/2012                                                                Adjusted:
W/O Effective:         08/06/2012                                       Amount Paid:           0%(      0 %)
Work Started:                                                           Time Passed:           0%(      0 %)


24282(04)     Contract: 120009     CTST     Residency:    03004         *-114A(243)TR/ 0.779 MI. CT.
STP-114A(197)AG/HSIPY*                                                  ST.:INTERSECTION MODIFICATION &
                                            JACOBS (AKA - CARTER-BURGESS)
                                                                        TRAFFIC SIGNALS. AT THE
Contractor:   MARKWELL PAVING COMPANY, INC.                             INTERSECTION OF US-77H & ROBIN
Engineer:     JACOBS (AKA - C-B)         Adjusted:
Contract Amount:       $1,982,395.61    (       $1,982,395.61)
Contract Time:         180              (    180 )
Letting Date:          02/16/2012
Contract Date:         03/15/2012
W/O Issued:            03/22/2012                                                               Adjusted:
W/O Effective:         06/19/2012                                Amount Paid:            33  %(       33 %)
Work Started:          06/04/2012                                Time Passed:            41  %(       41 %)


26840(04)     Contract: 120084      CTST    Residency:    03200        1.09 MI. CT.ST. WIDEN & RE-
STP-114B(256)AG                             PURCELL                    SURFACE(ASPHALT)ON PORTER AVE.IN
                                                                       THE CITY OF NORMAN, FROM
Contractor:   MARKWELL PAVING COMPANY, INC.                            WOODCREST DR., EXTEND NORTH.
Engineer:     Riemer, Caleb               Adjusted:
Contract Amount:        $1,936,526.29    (      $1,936,526.29)
Contract Time:          220              (   220 )
Letting Date:           02/16/2012
Contract Date:          03/15/2012
W/O Issued:             03/21/2012                                                              Adjusted:
W/O Effective:          06/04/2012                              Amount Paid:             12 %(        12 %)
Work Started:           06/04/2012                              Time Passed:             26 %(        26 %)




                                           Construction Status Report                                  Page 65
26474(04)     Contract: 110416      CTST   Residency:     03200        .5 MI. CTST AT THE INTERSECTION OF
HSIPY-114A(242)TR                          PURCELL                     CLASSEN BLVD AND IMHOFF RD. IN THE
                                                                       CITY OF NORMAN.
Contractor:   SHELL CONSTRUCTION COMPANY INC.
Engineer:     Riemer, Caleb               Adjusted:
Contract Amount:        $1,498,713.42    (      $1,498,713.42)
Contract Time:          120              (  120 )
Letting Date:           09/15/2011
Contract Date:          10/17/2011
W/O Issued:             10/20/2011                                                             Adjusted:
W/O Effective:          02/06/2012                              Amount Paid:             41 % (        41 %)
Work Started:           02/06/2012                              Time Passed:            143 % (      143 %)


26803(04)     Contract: 120130      CORD   Residency:     04600        *(655)AG/ 1.97 MI. CO.RD.
STP-114B(249)AG/STP-155B*                  OKLAHOMA CITY               GRADE,DRAIN & SURFACE(EASTERN
                                                                       AVE.)BEGIN ONE MILE E. OF  THE
Contractor:                                                             JV
              DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCIS-35/IS-240 JCT.
Engineer:     Howell, Terry               Adjusted:
Contract Amount:        $4,793,449.19    (      $4,793,449.19)
Contract Time:          375              (  375 )
Letting Date:           07/19/2012
Contract Date:          08/16/2012
W/O Issued:             08/20/2012                                                             Adjusted:
W/O Effective:          09/24/2012                              Amount Paid:              0%(         0 %)
Work Started:                                                   Time Passed:              0%(         0 %)


27795(04)     Contract: 120011     CTST      Residency:     03010          1.46 MI. CT.ST.;LIGHTING;ON MAIN
STPG-114B(278)AG                             ATKINS (AKA - PBS & J)        ST., FROM MERKLE DR., EX-TEND WEST
                                                                           IN THE CITY OF     NORMAN.
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
Engineer:     ATKINS (AKA - PBSJ)          Adjusted:
Contract Amount:       $1,083,917.00      (      $1,083,917.00)
Contract Time:         60                (    60   )
Letting Date:          02/16/2012
Contract Date:         03/20/2012
W/O Issued:            03/21/2012                                                                  Adjusted:
W/O Effective:         07/19/2012                                   Amount Paid:               5 %(         5 %)
Work Started:          07/20/2012                                   Time Passed:              77 %(       77 %)


28080(05)     Contract: 120085     SH-9      Residency:     03010          0.00 MI. SH-9; SAFETY IM-
STPG-114A(297)AG                             ATKINS (AKA - PBS & J)        PROVEMENT(SIGNALS &
                                                                           SIDEWALKS)FROM MCGEE DR., EXTEND
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.                               WEST IN THE CITY OF NORMAN.
Engineer:     ATKINS (AKA - PBSJ)          Adjusted:
Contract Amount:       $363,490.00        (        $363,490.00)
Contract Time:         60                (    60   )
Letting Date:          02/16/2012
Contract Date:         03/20/2012
W/O Issued:            03/21/2012                                                                   Adjusted:
W/O Effective:         06/04/2012                                   Amount Paid:             40 %(        40 %)
Work Started:          06/02/2012                                   Time Passed:            122 %(       122 %)




                                             Construction Status Report                              Page 66
23766(04)     Contract: 110512     CORD    Residency:     03004        *(201)AG / 0.108 MI. CO.RD.: BRIDGE &
STP-114D(176)AG/STP-114C*                                              APPROACHES:OVER BUCK-HEAD CR., 5.2
                                           JACOBS (AKA - CARTER-BURGESS)
                                                                       MI. E OF US- 77, OVER N. CANADIAN
Contractor:   BRIDGECO CONTRACTORS, INC.                               RIVER.
Engineer:     JACOBS (AKA - C-B)          Adjusted:
Contract Amount:       $467,942.75       (        $504,320.12)
Contract Time:         80                (  105 )
Letting Date:          11/17/2011
Contract Date:         12/07/2011
W/O Issued:            12/08/2011                                                               Adjusted:
W/O Effective:         03/05/2012                               Amount Paid:           102 % (          94 %)
Work Started:          12/19/2011                               Time Passed:           144 % (        110 %)


25922(04)     Contract: 100002      CT.ST.   Residency:     03200        0.706 MI. CT.ST., GRADE,
IM-0035-2(307)111MS                          PURCELL                     DRAIN,SURFACE & BRIDGE;FROM 36TH
                                                                         AVE.,EXTEND E. IN THE CITY OF
Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.                     NORMAN.
Engineer:     Riemer, Caleb                 Adjusted:
Contract Amount:        $4,989,217.88      (      $5,021,532.88)
Contract Time:          385                (  630 )
Letting Date:           01/28/2010
Contract Date:          02/18/2010
W/O Issued:             02/25/2010                                                                Adjusted:
W/O Effective:          06/07/2010                                Amount Paid:            100 % (      100 %)
Work Started:           06/08/2010                                Time Passed:            172 % (      105 %)


29011(04)     Contract: 120250      CTST      Residency:       03200           0.00 MI. CT.ST.:TRAFFIC
STPG-114F(303)AG                              PURCELL                          SIGNALS;MULTIPLE LOCATIONS IN THE
                                                                               CITY OF NORMAN.
Contractor:   TRAFFIC SIGNALS, INC.
Engineer:     Riemer, Caleb                 Adjusted:
Contract Amount:        $367,702.00        (        $367,702.00)
Contract Time:          90                 (   90   )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                                 Adjusted:
W/O Effective:          11/26/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                            Time Passed:           0 %(      0 %)


22140(04)     Contract: 110235      CTST   Residency:     03200        0.352 MI. CT.ST.;GRADE,DRAIN,
STP-114B(142)AG                            PURCELL                     SURFACE & TRAFFIC SIGNALS/
                                                                       (LINDSEY ST.)FROM JENKINS
Contractor:   SHELL CONSTRUCTION COMPANY INC.                          AVE.,EXTEND EAST IN NORMAN.
Engineer:     Riemer, Caleb               Adjusted:
Contract Amount:        $2,211,002.78    (      $2,211,002.78)
Contract Time:          205              (  205 )
Letting Date:           04/14/2011
Contract Date:          05/18/2011
W/O Issued:             05/26/2011                                                             Adjusted:
W/O Effective:          07/11/2011                              Amount Paid:            100 %(       100 %)
Work Started:           06/13/2011                              Time Passed:            187 %(       187 %)




                                            Construction Status Report                                  Page 67
27785(04)     Contract: 110325      CTST     Residency:       03200           0.520 MI. CT.ST. PEDESTRAIN IMPROV.
STP-114B(276)AG                              PURCELL                          (12TH ST.)FROM SANTA FEAVE.,EXTEND
                                                                              EAST TO JANEWAY AVE. IN THE CITY OF
Contractor:   RUDY CONSTRUCTION CO.                                           MOORE.
Engineer:     Riemer, Caleb                 Adjusted:
Contract Amount:        $158,341.50        (        $158,341.50)
Contract Time:          60                 (   60   )
Letting Date:           08/18/2011
Contract Date:          09/26/2011
W/O Issued:             09/29/2011                                                                 Adjusted:
W/O Effective:          12/05/2011                                      Amount Paid:         100 % (    100 %)
Work Started:           12/05/2011                                      Time Passed:         145 % (    145 %)


09031(15)     Contract: 120006     IS-35   Residency:     03003        0.00 MI. IS-35;SAFETY IMPROVE
IM-NHIY-0035-2(314)108                     COBB ENGINEERING CO., INC. -MENT(SOUND BARRIER WALL)ALONGTHE
                                                                       EAST SIDE OF IS-35 BE- TWEEN
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                          LINDSEY ST. & MAIN ST.
Engineer:     COBB                        Adjusted:
Contract Amount:       $1,440,205.50     (      $1,486,426.37)
Contract Time:         100               (  100 )
Letting Date:          01/19/2012
Contract Date:         02/22/2012
W/O Issued:            02/28/2012                                                               Adjusted:
W/O Effective:         06/04/2012                               Amount Paid:            102 % (       99 %)
Work Started:          04/05/2012                               Time Passed:             92 % (       92 %)


25648(04)     Contract: 120201     CTST      Residency:       03001           2.00 MI. CT.ST.;GRADE,DRAIN, SURFACE
STP-114B(222)AG                              ENGR. SERV. & TESTING            & BRIDGE/CT.ST.     (WESTERN
                                                                              AVE.)FROM SW 164TH ST.,EXTEND N. IN
Contractor:   ALLEN CONTRACTING, INC.                                         OKC.
Engineer:     EST                           Adjusted:
Contract Amount:       $8,891,822.53       (      $8,891,822.53)
Contract Time:         320                 (  320 )
Letting Date:          06/21/2012
Contract Date:         07/13/2012
W/O Issued:            07/18/2012                                                                 Adjusted:
W/O Effective:         10/01/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                           Time Passed:           0 %(      0 %)


24829(04)     Contract: 110202      CORD    Residency:    03200        5.983 MI. CO.RD.
CIRB-114C(210)RB                            PURCELL                    (EW-129):GRADE,DRAIN,&
                                                                       SURFACE;ETOWAH RD FROM 48TH AVE
Contractor:   MARKWELL PAVING COMPANY, INC.                            SW EXTEND EAST
Engineer:     Riemer, Caleb               Adjusted:
Contract Amount:        $5,483,149.88    (      $5,512,233.88)
Contract Time:          360              (   360 )
Letting Date:           10/20/2011
Contract Date:          11/17/2011
W/O Issued:             11/22/2011                                                           Adjusted:
W/O Effective:          03/05/2012                              Amount Paid:            31 %(       31 %)
Work Started:           03/05/2012                              Time Passed:            44 %(       44 %)




                                           Construction Status Report                                   Page 68
 24029(04)     Contract: 120049     IS-35   Residency:     03002        *114C(292)AG /0.907 MI.IS-
 ACSTP-114A(184)AG/STP-*                    TETRA TECH                  35;GRADE,DRAIN & SURFACE/
                                                                        FRONTAGE RD.(INTERSTATE DR.) I-35
 Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.                   NB RAMPS AT ROBINSON ST.
 Engineer:     TETR                        Adjusted:
 Contract Amount:       $2,730,900.00     (      $2,730,900.00)
 Contract Time:                           (        )
 Letting Date:          01/19/2012
 Contract Date:         02/23/2012                               Fixed Completion Date: 08/01/2012
 W/O Issued:            02/29/2012                                                              Adjusted:
 W/O Effective:                                                  Amount Paid:            83 % (       83 %)
 Work Started:          04/02/2012                               Time Passed:          125 % (        81 %)




County:          Coal                                         Commissioner District:                         3
Contracts Under Construction


 28215(04)     Contract: 120086       US-75   Residency:     03100        2.09 MI. US-75; RESURFACE
 NHY-017N(239)3P                              ADA                         (ASPHALT)FROM 7.5 MI. NORTH OFTHE
                                                                          ATOKA C/L, EXTEND NORTH.
 Contractor:   JOB CONSTRUCTION CO., INC.
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $812,724.80       (        $812,724.80)
 Contract Time:           45                (   45   )
 Letting Date:            02/16/2012
 Contract Date:           03/14/2012
 W/O Issued:              03/22/2012                                                              Adjusted:
 W/O Effective:           07/02/2012                               Amount Paid:            100 % (     100 %)
 Work Started:                                                     Time Passed:            118 % (     118 %)


 29036(04)     Contract: 120087       SH-31   Residency:     03100        5.20 MI. SH-31:RESURFACE
 STPY-215C(001)3P                             ADA                         (ASPHALT)FROM 8.5 MI. NORTH OFUS-75,
                                                                          EXTEND NORTH.
 Contractor:   JOB CONSTRUCTION CO., INC.
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $757,306.04       (        $757,306.04)
 Contract Time:           35                (   35   )
 Letting Date:            02/16/2012
 Contract Date:           03/14/2012
 W/O Issued:              03/22/2012                                                             Adjusted:
 W/O Effective:           07/02/2012                               Amount Paid:            99 %(         99 %)
 Work Started:            06/22/2012                               Time Passed:           117 % (      117 %)


 20967(04)     Contract: 110418       SH-48   Residency:     03100        .775 MI. SH-48 OVER CLEAR BOGGY
 BRFY-115C(026)                               ADA                         CREEK, 9 MI. NORTH OF JOHNSTON
                                                                          COUNTY LINE.
 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $4,077,515.62     (      $4,077,515.62)
 Contract Time:           180               (  215 )
 Letting Date:            09/15/2011
 Contract Date:           10/12/2011
 W/O Issued:              10/19/2011                                                              Adjusted:
 W/O Effective:           02/06/2012                               Amount Paid:            95  %(        95 %)
 Work Started:            11/15/2011                               Time Passed:           133  %(       112 %)




                                             Construction Status Report                            Page 69
County:          Comanche                                     Commissioner District:                                  7
Contracts Under Construction


 21614(04)     Contract: 120156       CORD     Residency:       07100           5.356 MI. CO.RD.:GRADE,DRAIN &
 STP-116C(110)CI                               DUNCAN                           SURFACE:FROM SH-115, EXTEND EAST.

 Contractor:   APAC-CENTRAL, INC.
 Engineer:     Harwell, Jerry M.              Adjusted:
 Contract Amount:         $5,233,521.39      (      $5,233,521.39)
 Contract Time:           165                (  165 )
 Letting Date:            04/19/2012
 Contract Date:           05/16/2012
 W/O Issued:              05/18/2012                                                                 Adjusted:
 W/O Effective:           08/06/2012                                      Amount Paid:           11 %(     11 %)
 Work Started:            07/09/2012                                      Time Passed:           23 %(     23 %)


 20955(04)     Contract: 110478      SH65      Residency:       07300           .570 MI. SH-65:GRADE,DRAIN,SURFACE
 BRFY-116C(095)                                ANADARKO                         AND BRIDGE; OVER WHISKEY CREEK, 2.4
                                                                                MI. SOUTH OF SH-17
 Contractor:   D. M. DOZERS, INC.
 Engineer:     Knight, Reese                  Adjusted:
 Contract Amount:        $2,393,655.43       (      $2,396,405.43)
 Contract Time:          180                 (  180 )
 Letting Date:           10/20/2011
 Contract Date:          11/21/2011
 W/O Issued:             11/28/2011                                                                   Adjusted:
 W/O Effective:          03/05/2012                                       Amount Paid:           51 % (     51 %)
 Work Started:           03/05/2012                                       Time Passed:           69 % (     69 %)


 20313(04)     Contract: 090497      I-44      Residency:       07100           2.545 MI. GRADE, DRAIN, SURFACE &
 IM-STIM(296)                                  DUNCAN                           BRIDGE I-44 FROM 1.6 MI. N. OF SH-7
                                                                                EXTEND NORTH.
 Contractor:   ALLEN CONTRACTING, INC.
 Engineer:     Harwell, Jerry M.              Adjusted:
 Contract Amount:         $15,797,093.11     (     $16,230,834.98)
 Contract Time:           360                (  888 )
 Letting Date:            06/18/2009
 Contract Date:           06/30/2009
 W/O Issued:              07/22/2009                                                                 Adjusted:
 W/O Effective:           08/24/2009                                      Amount Paid:          97 %(      95 %)
 Work Started:            08/24/2009                                      Time Passed:         248 % (    100 %)


 20298(04)     Contract: 090616       SH-7   Residency:     07100        3.26 MI. SH-7:GRADE,DRAIN,
 SAP-021N(029)                               DUNCAN                      SURFACE. BEGIN 3.3 MI. EAST OFIS-44,
                                                                         EXTEND EAST.
 Contractor:   DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
 Engineer:     Harwell, Jerry M.            Adjusted:
 Contract Amount:         $6,516,287.53    (      $6,701,884.15)
 Contract Time:           200              (  937 )
 Letting Date:            10/15/2009
 Contract Date:           11/13/2009
 W/O Issued:              11/16/2009                                                             Adjusted:
 W/O Effective:           03/01/2010                              Amount Paid:           100 %(          97 %)
 Work Started:            01/19/2010                              Time Passed:           264 %(          56 %)




                                             Construction Status Report                                    Page 70
28006(04)     Contract: 120172      US-62      Residency:      07100           0.00 MI. US-62:BRIDGE REPAIR :OVER
SAP-216A(005)                                  DUNCAN                          COUNTY RD. NS-247, 3.0 MI. EAST OF
                                                                               SH-115.
Contractor:   B & B CONSTRUCTION SERVICE    J.T., INC.
Engineer:     Harwell, Jerry M.              Adjusted:
Contract Amount:         $79,568.20         (            $79,568.20)
Contract Time:           15                 (     15   )
Letting Date:            04/19/2012
Contract Date:           05/18/2012
W/O Issued:              05/23/2012                                                               Adjusted:
W/O Effective:           06/18/2012                                      Amount Paid:           0%(      0 %)
Work Started:                                                            Time Passed:           0%(      0 %)


21716(04)     Contract: 120157      SH-115   Residency:     07300        1.283 MI. SH-115:GRADE,DRAIN,
SSP-116C(114)(195)SS                         ANADARKO                    SURFACE & BRIDGE:FROM EW-154,
                                                                         EXTEND NORTH IN MEERS.
Contractor:   T & G CONSTRUCTION, INC.
Engineer:     Knight, Reese                 Adjusted:
Contract Amount:        $2,839,916.88      (      $2,839,916.88)
Contract Time:          175                (  175 )
Letting Date:           04/19/2012
Contract Date:          05/21/2012
W/O Issued:             05/29/2012                                                              Adjusted:
W/O Effective:          08/16/2012                                Amount Paid:             0%(         0 %)
Work Started:           08/16/2012                                Time Passed:             0%(         0 %)


26850(04)     Contract: 110513      CORD   Residency:     07300        0.189 MI. CO.RD.;BRIDGE &
BRO-116D(182)CI                            ANADARKO                    APPROACHES:OVER WHISKEY CR., 1.8
                                                                       MI. E. OF IS-44.
Contractor:   BRIDGECO CONTRACTORS, INC.
Engineer:     Knight, Reese               Adjusted:
Contract Amount:        $358,418.20      (        $363,281.20)
Contract Time:          90               (   90   )
Letting Date:           11/17/2011
Contract Date:          12/16/2011
W/O Issued:             12/20/2011                                                             Adjusted:
W/O Effective:          03/05/2012                              Amount Paid:            101 %(      100 %)
Work Started:           02/07/2012                              Time Passed:             98 %(       98 %)


21715(04)     Contract: 110419      SH-17   Residency:     07300        .19 MI. SH-17 OVER COTTONWOOD
BRFY-116C(111)                              ANADARKO                    CREEK, .2 MI WEST OF GRADY CO.LINE.

Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
Engineer:     Knight, Reese                Adjusted:
Contract Amount:        $1,446,556.49     (      $1,449,616.49)
Contract Time:          210               (  210 )
Letting Date:           09/15/2011
Contract Date:          10/12/2011
W/O Issued:             10/17/2011                                                             Adjusted:
W/O Effective:          02/06/2012                               Amount Paid:            67  %(        67 %)
Work Started:           02/09/2012                               Time Passed:            72  %(        72 %)




                                            Construction Status Report                                   Page 71
28128(42)     Contract: 120175     IS-44       Residency:       07004           44.90 MI. IS-44/US-62/SH-7:   US-62
BTOP-216N(001)                                                            FROM
                                               JACOBS (AKA - CARTER-BURGESS) 9.0 MI. W. OF IS-44EXT E. TO
                                                                                IS-44, S. TO SH-7, THEN E. TO DUNCAN.
Contractor:   ROHL NETWORKS, LP
Engineer:     JACOBS (AKA - C-B)              Adjusted:
Contract Amount:       $1,713,132.83         (      $1,713,132.83)
Contract Time:         95                    (   95   )
Letting Date:          03/15/2012
Contract Date:         04/10/2012
W/O Issued:            05/14/2012                                                                     Adjusted:
W/O Effective:         06/04/2012                                         Amount Paid:           60 % (     60 %)
Work Started:          06/11/2012                                         Time Passed:           77 % (     77 %)


27330(04)     Contract: 110007       SH-65     Residency:       07100           0.191 MI. SH-65:BRIDGE REHAB. OVER
SBR-116C(190)SB                                DUNCAN                           THE WEST FORK OF BEAVER CR., 4.2 MI.
                                                                                N. OF N. OF THE SH-7 JUNCTION.
Contractor:   PBX CORPORATION
Engineer:     Harwell, Jerry M.               Adjusted:
Contract Amount:         $749,504.60         (        $749,504.60)
Contract Time:           120                 (  247 )
Letting Date:            01/20/2011
Contract Date:           02/16/2011
W/O Issued:              02/22/2011                                                                   Adjusted:
W/O Effective:           06/06/2011                                       Amount Paid:           91 % (     91 %)
Work Started:            07/08/2011                                       Time Passed:          200 % (     97 %)


20298(07)     Contract: 110237       SH-7   Residency:     07100        2.88 MI. SH-7:GRADE,DRAIN  &
NHY-021N(051)                               DUNCAN                      SURFACE;FROM 2.88 MI. WEST OF THE
                                                                        SH-65 JCT, EXTEND    EAST.
Contractor:   SHERWOOD CONSTRUCTION CO., INC.
Engineer:     Harwell, Jerry M.            Adjusted:
Contract Amount:         $5,893,347.18    (      $5,893,347.18)
Contract Time:           210              (  210 )
Letting Date:            04/14/2011
Contract Date:           05/12/2011
W/O Issued:              05/19/2011                                                            Adjusted:
W/O Effective:           09/06/2011                              Amount Paid:            96 %(        96 %)
Work Started:            09/06/2011                              Time Passed:           139 %(       139 %)


21717(08)     Contract: 120180     US-277   Residency:      07300        0.00 MI. US-277:RIGHT-OF-WAY
STPY-216C(006)RW                            ANADARKO                     CLEARANCE:BEGIN 0.04 MI. EAST OF
                                                                         US-62, EXTEND EAST.
Contractor:   M & M WRECKING, INC.
Engineer:     Knight, Reese                Adjusted:
Contract Amount:        $68,058.00        (          $68,058.00)
Contract Time:          180               (  180   )
Letting Date:           05/17/2012
Contract Date:          06/19/2012
W/O Issued:             07/13/2012                                                               Adjusted:
W/O Effective:          08/06/2012                                Amount Paid:              0 %(          0 %)
Work Started:                                                     Time Passed:              0 %(          0 %)




                                             Construction Status Report                                       Page 72
 28964(04)     Contract: 120131       US-62     Residency:       07100           25.00 MI. US-62:SIGNING;BEGIN AT THE
 HSIPG-116A(210)TR                              DUNCAN                           KIOWA C/L, EXTEND EAST.

 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $237,264.98         (        $237,264.98)
 Contract Time:           90                  (   90   )
 Letting Date:            03/15/2012
 Contract Date:           04/13/2012
 W/O Issued:              04/18/2012                                                                 Adjusted:
 W/O Effective:           07/17/2012                                       Amount Paid:            0%(      0 %)
 Work Started:            08/01/2012                                       Time Passed:            0%(      0 %)


 27054(04)     Contract: 100515       IS-44   Residency:     07100        2.547 MI. IS-44;PAVEMENT RE- HAB.
 SSP-116N(187)SS                              DUNCAN                      (P.C. CONCRETE)FROM 1.0 MISOUTH OF
                                                                          THE SH-7 EAST JCT, EXTEND NORTH.
 Contractor:   CHESTER BROSS CONSTRUCTION COMPANY/C.B. EQUIPMENT, INC.
 Engineer:     Harwell, Jerry M.             Adjusted:
 Contract Amount:         $4,736,418.47     (      $4,736,418.47)
 Contract Time:           180               (  180 )
 Letting Date:            04/14/2011
 Contract Date:           05/18/2011
 W/O Issued:              05/31/2011                                                             Adjusted:
 W/O Effective:           09/06/2011                               Amount Paid:             90 % (       90 %)
 Work Started:            07/20/2011                               Time Passed:            134 % (      134 %)


 20956(04)     Contract: 120013      SH-17      Residency:       07300           0.813 MI. SH-17;BRIDGE &
 BRFY-116C(098)                                 ANADARKO                         APPROACHES;OVER BEAVER CR. &
                                                                                 ATRIBUTARY OF BEAVER CR.,  1.1 MI.
 Contractor:   T & G CONSTRUCTION, INC.                                          E. OF SH-65 , STERLING
 Engineer:     Knight, Reese                   Adjusted:
 Contract Amount:        $3,898,376.63        (      $3,898,376.63)
 Contract Time:          210                  (  210 )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/27/2012                                                                  Adjusted:
 W/O Effective:          06/04/2012                                        Amount Paid:          19 %(     19 %)
 Work Started:           05/31/2012                                        Time Passed:          34 %(     34 %)


 27454(04)     Contract: 100431       IS-44     Residency:       07100           0.00 MI. IS-44;SIGNING/FROM THE
 IMG-44-1(116)030TR                             DUNCAN                           SH-36 JUNCTION, EXTEND NORTH.

 Contractor:   TIME STRIPING, INC.
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $381,248.95         (        $406,522.28)
 Contract Time:           120                 (  311   )
 Letting Date:            07/22/2010
 Contract Date:           08/25/2010
 W/O Issued:              10/19/2010                                                                 Adjusted:
 W/O Effective:           01/17/2011                                       Amount Paid:          66 %(     62 %)
 Work Started:            05/03/2011                                       Time Passed:         252 %(     97 %)




County:          Cotton                                        Commissioner District:                                   7
Contracts Under Construction




                                              Construction Status Report                                   Page 73
 23229(04)     Contract: 100552       SH-53     Residency:       07100           1.53 MI. SH-53/GRADE,DRAIN, SURFACE
 BRFY-117B(046)SS                               DUNCAN                           & BRIDGE:OVER BEAVER CR.,
                                                                                 OVERFLOW & LITTLE BEAVER
 Contractor:   SEWELL BROS., INC.                                                CR.,OVERFLOW,8.7 MI. & 9.1 MI.
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $6,858,838.76       (      $6,858,838.76)
 Contract Time:           360                 (  360 )
 Letting Date:            08/18/2011
 Contract Date:           09/26/2011
 W/O Issued:              09/29/2011                                                                  Adjusted:
 W/O Effective:           01/02/2012                                       Amount Paid:          75 % (     75 %)
 Work Started:            11/14/2011                                       Time Passed:          68 % (     68 %)
 EAST OF THE SH-5 JCT.

 27486(04)     Contract: 110465       CORD   Residency:     07100        .134 MI. CORD (NS-157) OVER BIRD
 BRO-117D(087)CI                             DUNCAN                      CREEK, 1.7 MI. SOUTH OF US-70 JCT.

 Contractor:   KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:     Harwell, Jerry M.            Adjusted:
 Contract Amount:         $200,189.74      (        $200,189.74)
 Contract Time:           90               (   90   )
 Letting Date:            09/15/2011
 Contract Date:           10/17/2011
 W/O Issued:              10/20/2011                                                             Adjusted:
 W/O Effective:           11/28/2011                              Amount Paid:            84 % (         84 %)
 Work Started:            11/14/2011                              Time Passed:           151 % (        151 %)




County:          Craig                                         Commissioner District:                                  8
Contracts Under Construction


 23910(04)     Contract: 110266     CTST        Residency:       08001           .372 MI. CTST:GRADE,DRAIN & SURFACE
 STP-118C(074)UR                                ENGR. SERV. & TESTING            EXCELSIOR AVE FROM US-60TO 4TH
                                                                                 STREET IN VINITA
 Contractor:   APAC-CENTRAL, INC.
 Engineer:     EST                             Adjusted:
 Contract Amount:       $755,297.46           (        $755,297.46)
 Contract Time:         180                   (  180   )
 Letting Date:          10/20/2011
 Contract Date:         11/21/2011
 W/O Issued:            02/17/2012                                                                    Adjusted:
 W/O Effective:         03/05/2012                                         Amount Paid:          97 %(      97 %)
 Work Started:          03/05/2012                                         Time Passed:          56 % (     56 %)


 24183(04)     Contract: 110420      SH66       Residency:       08300           5.62 MI. SH-66:WIDEN AND RESURFACE;
 STPY-118C(096)SS                               CLAREMORE                        1.25 MI. E OF ROGERS CO.LINE EXTEND
                                                                                 NORTHEAST.
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Bray, Timothy                   Adjusted:
 Contract Amount:        $7,425,911.85        (      $7,425,911.85)
 Contract Time:          270                  (  270 )
 Letting Date:           10/20/2011
 Contract Date:          11/17/2011
 W/O Issued:             02/03/2012                                                                  Adjusted:
 W/O Effective:          03/05/2012                                        Amount Paid:          20 %(     20 %)
 Work Started:           03/05/2012                                        Time Passed:          53 %(     53 %)




                                              Construction Status Report                                   Page 74
 24220(04)     Contract: 110421      US-60     Residency:       08300           .2 MI. US-60 OVER BIG CABIN CREEK,
 BRFY-018N(050)                                CLAREMORE                        3.7 MI. EAST OF SH-66 JCT

 Contractor:   B & B BRIDGE COMPANY, LLC
 Engineer:     Bray, Timothy                  Adjusted:
 Contract Amount:        $3,181,543.16       (      $3,230,885.09)
 Contract Time:          180                 (  196 )
 Letting Date:           09/15/2011
 Contract Date:          10/14/2011
 W/O Issued:             11/10/2011                                                                   Adjusted:
 W/O Effective:          12/19/2011                                       Amount Paid:           76 % (     75 %)
 Work Started:           12/09/2011                                       Time Passed:           89 % (     82 %)


 29089(04)     Contract: 120088      SH-25     Residency:       08300           *STPY-258C(002)3P/SH-25;RE-
 STPY-218C(004)(005)3P*                        CLAREMORE                        SURFACE(ASPHALT)FROM SH-2 EX- TEND
                                                                                EAST.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     Bray, Timothy                  Adjusted:
 Contract Amount:        $2,371,387.22       (      $2,371,387.22)
 Contract Time:          100                 (  100 )
 Letting Date:           02/16/2012
 Contract Date:          03/19/2012
 W/O Issued:             06/06/2012                                                                 Adjusted:
 W/O Effective:          07/02/2012                                       Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)


 29092(04)     Contract: 120090      US-60     Residency:       08300           5.72 MI. US-60;RESURFACE
 NHY-018N(068)3P                               CLAREMORE                        (ASPHALT)FROM 6.1 MI. EAST OF THE
                                                                                NOWATA C/L, EXTEND EAST.
 Contractor:   APAC-CENTRAL, INC.
 Engineer:     Bray, Timothy                  Adjusted:
 Contract Amount:        $961,840.42         (        $961,840.42)
 Contract Time:          45                  (   45   )
 Letting Date:           02/16/2012
 Contract Date:          03/13/2012
 W/O Issued:             03/21/2012                                                                  Adjusted:
 W/O Effective:          07/02/2012                                       Amount Paid:           97 %(     97 %)
 Work Started:           05/03/2012                                       Time Passed:           51 %(     51 %)




County:          Creek                                        Commissioner District:                                 8
Contracts Under Construction


 25562(04)     Contract: 100483      SH-66     Residency:       08400           1.471 MI. SH-66;BRIDGE &
 BRFY-119C(176)                                SAND SPRINGS                     APPROACHES;OVER IS-44 (TURNER
                                                                                TURNPIKE).
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Williams, Mark J.              Adjusted:
 Contract Amount:        $8,215,224.30       (      $8,368,224.30)
 Contract Time:          280                 (  549 )
 Letting Date:           08/19/2010
 Contract Date:          09/23/2010
 W/O Issued:             11/03/2010                                                                 Adjusted:
 W/O Effective:          01/03/2011                                       Amount Paid:          86 %(     85 %)
 Work Started:           01/03/2011                                       Time Passed:         211 %(    108 %)




                                             Construction Status Report                                    Page 75
20890(04)     Contract: 110377      SH-16   Residency:     08400        0.099 MI. SH-16/BRIDGE &
BRFY-119C(102)                              SAND SPRINGS                APPROACHES/OVER ROCK CR., 2.2 MI.
                                                                        EAST OF THE SH-48 JCT.
Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
Engineer:     Williams, Mark J.            Adjusted:
Contract Amount:        $955,789.64       (        $973,822.64)
Contract Time:          120               (  127 )
Letting Date:           08/18/2011
Contract Date:          09/26/2011
W/O Issued:             09/28/2011                                                              Adjusted:
W/O Effective:          11/07/2011                               Amount Paid:            94 % (       93 %)
Work Started:           11/02/2011                               Time Passed:           121 % (      114 %)


29059(04)     Contract: 120037      SH-33     Residency:       08400           1.78 MI. SH-33/SH-99B;PAVE -MENT
SSR-219B(002)SR                               SAND SPRINGS                     REHAB(AC & PC)BEGIN AT THE PAYNE
                                                                               CL, EXTEND EAST. BEGIN AT
Contractor:   BECCO CONTRACTORS, INC.                                          SH-33,EXTEND NORTH.
Engineer:     Williams, Mark J.              Adjusted:
Contract Amount:        $1,245,046.00       (      $1,248,113.68)
Contract Time:          90                  (   92   )
Letting Date:           01/19/2012
Contract Date:          02/21/2012
W/O Issued:             02/27/2012                                                                  Adjusted:
W/O Effective:          06/04/2012                                       Amount Paid:          68 % (     68 %)
Work Started:           06/04/2012                                       Time Passed:          80 % (     78 %)


29093(04)     Contract: 120091      SH-99     Residency:       08400           1.07 MI. SH-99;RESURFACE  (P.C.
STPY-219B(004)3P                              SAND SPRINGS                     CONCRETE)FROM THE SH-99BJUNCTION,
                                                                               EXTEND NORTH.
Contractor:   DIAMOND SURFACE, INC.
Engineer:     Williams, Mark J.              Adjusted:
Contract Amount:        $547,841.97         (        $547,841.97)
Contract Time:          30                  (   30   )
Letting Date:           02/16/2012
Contract Date:          03/15/2012
W/O Issued:             03/29/2012                                                                 Adjusted:
W/O Effective:          06/04/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                            Time Passed:           0 %(      0 %)


22750(04)     Contract: 120181      CORD      Residency:       08400           0.283 MI. CO.RD. BRIDGE &
BRO-119D(129)CO                               SAND SPRINGS                     APPROACHES:OVER LAGOON CR. 2.0MI.
                                                                               N. & 1.0 MI. W. OF THE SH-51/SH-99
Contractor:   BELK BRIDGE, INC.                                                JCT.
Engineer:     Williams, Mark J.              Adjusted:
Contract Amount:        $620,757.75         (        $620,757.75)
Contract Time:          120                 (  120   )
Letting Date:           05/17/2012
Contract Date:          06/15/2012
W/O Issued:             06/20/2012                                                                 Adjusted:
W/O Effective:          09/04/2012                                       Amount Paid:          15 %(     15 %)
Work Started:           07/10/2012                                       Time Passed:          31 %(     31 %)




                                            Construction Status Report                                   Page 76
 20891(04)     Contract: 100432      SH-16   Residency:     08400         0.274 MI. SH-16;BRIDGE &
 BRFY-119C(105)                              SAND SPRINGS                 APPROACHES;OVER TURKEY CR., 11.2
                                                                          MI. EAST OF THE SH-48 JCT.
 Contractor:   PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:     Williams, Mark J.            Adjusted:
 Contract Amount:        $1,294,356.43     (      $1,294,356.43)
 Contract Time:          120               (  521 )
 Letting Date:           07/22/2010
 Contract Date:          08/17/2010
 W/O Issued:             08/18/2010                                                               Adjusted:
 W/O Effective:          10/05/2010                               Amount Paid:             97 % (       97 %)
 Work Started:           09/27/2010                               Time Passed:            472 % (      109 %)




County:          Custer                                       Commissioner District:                                5
Contracts Under Construction


 24426(04)     Contract: 120158     SH-47      Residency:       05100           0.00 MI. SH-47;WATERPROOF
 BRFY-220C(006)                                CLINTON                          SEAL/IS-40/SH-6/SH-34/SH-54/
                                                                                SH-55/SH-152. AT VARIOUS
 Contractor:   GARY A. CRAIN, INC.                                              LOCATIONS IN DIV. V
 Engineer:     Greer, Randy                   Adjusted:
 Contract Amount:        $68,343.25          (          $68,343.25)
 Contract Time:          45                  (   45   )
 Letting Date:           04/19/2012
 Contract Date:          05/21/2012
 W/O Issued:             05/24/2012                                                                Adjusted:
 W/O Effective:          08/06/2012                                       Amount Paid:           0%(      0 %)
 Work Started:           08/23/2012                                       Time Passed:           0%(      0 %)


 20804(04)     Contract: 100361      SH-54     Residency:       05100           1.062 MI. SH-54;BRIDGE &
 BRFY-120C(086)(089)                           CLINTON                          APPROACHES;OVER DEER & HORSE CR.,
                                                                                8.2 MI. & 6.8 MI. N. OF THE IS-40
 Contractor:   SEWELL BROS., INC.                                               JUNCTION.
 Engineer:     Greer, Randy                   Adjusted:
 Contract Amount:        $4,275,740.07       (      $4,275,740.07)
 Contract Time:          300                 (  429 )
 Letting Date:           05/20/2010
 Contract Date:          06/23/2010
 W/O Issued:             07/01/2010                                                                  Adjusted:
 W/O Effective:          10/04/2010                                       Amount Paid:          94 %(      94 %)
 Work Started:           10/04/2010                                       Time Passed:         141 % (     99 %)


 28133(04)     Contract: 110287      SH-33     Residency:       05100           9.36 MI. SH-33;RESURFACE
 SSR-120B(194)(195)SR                          CLINTON                          (ASPHALT)BEGIN 4.5 MI. EAST OFTHE
                                                                                US-183 JCT, EXTEND EAST.
 Contractor:   CASWELL CONTRACTING, INC.
 Engineer:     Greer, Randy                   Adjusted:
 Contract Amount:        $1,538,943.16       (      $1,538,943.16)
 Contract Time:          75                  (   75   )
 Letting Date:           01/19/2012
 Contract Date:          02/22/2012
 W/O Issued:             02/28/2012                                                                 Adjusted:
 W/O Effective:          05/02/2012                                       Amount Paid:         100 %(    100 %)
 Work Started:           06/13/2012                                       Time Passed:          92 %(     92 %)




                                             Construction Status Report                                   Page 77
09278(04)     Contract: 120092      US-183   Residency:     05100        3.41 MI. US-183;GRADE,DRAIN, &
NHY-009N(019)SS                              CLINTON                     SURFACE;FROM THE WASHITA RIVER,
                                                                         EXTEND NORTH.
Contractor:   CORNELL CONSTRUCTION COMPANY, INC.
Engineer:     Greer, Randy                  Adjusted:
Contract Amount:        $7,762,288.72      (      $7,762,288.72)
Contract Time:          210                (  210 )
Letting Date:           02/16/2012
Contract Date:          03/22/2012
W/O Issued:             03/26/2012                                                              Adjusted:
W/O Effective:          07/02/2012                                Amount Paid:             0%(          0 %)
Work Started:                                                     Time Passed:             0%(          0 %)


29154(04)     Contract: 120116      SH-34     Residency:       05100           6.00 MI. SH-34;RESURFACE
STPY-220B(004)3P                              CLINTON                          (ASPHALT)FROM 1.2 MI. NORTH OFSH-33,
                                                                               EXTEND NORTH.
Contractor:   CASWELL CONTRACTING, INC.
Engineer:     Greer, Randy                   Adjusted:
Contract Amount:        $1,369,086.65       (      $1,369,086.65)
Contract Time:          45                  (   45   )
Letting Date:           02/16/2012
Contract Date:          03/19/2012
W/O Issued:             03/21/2012                                                                 Adjusted:
W/O Effective:          07/02/2012                                       Amount Paid:            0%(      0 %)
Work Started:           08/20/2012                                       Time Passed:            0%(      0 %)


24670(04)     Contract: 110466      CORD      Residency:       05005           .199 MI. CO.RD. (EW-89) OVER DEER
BRO-120D(153)CI                               CIRCUIT ENGR. DISTR. # 7         CREEK, 3.2 MI. W OF SH-33 JCT.

Contractor:   K & R BUILDERS, INC.
Engineer:     CED7                           Adjusted:
Contract Amount:        $565,376.10         (        $565,376.10)
Contract Time:          120                 (  120   )
Letting Date:           09/15/2011
Contract Date:          10/12/2011
W/O Issued:             10/14/2011                                                                 Adjusted:
W/O Effective:          02/06/2012                                       Amount Paid:          96 %(     96 %)
Work Started:           01/23/2012                                       Time Passed:         106 %(    106 %)


28904(04)     Contract: 120206      I-40      Residency:       05100           0.00 MI. I-40:BRIDGE REPAIR/
BHFY-220N(012)                                CLINTON                          EASTBOUND OFF RAMP AT MILE     POST
                                                                               65 IN CLINTON.
Contractor:   PBX CORPORATION
Engineer:     Greer, Randy                   Adjusted:
Contract Amount:        $253,807.50         (        $253,807.50)
Contract Time:          45                  (   45   )
Letting Date:           05/17/2012
Contract Date:          06/15/2012
W/O Issued:             06/20/2012                                                                  Adjusted:
W/O Effective:          10/01/2012                                       Amount Paid:            0 %(      0 %)
Work Started:                                                            Time Passed:            0 %(      0 %)




                                            Construction Status Report                                    Page 78
 28128(26)     Contract: 120060     US-183   Residency:     05003        47.08 MI. US-183;SAFETY IM-
 BTOP-220N(002)                              COBB ENGINEERING CO., INC. PROVEMENTS(FIBER OPTIC CABLE) FROM
                                                                         THE CITY OF CLINTON TO THE CITY OF
 Contractor:   HENKELS & MCCOY, INC.                                     SEILING.
 Engineer:     COBB                         Adjusted:
 Contract Amount:       $1,335,179.44      (      $1,335,179.44)
 Contract Time:         135                (  135 )
 Letting Date:          01/19/2012
 Contract Date:         02/21/2012
 W/O Issued:            02/24/2012                                                               Adjusted:
 W/O Effective:         03/26/2012                                Amount Paid:           100 % (      100 %)
 Work Started:          03/20/2012                                Time Passed:            87 % (       87 %)




County:         Delaware                                     Commissioner District:                                  8
Contracts Under Construction


 28320(04)     Contract: 120208     CORD      Residency:       08001           2.42 MI. CO.RD.:RESURFACE
 STP-121C(152)CO                              ENGR. SERV. & TESTING            (ASPHALT)(OLD SH-33/E580)BE- GIN AT
                                                                               US-412 EXTEND EAST.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     EST                          Adjusted:
 Contract Amount:       $498,118.77        (        $498,118.77)
 Contract Time:                            (        )
 Letting Date:          06/21/2012
 Contract Date:         07/17/2012                                       Fixed Completion Date: 10/31/2012
 W/O Issued:            07/18/2012                                                                Adjusted:
 W/O Effective:                                                          Amount Paid:         0%(        0 %)
 Work Started:                                                           Time Passed:         0%(        0 %)


 20622(05)     Contract: 110515     CORD      Residency:       08002           0.568 MI.CO.RD. BRIDGE &
 CIRB-121C(109)RB                             TETRA TECH                       APPROACHES:OVER SPAVINAW CR., 4.6
                                                                               MI. N. & 3.9 MI. W.  OF COLCORD.
 Contractor:   A. M. COHRON & SON, INC.
 Engineer:     TETR                         Adjusted:
 Contract Amount:       $1,328,040.72      (      $1,328,040.72)
 Contract Time:         210                (  210 )
 Letting Date:          11/17/2011
 Contract Date:         12/15/2011
 W/O Issued:            01/23/2012                                                                  Adjusted:
 W/O Effective:         03/05/2012                                       Amount Paid:          79 %(      79 %)
 Work Started:          03/05/2012                                       Time Passed:          74 % (     74 %)


 25901(04)     Contract: 120251     CORD      Residency:       08001           0.25 MI. CO.RD.;BRIDGE &
 BRF-121C(122)CI                              ENGR. SERV. & TESTING            APPROACHES/OVER CARR CR. 1.0 MI.N.
                                                                               & 3.0 MI. E. OF SH-10 /SH-25 JCT.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     EST                          Adjusted:
 Contract Amount:       $565,597.19        (        $565,597.19)
 Contract Time:         90                 (   90   )
 Letting Date:          07/19/2012
 Contract Date:         08/21/2012
 W/O Issued:            08/24/2012                                                                 Adjusted:
 W/O Effective:         11/05/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                           Time Passed:           0 %(      0 %)




                                            Construction Status Report                                   Page 79
County:          Dewey                                        Commissioner District:                               5
Contracts Under Construction


 28128(13)     Contract: 110500     I-40      Residency:    04011        0.00 MI. I-35/I-40/US-60/US-270/US-412
 BTOP-109E(191)                               GARVER, LLC.               AT VARIOUS LOCATIONS IN DIVISION
                                                                         4,5 & 6.
 Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:     GARV                         Adjusted:
 Contract Amount:       $967,763.44        (        $967,763.44)
 Contract Time:         150               (    150  )
 Letting Date:          09/15/2011
 Contract Date:         10/17/2011
 W/O Issued:            10/22/2011                                                                Adjusted:
 W/O Effective:         11/21/2011                                Amount Paid:              96 %(         96 %)
 Work Started:          01/25/2012                                Time Passed:            114  %(        114 %)


 28128(36)     Contract: 120061     US-270   Residency:     05003        35.20 MI. US-270;SAFETY IM-
 BTOP-222N(001)                              COBB ENGINEERING CO., INC. PROVEMENTS(FIBER OPTIC CABLE) FROM
                                                                         THE CITY OF WOODWARD TO THE CITY
 Contractor:   HENKELS & MCCOY, INC.                                     OF SEILING.
 Engineer:     COBB                         Adjusted:
 Contract Amount:       $1,090,231.56      (      $1,090,231.56)
 Contract Time:         95                 (   95   )
 Letting Date:          01/19/2012
 Contract Date:         02/21/2012
 W/O Issued:            02/24/2012                                                               Adjusted:
 W/O Effective:         03/26/2012                                Amount Paid:           100 % (      100 %)
 Work Started:          03/26/2012                                Time Passed:            84 % (       84 %)




County:          Ellis                                        Commissioner District:                               6
Contracts Under Construction


 26248(04)     Contract: 110473     CORD   Residency:      06009                4.50 MI. CO.RD. RESURFACE
 STP-123C(069)CI                           CIRCUIT ENGR. DISTR.           #8    (ASPHALT)FROM 5.0 MI. SOUTH
                                                                                OFSH-15,EXTEND NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     CED8                       Adjusted:
 Contract Amount:       $1,318,680.02    (       $1,399,218.45)
 Contract Time:                          (        )
 Letting Date:          08/18/2011
 Contract Date:         09/20/2011                                        Fixed Completion Date: 10/31/2011
 W/O Issued:            09/22/2011                                                                 Adjusted:
 W/O Effective:                                                           Amount Paid:       105 %(      99 %)
 Work Started:          10/03/2011                                        Time Passed:       159 % (     77 %)




                                             Construction Status Report                                  Page 80
 20942(04)     Contract: 090101     US-283   Residency:     06100        1.280 MI. US-283;BRIDGE &
 SSP-123B(030)SS                             BUFFALO                     APPROACHES/ OVER WOLF CREEK,
                                                                         NORTH OF SHATTUCK.
 Contractor:   SEWELL BROS., INC.
 Engineer:     Burke, David                 Adjusted:
 Contract Amount:       $6,597,222.13      (      $6,621,987.04)
 Contract Time:         255                (  499 )
 Letting Date:          02/19/2009
 Contract Date:         03/10/2009
 W/O Issued:            03/12/2009                                                               Adjusted:
 W/O Effective:         07/06/2009                                Amount Paid:           100 % (      100 %)
 Work Started:          04/24/2009                                Time Passed:           206 % (      105 %)


 24850(04)     Contract: 100517     US-60     Residency:       06100           0.00 MI. US-60;BRIDGE REPR. :OVER
 SBR-123B(059)SB                              BUFFALO                          RED BLUFF CR.,2.7 MI. E.OF TH US-283
                                                                               JUNCTION.
 Contractor:   PBX CORPORATION
 Engineer:     Burke, David                  Adjusted:
 Contract Amount:       $200,188.30         (        $200,188.30)
 Contract Time:         45                  (   50   )
 Letting Date:          09/16/2010
 Contract Date:         10/27/2010
 W/O Issued:            10/28/2010                                                                  Adjusted:
 W/O Effective:         02/07/2011                                       Amount Paid:         100 % (    100 %)
 Work Started:          02/07/2011                                       Time Passed:         118 % (    106 %)


 24339(04)     Contract: 110179     CORD      Residency:       06009           0.207 MI. CO.RD.:BRIDGE &
 BRF-123C(055)CI                              CIRCUIT ENGR. DISTR. # 8         APPROACHES/OVER A TRIBUTARY
                                                                               OFLONG CREEK, 5.75 MI. W. OF THE
 Contractor:   SEWELL BROS., INC.                                              US-283 JUNCTION.
 Engineer:     CED8                          Adjusted:
 Contract Amount:       $508,780.11         (        $556,882.46)
 Contract Time:         90                  (  142   )
 Letting Date:          03/17/2011
 Contract Date:         04/18/2011
 W/O Issued:            04/27/2011                                                                 Adjusted:
 W/O Effective:         07/05/2011                                       Amount Paid:         106 %(     96 %)
 Work Started:          06/13/2011                                       Time Passed:         173 %(    110 %)




County:         Garfield                                     Commissioner District:                                   4
Contracts Under Construction


 24867(04)     Contract: 110423      CORD   Residency:     04300        2.42 MI. CO.RD.;GRADE,DRAIN,
 CIRB-124C(111)RB                           ENID                        SURFACE & BRIDGE;FROM 6.0 MI. N. OF
                                                                        THE KINGFISHER C/L,   EXTEND NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Crowl, Kenny (Act.)         Adjusted:
 Contract Amount:        $1,676,860.73    (      $1,676,860.73)
 Contract Time:          135              (  135 )
 Letting Date:           11/17/2011
 Contract Date:          12/20/2011
 W/O Issued:             12/29/2011                                                            Adjusted:
 W/O Effective:          03/05/2012                              Amount Paid:            91 %(         91 %)
 Work Started:           03/13/2012                              Time Passed:           110 %(        110 %)




                                            Construction Status Report                                    Page 81
23300(04)     Contract: 120132      US-60     Residency:       04300           0.435 MI. US-60;GRADE,DRAIN,
BRFY-124A(083)                                ENID                             SURFACE & BRIDGE. OVER SOUTH-
                                                                               BOUND US-64, 3.8 MI. N. OF US-412.
Contractor:   ALLEN CONTRACTING, INC.
Engineer:     Crowl, Kenny (Act.)            Adjusted:
Contract Amount:        $2,675,669.70       (      $2,675,669.70)
Contract Time:          150                 (  150 )
Letting Date:           03/15/2012
Contract Date:          04/16/2012
W/O Issued:             04/18/2012                                                                Adjusted:
W/O Effective:          08/06/2012                                       Amount Paid:           4%(      4 %)
Work Started:           08/06/2012                                       Time Passed:           7%(      7 %)


28221(04)     Contract: 110289      US-81   Residency:     04300        0.92 MI. US-81;RESURFACE
SSR-124N(139)SR                             ENID                        (ASPHALT)FROM 1.0 MI. SOUTH
                                                                        OFUS-412, EXTEND NORTH.
Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
Engineer:     Crowl, Kenny (Act.)          Adjusted:
Contract Amount:        $679,606.00       (        $679,606.00)
Contract Time:          75                (   75   )
Letting Date:           01/19/2012
Contract Date:          02/21/2012
W/O Issued:             02/27/2012                                                             Adjusted:
W/O Effective:          04/02/2012                               Amount Paid:            88 % (      88 %)
Work Started:           03/25/2012                               Time Passed:            73 % (      73 %)


24867(07)     Contract: 120178      CORD   Residency:     04300        4.97 MI. CO.RD.:GRADE,DRAIN
CIRB-124C(112)RB                           ENID                        SURFACE & BRIDGE:FROM 7.5 MI. SOUTH
                                                                       OF US-64, EXTEND NORTH.
Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
Engineer:     Crowl, Kenny (Act.)         Adjusted:
Contract Amount:        $2,915,938.66    (      $2,915,938.66)
Contract Time:          90               (   90   )
Letting Date:           04/19/2012
Contract Date:          05/16/2012
W/O Issued:             05/18/2012                                                            Adjusted:
W/O Effective:          06/18/2012                              Amount Paid:            42 %(         42 %)
Work Started:           07/17/2012                              Time Passed:            66 %(         66 %)


29194(04)     Contract: 120126      SH-74   Residency:     04300        9.34 MI. SH-74:RESURFACE
STPY-224C(003)(004)3P                       ENID                        (ASPHALT)FROM THE LOGAN C/L,
                                                                        EXTEND NORTH.
Contractor:   HASKELL LEMON CONSTRUCTION CO.
Engineer:     Crowl, Kenny (Act.)          Adjusted:
Contract Amount:        $1,740,529.00     (      $1,740,529.00)
Contract Time:          60                (   60   )
Letting Date:           02/16/2012
Contract Date:          03/19/2012
W/O Issued:             03/21/2012                                                             Adjusted:
W/O Effective:          07/02/2012                               Amount Paid:            91 %(       91 %)
Work Started:           06/05/2012                               Time Passed:            80 %(       80 %)




                                            Construction Status Report                                   Page 82
 28128(39)     Contract: 120065      US-412   Residency:     04300        *(001)/ 65.80 MI. US-412;  SAFETY
 BTOP-224N(001)/BTOP-247N*                    ENID                        IMPROVEMENTS(FIBER      OPTIC
                                                                          CABLE)FROM THE CITY OF ORIENTA
 Contractor:   B & H CONSTRUCTION, INC                                    EAST TO IS-35.
 Engineer:     Crowl, Kenny (Act.)           Adjusted:
 Contract Amount:        $1,643,186.00      (      $1,652,986.00)
 Contract Time:          210                (  210 )
 Letting Date:           01/19/2012
 Contract Date:          02/13/2012
 W/O Issued:             02/15/2012                                                                Adjusted:
 W/O Effective:          03/12/2012                                Amount Paid:            100 % (      100 %)
 Work Started:           03/12/2012                                Time Passed:             68 % (        68 %)




County:          Garvin                                       Commissioner District:                                  3
Contracts Under Construction


 28175(04)     Contract: 110331      SH-74     Residency:       03200           0.112 MI. SH-74;BRIDGE RE-
 SBR-125C(197)SB                               PURCELL                          HAB.:OVER ROCK CREEK, 7.76 MI.NORTH
                                                                                OF THE CARTER C/L.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     Riemer, Caleb                  Adjusted:
 Contract Amount:        $585,584.77         (        $585,584.77)
 Contract Time:          120                 (  120 )
 Letting Date:           07/21/2011
 Contract Date:          08/09/2011
 W/O Issued:             08/18/2011                                                                 Adjusted:
 W/O Effective:          12/05/2011                                       Amount Paid:        100 % (    100 %)
 Work Started:           01/23/2012                                       Time Passed:        118 % (    118 %)


 26811(04)     Contract: 110467      CORD   Residency:     03200        .167 MI. CO. RD. (NS-318) OVER A
 BRO-125D(173)CI                            PURCELL                     TRIBUTARY OF RUSH CREEK, 4.0 MI.
                                                                        SOUTH OF SH-19 JCT.
 Contractor:   KLAVER CONSTRUCTION COMPANY, INC.
 Engineer:     Riemer, Caleb               Adjusted:
 Contract Amount:        $282,307.33      (        $297,781.47)
 Contract Time:          90               (   90   )
 Letting Date:           09/15/2011
 Contract Date:          10/17/2011
 W/O Issued:             10/20/2011                                                              Adjusted:
 W/O Effective:          01/02/2012                              Amount Paid:             99  %(         94 %)
 Work Started:           12/06/2011                              Time Passed:            159 % (        159 %)


 10444(04)     Contract: 110425      SH-74   Residency:     03200        .852 MI. SH-74 OVER RUSH CREEKAND
 BRFY-025C(274)                              PURCELL                     LIGHTNING CREEK, 8.0 MI. NOF SH-29
                                                                         JCT.
 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
 Engineer:     Riemer, Caleb                Adjusted:
 Contract Amount:        $4,396,629.34     (      $4,396,629.34)
 Contract Time:          300               (  300 )
 Letting Date:           09/15/2011
 Contract Date:          10/12/2011
 W/O Issued:             10/19/2011                                                             Adjusted:
 W/O Effective:          02/06/2012                               Amount Paid:            46  %(         46 %)
 Work Started:           02/06/2012                               Time Passed:            60  %(         60 %)




                                             Construction Status Report                                  Page 83
 27544(04)     Contract: 110290      SH-19   Residency:     03200        2.63 MI. SH-19:RESURFACE
 SSR-125C(188)SR                             PURCELL                     (ASPHALT)FROM 6.51 MI. EAST OFSH-74,
                                                                         EXTEND EAST.
 Contractor:   MARKWELL PAVING COMPANY, INC.
 Engineer:     Riemer, Caleb                Adjusted:
 Contract Amount:        $453,353.70       (        $453,353.70)
 Contract Time:          21                (   21   )
 Letting Date:           06/21/2012
 Contract Date:          07/18/2012
 W/O Issued:             07/20/2012                                                             Adjusted:
 W/O Effective:          08/13/2012                               Amount Paid:             0%(           0 %)
 Work Started:           08/14/2012                               Time Passed:             0%(           0 %)


 27134(04)     Contract: 100572      SH-74     Residency:       03200           0.00 MI. SH-74;BANK PROTEC
 SSP-125C(180)SS                               PURCELL                          -TION/RIPRAP:OVER WASHITA     RIVER,
                                                                                1.25 MI. N. OF THE  SH-19 JUNCTION.
 Contractor:   K & K CONTRACTING, INC.
 Engineer:     Riemer, Caleb                  Adjusted:
 Contract Amount:        $1,247,607.16       (      $1,433,721.96)
 Contract Time:          90                  (   90   )
 Letting Date:           11/18/2010
 Contract Date:          12/28/2010
 W/O Issued:             01/04/2011                                                                  Adjusted:
 W/O Effective:          04/04/2011                                       Amount Paid:         112 % (     97 %)
 Work Started:           04/04/2011                                       Time Passed:         170 % (    170 %)


 25980(04)     Contract: 120015      IS-35   Residency:     07200        3.33 MI. IS-35;RESURFACE(AS- PHALT)&
 IMY-0035-2(323)055 3P                       ARDMORE                     BRIDGE RPR. BEGIN 6.56MI. N. OF THE
                                                                         CARTER C/L, EXT.N. 3.3 MI.,& BRIDGE
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.                        REPR.
 Engineer:     Earp, Jay                    Adjusted:
 Contract Amount:        $3,095,260.14     (      $3,098,896.14)
 Contract Time:          90                (   90   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/24/2012                                                               Adjusted:
 W/O Effective:          03/26/2012                               Amount Paid:             96 %(          96 %)
 Work Started:           04/02/2012                               Time Passed:             94 %(          94 %)




County:          Grady                                        Commissioner District:                                   7
Contracts Under Construction


 20234(04)     Contract: 090044     SH-37      Residency:       07004        2.58 MI. SH-37;GRADE,DRAIN &
 STPY-126C(060)                                JACOBS (AKA -                 SURFACE;BEGIN 4.62 MI. E. OF
                                                                CARTER-BURGESS)
                                                                             US-81,EXTEND E. TO      GREGORY ST.
 Contractor:   OVERLAND CORPORATION
 Engineer:     JACOBS (AKA - C-B)             Adjusted:
 Contract Amount:       $4,939,237.40        (      $4,967,149.54)
 Contract Time:         300                  (  825 )
 Letting Date:          04/23/2009
 Contract Date:         05/13/2009
 W/O Issued:            05/15/2009                                                                  Adjusted:
 W/O Effective:         07/06/2009                                        Amount Paid:          97 %(     97 %)
 Work Started:          07/06/2009                                        Time Passed:         272 %(     99 %)




                                             Construction Status Report                                    Page 84
 26851(04)     Contract: 120239      CORD      Residency:       07300           0.34 MI. CO.RD.:BRIDGE &
 BRO-126D(176)CI                               ANADARKO                         APPROACHES:OVER SALT CR., 1.7 MI.
                                                                                NORTH & 2.0 MI. EAST    OF POCASSET.
 Contractor:   D. M. DOZERS, INC.
 Engineer:     Knight, Reese                  Adjusted:
 Contract Amount:        $514,292.70         (        $514,292.70)
 Contract Time:          90                  (   90   )
 Letting Date:           06/21/2012
 Contract Date:          07/17/2012
 W/O Issued:             07/18/2012                                                                Adjusted:
 W/O Effective:          10/01/2012                                       Amount Paid:           0%(      0 %)
 Work Started:           08/07/2012                                       Time Passed:           0%(      0 %)


 20960(04)     Contract: 110241      SH-37     Residency:       07300           0.558 MI. SH-37/BRIDGE &
 BRFY-126C(082)                                ANADARKO                         APPROACHES:OVER BUGGY CREEK, 0.6
                                                                                MI. EAST OF US-81.
 Contractor:   SEWELL BROS., INC.
 Engineer:     Knight, Reese                  Adjusted:
 Contract Amount:        $2,403,359.07       (      $2,403,359.07)
 Contract Time:          180                 (  180 )
 Letting Date:           04/19/2012
 Contract Date:          05/22/2012
 W/O Issued:             05/25/2012                                                                Adjusted:
 W/O Effective:          09/04/2012                                       Amount Paid:           0%(      0 %)
 Work Started:                                                            Time Passed:           0%(      0 %)




County:          Grant                                        Commissioner District:                                   4
Contracts Under Construction


 26420(04)     Contract: 110482      US60      Residency:       04300           .56 MI. US-60: GRADE,DRAIN,SURFACE
 BRFY-127B(152)SS                              ENID                             AND BRIDGE; OVER SALT FORK OF THE
                                                                                ARKANSAS RIVER, 1.0 MI. E OF US-81
 Contractor:   SEWELL BROS., INC.
 Engineer:     Crowl, Kenny (Act.)            Adjusted:
 Contract Amount:        $5,420,085.61       (      $5,420,085.61)
 Contract Time:          300                 (  300 )
 Letting Date:           10/20/2011
 Contract Date:          11/22/2011
 W/O Issued:             11/28/2011                                                                  Adjusted:
 W/O Effective:          03/05/2012                                       Amount Paid:          38 %(      38 %)
 Work Started:           03/05/2012                                       Time Passed:          55 % (     55 %)


 29242(04)     Contract: 120147      SH-132   Residency:     04300        12.760 MI. SH-132:RESURFACE
 STPY-227C(003)(004)3P                        ENID                        (ASPHALT) BEGIN AT SH-11 EX- TEND
                                                                          NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Crowl, Kenny (Act.)           Adjusted:
 Contract Amount:        $1,759,330.00      (      $1,759,330.00)
 Contract Time:                             (        )
 Letting Date:           05/17/2012
 Contract Date:          06/15/2012                                Fixed Completion Date: 10/31/2012
 W/O Issued:             06/20/2012                                                              Adjusted:
 W/O Effective:                                                    Amount Paid:              0 %(         0 %)
 Work Started:                                                     Time Passed:              0 %(         0 %)




                                             Construction Status Report                                   Page 85
County:          Greer                                        Commissioner District:                                5
Contracts Under Construction


 28128(14)     Contract: 110502     I-40      Residency:    05003        0.00 MI. I-40/SH-6/SH-9 AT VARIOUS
 BTOP-120E(201)                               COBB ENGINEERING CO., INC. LOCATIONS IN DIVISION 5.
 Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:     COBB                         Adjusted:
 Contract Amount:       $961,786.64        (        $961,786.64)
 Contract Time:         150               (    150  )
 Letting Date:          09/15/2011
 Contract Date:         10/17/2011
 W/O Issued:            10/22/2011                                                                Adjusted:
 W/O Effective:         11/21/2011                                Amount Paid:             94 %(          94 %)
 Work Started:          11/21/2011                                Time Passed:             90 %(          90 %)




County:          Harmon                                       Commissioner District:                                5
Contracts Under Construction


 28020(04)     Contract: 110516      CORD      Residency:       05005           0.161 MI. CO.RD. BRIDGE &
 BRO-129D(047)CI                               CIRCUIT ENGR. DISTR. # 7         APPROACHES;OVER TURKEY CR.,   6.5
                                                                                MI. N. OF THE US-62    JCT.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     CED7                          Adjusted:
 Contract Amount:        $279,104.42        (        $279,104.42)
 Contract Time:          90                 (  120 )
 Letting Date:           11/17/2011
 Contract Date:          12/20/2011
 W/O Issued:             12/29/2011                                                                 Adjusted:
 W/O Effective:          04/02/2012                                       Amount Paid:         57 % (     57 %)
 Work Started:           04/02/2012                                       Time Passed:        134 % (    101 %)


 29153(04)     Contract: 120121      US-62   Residency:     05200        5.24 MI. US-62/RESURFACE
 NHY-020N(041)3P                             ALTUS                       (ASPHALT)FROM 9.0 MI. EAST OF SH-30,
                                                                         EXTEND EAST.
 Contractor:   CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:     Nedbalek, Will               Adjusted:
 Contract Amount:        $946,654.34       (        $947,509.39)
 Contract Time:          45                (   45   )
 Letting Date:           02/16/2012
 Contract Date:          03/12/2012
 W/O Issued:             03/13/2012                                                             Adjusted:
 W/O Effective:          07/02/2012                               Amount Paid:           100 %(        100 %)
 Work Started:           03/20/2012                               Time Passed:            40 % (        40 %)




County:          Harper                                       Commissioner District:                                6
Contracts Under Construction




                                             Construction Status Report                                  Page 86
 27434(04)     Contract: 120016     US-270   Residency:     06100        0.00 MI. US-270;BRIDGE RE-
 SBR-130N(148)SB                             BUFFALO                     HABILITATION;OVER OTTER CR., 13.6
                                                                         MI. EAST OF THE BEAVER CL.
 Contractor:   WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES
 Engineer:     Burke, David                 Adjusted:
 Contract Amount:       $192,397.20        (        $192,397.20)
 Contract Time:         45                 (   45   )
 Letting Date:          01/19/2012
 Contract Date:         02/17/2012
 W/O Issued:            03/20/2012                                                               Adjusted:
 W/O Effective:         06/04/2012                                Amount Paid:              0%(          0 %)
 Work Started:                                                    Time Passed:              0%(          0 %)




County:          Haskell                                      Commissioner District:                                1
Contracts Under Construction


 23102(04)     Contract: 100603      SH-9   Residency:      01100         0.232 MI. SH-9;BRIDGE & AP-
 BRFY-131B(067)                             MUSKOGEE                      PROACHES; OVER KINGS CR., 1.0 MI. E.
                                                                          OF THE SH-2 JUNCTION.
 Contractor:   PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
 Engineer:     Ivy, Steve (Act.)           Adjusted:
 Contract Amount:        $1,759,826.88    (       $1,770,283.64)
 Contract Time:          180              (  180 )
 Letting Date:           10/21/2010
 Contract Date:          11/23/2010
 W/O Issued:             11/24/2010                                                               Adjusted:
 W/O Effective:          03/07/2011                               Amount Paid:             94 % (        93 %)
 Work Started:           04/12/2011                               Time Passed:            116 % (       116 %)


 24965(04)     Contract: 110270     CORD       Residency:       01200           1.271 MI. CO.RD. BRIDGE &
 CIRB-131C(085)RB                              SALLISAW                         APPROACHES:OVER SANS BOIS CR.,AT
                                                                                THE KERR RESERVOIR, 2.5 MI. NORTH
 Contractor:   GLOVER & ASSOCIATES, INC.                                        OF SH-9.
 Engineer:     Edwards, Carl                 Adjusted:
 Contract Amount:       $1,419,499.88       (      $1,419,499.88)
 Contract Time:         150                 (  150 )
 Letting Date:          05/19/2011
 Contract Date:         06/14/2011
 W/O Issued:            06/22/2011                                                                  Adjusted:
 W/O Effective:         09/01/2011                                        Amount Paid:         95 %(      95 %)
 Work Started:          09/01/2011                                        Time Passed:         89 % (     89 %)


 23101(04)     Contract: 110242     SH-9   Residency:     01200        .709 MI. SH-9 OVER SNAKE CREEK, 5.5
 BRFY-131B(064)                            SALLISAW                    MI. EAST OF SH-2 JCT.

 Contractor:   C-GAWF CONSTRUCTION, INC.
 Engineer:     Edwards, Carl              Adjusted:
 Contract Amount:       $2,719,722.44    (      $2,729,737.56)
 Contract Time:         240              (  240 )
 Letting Date:          09/15/2011
 Contract Date:         10/12/2011
 W/O Issued:            10/19/2011                                                            Adjusted:
 W/O Effective:         02/06/2012                              Amount Paid:             30  %(        30 %)
 Work Started:          02/06/2012                              Time Passed:             49  %(        49 %)




                                             Construction Status Report                                  Page 87
County:          Hughes                                       Commissioner District:                                 3
Contracts Under Construction


 20973(04)     Contract: 110291      US-75     Residency:       03300           2.72 MI. US-75:GRADE,SURFACE &
 STPY-132B(071)                                WEWOKA                           BRIDGE:FROM GRAND AVE. IN THE CITY
                                                                                OF WETUMKA,EXTEND NORTHEAST.
 Contractor:   SEWELL BROS., INC.
 Engineer:     Moore, Archie (Act.)           Adjusted:
 Contract Amount:        $8,521,068.29       (      $8,599,019.85)
 Contract Time:          330                 (  330 )
 Letting Date:           06/16/2011
 Contract Date:          07/22/2011
 W/O Issued:             07/29/2011                                                                 Adjusted:
 W/O Effective:          11/07/2011                                       Amount Paid:          89 %(     88 %)
 Work Started:           08/15/2011                                       Time Passed:          91 %(     91 %)


 28176(04)     Contract: 110334      US-75     Residency:       03004           0.00 MI. US-75:BRIDGE REHAB. :OVER
 SBR-132B(155)SB                                                          WEWOKA CREEK, 2.5 MI.
                                               JACOBS (AKA - CARTER-BURGESS)                            SOUTH OF
                                                                                THE SH-9 JCT/
 Contractor:   B & B BRIDGE COMPANY, LLC
 Engineer:     JACOBS (AKA - C-B)             Adjusted:
 Contract Amount:        $1,054,622.03       (      $1,054,622.03)
 Contract Time:          120                 (  129 )
 Letting Date:           07/21/2011
 Contract Date:          08/16/2011
 W/O Issued:             08/29/2011                                                                  Adjusted:
 W/O Effective:          12/05/2011                                       Amount Paid:          91 % (     91 %)
 Work Started:           10/24/2011                                       Time Passed:         167 % (    155 %)




County:          Jackson                                      Commissioner District:                                 5
Contracts Under Construction


 27539(04)     Contract: 110292      US-283   Residency:     05200        2.00 MI. US-283;RESURFACE
 SSR-133B(120)SR                              ALTUS                       (ASPHALT)BEGIN 3.0 MI. SOUTH OF
                                                                          US-62, EXTEND NORTH.
 Contractor:   APAC-CENTRAL, INC.
 Engineer:     Nedbalek, Will                Adjusted:
 Contract Amount:        $506,074.28        (        $509,249.33)
 Contract Time:          30                 (   30   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/27/2012                                                               Adjusted:
 W/O Effective:          05/07/2012                                Amount Paid:           101 %(       100 %)
 Work Started:           04/11/2012                                Time Passed:            33 % (       33 %)




                                             Construction Status Report                                   Page 88
 26627(04)     Contract: 120240      CORD       Residency:       05005           0.189 MI. CO.RD.:BRIDGE &
 BRF-133C(105)CI                                CIRCUIT ENGR. DISTR. # 7         APPROACHES/OVER UNNAMED CR., 4.5
                                                                                 MI. EAST OF US-283.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     CED7                            Adjusted:
 Contract Amount:        $584,381.51          (        $584,381.51)
 Contract Time:          120                  (  120 )
 Letting Date:           06/21/2012
 Contract Date:          07/20/2012
 W/O Issued:             07/24/2012                                                                 Adjusted:
 W/O Effective:          11/05/2012                                        Amount Paid:           0%(      0 %)
 Work Started:                                                             Time Passed:           0%(      0 %)




County:          Jefferson                                     Commissioner District:                                  7
Contracts Under Construction


 24971(04)     Contract: 110203       CORD      Residency:       07100           5.02 MI. CORD(NS-278):GRADE,DRAIN &
 CIRB-134C(065)RB                               DUNCAN                           SURFACE; FROM US-70 EXTEND SOUTH

 Contractor:   OVERLAND CORPORATION
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $2,787,256.70       (      $2,787,256.70)
 Contract Time:           150                 (  150 )
 Letting Date:            10/20/2011
 Contract Date:           11/17/2011
 W/O Issued:              11/22/2011                                                                  Adjusted:
 W/O Effective:           02/06/2012                                       Amount Paid:          90 % (     90 %)
 Work Started:            02/06/2012                                       Time Passed:          98 % (     98 %)


 23125(09)     Contract: 120159     IS-35       Residency:       07200           0.00 MI. IS-35;BRIDGEPROOF
 BRFY-234C(005)                                 ARDMORE                          SEAL;US-70/SH-76/SH-199. AT
                                                                                 MULTIPLE LOCATIONS IN DIV. VII.
 Contractor:   GARY A. CRAIN, INC.
 Engineer:     Earp, Jay                       Adjusted:
 Contract Amount:        $28,677.00           (          $28,677.00)
 Contract Time:          30                   (   30   )
 Letting Date:           04/19/2012
 Contract Date:          05/21/2012
 W/O Issued:             05/23/2012                                                                   Adjusted:
 W/O Effective:          08/06/2012                                        Amount Paid:          99 %(      99 %)
 Work Started:           07/17/2012                                        Time Passed:          33 % (     33 %)


 27324(04)     Contract: 100354       US-70     Residency:       07100           0.274 MI. US-70;BRIDGE RE-
 SBR-134B(77)(78)SB                             DUNCAN                           HAB.:OVER WEST MUD CR.,6.21 MIEAST
                                                                                 OF THE US-81 JCT &    OVER UNNAMED
 Contractor:   PBX CORPORATION                                                   CREEK.
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $1,085,152.59       (      $1,085,152.59)
 Contract Time:           120                 (  163 )
 Letting Date:            05/20/2010
 Contract Date:           06/23/2010
 W/O Issued:              07/02/2010                                                                Adjusted:
 W/O Effective:           08/16/2010                                       Amount Paid:         92 %(     92 %)
 Work Started:            10/18/2010                                       Time Passed:        164 %(    121 %)




                                              Construction Status Report                                   Page 89
25597(04)     Contract: 100385       CORD   Residency:     07100         0.1880 MI. CO.RD.;BRIDGE &
BRO-134D(072)CO                             DUNCAN                       APPROACHES;OVER A TRIBUTARY TO
                                                                         RED CREEK, 5.4 MI. EAST OF THE
Contractor:   PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                         US-81 JCT.
Engineer:     Harwell, Jerry M.            Adjusted:
Contract Amount:         $280,132.67      (        $280,132.67)
Contract Time:           90               (  181 )
Letting Date:            06/17/2010
Contract Date:           07/28/2010
W/O Issued:              07/29/2010                                                             Adjusted:
W/O Effective:           10/04/2010                              Amount Paid:             87 % (        87 %)
Work Started:            08/11/2010                              Time Passed:            160 % (        80 %)


28128(44)     Contract: 120176     US-81      Residency:       07004           51.97 MI. US-81;SAFETY IM-
BTOP-234B(001)                                                           PROVEMENTS(FIBER OPTIC CABLE)
                                              JACOBS (AKA - CARTER-BURGESS)
                                                                               US-70;BEGIN 4.7 MI. N. OF
Contractor:   ROHL NETWORKS, LP                                                US-70,EXTEND S., THEN E. ON US
Engineer:     JACOBS (AKA - C-B)             Adjusted:
Contract Amount:       $1,519,496.64        (      $1,519,496.64)
Contract Time:         140                  (  140 )
Letting Date:          03/15/2012
Contract Date:         04/12/2012
W/O Issued:            05/09/2012                                                                    Adjusted:
W/O Effective:         06/04/2012                                        Amount Paid:            7%(        7 %)
Work Started:          07/11/2012                                        Time Passed:           52 % (     52 %)
-70.

29220(04)     Contract: 120304     US-81   Residency:     07002        0.00 MI. US-81:BRIDGE REHAB. :OVER
SBR-234N(007)SB                            TETRA TECH                  SQUIRREL CR. 3.5 MI. S. OF US-70.

Contractor:   MERIDIAN CONTRACTING, INC.
Engineer:     TETR                        Adjusted:
Contract Amount:       $536,823.00       (        $536,823.00)
Contract Time:         120               (  120   )
Letting Date:          07/19/2012
Contract Date:         08/17/2012
W/O Issued:            08/22/2012                                                               Adjusted:
W/O Effective:         12/03/2012                               Amount Paid:              0 %(           0 %)
Work Started:                                                   Time Passed:              0 %(           0 %)


25598(04)     Contract: 100485       CORD     Residency:       07100           0.221 MI. CO.RD.;BRIDGE &
BRO-134D(073)CO                               DUNCAN                           APPROACHES/OVER CLEAR CR., 0.5MI.
                                                                               EAST OF THE SH-89      JUNCTION.
Contractor:   K & R BUILDERS, INC.
Engineer:     Harwell, Jerry M.              Adjusted:
Contract Amount:         $346,494.32        (        $346,494.32)
Contract Time:           90                 (  189   )
Letting Date:            08/19/2010
Contract Date:           09/20/2010
W/O Issued:              09/28/2010                                                                Adjusted:
W/O Effective:           12/06/2010                                      Amount Paid:          95 %(     95 %)
Work Started:            12/06/2010                                      Time Passed:         216 %(    103 %)




                                            Construction Status Report                                      Page 90
 29174(04)     Contract: 120303      SH-32   Residency:     07002        0.00 MI. SH-32:BRIDGE REHAB. /OVER
 SBR-234C(002)SB                             TETRA TECH                  RED CR., 8.1 MI. E. OF US-81.

 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
 Engineer:     TETR                         Adjusted:
 Contract Amount:        $599,815.61       (        $599,815.61)
 Contract Time:          100               (  100 )
 Letting Date:           07/19/2012
 Contract Date:          08/16/2012
 W/O Issued:             08/21/2012                                                               Adjusted:
 W/O Effective:          12/03/2012                               Amount Paid:               0%(         0 %)
 Work Started:                                                    Time Passed:               0%(         0 %)




County:         Johnston                                     Commissioner District:                         3
Contracts Under Construction


 28606(04)     Contract: 110426     US-75   Residency:     03001        0.00 MI. US-75/SH-3E/SH-7/SH-22/CORD
 BRFY-NBIP(448)3B                           ENGR. SERV. & TESTING       AT VARIOUS LOCATIONS INDIVISION 3.

 Contractor:   POSEIDON CONSTRUCTION, INC.
 Engineer:     EST                         Adjusted:
 Contract Amount:       $415,994.00       (        $415,994.00)
 Contract Time:         75                (   75   )
 Letting Date:          09/15/2011
 Contract Date:         10/18/2011
 W/O Issued:            11/01/2011                                                              Adjusted:
 W/O Effective:         02/06/2012                                Amount Paid:           64 % (         64 %)
 Work Started:          02/06/2012                               Time Passed:            45 % (         45 %)


 28218(04)     Contract: 120095       SH-99   Residency:     03100        6.04 MI. SH-99:RESURFACE
 STPY-135B(130)(131)3P                        ADA                         (ASPHALT)FROM THE MARSHALL C/L,
                                                                          EXTEND NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $1,062,142.16     (      $1,062,142.16)
 Contract Time:           45                (   45   )
 Letting Date:            02/16/2012
 Contract Date:           03/14/2012
 W/O Issued:              03/21/2012                                                             Adjusted:
 W/O Effective:           07/02/2012                               Amount Paid:            86 %(        86 %)
 Work Started:            05/09/2012                               Time Passed:           120 % (     120 %)




County:         Kay                                          Commissioner District:                         4
Contracts Under Construction




                                            Construction Status Report                            Page 91
25909(13)     Contract: 100550      I-35   Residency:     04100        1.453 MI. IS-35;GRADE,DRAIN
ACIMY-0035-4(224)235MS                     PERRY                       ,SURFACE, & SITE PLAN:TRUCK WEIGH
                                                                       STATION 2.0 MI. S. OF THE OK/KANSAS
Contractor:                                                             JV
              DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCSTATE LINE.
Engineer:     Zachary, Ted                Adjusted:
Contract Amount:        $7,489,962.67    (      $7,647,522.71)
Contract Time:          290              (  544 )
Letting Date:           09/16/2010
Contract Date:          10/14/2010
W/O Issued:             11/09/2010                                                             Adjusted:
W/O Effective:          01/10/2011                              Amount Paid:            100 % (       98 %)
Work Started:           12/07/2010                              Time Passed:            187 % (      100 %)


28315(04)     Contract: 120140      US-60B   Residency:     04100        0.06 MI. US-60B/BRIDGE RE-
SBR-136N(211)SB                              PERRY                       HABILITATION/US-177;OVER US- 60 IN
                                                                         TONKAWA.
Contractor:   K & R BUILDERS, INC.
Engineer:     Zachary, Ted                  Adjusted:
Contract Amount:        $1,228,814.77      (      $1,228,814.77)
Contract Time:          90                 (   90   )
Letting Date:           03/15/2012
Contract Date:          04/13/2012
W/O Issued:             04/18/2012                                                               Adjusted:
W/O Effective:          08/06/2012                                Amount Paid:            10 % (       10 %)
Work Started:           08/06/2012                                Time Passed:            10 % (       10 %)


27594(04)     Contract: 120305      US-60     Residency:       04100           0.070 MI. US-60:BRIDGE REHAB. OVER
SBR-136B(217)SB                               PERRY                            US-60B S.W. OF PONCA CITY

Contractor:   A. M. COHRON & SON, INC.
Engineer:     Zachary, Ted                   Adjusted:
Contract Amount:        $768,838.37         (        $768,838.37)
Contract Time:          90                  (   90   )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                                 Adjusted:
W/O Effective:          12/03/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                            Time Passed:           0 %(      0 %)


27063(04)     Contract: 110483      I35    Residency:      04100        .359 MI. I-35:BRIDGE AND APPROACHES;
BRIY-0035-4(239)232                        PERRY                        OVER US-177

Contractor:   WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES
Engineer:     Zachary, Ted                Adjusted:
Contract Amount:        $4,078,821.42    (       $4,078,821.42)
Contract Time:          240              (   240 )
Letting Date:           10/20/2011
Contract Date:          11/17/2011
W/O Issued:             01/30/2012                                                              Adjusted:
W/O Effective:          03/05/2012                               Amount Paid:             64 %(        64 %)
Work Started:           02/20/2012                               Time Passed:             69 %(        69 %)




                                            Construction Status Report                                   Page 92
 27446(04)     Contract: 120097      IS-35   Residency:     04100        3.98 MI. IS-35:RESURFACE
 SSR-136N(198)SR                             PERRY                       (ASPHALT)FROM 3.98 MI. SOUTH OF THE
                                                                         KANSAS STATE LINE,    EXTEND NORTH.
 Contractor:   EVANS & ASSOCIATES CONSTRUCTION CO., INC.
 Engineer:     Zachary, Ted                 Adjusted:
 Contract Amount:        $2,369,970.00     (      $2,369,970.00)
 Contract Time:                            (        )
 Letting Date:           06/21/2012
 Contract Date:          07/13/2012                               Fixed Completion Date: 10/31/2012
 W/O Issued:             07/18/2012                                                              Adjusted:
 W/O Effective:                                                   Amount Paid:              0%(          0 %)
 Work Started:                                                    Time Passed:              0%(          0 %)


 22953(04)     Contract: 110380      CTST   Residency:     04100        1.734 MI. CT.ST.:GRADE,DRAIN &
 STP-136D(117)CI                            PERRY                       SURFACE/ON HUBBARD RD. IN PONCA
                                                                        CITY, FROM WAVERLY RD. EXTEND
 Contractor:   EVANS & ASSOCIATES CONSTRUCTION CO., INC.                EAST.
 Engineer:     Zachary, Ted                Adjusted:
 Contract Amount:        $3,181,697.06    (      $3,230,473.32)
 Contract Time:          200              (  216 )
 Letting Date:           08/18/2011
 Contract Date:          09/20/2011
 W/O Issued:             09/22/2011                                                             Adjusted:
 W/O Effective:          12/05/2011                              Amount Paid:             47 % (       46 %)
 Work Started:           02/21/2012                              Time Passed:             84 % (       78 %)


 29310(04)     Contract: 120254      I-35    Residency:     04100        0.00 MI. IS-35:STRIPING &  PAVEMENT
 HSIPG-236F(003)TR                           PERRY                       MARKING/US-60/US-77/
                                                                         US-177/SH-51:MULTIPLE LO-    CATIONS
 Contractor:   DIRECT TRAFFIC CONTROL INC.                               IN DIV. IV.
 Engineer:     Zachary, Ted                 Adjusted:
 Contract Amount:        $157,250.00       (        $157,250.00)
 Contract Time:          45                (   45   )
 Letting Date:           07/19/2012
 Contract Date:          08/21/2012
 W/O Issued:             08/24/2012                                                               Adjusted:
 W/O Effective:          09/17/2012                               Amount Paid:              0  %(         0 %)
 Work Started:                                                    Time Passed:              0  %(         0 %)




County:          Kingfisher                                   Commissioner District:                                 4
Contracts Under Construction


 24882(04)     Contract: 110082      US-81     Residency:       04300           0.28 MI. US-81/BRIDGE REHAB. :OVER
 SBR-137N(072)SB                               ENID                             THE CIMARRON RIVER, 6.8 MI. NORTH
                                                                                OF THE SH-33 JUNC- TION.
 Contractor:   A. M. COHRON & SON, INC.
 Engineer:     Crowl, Kenny (Act.)            Adjusted:
 Contract Amount:        $2,043,649.08       (      $2,060,875.16)
 Contract Time:          180                 (  218 )
 Letting Date:           07/21/2011
 Contract Date:          08/12/2011
 W/O Issued:             09/12/2011                                                                 Adjusted:
 W/O Effective:          12/05/2011                                       Amount Paid:          91 %(     90 %)
 Work Started:           10/26/2011                                       Time Passed:         134 %(    111 %)




                                             Construction Status Report                                   Page 93
 29085(04)     Contract: 120255     US-81      Residency:       04011           0.177 MI. US-81:GRADE,DRAIN, &
 SSP-237E(001)SS                               GARVER, LLC.                     SURFACE:FROM 2.6 MI. S. OF THE SH-33
                                                                                JCT EXTEND NORTH.
 Contractor:   TOM HUDSON PAVING, INC.
 Engineer:     GARV                          Adjusted:
 Contract Amount:       $536,881.85         (        $536,881.85)
 Contract Time:         90                  (   90   )
 Letting Date:          07/19/2012
 Contract Date:         08/16/2012
 W/O Issued:            08/21/2012                                                                 Adjusted:
 W/O Effective:         12/03/2012                                        Amount Paid:           0%(      0 %)
 Work Started:                                                            Time Passed:           0%(      0 %)




County:          Kiowa                                        Commissioner District:                                   5
Contracts Under Construction


 16063(45)     Contract: 120160      US-183   Residency:     05200        3.04 MI./US-183/GRADE,DRAIN, &
 NHY-009N(098)                                ALTUS                       SURFACE;FROM 1.5 MI. N. OF THE SH-9
                                                                          WEST JUNCTION, EX- TEND NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Nedbalek, Will                Adjusted:
 Contract Amount:        $7,121,528.84      (      $7,121,528.84)
 Contract Time:          180                (  180 )
 Letting Date:           04/19/2012
 Contract Date:          05/16/2012
 W/O Issued:             05/18/2012                                                              Adjusted:
 W/O Effective:          08/06/2012                                Amount Paid:             4%(           4 %)
 Work Started:           08/13/2012                                Time Passed:             6%(           6 %)


 26972(04)     Contract: 110484     CORD       Residency:       05005           .246 MI. CO.RD.(NS-225):BRIDGE AND
 BRO-NBIL(174)CI                               CIRCUIT ENGR. DISTR. # 7         APPOACHES OVER OTTER CREEK 3.5 MI.
                                                                                N OFUS-62 AND 1.0 MI. W OF US-183
 Contractor:   SEWELL BROS., INC.
 Engineer:     CED7                          Adjusted:
 Contract Amount:       $383,549.36         (        $383,549.36)
 Contract Time:         90                  (  102   )
 Letting Date:          10/20/2011
 Contract Date:         11/22/2011
 W/O Issued:            11/29/2011                                                                   Adjusted:
 W/O Effective:         03/05/2012                                        Amount Paid:          94 %(      94 %)
 Work Started:          02/27/2012                                        Time Passed:         126 % (    111 %)


 16063(44)     Contract: 110295      US-183   Residency:     05200        2.268 MI. US-183/GRADE,DRAIN &
 NHY-009N(097)SS                              ALTUS                       BRIDGE:FROM 1.8 MI. NORTH OF THE
                                                                          SH-9 WEST JUNCTION, EXTEND NORTH.
 Contractor:   CORNELL CONSTRUCTION COMPANY, INC.
 Engineer:     Nedbalek, Will                Adjusted:
 Contract Amount:        $1,081,602.56      (      $1,086,085.32)
 Contract Time:          120                (  121 )
 Letting Date:           08/18/2011
 Contract Date:          09/26/2011
 W/O Issued:             09/29/2011                                                              Adjusted:
 W/O Effective:          01/02/2012                                Amount Paid:            88 %(        87 %)
 Work Started:           12/08/2011                                Time Passed:           103 %(       102 %)




                                             Construction Status Report                                   Page 94
County:          Latimer                                      Commissioner District:                                     2
Contracts Under Construction


 18843(04)     Contract: 100387      US-270   Residency:     02400        1.402 MI. US-270;GRADE,DRAIN
 CIP-139B(025)IP                              MCALESTER                   ,SURFACE & BRIDGE;FROM 6.5 MI.EAST
                                                                          OF THE SH-2 JCT, EXTEND EAST.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     Plymate, Larry                Adjusted:
 Contract Amount:        $3,901,084.36      (      $4,020,957.62)
 Contract Time:          360                (  624 )
 Letting Date:           06/17/2010
 Contract Date:          07/26/2010
 W/O Issued:             10/11/2010                                                              Adjusted:
 W/O Effective:          11/01/2010                                Amount Paid:             94 %(        92 %)
 Work Started:           11/30/2010                                Time Passed:           182  %(       105 %)


 28614(04)     Contract: 120256     CORD       Residency:       02013           0.311 MI. CO.RD.:GRADE,DRAIN,
 STP-139C(120)CI                               CIRCUIT ENGR. DISTRICT # 3       SURFACE & BRIDGE(CRAVENS RD.) OVER
                                                                                AN UNNAMED CR. 4.3 MI. E. & 1.3 MI. S.
 Contractor:   GLOVER & ASSOCIATES, INC.                                        OF US-270.
 Engineer:     CED3                          Adjusted:
 Contract Amount:       $531,458.49         (        $531,458.49)
 Contract Time:         90                  (   90   )
 Letting Date:          07/19/2012
 Contract Date:         08/21/2012
 W/O Issued:            08/24/2012                                                                  Adjusted:
 W/O Effective:         09/17/2012                                        Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)


 00464(14)     Contract: 120211     SH-82   Residency:     02200        0.616 MI. SH-82:GRADE,DRAIN &
 STPY-139C(094)                             HEAVENER                    SURFACE:SLIDE REPR. FROM 64 MI.
                                                                        NORTH OF US-270, EX- TEND NORTH.
 Contractor:   T. MCDONALD CONSTRUCTION, INC.
 Engineer:     Huddleston, David           Adjusted:
 Contract Amount:       $2,917,533.98     (      $2,917,533.98)
 Contract Time:         300               (  300 )
 Letting Date:          06/21/2012
 Contract Date:         07/12/2012
 W/O Issued:            07/18/2012                                                             Adjusted:
 W/O Effective:         11/05/2012                               Amount Paid:             0 %(        0 %)
 Work Started:                                                   Time Passed:             0%(         0 %)


 00464(16)     Contract: 110257     SH-82   Residency:     02200        0.700 MI. SH-82;GRADE,DRAIN
 ERSTP-139C(096)ER                          HEAVENER                    SURFACE & EROSION
                                                                        CONTROL;LANDSLIDE REPR. FROM 4.8
 Contractor:   SHERWOOD CONSTRUCTION CO., INC.                          MI.    NORTH OF US-270
 Engineer:     Huddleston, David           Adjusted:                    JCT,EXT.NORTH.
 Contract Amount:       $4,322,783.60     (      $4,322,783.60)
 Contract Time:         270               (  270 )
 Letting Date:          04/14/2011
 Contract Date:         05/12/2011
 W/O Issued:            05/26/2011                                                             Adjusted:
 W/O Effective:         07/11/2011                               Amount Paid:            96 %(       96 %)
 Work Started:          07/15/2011                               Time Passed:           114 %(      114 %)




                                             Construction Status Report                                    Page 95
 26298(04)     Contract: 120050     CORD   Residency:     02013        0.179 MI. CO.RD.;BRIDGE &
 BRO-139D(101)CI                           CIRCUIT ENGR. DISTRICT # 3 APPROACHES:OVER CROOKED CR., 1.1
                                                                       MI. S. OF SH-63 & 1.2  MI. W. OF THE
 Contractor:   C-GAWF CONSTRUCTION, INC.                               LEFLORE CL.
 Engineer:     CED3                       Adjusted:
 Contract Amount:       $471,868.77      (        $471,868.77)
 Contract Time:         120              (  120 )
 Letting Date:          01/19/2012
 Contract Date:         02/24/2012
 W/O Issued:            03/01/2012                                                             Adjusted:
 W/O Effective:         05/07/2012                              Amount Paid:             24 % (         24 %)
 Work Started:                                                  Time Passed:             66 % (         66 %)


 28128(47)     Contract: 120066     US-270   Residency:     02200        41.79 MI. US-270/US-271;   SAFETY
 BTOP-239B(001)                              HEAVENER                    IMPROVEMENTS(FIBER     OPTIC
                                                                         CABLE)FROM THE CITY    OF
 Contractor:   AMERICAN DIRECTIONAL BORING,INC. DBA ADB UTILITY CONTRACTORS
                                                                         WILBURTON, IN POTEAU.
 Engineer:     Huddleston, David            Adjusted:
 Contract Amount:       $1,906,450.18      (      $1,906,450.18)
 Contract Time:         125                (  125 )
 Letting Date:          01/19/2012
 Contract Date:         02/23/2012
 W/O Issued:            03/06/2012                                                               Adjusted:
 W/O Effective:         04/02/2012                                Amount Paid:            90 % (        90 %)
 Work Started:          04/02/2012                                Time Passed:            97 % (        97 %)




County:          Le Flore                                     Commissioner District:                         2
Contracts Under Construction


 28586(04)     Contract: 110387     US-259   Residency:     02200        0.00 MI. US-259:BRIDGE PAINT
 BRFY-NBIP(441)3B                            HEAVENER                    -ING/SH-3/SH-112:AT VARIOUS
                                                                         LOCATIONS IN DIV. II.
 Contractor:   POSEIDON CONSTRUCTION, INC.
 Engineer:     Huddleston, David            Adjusted:
 Contract Amount:       $269,944.00        (        $269,944.00)
 Contract Time:         75                 (   75   )
 Letting Date:          08/18/2011
 Contract Date:         09/28/2011
 W/O Issued:            11/01/2011                                                               Adjusted:
 W/O Effective:         03/05/2012                                Amount Paid:            69   %(      69 %)
 Work Started:          05/04/2012                                Time Passed:            95 % (       95 %)


 28454(04)     Contract: 120182     US-259   Residency:     02200        0.221 MI. US-259:SAFETYH IM-
 STPG-140A(211)TR                            HEAVENER                    PROVEMENT(CONCRETE BARRIER
                                                                         WALL)BEGIN 3.36 MI. S. OF   SH-63,
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                           EXTEND SOUTH.
 Engineer:     Huddleston, David            Adjusted:
 Contract Amount:       $1,033,890.85      (      $1,033,890.85)
 Contract Time:         150                (  150 )
 Letting Date:          07/19/2012
 Contract Date:         08/21/2012
 W/O Issued:            08/24/2012                                                               Adjusted:
 W/O Effective:         09/24/2012                                Amount Paid:              0 %(          0 %)
 Work Started:                                                    Time Passed:              0 %(          0 %)




                                             Construction Status Report                            Page 96
26904(04)     Contract: 120148     CORD       Residency:      02013           0.07 MI. CO. RD.:BRIDGE &
BRO-140D(189)CI                               CIRCUIT ENGR. DISTRICT # 3      APPROACHES/OVER TRIBUTARY OF
                                                                              POTEAU RIVER 2.8 MI. S. & 0.5 MI. W.
Contractor:   HUB CONSTRUCTION, INC.                                          OF US-271/SH-9 JCT
Engineer:     CED3                          Adjusted:
Contract Amount:       $214,245.60         (        $214,245.60)
Contract Time:         90                  (   90   )
Letting Date:          03/15/2012
Contract Date:         04/16/2012
W/O Issued:            04/18/2012                                                                  Adjusted:
W/O Effective:         07/02/2012                                       Amount Paid:          65 % (     65 %)
Work Started:                                                           Time Passed:          43 % (     43 %)


25101(04)     Contract: 110532     CORD       Residency:      02013           0.246 MI. CO.RD./BRIDGE &
CIRB-140D(162)RB                              CIRCUIT ENGR. DISTRICT # 3      APPROACHES:OVER THE POTEAU
                                                                              RIVER, 0.4 MI. SOUTH OF   SH-128.
Contractor:   HUB CONSTRUCTION, INC.
Engineer:     CED3                          Adjusted:
Contract Amount:       $1,257,926.90       (      $1,257,926.90)
Contract Time:         150                 (  150 )
Letting Date:          11/17/2011
Contract Date:         12/15/2011
W/O Issued:            12/20/2011                                                                  Adjusted:
W/O Effective:         01/23/2012                                       Amount Paid:          49 % (     49 %)
Work Started:          04/26/2012                                       Time Passed:          69 % (     69 %)


28128(48)     Contract: 120071     US-59      Residency:      02200           36.18 MI. US-59;SAFETY IM-
BTOP-240A(001)                                HEAVENER                        PROVEMENT(FIBER OPTIC CABLE) FROM
                                                                              POTEAU EXTEND NORTH       TO
Contractor:   BEAR COMMUNICATIONS, LLC                                        SALLISAW.
Engineer:     Huddleston, David             Adjusted:
Contract Amount:       $1,242,465.04       (      $1,242,465.04)
Contract Time:         110                 (  110 )
Letting Date:          02/16/2012
Contract Date:         03/20/2012
W/O Issued:            04/10/2012                                                                 Adjusted:
W/O Effective:         05/07/2012                                       Amount Paid:          54 %(     54 %)
Work Started:          05/15/2012                                       Time Passed:          92 %(     92 %)


23145(07)     Contract: 120033     SH-31   Residency:     02200        0.00 MI. SH-31 BRIDGE PAIN- TING;
BRFY-NBIP(450)                             HEAVENER                    MULTIPLE LOCATIONS IN DIV. II.

Contractor:   POSEIDON CONSTRUCTION, INC.
Engineer:     Huddleston, David           Adjusted:
Contract Amount:       $722,922.00       (        $722,922.00)
Contract Time:         90                (   90   )
Letting Date:          01/19/2012
Contract Date:         02/22/2012
W/O Issued:            05/31/2012                                                              Adjusted:
W/O Effective:         06/04/2012                               Amount Paid:              0 %(          0 %)
Work Started:          08/14/2012                               Time Passed:              0 %(          0 %)




                                           Construction Status Report                                   Page 97
 26905(04)     Contract: 120051     CORD   Residency:     02013        0.08 MI. CO.RD.;BRIDGE &
 BRO-140D(190)CI                           CIRCUIT ENGR. DISTRICT # 3 APPROACHES/OVER UNNAMED CR., 4.0
                                                                       MI. SOUTH & 1,.7 MI.   WEST OF
 Contractor:   C-GAWF CONSTRUCTION, INC.                               POCOLA.
 Engineer:     CED3                       Adjusted:
 Contract Amount:       $235,577.04      (        $235,577.04)
 Contract Time:         90               (   90   )
 Letting Date:          01/19/2012
 Contract Date:         02/24/2012
 W/O Issued:            02/29/2012                                                             Adjusted:
 W/O Effective:         06/04/2012                              Amount Paid:             85 % (       85 %)
 Work Started:          04/26/2012                              Time Passed:           110 % (       110 %)




County:          Lincoln                                       Commissioner District:                                 3
Contracts Under Construction


 25087(04)     Contract: 110153     CORD        Residency:       03003           5.93 MI. CO.RD.(EW-87):SURFACELAKE
 CIRB-141C(191)RB                               COBB ENGINEERING CO., INC.       RD US-177 EXTEND EAST.

 Contractor:   THE QUAPAW COMPANY
 Engineer:     COBB                            Adjusted:
 Contract Amount:       $2,323,488.45         (      $2,546,230.37)
 Contract Time:         90                    (  140 )
 Letting Date:          10/20/2011
 Contract Date:         11/21/2011
 W/O Issued:            11/22/2011                                                                    Adjusted:
 W/O Effective:         03/05/2012                                         Amount Paid:          49 % (     44 %)
 Work Started:          03/05/2012                                         Time Passed:         152 % (     98 %)


 24180(08)     Contract: 120018      US-177   Residency:     03300        0.715 MI. US-177;GRADE,DRAIN
 BRFY-141B(206)                               WEWOKA                      ,SURFACE & BRIDGE/OVER SPRING CR.,
                                                                          & DEEP FORK N.CANADIAN RIVER 0.24
 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) & 0.53 MI. N. OF SH
 Engineer:     Moore, Archie (Act.)          Adjusted:
 Contract Amount:        $4,046,554.18      (      $4,046,554.18)
 Contract Time:          210                (  210 )
 Letting Date:           01/19/2012
 Contract Date:          02/14/2012
 W/O Issued:             04/05/2012                                                              Adjusted:
 W/O Effective:          06/04/2012                                Amount Paid:            46 %(        46 %)
 Work Started:           05/16/2012                                Time Passed:            44 % (       44 %)
 -66.

 20995(04)     Contract: 110244       US-75     Residency:       03100           0.00 MI. US-75:JOINT SEAL/
 BRFY-141F(229)                                 ADA                              REPAIR;SH-3/SH-66:AT MULTIPLE
                                                                                 LOCATIONS IN DIV. III.
 Contractor:   PBX CORPORATION
 Engineer:     Russell, Julie                  Adjusted:
 Contract Amount:         $381,844.50         (        $381,844.50)
 Contract Time:           90                  (  120   )
 Letting Date:            04/14/2011
 Contract Date:           05/18/2011
 W/O Issued:              05/25/2011                                                                 Adjusted:
 W/O Effective:           09/01/2011                                       Amount Paid:          92 %(     92 %)
 Work Started:            10/01/2011                                       Time Passed:         146 %(    109 %)




                                              Construction Status Report                                   Page 98
 05859(10)     Contract: 110462      SH-18   Residency:     03300        3.84 MI. SH-18 FROM 3.8 MI. SOUTH OF
 STPY-063C(372)                              WEWOKA                      SH-62 IN MEEKER EXTEND NORTH.

 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Moore, Archie (Act.)         Adjusted:
 Contract Amount:        $6,764,377.57     (      $7,049,790.97)
 Contract Time:          325               (  325 )
 Letting Date:           09/15/2011
 Contract Date:          10/12/2011
 W/O Issued:             10/20/2011                                                              Adjusted:
 W/O Effective:          03/05/2012                               Amount Paid:            14 % (         13 %)
 Work Started:           12/27/2011                               Time Passed:            58 % (         58 %)


 24679(04)     Contract: 110300      SH-105   Residency:     03300        6.91 MI. SH-105:RESURFACE
 SSR-141C(185)SR                              WEWOKA                      (ASPHALT)FROM THE LOGAN CL,
                                                                          EXTEND EAST.
 Contractor:   ATLAS PAVING COMPANY
 Engineer:     Moore, Archie (Act.)          Adjusted:
 Contract Amount:        $1,004,183.47      (      $1,004,183.47)
 Contract Time:          40                 (   40   )
 Letting Date:           06/21/2012
 Contract Date:          07/11/2012
 W/O Issued:             07/18/2012                                                              Adjusted:
 W/O Effective:          08/06/2012                                Amount Paid:              0%(        0 %)
 Work Started:                                                     Time Passed:              0%(        0 %)




County:          Logan                                        Commissioner District:                         4
Contracts Under Construction


 24217(04)     Contract: 110461      I-35   Residency:     04500        .709 MI. I-35:BRIDGE & APPROACHES
 IMY-0035-4(215)151                         STILLWATER                  OVER SEWARD RD 5.0 MI. N OF
                                                                        OKLAHOMA COUNTY LINE
 Contractor:   SHERWOOD CONSTRUCTION CO., INC.
 Engineer:     Arps, Jonathan              Adjusted:
 Contract Amount:        $7,119,614.24    (      $7,201,952.07)
 Contract Time:          240              (  240 )
 Letting Date:           10/20/2011
 Contract Date:          11/17/2011
 W/O Issued:             11/22/2011                                                              Adjusted:
 W/O Effective:          03/05/2012                              Amount Paid:             63 %(        62 %)
 Work Started:           03/05/2012                              Time Passed:             62 % (       62 %)


 29196(04)     Contract: 120124      US-77   Residency:     04500        5.29 MI. US-77;RESURFACE
 STPY-242C(002)3P                            STILLWATER                  (ASPHALT)FROM 7.25 MI. N. OF SH-33,
                                                                         EXTEND NORTH.
 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Arps, Jonathan               Adjusted:
 Contract Amount:        $1,042,269.00     (      $1,042,269.00)
 Contract Time:          45                (   45   )
 Letting Date:           04/19/2012
 Contract Date:          05/16/2012
 W/O Issued:             05/18/2012                                                             Adjusted:
 W/O Effective:          08/06/2012                               Amount Paid:             0 %(           0 %)
 Work Started:                                                    Time Passed:             0 %(           0 %)




                                             Construction Status Report                            Page 99
 23018(04)     Contract: 120134      CORD   Residency:     04500        0.302 MI. CO.RD./BRIDGE &
 STP-142C(119)AG                            STILLWATER                  APPROACHES:BROADWAY BLVD.OVER
                                                                        COTTONWOOD CR., 0.5 MI. S. & 3.5
 Contractor:   BRIDGECO CONTRACTORS, INC.                               MI. W. OF IS-35/US-77 JC
 Engineer:     Arps, Jonathan              Adjusted:
 Contract Amount:        $1,115,636.70    (      $1,122,681.50)
 Contract Time:          180              (  180 )
 Letting Date:           03/15/2012
 Contract Date:          04/12/2012
 W/O Issued:             04/18/2012                                                              Adjusted:
 W/O Effective:          07/02/2012                              Amount Paid:              7%(          7 %)
 Work Started:                                                   Time Passed:             13 % (       13 %)
 T

 24381(04)     Contract: 120019      SH-33   Residency:     04500        0.725 MI. SH-33;GRADE,DRAIN &
 SSP-142C(146)SS                             STILLWATER                  SURFACE/FROM SH-74, EXTEND WEST.

 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Arps, Jonathan               Adjusted:
 Contract Amount:        $1,288,459.25     (      $1,288,459.25)
 Contract Time:          90                (   90   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/27/2012                                                             Adjusted:
 W/O Effective:          04/02/2012                               Amount Paid:            91 % (       91 %)
 Work Started:           04/02/2012                               Time Passed:           102 % (      102 %)




County:          Love                                         Commissioner District:                           7
Contracts Under Construction


 27166(04)     Contract: 100604     IS-35   Residency:     07200        *-1(157)14/ 5.73 MI. IS-35
 IMY-0035-1(156)11/IMY-35*                  ARDMORE                     ;GRADE,DRAIN,& SURFACE/FROM 11.75
                                                                        MI. N. OF TX. STATE    LINE, EXTEND
 Contractor:                                                             JV
               DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCNORTH.
 Engineer:     Earp, Jay                   Adjusted:
 Contract Amount:        $13,041,382.34   (     $13,458,245.53)
 Contract Time:          300              (  648 )
 Letting Date:           10/21/2010
 Contract Date:          11/16/2010
 W/O Issued:             11/17/2010                                                               Adjusted:
 W/O Effective:          03/07/2011                              Amount Paid:            102  %(          99 %)
 Work Started:           12/13/2010                              Time Passed:            199 % (          92 %)


 27166(05)     Contract: 110527      I-35   Residency:     07200        .265 MI. I-35: GRADE,DRAIN, SURGACE
 BRIY-0035-1(151)015                        ARDMORE                     AND BRIDGE; OVER SH-32

 Contractor:   MERIDIAN CONTRACTING, INC.
 Engineer:     Earp, Jay                   Adjusted:
 Contract Amount:        $5,141,923.65    (      $5,141,923.65)
 Contract Time:          270              (  270 )
 Letting Date:           10/20/2011
 Contract Date:          11/29/2011
 W/O Issued:             12/08/2011                                                             Adjusted:
 W/O Effective:          01/09/2012                              Amount Paid:             61 %(         61 %)
 Work Started:           01/09/2012                              Time Passed:             77 %(         77 %)




                                             Construction Status Report                             Page 100
 23123(04)     Contract: 110433      US-77     Residency:       07200           .312 MI. US-77 OVER HICKORY CREEK
 BRFY-143C(075)SS                              ARDMORE                          AND SOUTH BRANCH OF HICKORY CREEK
                                                                                6.7 MI. N OR SH-32 JCT.
 Contractor:   EARTH BUILDERS, L.P.
 Engineer:     Earp, Jay                      Adjusted:
 Contract Amount:        $2,902,066.85       (      $2,923,527.74)
 Contract Time:          180                 (  180 )
 Letting Date:           09/15/2011
 Contract Date:          10/17/2011
 W/O Issued:             11/29/2011                                                                  Adjusted:
 W/O Effective:          02/06/2012                                       Amount Paid:          70 % (     69 %)
 Work Started:           02/06/2012                                       Time Passed:          98 % (     98 %)


 23124(04)     Contract: 110434      SH-32   Residency:     07200        .151 MI. SH-32 OVER COFFEE POT
 BRFY-143C(078)                              ARDMORE                     CREEK, 1.5 MI. WEST OF SH-76 JCT.

 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
 Engineer:     Earp, Jay                    Adjusted:
 Contract Amount:        $1,807,025.55     (      $1,807,025.55)
 Contract Time:          180               (  180 )
 Letting Date:           09/15/2011
 Contract Date:          10/12/2011
 W/O Issued:             10/19/2011                                                              Adjusted:
 W/O Effective:          02/06/2012                               Amount Paid:            93 % (         93 %)
 Work Started:           12/12/2011                               Time Passed:            99 % (         99 %)




County:          McClain                                      Commissioner District:                                 3
Contracts Under Construction


 22526(04)     Contract: 110251      CORD      Residency:       03200           .26 MI. CORD(EW-146):BRIDGE &
 BRO-144D(095)CI                               PURCELL                          APPROACHES OVER FINN CREEK .9 MI E
                                                                                OF SH-24 AND 1.0 MI. S OF SH-59.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     Riemer, Caleb                  Adjusted:
 Contract Amount:        $835,867.08         (        $835,867.08)
 Contract Time:          150                 (  150   )
 Letting Date:           10/20/2011
 Contract Date:          11/17/2011
 W/O Issued:             11/22/2011                                                                  Adjusted:
 W/O Effective:          03/05/2012                                       Amount Paid:          49 %(      49 %)
 Work Started:           03/05/2012                                       Time Passed:          59 % (     59 %)


 24142(04)     Contract: 100611     SH-39    Residency:    03003        5.05 MI. SH-39;WIDEN,RESUR- FACE &
 STPY-144C(121)                              COBB ENGINEERING CO., INC. BRIDGE;FROM 1.78 MI. E.OF THE SH-24
                                                                        JUNCTION, EX- TEND EAST.
 Contractor:   MARKWELL PAVING COMPANY, INC.
 Engineer:     COBB                        Adjusted:
 Contract Amount:       $6,839,607.41     (      $7,371,223.59)
 Contract Time:         365               (   365 )
 Letting Date:          11/18/2010
 Contract Date:         12/22/2010
 W/O Issued:            01/04/2011                                                             Adjusted:
 W/O Effective:         04/04/2011                               Amount Paid:           103 %(          96 %)
 Work Started:          04/04/2011                               Time Passed:           113 %(        113 %)




                                             Construction Status Report                                   Page 101
 28103(04)     Contract: 110436     I-35       Residency:       03001           0.00 MI. I-35 FROM SH-59 OVERPASS
 IMG-0035-2(312)086TR                          ENGR. SERV. & TESTING            EXTEND NORTH.

 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     EST                           Adjusted:
 Contract Amount:       $909,180.55         (        $909,180.55)
 Contract Time:         90                  (   90   )
 Letting Date:          09/15/2011
 Contract Date:         10/17/2011
 W/O Issued:            10/22/2011                                                                   Adjusted:
 W/O Effective:         01/02/2012                                        Amount Paid:          53 % (     53 %)
 Work Started:          01/02/2012                                        Time Passed:         143 % (    143 %)


 28217(04)     Contract: 120101       SH-59A   Residency:     03100        *-162C(223)3P/ 5.270 MI. SH-
 STPY-144C(163)3P/STPY*                        ADA                         59A:RESURFACE(ASPHALT)FROM
                                                                           US-177,EXTEND EAST.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Russell, Julie                 Adjusted:
 Contract Amount:         $934,707.70        (        $934,707.70)
 Contract Time:           45                 (   45   )
 Letting Date:            02/16/2012
 Contract Date:           03/14/2012
 W/O Issued:              03/21/2012                                                                Adjusted:
 W/O Effective:           07/02/2012                                Amount Paid:            88 % (        88 %)
 Work Started:            07/02/2012                                Time Passed:            93 % (        93 %)


 28177(04)     Contract: 110517     SH-59   Residency:     03004        0.00 MI. SH-59 BRIDGE REHAB. :OVER
 SBR-144C(157)SB                                                        FINN
                                            JACOBS (AKA - CARTER-BURGESS) CR., 2.8 MI. WEST OF THE SH-74
                                                                        JCT.
 Contractor:   CIMARRON CONSTRUCTION COMPANY
 Engineer:     JACOBS (AKA - C-B)          Adjusted:
 Contract Amount:       $964,159.55       (        $964,159.55)
 Contract Time:         90                (   90   )
 Letting Date:          11/17/2011
 Contract Date:         12/15/2011
 W/O Issued:            12/21/2011                                                              Adjusted:
 W/O Effective:         05/07/2012                               Amount Paid:             66 %(        66 %)
 Work Started:          05/07/2012                               Time Passed:           112  %(       112 %)




County:          McCurtain                                    Commissioner District:                                 2
Contracts Under Construction


 24185(04)     Contract: 110301     SH-3   Residency:      02100        5.77 MI. SH-3:GRADE,DRAIN, SURFACE
 SEC1702Y-145B(153)SS                      ANTLERS                      & BRIDGE/FROM 4.5 MI. EAST OF THE
                                                                        PUSHMATAHA C/L, EXTEND EAST.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Moy, Ryan                  Adjusted:
 Contract Amount:        $12,154,400.76  (      $12,154,400.76)
 Contract Time:          360             (   360 )
 Letting Date:           06/16/2011
 Contract Date:          07/26/2011
 W/O Issued:             08/02/2011                                                            Adjusted:
 W/O Effective:          11/07/2011                              Amount Paid:            22 %(          22 %)
 Work Started:           08/29/2011                              Time Passed:            66 %(          66 %)




                                             Construction Status Report                                   Page 102
 29031(04)     Contract: 120183      US-259   Residency:     02100        12.00 MI. US-259:RESURFACE
 SSR-245A(001)(002)SR                         ANTLERS                     (ASPHALT)BEGIN 9.656 NORTH OF THE
                                                                          END OF CONCRETE PAV' IN BROKEN
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.                         BOW(6TH ST.)& EXTEND N.
 Engineer:     Moy, Ryan                     Adjusted:
 Contract Amount:        $2,685,984.80      (      $2,685,984.80)
 Contract Time:          75                 (   75   )
 Letting Date:           05/17/2012
 Contract Date:          06/15/2012
 W/O Issued:             06/21/2012                                                              Adjusted:
 W/O Effective:          07/16/2012                                Amount Paid:              0%(          0 %)
 Work Started:                                                     Time Passed:              0%(          0 %)




County:          McIntosh                                     Commissioner District:                          1
Contracts Under Construction


 20584(04)     Contract: 120161     CORD   Residency:     01003        0.226 MI. CO.RD.:BRIDGE &
 BRF-146C(054)CI                           COBB ENGINEERING CO., INC. APPROACHES/OVER MILL CREEK, 4.0
                                                                       MI. SOUTH OF SH-9.
 Contractor:   C-GAWF CONSTRUCTION, INC.
 Engineer:     COBB                       Adjusted:
 Contract Amount:       $448,077.30      (        $448,077.30)
 Contract Time:         75               (   75   )
 Letting Date:          04/19/2012
 Contract Date:         05/22/2012
 W/O Issued:            05/25/2012                                                             Adjusted:
 W/O Effective:         07/02/2012                              Amount Paid:             57 % (      57 %)
 Work Started:          07/02/2012                              Time Passed:             60 % (      60 %)


 23511(04)     Contract: 110382     CORD   Residency:     01200        0.331 MI. CO.RD.:BRIDGE RE- HAB &
 CIRB-146C(085)RB                          SALLISAW                    APPROACHES:OVER DUCHESS CR., 3.0
                                                                       MI. W. OF THE      MUSKOGEE C/L AT
 Contractor:   JENSEN CONSTRUCTION COMPANY                             LAKE EUFAULA.
 Engineer:     Edwards, Carl              Adjusted:
 Contract Amount:       $3,480,844.47    (      $3,480,844.47)
 Contract Time:         270              (  270 )
 Letting Date:          08/18/2011
 Contract Date:         09/28/2011
 W/O Issued:            10/03/2011                                                             Adjusted:
 W/O Effective:         11/07/2011                              Amount Paid:             71 %(         71 %)
 Work Started:          10/31/2011                              Time Passed:             81 % (        81 %)


 08156(04)     Contract: 100238     US-69   Residency:     01100        0.429 MI.;US-69/BRIDGE RE-
 BHFY-013N(020)                             MUSKOGEE                    HAB.,OVER THE NORTH CANADIAN
                                                                        RIVER, 7.9 MI. NORTH OF THE
 Contractor:   JENSEN CONSTRUCTION COMPANY                              PITTSBURG C/L.
 Engineer:     Ivy, Steve (Act.)           Adjusted:
 Contract Amount:        $11,498,787.17   (     $11,944,862.33)
 Contract Time:          635              (  770 )
 Letting Date:           07/22/2010
 Contract Date:          09/10/2010
 W/O Issued:             09/16/2010                                                             Adjusted:
 W/O Effective:          12/06/2010                              Amount Paid:             87 %(       84 %)
 Work Started:           11/01/2010                              Time Passed:            103 %(       85 %)




                                             Construction Status Report                            Page 103
 24003(04)     Contract: 110173      CORD      Residency:      01100           1.671 MI. CO.RD.;GRADE,DRAIN , &
 SEC1702-146C(088)HP                           MUSKOGEE                        SURFACE:(TEXANNA RD.)FROM THE
                                                                               US-69 JCT NEAR LAKE
 Contractor:   GLOVER & ASSOCIATES, INC.                                       EUFAULA,EXTEND EAST.
 Engineer:     Ivy, Steve (Act.)             Adjusted:
 Contract Amount:        $1,153,615.03      (      $1,157,559.54)
 Contract Time:          90                 (  129 )
 Letting Date:           04/14/2011
 Contract Date:          07/27/2011
 W/O Issued:             08/04/2011                                                                 Adjusted:
 W/O Effective:          08/29/2011                                      Amount Paid:          82 % (     82 %)
 Work Started:           09/12/2011                                      Time Passed:         143 % (    100 %)


 20884(06)     Contract: 100605     IS-40   Residency:     01100        4.987 MI. IS-40;PAVEMENT RE
 IMY-0040-6(369)265                         MUSKOGEE                    -HAB(P.C. CONCRETE)FROM THE US-69
                                                                        BUSINESS RD. IN CHECOTAH , EXTEND
 Contractor:   DOBSON BROTHERS CONSTRUCTION CO.                         EAST.
 Engineer:     Ivy, Steve (Act.)           Adjusted:
 Contract Amount:        $15,987,937.22   (     $16,080,499.91)
 Contract Time:          400              (  527 )
 Letting Date:           10/21/2010
 Contract Date:          11/17/2010
 W/O Issued:             11/19/2010                                                            Adjusted:
 W/O Effective:          03/07/2011                              Amount Paid:             89 % (      88 %)
 Work Started:           02/01/2011                              Time Passed:            122 % (      92 %)




County:         Major                                        Commissioner District:                                 6
Contracts Under Construction


 17360(18)     Contract: 100528     US-412   Residency:     06100        6.640 MI.;US-412/GRADE,DRAIN
 NHY-147N(075)IP                             BUFFALO                     ,SURFACE & BRIDGE;FROM 8.4 MI.E. OF
                                                                         THE US-281 JUNCTION, EXTEND EAST.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Burke, David                 Adjusted:
 Contract Amount:       $9,815,494.00      (     $10,531,136.39)
 Contract Time:         310                (  561 )
 Letting Date:          10/21/2010
 Contract Date:         11/24/2010
 W/O Issued:            12/02/2010                                                              Adjusted:
 W/O Effective:         01/24/2011                                Amount Paid:            96 %(         90 %)
 Work Started:          01/24/2011                                Time Passed:           169 % (        93 %)


 25104(04)     Contract: 120055     CORD       Residency:      06004        8.90 MI. CO.RD.;RESURFACE
 CIRB-147C(135)(167)RB                         JACOBS (AKA -                (ASPHALT)BEGIN AT SH-58, EX- TEND
                                                               CARTER-BURGESS)
                                                                            EAST.
 Contractor:   J & R SAND COMPANY, INC.
 Engineer:     JACOBS (AKA - C-B)            Adjusted:
 Contract Amount:       $3,894,981.34       (      $3,894,981.34)
 Contract Time:         90                  (   90   )
 Letting Date:          01/19/2012
 Contract Date:         02/21/2012
 W/O Issued:            02/28/2012                                                                 Adjusted:
 W/O Effective:         06/04/2012                                       Amount Paid:          88 %(     88 %)
 Work Started:          06/05/2012                                       Time Passed:          80 %(     80 %)




                                            Construction Status Report                                   Page 104
24615(04)     Contract: 110518     CORD    Residency:     06009        0.151 MI. CO.RD.;BRIDGE &
BRF-147C(127)CI                            CIRCUIT ENGR. DISTR. # 8    APPROACHES/OVER WEST BRANCH
                                                                       BARNEY CR., 8.3 MI. EAST   OF US-281.
Contractor:   BRIDGECO CONTRACTORS, INC.
Engineer:     CED8                        Adjusted:
Contract Amount:       $385,007.89       (        $401,188.60)
Contract Time:         120               (  127 )
Letting Date:          11/17/2011
Contract Date:         12/16/2011
W/O Issued:            12/20/2011                                                               Adjusted:
W/O Effective:         03/05/2012                                Amount Paid:            95 % (        91 %)
Work Started:          03/05/2012                               Time Passed:             98 % (        93 %)


25831(04)     Contract: 110337      CORD      Residency:      06009           0.321 MI. CO.RD.:BRIDGE &
BRO-147D(145)CI                               CIRCUIT ENGR. DISTR. # 8        APPROACHES/OVER EAGLE CHIEF
                                                                              CREEK, 3.5 MI. NORTH OF THE US-60
Contractor:   K & R BUILDERS, INC.                                            JUNCTION
Engineer:     CED8                          Adjusted:
Contract Amount:        $592,169.50        (        $592,169.50)
Contract Time:          120                (  129 )
Letting Date:           07/21/2011
Contract Date:          08/09/2011
W/O Issued:             08/18/2011                                                                Adjusted:
W/O Effective:          11/07/2011                                      Amount Paid:         94 % (     94 %)
Work Started:           09/14/2011                                      Time Passed:        100 % (     93 %)


23274(08)     Contract: 110333     US-64      Residency:      06200           0.00 MI. US-64;BRIDGE WATER PROOF
BRFY-147C(170)                                GUYMON                          SEAL/US-283/US-287/SH-8 /SH-58:AT
                                                                              VARIOUS LOCATIONS IN DIV. VI.
Contractor:   GARY A. CRAIN, INC.
Engineer:     Michael, Charles              Adjusted:
Contract Amount:        $58,818.00         (          $58,818.00)
Contract Time:          30                 (   30   )
Letting Date:           08/18/2011
Contract Date:          09/28/2011
W/O Issued:             10/04/2011                                                                Adjusted:
W/O Effective:          11/07/2011                                      Amount Paid:          86 %(     86 %)
Work Started:           04/10/2012                                      Time Passed:          63 %(     63 %)


24068(04)     Contract: 100091     US-281   Residency:     06100        0.491 MI. US-281;BRIDGE &
STP-STIM(519)                               BUFFALO                     APPROACHES,OVER GRIEVER CR., 5.0
                                                                        MI. NORTH OF US-60E.
Contractor:   SEWELL BROS., INC.
Engineer:     Burke, David                 Adjusted:
Contract Amount:       $3,035,684.32      (      $3,038,474.32)
Contract Time:         275                (  483 )
Letting Date:          03/18/2010
Contract Date:         04/26/2010
W/O Issued:            05/03/2010                                                               Adjusted:
W/O Effective:         08/02/2010                                Amount Paid:            88  %(       88 %)
Work Started:          06/25/2010                                Time Passed:           180  %(      102 %)




                                           Construction Status Report                                  Page 105
 24230(04)     Contract: 120213     SH-58      Residency:      06100           0.632 MI. SH-58;BRIDGE &
 BRFY-147C(121)                                BUFFALO                         APPROACHES/OVER INDIAN CR. 4.0MI.
                                                                               N. & 3.0 MI. EAST OF  SH-8/SH-58 JCT.
 Contractor:   UNITED CONTRACTORS, INC.
 Engineer:     Burke, David                  Adjusted:
 Contract Amount:       $3,892,474.05       (      $3,892,474.05)
 Contract Time:         160                 (  160 )
 Letting Date:          05/17/2012
 Contract Date:         06/14/2012
 W/O Issued:            07/13/2012                                                                 Adjusted:
 W/O Effective:         09/04/2012                                       Amount Paid:            0%(      0 %)
 Work Started:                                                           Time Passed:            0%(      0 %)




County:         Marshall                                     Commissioner District:                                    2
Contracts Under Construction


 21097(04)     Contract: 120135      CORD      Residency:      02013           0.275 MI. CO.RD.:BRIDGE &
 BRO-148D(041)CI                               CIRCUIT ENGR. DISTRICT # 3      APPROACHES:OVER CANEY CR. 1.7 MI. S.
                                                                               & 0.4 MI. W. OF US- 70/SH-32 JCT.
 Contractor:   L & N BRIDGE, LLC
 Engineer:     CED3                          Adjusted:
 Contract Amount:        $854,852.70        (        $854,852.70)
 Contract Time:          150                (  150 )
 Letting Date:           03/15/2012
 Contract Date:          04/19/2012
 W/O Issued:             04/23/2012                                                                 Adjusted:
 W/O Effective:          07/02/2012                                      Amount Paid:          26 % (     26 %)
 Work Started:           07/02/2012                                      Time Passed:          30 % (     30 %)




County:         Mayes                                        Commissioner District:                                    8
Contracts Under Construction


 20893(05)     Contract: 120267      US-69   Residency:     08300        0.00 MI. US-69:BRIDGE REHAB. OVER
 SBR-249N(004)SB                             CLAREMORE                   CHOUTEAU CR., 9.4 MI. N. OF THE
                                                                         WAGONER C/L.
 Contractor:   SCR CONSTRUCTION CO., INC.
 Engineer:     Bray, Timothy                Adjusted:
 Contract Amount:        $668,821.90       (        $668,821.90)
 Contract Time:          80                (   80   )
 Letting Date:           06/21/2012
 Contract Date:          07/18/2012
 W/O Issued:             07/20/2012                                                              Adjusted:
 W/O Effective:          08/13/2012                               Amount Paid:              0 %(         0 %)
 Work Started:           08/24/2012                               Time Passed:              0%(          0 %)




                                            Construction Status Report                                   Page 106
25417(04)     Contract: 110440     CORD       Residency:      08004           2.03 MI. CO.RD. CHIMNEY ROCK RD
STP-149D(124)CI                                                          (EW-50) FROM SH-28 EXTEND EAST.
                                              JACOBS (AKA - CARTER-BURGESS)
Contractor:   GLOVER & ASSOCIATES, INC.
Engineer:     JACOBS (AKA - C-B)            Adjusted:
Contract Amount:       $2,881,866.71       (      $2,881,866.71)
Contract Time:         190                 (  190 )
Letting Date:          09/15/2011
Contract Date:         10/12/2011
W/O Issued:            10/19/2011                                                                  Adjusted:
W/O Effective:         01/02/2012                                       Amount Paid:          41 % (     41 %)
Work Started:          02/23/2012                                       Time Passed:          96 % (     96 %)


28497(04)     Contract: 120136     CORD       Residency:      08012           0.052 MI. CO.RD.;BRIDGE REHA-
BHO-149D(148)CI                               PSA-DEWBERRY                    BILITATION/OVER UNION PACIFIC R/R
                                                                              0.30 MI. WEST OF US-69
Contractor:   PBX CORPORATION
Engineer:     PSAD                          Adjusted:
Contract Amount:       $492,418.00         (        $492,418.00)
Contract Time:         60                  (   60   )
Letting Date:          05/17/2012
Contract Date:         06/15/2012
W/O Issued:            06/20/2012                                                                Adjusted:
W/O Effective:         09/04/2012                                       Amount Paid:           0%(      0 %)
Work Started:                                                           Time Passed:           0%(      0 %)


28965(04)     Contract: 120137     US-412   Residency:     08012        *-266A(004)TR/ 26.50 MI. US
HSIPG-149A(150)TR/HSIPG*                    PSA-DEWBERRY                -412(SIGNING) BEGIN AT IS-44 EXTEND
                                                                        EAST.
Contractor:   ADVANCED WORKZONE SERVICES, LLC
Engineer:     PSAD                         Adjusted:
Contract Amount:       $284,490.36        (        $284,490.36)
Contract Time:         150                (  150   )
Letting Date:          03/15/2012
Contract Date:         04/19/2012
W/O Issued:            04/23/2012                                                               Adjusted:
W/O Effective:         07/22/2012                                Amount Paid:            17  %(        17 %)
Work Started:          06/18/2012                                Time Passed:            30  %(        30 %)


06549(04)     Contract: 120184     CORD       Residency:      08012           2.032 MI. CO.RD./GRADE,DRAIN, &
CIRB-049C(286)RB                              PSA-DEWBERRY                    SURFACE(ELLIOT ST.)FROM SH- 69A,
                                                                              EXTEND NORTH.
Contractor:   BECCO CONTRACTORS, INC.
Engineer:     PSAD                          Adjusted:
Contract Amount:       $2,787,246.48       (      $2,787,246.48)
Contract Time:         150                 (  150 )
Letting Date:          05/17/2012
Contract Date:         06/14/2012
W/O Issued:            06/18/2012                                                                 Adjusted:
W/O Effective:         09/04/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                           Time Passed:           0 %(      0 %)




                                           Construction Status Report                                   Page 107
 23169(07)     Contract: 120022      US-69   Residency:     08300        6.79 MI. US-69;PAVEMENT RE- HAB.
 SSR-149N(146)SR                             CLAREMORE                   (P.C.CONCRETE)FROM THE WAGONER
                                                                         COUNTY LINE,EXTEND NORTH.
 Contractor:   CHESTER BROSS CONSTRUCTION COMPANY/C.B. EQUIPMENT, INC.
 Engineer:     Bray, Timothy                Adjusted:
 Contract Amount:        $1,880,427.62     (      $1,880,427.62)
 Contract Time:          180               (  180 )
 Letting Date:           01/19/2012
 Contract Date:          02/15/2012
 W/O Issued:             03/20/2012                                                             Adjusted:
 W/O Effective:          05/07/2012                               Amount Paid:            55 % (       55 %)
 Work Started:           04/23/2012                               Time Passed:            57 % (       57 %)


 21910(04)     Contract: 110338     SH28       Residency:       08004           1.11 MI. SH-28:BRIDGE AND
 BRFY-149C(079)                                                           APPROACHES OVER BIG CABIN CREEK,
                                               JACOBS (AKA - CARTER-BURGESS)
                                                                                7.5 MI. E OF US-69
 Contractor:   UNITED CONTRACTORS, INC.
 Engineer:     JACOBS (AKA - C-B)            Adjusted:
 Contract Amount:       $7,829,965.12       (      $7,829,965.12)
 Contract Time:         330                 (  330 )
 Letting Date:          10/20/2011
 Contract Date:         11/21/2011
 W/O Issued:            01/11/2012                                                                    Adjusted:
 W/O Effective:         03/05/2012                                        Amount Paid:           47 % (     47 %)
 Work Started:          02/06/2012                                        Time Passed:           58 % (     58 %)




County:          Murray                                       Commissioner District:                                   7
Contracts Under Construction


 26241(04)     Contract: 110191     US177   Residency:     07003        .99 MI. US-177:GRADE,DRAIN, AND
 SSP-150B(079)SS                            COBB ENGINEERING CO., INC. SURFACE;CHICKASAW TURNPIKE, 2.0 MI.
                                                                        N OF SH-7
 Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.
 Engineer:     COBB                        Adjusted:
 Contract Amount:       $2,756,145.50     (      $2,763,531.58)
 Contract Time:         160               (  183 )
 Letting Date:          10/20/2011
 Contract Date:         11/23/2011
 W/O Issued:            12/07/2011                                                             Adjusted:
 W/O Effective:         03/05/2012                               Amount Paid:            75 %(          75 %)
 Work Started:          03/05/2012                               Time Passed:            93 % (         81 %)


 20303(04)     Contract: 110475      SH-77D   Residency:     07200        1.907 MI. SH-77D;GRADE,DRAIN &
 STPY-150C(090)                               ARDMORE                     SURFACE/FROM THE US-77 JCT, EXT.
                                                                          SOUTHEAST.
 Contractor:   MERIDIAN CONTRACTING, INC.
 Engineer:     Earp, Jay                     Adjusted:
 Contract Amount:        $4,513,391.00      (      $4,513,391.00)
 Contract Time:          180                (  180 )
 Letting Date:           05/17/2012
 Contract Date:          06/15/2012
 W/O Issued:             06/20/2012                                                              Adjusted:
 W/O Effective:          08/06/2012                                Amount Paid:             0 %(           0 %)
 Work Started:           08/06/2012                                Time Passed:             0 %(           0 %)




                                             Construction Status Report                                     Page 108
 20328(05)     Contract: 120214     I-35      Residency:    07001         0.00 MI. I-35/US-77:BRIDGE
 BRFY-NBIP(452)                               ENGR. SERV. & TESTING       PAINTING: AT MULTIPLE LO-  CATIONS
                                                                          IN DIV. VII.
 Contractor:   PACIFIC PAINTING COMPANY, INC.
 Engineer:     EST                          Adjusted:
 Contract Amount:       $581,000.00        (        $581,000.00)
 Contract Time:         140                (   140 )
 Letting Date:          05/17/2012
 Contract Date:         06/19/2012
 W/O Issued:            06/22/2012                                                                Adjusted:
 W/O Effective:         10/01/2012                                  Amount Paid:            50 % (      50 %)
 Work Started:          07/09/2012                                 Time Passed:             26 % (      26 %)


 20328(08)     Contract: 120215     I-35       Residency:       07001           0.00 MI. I-35/US-77:JOINT
 BRFY-250N(002)                                ENGR. SERV. & TESTING            SEAL/REPAIR: AT MULTIPLE LO-
                                                                                CATIONS IN DIV. VII.
 Contractor:   PBX CORPORATION
 Engineer:     EST                            Adjusted:
 Contract Amount:       $373,819.00          (        $373,819.00)
 Contract Time:         60                   (   60   )
 Letting Date:          05/17/2012
 Contract Date:         06/15/2012
 W/O Issued:            06/20/2012                                                                  Adjusted:
 W/O Effective:         10/01/2012                                        Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)




County:          Muskogee                                     Commissioner District:                                 1
Contracts Under Construction


 23105(09)     Contract: 120162     IS-40      Residency:       01100           0.00 MI. IS-40/BRIDGE WATER- PROOF
 BRFY-251C(004)                                MUSKOGEE                         SEAL/SH-2/SH-16/SH-51: AT MULTIPLE
                                                                                LOCATIONS IN DIV. I.
 Contractor:   GARY A. CRAIN, INC.
 Engineer:     Ivy, Steve (Act.)              Adjusted:
 Contract Amount:        $61,220.00          (          $61,220.00)
 Contract Time:          30                  (   30   )
 Letting Date:           04/19/2012
 Contract Date:          05/21/2012
 W/O Issued:             05/24/2012                                                                  Adjusted:
 W/O Effective:          08/06/2012                                       Amount Paid:          82 %(      82 %)
 Work Started:           07/31/2012                                       Time Passed:          53 % (     53 %)


 29022(04)     Contract: 120106      US-69     Residency:       01100           2.85 MI. US-69:RESURFACE
 NHY-013N(154)3P                               MUSKOGEE                         (ASPHALT)FROM JUST NORTH OF US-62
                                                                                EAST, EXTEND NORTH.
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Ivy, Steve (Act.)              Adjusted:
 Contract Amount:        $1,042,275.00       (      $1,042,275.00)
 Contract Time:          60                  (   60   )
 Letting Date:           02/16/2012
 Contract Date:          03/14/2012
 W/O Issued:             03/22/2012                                                                 Adjusted:
 W/O Effective:          08/06/2012                                       Amount Paid:           8 %(      8 %)
 Work Started:           08/14/2012                                       Time Passed:          17 %(     17 %)




                                             Construction Status Report                                   Page 109
 29187(04)     Contract: 120216     I-40       Residency:       01200           8.500 MI. IS-40:SAFETY IM-
 HSIPIG-0040-6(379)282TR                       SALLISAW                         PROVEMENT(CABLE BARRIER)FROM
                                                                                MILE MARKER 282, EXTEND    EAST.
 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     Edwards, Carl                  Adjusted:
 Contract Amount:       $876,720.10          (        $876,720.10)
 Contract Time:         180                  (  180 )
 Letting Date:          05/17/2012
 Contract Date:         06/21/2012
 W/O Issued:            06/28/2012                                                                  Adjusted:
 W/O Effective:         09/04/2012                                        Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)




County:          Noble                                        Commissioner District:                                   4
Contracts Under Construction


 26181(04)     Contract: 110489      I35       Residency:       04100           7.04 MI. I-35: CABLE BARRIER FROM MM
 IMG-0035-4(231)190TR                          PERRY                            190 TO MM 198

 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     Zachary, Ted                   Adjusted:
 Contract Amount:        $1,013,113.67       (      $1,013,113.67)
 Contract Time:          120                 (  120 )
 Letting Date:           10/20/2011
 Contract Date:          11/21/2011
 W/O Issued:             11/28/2011                                                                  Adjusted:
 W/O Effective:          02/06/2012                                       Amount Paid:          78 % (     78 %)
 Work Started:           03/01/2012                                       Time Passed:         100 % (    100 %)


 27909(04)     Contract: 110490      I-35   Residency:     04100        .74 MI. I-35:BRIDGE,APPROACHES,&
 IMY-0035-4(244)186/SBR-*                   PERRY                       CABLE BARRIER;OVER US-64(FIR ST)1.0
                                                                        MI. N OF US-77 IN PERRY, OVER BNSF
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                          RAILROAD.
 Engineer:     Zachary, Ted                Adjusted:
 Contract Amount:        $6,254,011.33    (      $6,424,547.38)
 Contract Time:          300              (  330 )
 Letting Date:           10/20/2011
 Contract Date:          11/17/2011
 W/O Issued:             12/07/2011                                                              Adjusted:
 W/O Effective:          02/06/2012                              Amount Paid:             49 %(         48 %)
 Work Started:           02/06/2012                              Time Passed:             58 % (        53 %)
 *152N(191)SB

 29190(04)     Contract: 120262      IS-35     Residency:       04500           5.70 MI. IS-35:SAFETY IMPROV. (CABLE
 HSIPIG-0035-4(246)170                         STILLWATER                       BARRIER)IN PAYNE CO. FROM MM170
                                                                                EXTEND N. 4.0 MI. IN NOBLE CO.
 Contractor:   ACTION SAFETY SUPPLY CO.
 Engineer:     Arps, Jonathan                 Adjusted:
 Contract Amount:        $658,048.73         (        $658,048.73)
 Contract Time:          140                 (  140   )
 Letting Date:           07/19/2012
 Contract Date:          08/21/2012
 W/O Issued:             08/24/2012                                                                  Adjusted:
 W/O Effective:          09/17/2012                                       Amount Paid:            0 %(      0 %)
 Work Started:                                                            Time Passed:            0 %(      0 %)




                                             Construction Status Report                                    Page 110
 20311(04)     Contract: 110247      US-64   Residency:     04100        6.523 MI. US-64;GRADE,DRAIN &
 STPY-152B(105)                              PERRY                       BRIDGE;FROM BOUNDARY ST. IN PERRY,
                                                                         EXTEND EAST.
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
 Engineer:     Zachary, Ted                 Adjusted:
 Contract Amount:        $6,812,122.07     (      $6,812,122.07)
 Contract Time:          360               (  412 )
 Letting Date:           04/14/2011
 Contract Date:          05/12/2011
 W/O Issued:             05/18/2011                                                             Adjusted:
 W/O Effective:          09/06/2011                               Amount Paid:            40 % (       40 %)
 Work Started:           09/07/2011                               Time Passed:            96 % (       84 %)


 23306(09)     Contract: 120185      I-35      Residency:       04500           0.00 MI. I-35/I-40/US-64/
 BRFY-252F(004)                                STILLWATER                       US-77/US-177/SH-15/SH-33/SH-86SH-156
                                                                                :VARIOUS LOCATIONS        IN DIV. IV.
 Contractor:   GARY A. CRAIN, INC.
 Engineer:     Arps, Jonathan                 Adjusted:
 Contract Amount:        $659,148.75         (        $659,148.75)
 Contract Time:          100                 (  100 )
 Letting Date:           05/17/2012
 Contract Date:          06/19/2012
 W/O Issued:             06/21/2012                                                                  Adjusted:
 W/O Effective:          07/16/2012                                       Amount Paid:          37 % (     37 %)
 Work Started:                                                            Time Passed:          29 % (     29 %)


 21861(04)     Contract: 120023      US-77     Residency:       04100           0.139 MI. US-77;BRIDGE &
 BRFY-152C(068)                                PERRY                            APPROACHES/OVER BLACK BEAR CR.4.2
                                                                                MI. NORTH OF THE US-     64 JCT.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     Zachary, Ted                   Adjusted:
 Contract Amount:        $1,386,675.28       (      $1,392,203.32)
 Contract Time:          90                  (   90   )
 Letting Date:           01/19/2012
 Contract Date:          02/23/2012
 W/O Issued:             03/12/2012                                                                 Adjusted:
 W/O Effective:          04/16/2012                                       Amount Paid:          98 %(     97 %)
 Work Started:           04/16/2012                                       Time Passed:          91 %(     91 %)


 27600(04)     Contract: 120234      US-77   Residency:     04100        5.3600 MI. US-77/ RESURFACE
 SSR-152C(190)SR                             PERRY                       (ASPHALT) FROM SH-164, EXTEND EAST.

 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Zachary, Ted                 Adjusted:
 Contract Amount:        $1,764,920.00     (      $1,764,920.00)
 Contract Time:                            (        )
 Letting Date:           05/17/2012
 Contract Date:          06/14/2012                               Fixed Completion Date: 10/31/2012
 W/O Issued:             06/18/2012                                                              Adjusted:
 W/O Effective:                                                   Amount Paid:              0 %(         0 %)
 Work Started:           07/27/2012                               Time Passed:              5 %(         4 %)




County:          Nowata                                       Commissioner District:                                    8
Contracts Under Construction




                                             Construction Status Report                                   Page 111
 23129(04)     Contract: 110441      US-169   Residency:     08300        .275 MI. US-169 OVER CALIFORNIA
 BRFY-153N(147)                               CLAREMORE                   CREEK, 3.5 MI. N OF US-60 JCT.

 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Bray, Timothy                 Adjusted:
 Contract Amount:        $3,277,995.45      (      $3,277,995.45)
 Contract Time:          180                (  180 )
 Letting Date:           09/15/2011
 Contract Date:          10/12/2011
 W/O Issued:             10/25/2011                                                               Adjusted:
 W/O Effective:          11/28/2011                                Amount Paid:             51 % (        51 %)
 Work Started:           11/30/2011                                Time Passed:            105 % (       105 %)




County:          Okfuskee                                     Commissioner District:                                      3
Contracts Under Construction


 28198(04)     Contract: 110304      US-62   Residency:     03300        3.670 MI. US-62;RESURFACE
 SSR-154C(167)SR                             WEWOKA                      (ASPHALT)FROM SH-27, EXTEND WEST.

 Contractor:   HASKELL LEMON CONSTRUCTION CO.
 Engineer:     Moore, Archie (Act.)         Adjusted:
 Contract Amount:        $641,355.00       (        $641,355.00)
 Contract Time:          35                (   35   )
 Letting Date:           06/21/2012
 Contract Date:          07/18/2012
 W/O Issued:             07/20/2012                                                             Adjusted:
 W/O Effective:          08/13/2012                               Amount Paid:              0%(        0 %)
 Work Started:           08/20/2012                               Time Passed:              0%(        0 %)


 23958(04)     Contract: 120056      CORD      Residency:       03300           0.189 MI. CO.RD.;BRIDGE &
 BRF-154C(100)CI                               WEWOKA                           APPROACHES/OVER HILLIBY
                                                                                TRIBU-TARY, 2.1 MI. N. & 2.6 MI.   EAST
 Contractor:   BELK BRIDGE, INC.                                                OF PADEN.
 Engineer:     Moore, Archie (Act.)          Adjusted:
 Contract Amount:        $302,781.75        (        $302,781.75)
 Contract Time:          90                 (   97   )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/28/2012                                                                    Adjusted:
 W/O Effective:          06/04/2012                                       Amount Paid:            93 %(      93 %)
 Work Started:           04/05/2012                                       Time Passed:            99 % (     92 %)




County:          Oklahoma                                     Commissioner District:                                      4
Contracts Under Construction




                                             Construction Status Report                                      Page 112
17428(81)     Contract: 120024     IS-40   Residency:     04400        0.382 MI. IS-40;GRADE,DRAIN, SURFACE
IMY-XTWN(074)                              EDMOND                      & BRIDGE. WEST CONNEC-TION FROM
                                                                       EAST OF AGNEW AVE. TO
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                          PENNSYLVANIA AVE.
Engineer:     Hubbard, Tom                Adjusted:
Contract Amount:       $9,162,185.05     (      $9,162,185.05)
Contract Time:         240               (  240 )
Letting Date:          01/19/2012
Contract Date:         02/22/2012
W/O Issued:            03/06/2012                                                              Adjusted:
W/O Effective:         04/09/2012                               Amount Paid:             61 % (       61 %)
Work Started:          04/09/2012                               Time Passed:             51 % (       51 %)


27589(04)     Contract: 110276     IS-44   Residency:     04400        0.07 MI. IS-44;BRIDGE IMPRO-
SBR-155A(875)SB                            EDMOND                      VEMENTS. CT.ST.(LINCOLN BLVD)
                                                                       SOUTHBOUND LINCOLN BLVD. OVER
Contractor:   SCR CONSTRUCTION CO., INC.                               IS-44.
Engineer:     Hubbard, Tom                Adjusted:
Contract Amount:       $465,034.95       (        $465,034.95)
Contract Time:         60                (   60   )
Letting Date:          01/19/2012
Contract Date:         02/23/2012
W/O Issued:            03/01/2012                                                              Adjusted:
W/O Effective:         06/04/2012                               Amount Paid:             76 % (       76 %)
Work Started:          06/04/2012                               Time Passed:            122 % (      122 %)


17428(28)     Contract: 100503    IS-40    Residency:     04400        *(12)TI/SEC115-155N(807)SG; 2.2 MI.
OKCY-XTWN(009)/OKCY-XTWN*                  EDMOND                      IS-40;SURFACING &    TRAFFIC
                                                                       CONTROL/FROM W. OF MAY
Contractor:                                                             JV
              DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCAVE.,EXTEND E. IN OKC.
Engineer:     Hubbard, Tom               Adjusted:
Contract Amount:       $29,346,556.72   (      $31,566,323.54)
Contract Time:         370              (   526 )
Letting Date:          08/19/2010
Contract Date:         09/20/2010
W/O Issued:            09/27/2010                                                             Adjusted:
W/O Effective:         11/08/2010                               Amount Paid:           104 %(        97 %)
Work Started:          10/20/2010                               Time Passed:           121 %(        85 %)


28588(04)     Contract: 110480     I240      Residency:       04002           0.00 MI. I-240/SH-152: BRIDGE
BRFY-NBIP(443)3B                             TETRA TECH                       PAINTING VARIOUS LOCATION IN DIV. 4.

Contractor:   SEMINOLE EQUIPMENT, INC.
Engineer:     TETR                         Adjusted:
Contract Amount:       $411,000.00        (        $411,000.00)
Contract Time:         60                 (   60   )
Letting Date:          10/20/2011
Contract Date:         11/21/2011
W/O Issued:            03/02/2012                                                                 Adjusted:
W/O Effective:         03/05/2012                                       Amount Paid:          85 %(     85 %)
Work Started:          03/21/2012                                       Time Passed:         182 %(    182 %)




                                           Construction Status Report                                   Page 113
09033(40)     Contract: 100615    IS-235   Residency:     04400        2.19 MI. IS-235:GRADE,DRAIN, SURFACE
IMY-0235-1(103)005IP                       EDMOND                      & BRIDGE/ON THE SOUTH-BOUND TO
                                                                       WESTBOUND OFF RAMPS, AT THE IS-44
Contractor:   HASKELL LEMON CONSTRUCTION CO.                           INTERCHANGE.
Engineer:     Hubbard, Tom                Adjusted:
Contract Amount:       $18,135,376.41    (     $18,746,715.78)
Contract Time:         400               (  424 )
Letting Date:          01/20/2011
Contract Date:         02/25/2011
W/O Issued:            04/26/2011                                                              Adjusted:
W/O Effective:         06/06/2011                               Amount Paid:            103 % (      100 %)
Work Started:          06/20/2011                               Time Passed:            109 % (      103 %)


27834(04)     Contract: 120163      CTST   Residency:     04600        0.370 MI. CT.ST.:INTERSEC- TION
STP-155B(800)AG                            OKLAHOMA CITY               MODIFICATION/AT N.E. 10THST. IN THE
                                                                       CITY OF NICOMA     PARK.
Contractor:   SCHIRALLI CONSTRUCTION CORP.
Engineer:     Howell, Terry               Adjusted:
Contract Amount:        $923,530.70      (        $923,530.70)
Contract Time:          75               (   75   )
Letting Date:           04/19/2012
Contract Date:          05/18/2012
W/O Issued:             05/23/2012                                                              Adjusted:
W/O Effective:          06/24/2012                              Amount Paid:             48 % (        48 %)
Work Started:           06/18/2012                              Time Passed:             75 % (        75 %)


29266(04)     Contract: 120170      CTST   Residency:     04600        0.52 MI. CT.ST.(LINCOLN
CMC-255A(062)                              OKLAHOMA CITY               BLVD.)RESURFACE (ASPHALT)FROM JUST
                                                                       S. OF 14TH ST., EXTEND NORTH IN OKC.
Contractor:   HASKELL LEMON CONSTRUCTION CO.
Engineer:     Howell, Terry               Adjusted:
Contract Amount:        $360,375.00      (        $360,375.00)
Contract Time:          45               (   45   )
Letting Date:           04/19/2012
Contract Date:          05/16/2012
W/O Issued:             05/18/2012                                                             Adjusted:
W/O Effective:          08/06/2012                              Amount Paid:              22 %(       22 %)
Work Started:           07/10/2012                              Time Passed:               7 %(         7 %)


21043(04)     Contract: 110012     CTST       Residency:      04004           0.63 MI. CT.ST.:GRADE,DRAIN &
STP-155B(412)AG                                                          SURFACE:(15TH ST.)FROM
                                              JACOBS (AKA - CARTER-BURGESS)                             VICKIE
                                                                              DRIVE, EXTEND EAST   IN DEL CITY.
Contractor:   SCHWARZ PAVING CO., INC.
Engineer:     JACOBS (AKA - C-B)            Adjusted:
Contract Amount:       $2,576,116.82       (      $2,636,975.56)
Contract Time:         240                 (  352 )
Letting Date:          06/16/2011
Contract Date:         07/26/2011
W/O Issued:            08/01/2011                                                                 Adjusted:
W/O Effective:         10/03/2011                                       Amount Paid:          94 %(     91 %)
Work Started:          10/10/2011                                       Time Passed:         130 %(     89 %)




                                           Construction Status Report                                       Page 114
24041(05)     Contract: 110491    CTST     Residency:     04400        2.62 MI. CTST: GRADE,DRAIN AND
STP-155C(651)(852)AG                       EDMOND                      SURFACE; KELLY AVE FROM N OF 192ND
                                                                       ST EXT N, AND COVELL RD FROM E OF
Contractor:                                                             JV
              DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCSANTE FE EXT E IN ED
Engineer:     Hubbard, Tom               Adjusted:
Contract Amount:       $14,769,759.12   (      $14,788,266.78)
Contract Time:         325             (    325 )
Letting Date:          10/20/2011
Contract Date:         11/17/2011
W/O Issued:            11/22/2011                                                             Adjusted:
W/O Effective:         02/06/2012                               Amount Paid:            54 % (        54 %)
Work Started:          01/16/2012                               Time Passed:            66 % (        66 %)
MOND.

28588(05)     Contract: 110496    I240        Residency:       04002           0.00 MI. I-240/SH-152: JOINT
BRFY-155A(877)3B                              TETRA TECH                       SEAL/REPAIR; VARIOUS LOCATIONS IN
                                                                               DIVISION 4.
Contractor:   PBX CORPORATION
Engineer:     TETR                           Adjusted:
Contract Amount:       $44,218.00           (          $44,218.00)
Contract Time:         60                   (   60   )
Letting Date:          10/20/2011
Contract Date:         11/22/2011
W/O Issued:            11/29/2011                                                                  Adjusted:
W/O Effective:         03/05/2012                                        Amount Paid:            0%(      0 %)
Work Started:                                                            Time Passed:            0%(      0 %)


28541(04)     Contract: 110519     CT.ST.     Residency:       04400           1.723 MI. CT.ST.;RESURFACE
STP-155A(870)AG                               EDMOND                           (ASPHALT)(MEMORIAL RD.)FROM
                                                                               WESTERN AVE., EXTEND EAST   IN OKC.
Contractor:   ATLAS PAVING COMPANY
Engineer:     Hubbard, Tom                   Adjusted:
Contract Amount:       $1,048,923.35        (      $1,048,923.35)
Contract Time:         45                   (   45   )
Letting Date:          11/17/2011
Contract Date:         12/12/2011
W/O Issued:            12/19/2011                                                                   Adjusted:
W/O Effective:         05/07/2012                                        Amount Paid:           91 %(     91 %)
Work Started:          05/07/2012                                        Time Passed:           96 %(     96 %)


29188(04)     Contract: 120232      I-240     Residency:       04600           2.97 MI. I-240;SAFETY IMPROV. (CABLE
HSIPIG-0240-1(357)008TR                       OKLAHOMA CITY                    BARRIER)FROM MILE      MARKER8,
                                                                               EXTEND EAST.
Contractor:   ACTION SAFETY SUPPLY CO.
Engineer:     Howell, Terry                  Adjusted:
Contract Amount:        $653,775.36         (        $653,775.36)
Contract Time:          60                  (   60   )
Letting Date:           05/17/2012
Contract Date:          06/21/2012
W/O Issued:             06/28/2012                                                                  Adjusted:
W/O Effective:          09/04/2012                                       Amount Paid:            0 %(      0 %)
Work Started:           08/20/2012                                       Time Passed:            0 %(      0 %)




                                            Construction Status Report                                    Page 115
28128(30)     Contract: 120072      IS-40   Residency:     04600        22.900 MI. IS-40;SAFETY IM-
BTOP-255N(002)                              OKLAHOMA CITY               PROVEMENTS(FIBER OPTIC CABLE) FROM
                                                                        THE EDUCATIONAL TELE- VISIONS
Contractor:   EWING SIGNAL CONSTRUCTION                                 NETWORK BLDG.IN OKC.
Engineer:     Howell, Terry                Adjusted:
Contract Amount:        $999,031.60       (        $999,031.60)
Contract Time:          70                (   70   )
Letting Date:           03/15/2012
Contract Date:          04/10/2012
W/O Issued:             05/16/2012                                                               Adjusted:
W/O Effective:          06/04/2012                               Amount Paid:             90 % (       90 %)
Work Started:           06/04/2012                               Time Passed:            101 % (      101 %)


28014(04)     Contract: 110255      I-240    Residency:    04600        4.53 MI. I-240 FROM DOUGLAS BLVD.
IMG-0240-1(355)011TR                         OKLAHOMA CITY              EXTEND EAST.

Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
Engineer:     Howell, Terry                Adjusted:
Contract Amount:        $1,150,500.14     (      $1,150,500.14)
Contract Time:          120               (   120 )
Letting Date:           09/15/2011
Contract Date:          10/14/2011
W/O Issued:             10/20/2011                                                             Adjusted:
W/O Effective:          01/02/2012                               Amount Paid:             70 % (       70 %)
Work Started:           01/02/2012                               Time Passed:            116 % (      116 %)


17428(58)     Contract: 110504    IS-40       Residency:       04400           0.089 MI., IS-40/AGNEW AVE.
OKCY-XTWN(046)                                EDMOND                           ;GRADE,DRAIN,SURFACE & BRIDGE
                                                                               FROM W. OF MAY AVE,EXTEND   EAST
Contractor:   ALLEN CONTRACTING, INC.                                          IN OKC, AGNEW AVE.
Engineer:     Hubbard, Tom                  Adjusted:
Contract Amount:       $17,699,647.18      (     $17,702,096.18)
Contract Time:         300                 (  300 )
Letting Date:          11/17/2011
Contract Date:         12/16/2011
W/O Issued:            12/20/2011                                                                 Adjusted:
W/O Effective:         02/15/2011                                        Amount Paid:         49 %(     49 %)
Work Started:          02/27/2012                                        Time Passed:         57 %(     57 %)


17428(77)     Contract: 110530       IS-40   Residency:     04200        1.591 MI. IS-40;BRIDGE &
ACIMY-XTWN(067)                              EL RENO                     APPROACHES(REMOVAL) DECONS-
                                                                         TRUCTION OF BRIDGE FROM
Contractor:   SHERWOOD CONSTRUCTION CO., INC.                            WESTERN AVE. TO JUST EAST.
Engineer:     Vonfeldt, Cole                Adjusted:
Contract Amount:         $9,660,191.37     (      $9,660,191.37)
Contract Time:           270               (  270 )
Letting Date:            11/17/2011
Contract Date:           12/12/2011
W/O Issued:              03/27/2012                                                               Adjusted:
W/O Effective:           04/26/2012                               Amount Paid:             84 %(        84 %)
Work Started:            04/26/2012                               Time Passed:             41 %(        41 %)




                                            Construction Status Report                                  Page 116
21978(04)     Contract: 100392     CTST     Residency:    04003        0.871 MI. CT.ST.,GRADE,DRAIN
STP-STIM(517)AG                             COBB ENGINEERING CO., INC. ,SURFACE & BRIDGE;(POST RD.) FROM
                                                                       SE 15TH ST.,EXTEND     NORTH TO
Contractor:   MARKWELL PAVING COMPANY, INC.                            MIDWEST CITY.
Engineer:     COBB                       Adjusted:
Contract Amount:       $3,206,824.41    (       $3,254,108.41)
Contract Time:         280              (    528 )
Letting Date:          06/17/2010
Contract Date:         07/15/2010
W/O Issued:            07/16/2010                                                              Adjusted:
W/O Effective:         10/04/2010                               Amount Paid:             99 % (       98 %)
Work Started:          10/04/2010                               Time Passed:            195 % (      103 %)


26273(04)     Contract: 110341      IS-35     Residency:       04600           2.67 MI. IS-35;SAFETY IMPROV
IMG-0035-3(298)129TR                          OKLAHOMA CITY                    -MENT(CABLE BARRIER)FROM 0.40 MI.
                                                                               NO. OF THE US-62 JCT, IN OKC, EXTEND
Contractor:   ACTION SAFETY SUPPLY CO.                                         NORTH.
Engineer:     Howell, Terry                  Adjusted:
Contract Amount:        $841,662.63         (        $841,662.63)
Contract Time:          90                  (   90   )
Letting Date:           07/21/2011
Contract Date:          08/16/2011
W/O Issued:             08/19/2011                                                                  Adjusted:
W/O Effective:          11/07/2011                                       Amount Paid:          74 % (     74 %)
Work Started:           01/03/2012                                       Time Passed:         109 % (    109 %)


21133(04)     Contract: 120217      CTST     Residency:    04600        0.00 MI. CT.ST.;SAFETY IM-
STPG-155F(424)AG                             OKLAHOMA CITY              PROVEMENTS(SCHOOL ZONES)
                                                                        MULTIPLE LOCATIONS IN THE    OKLA.
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.                            CITY METRO.
Engineer:     Howell, Terry                Adjusted:
Contract Amount:        $475,930.20       (        $475,930.20)
Contract Time:          180              (    180  )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                               Adjusted:
W/O Effective:          11/26/2012                               Amount Paid:              0 %(         0 %)
Work Started:                                                    Time Passed:              0 %(         0 %)


24107(04)     Contract: 120258     CORD       Residency:       04400           14.91 MI. CO.RD.:STRIPING   (COVELL
STPG-155F(605)AG                              EDMOND                           RD./EDMOND RD./MACAR- THUR BLVD.)
                                                                               MULTIPLE LO-     CATIONS IN OKLA.
Contractor:   ACTION SAFETY SUPPLY CO.                                         COUNTY.
Engineer:     Hubbard, Tom                   Adjusted:
Contract Amount:       $109,271.30          (        $109,271.30)
Contract Time:         30                   (   30   )
Letting Date:          07/19/2012
Contract Date:         08/21/2012
W/O Issued:            08/24/2012                                                                   Adjusted:
W/O Effective:         09/17/2012                                        Amount Paid:            0 %(      0 %)
Work Started:                                                            Time Passed:            0 %(      0 %)




                                            Construction Status Report                                   Page 117
17428(22)     Contract: 090501      I-40   Residency:     04200        1.072 MI. GRADE, DRAIN, SURFACE,
OKCY-XTWN(003)TI                           EL RENO                     BRIDGE & RAILROAD I-40 FROM EAST OF
                                                                       WESTERN AVE. EXTEND EAST.
Contractor:   ALLEN CONTR., INC./SHERWOOD CONST. CO, INC./MANHATTAN RD. &
Engineer:     Vonfeldt, Cole              Adjusted:
Contract Amount:         $63,211,594.70  (     $66,216,867.56)
Contract Time:           520             (  843 )
Letting Date:            07/23/2009
Contract Date:           08/10/2009
W/O Issued:              08/11/2009                                                            Adjusted:
W/O Effective:           09/14/2009                             Amount Paid:           105 % (       100 %)
Work Started:            09/08/2009                             Time Passed:           192 % (       118 %)


26119(04)     Contract: 110248     CT.ST.    Residency:     04011        0.026 MI. CT.ST. BRIDGE &
STP-155A(691)AG                              GARVER, LLC.                APPROACHES/(RENO AVE.)OVER
                                                                         CROOKED OAK CR., AT BRYANT AVE.
Contractor:   C-P INTEGRATED SERVICES, INC.                              IN DEL CITY.
Engineer:     GARV                          Adjusted:
Contract Amount:       $641,907.69        (         $675,037.69)
Contract Time:         90                 (   190 )
Letting Date:          04/14/2011
Contract Date:         05/18/2011
W/O Issued:            05/25/2011                                                                 Adjusted:
W/O Effective:         08/01/2011                                 Amount Paid:             90 % (       86 %)
Work Started:          08/01/2011                                 Time Passed:            387 % (      183 %)


28510(04)     Contract: 110358      IS-35    Residency:    08100        *-172F(530)IT/ 0.00 MI. IS -35:SAFETY
HSIPG-155F(865)IT/HSIPG*                     TULSA                      IMPROVEMENT:AT VA- RIOUS
                                                                        LOCATIONS IN OKC METRO AREA.ALSO
Contractor:   MIDSTATE TRAFFIC CONTROL, INC.                            IN THE TULSA AREA.
Engineer:     Arnold, Bruce                Adjusted:
Contract Amount:        $1,822,347.10     (      $1,829,690.22)
Contract Time:                            (        )
Letting Date:           07/21/2011
Contract Date:          08/16/2011                               Fixed Completion Date: 04/25/2012
W/O Issued:             08/22/2011                                                                Adjusted:
W/O Effective:                                                   Amount Paid:             50 %(         50 %)
Work Started:           01/09/2012                               Time Passed:           174  %(         70 %)


17428(23)     Contract: 110197      IS-40   Residency:     04200        *-XTWN(73)TE/SEC115-155N(826) SG
OKCY-XTWN(004)TI/ACOKCY*                    EL RENO                     /1.442 MI. IS-40;SURFACING,BRIDGE
                                                                        FOUNDATION & SAFETY
Contractor:                                                              JV
              DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCIMPROVEMENT(ITS)
Engineer:     Vonfeldt, Cole               Adjusted:
Contract Amount:         $25,544,186.10   (     $26,836,620.29)
Contract Time:           260              (  260 )
Letting Date:            07/21/2011
Contract Date:           08/12/2011
W/O Issued:              08/15/2011                                                             Adjusted:
W/O Effective:           08/29/2011                              Amount Paid:            104 %(         99 %)
Work Started:            08/29/2011                              Time Passed:             85 %(         85 %)




                                            Construction Status Report                            Page 118
 28308(04)     Contract: 110273     I-40       Residency:       04400           0.173 MI. IS-40/BRIDGE RE-
 SBR-155N(837)SB                               EDMOND                           HAB.:OVER IS-44, 5.4 MI. EAST OF THE
                                                                                CANADIAN C/L.
 Contractor:   PBX CORPORATION
 Engineer:     Hubbard, Tom                   Adjusted:
 Contract Amount:       $1,384,147.70        (      $1,384,147.70)
 Contract Time:         100                  (  100 )
 Letting Date:          07/21/2011
 Contract Date:         08/09/2011
 W/O Issued:            08/25/2011                                                                   Adjusted:
 W/O Effective:         10/03/2011                                        Amount Paid:         100 % (    100 %)
 Work Started:          10/03/2011                                        Time Passed:         292 % (    292 %)


 17428(32)     Contract: 100313     I-40       Residency:       04600           *XTWN(15)TI/SEC115-155N(806)
 IMY-40-4(432)152SS/OKCY-*                     OKLAHOMA CITY                    SG/1.024 MI.
                                                                                IS-40:GRADE,DRAIN,SURFACE &
 Contractor:   ALLEN CONTRACTING, INC.                                          BRIDGE/CT. STREETS W.RENO,
 Engineer:     Howell, Terry                  Adjusted:                         S.LINCOLN BLVD. INT.
 Contract Amount:        $28,127,553.86      (     $29,862,654.75)
 Contract Time:                              (        )
 Letting Date:           07/22/2010
 Contract Date:          08/27/2010                                       Fixed Completion Date: 12/27/2012
 W/O Issued:             09/14/2010                                                                Adjusted:
 W/O Effective:                                                           Amount Paid:        87 % (     82 %)
 Work Started:           10/11/2010                                       Time Passed:       672 % (     80 %)


 29332(04)     Contract: 120259      CT.ST.   Residency:     04600        0.00 MI. CT.ST.:RESURFACE
 CMC-255E(091)                                OKLAHOMA CITY               (ASPHALT)PARKING LOT:BEGIN @ THE
                                                                          SW QUADRANT OF THE INTER- SECTION
 Contractor:   SILVER STAR CONSTRUCTION COMPANY, INC.                     OF LINCOLN & NE 18TH.
 Engineer:     Howell, Terry                 Adjusted:
 Contract Amount:        $160,294.00        (        $160,294.00)
 Contract Time:                             (        )
 Letting Date:           07/19/2012
 Contract Date:          08/16/2012                                Fixed Completion Date: 10/15/2012
 W/O Issued:             08/24/2012                                                               Adjusted:
 W/O Effective:                                                    Amount Paid:              0 %(        0 %)
 Work Started:                                                     Time Passed:              0 %(        0 %)




County:          Okmulgee                                     Commissioner District:                                   1
Contracts Under Construction


 27592(04)     Contract: 120039      US-75     Residency:       01100           *(174)(181)SR/ 9.26 MI. US-
 SSR-14N(85)SR/SSR-156N*                       MUSKOGEE                         75;RESURFACE (ASPHALT)BEGIN JUST
                                                                                NORTH OF US-62E, EXTEND NORTH.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     Ivy, Steve (Act.)              Adjusted:
 Contract Amount:        $2,800,836.17       (      $2,800,836.17)
 Contract Time:          150                 (  150 )
 Letting Date:           01/19/2012
 Contract Date:          02/21/2012
 W/O Issued:             02/28/2012                                                                  Adjusted:
 W/O Effective:          07/02/2012                                       Amount Paid:            0 %(      0 %)
 Work Started:           08/29/2012                                       Time Passed:            0 %(      0 %)




                                             Construction Status Report                                    Page 119
15205(04)     Contract: 120164     CORD       Residency:       01010           0.196 MI. CO.RD./BRIDGE &
BRF-056C(253)CI                               ATKINS (AKA - PBS & J)           APPROACHES;OVER MONTEZUMA CR.
                                                                               2.75 MI. N. OF I-40.
Contractor:   SEWELL BROS., INC.
Engineer:     ATKINS (AKA - PBSJ)            Adjusted:
Contract Amount:       $598,213.90          (        $598,213.90)
Contract Time:         120                  (  120 )
Letting Date:          04/19/2012
Contract Date:         05/22/2012
W/O Issued:            05/29/2012                                                                  Adjusted:
W/O Effective:         08/06/2012                                        Amount Paid:            0%(      0 %)
Work Started:          08/06/2012                                        Time Passed:            0%(      0 %)


20908(05)     Contract: 110492     I-40    Residency:     01100        6.34 MI. I-40: PAVEMENT
IMY-0040-6(370)233/IMY-*                   MUSKOGEE                    REHABILITATION AND BRIDGE
                                                                       PAINTING; FROM US-75 EXTEND EAST.
Contractor:   DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV
Engineer:     Ivy, Steve (Act.)          Adjusted:
Contract Amount:        $24,494,383.94  (      $24,656,790.59)
Contract Time:          620             (   620 )
Letting Date:           10/20/2011
Contract Date:          11/17/2011
W/O Issued:             11/28/2011                                                             Adjusted:
W/O Effective:          01/09/2012                              Amount Paid:             47 % (      46 %)
Work Started:           01/09/2012                              Time Passed:             31 % (      31 %)
*0040-5(386)207/BRFY-NBIP(422)

22181(04)     Contract: 120260      CORD   Residency:     01100        *-156D(105)RB/ 0.233 MI. CO.
CIRB-156C(104)RB/CIRB*                     MUSKOGEE                    RD.:BRIDGE & APPROACHES:OVER
                                                                       NEGRO CR. 3.1 MI. N. & 1.1 MI.W. OF
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                          US-75/SH-56 JCT.
Engineer:     Ivy, Steve (Act.)           Adjusted:
Contract Amount:        $781,201.21      (        $781,201.21)
Contract Time:          90               (   90   )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                              Adjusted:
W/O Effective:          12/03/2012                              Amount Paid:              0 %(            0 %)
Work Started:                                                   Time Passed:              0 %(            0 %)


28289(04)     Contract: 120307      SH-56     Residency:       01100           0.00 MI. SH-56:BRIDGE REHAB. OVER
SBR-156C(175)SB                               MUSKOGEE                         DEEP FORK RIVER,13.8 MI. E. OF THE
                                                                               OKFUSKEE C/L.
Contractor:   BECCO CONTRACTORS, INC.
Engineer:     Ivy, Steve (Act.)              Adjusted:
Contract Amount:        $1,432,819.90       (      $1,432,819.90)
Contract Time:          180                 (  180 )
Letting Date:           07/19/2012
Contract Date:          08/16/2012
W/O Issued:             08/21/2012                                                                  Adjusted:
W/O Effective:          12/03/2012                                       Amount Paid:            0 %(      0 %)
Work Started:                                                            Time Passed:            0 %(      0 %)




                                            Construction Status Report                                   Page 120
 28128(35)     Contract: 120073     IS-40      Residency:       01010           46.50 MI. IS-40;SAFETY IM-
 BTOP-256N(001)                                ATKINS (AKA - PBS & J)           PROVEMENT(FIBER OPTIC CABLE)
                                                                                BEGIN AT HENRYETTA, EXTEND EAST
 Contractor:   ROHL NETWORKS, LP                                                TO WEBBER FALLS.
 Engineer:     ATKINS (AKA - PBSJ)            Adjusted:
 Contract Amount:       $1,255,674.00        (      $1,255,674.00)
 Contract Time:         160                  (  160 )
 Letting Date:          03/15/2012
 Contract Date:         04/10/2012
 W/O Issued:            05/09/2012                                                                    Adjusted:
 W/O Effective:         06/04/2012                                        Amount Paid:           48 % (     48 %)
 Work Started:          05/29/2012                                        Time Passed:           30 % (     30 %)


 28128(16)     Contract: 110503     I-40       Residency:       01010           0.00 MI. I-40/US-59/SH-99/INDIAN
 BTOP-167E(194)                                ATKINS (AKA - PBS & J)           NATION TURNPIKE AT VARIOUS
                                                                                LOCATIONS IN DIVISION 1 & 3.
 Contractor:   TELCO SUPPLY COMPANY
 Engineer:     ATKINS (AKA - PBSJ)            Adjusted:
 Contract Amount:       $965,532.92          (      $1,055,408.71)
 Contract Time:         150                  (  161 )
 Letting Date:          09/15/2011
 Contract Date:         10/17/2011
 W/O Issued:            10/22/2011                                                                   Adjusted:
 W/O Effective:         11/21/2011                                        Amount Paid:         108 % (     99 %)
 Work Started:          12/27/2011                                        Time Passed:         107 % (    100 %)




County:          Osage                                        Commissioner District:                                  8
Contracts Under Construction


 28262(04)     Contract: 120301      SH-11   Residency:     08400        0.022 MI. SH-11:BRIDGE &
 E-SAP-257B(011)                             SAND SPRINGS                APPROACHES:OVER RED EAGLE
                                                                         BRANCH CR., 9.2 MI. EAST   OF JCT
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                           SH-99.
 Engineer:     Williams, Mark J.            Adjusted:
 Contract Amount:        $684,792.80       (        $684,792.80)
 Contract Time:          60                (   60   )
 Letting Date:           06/21/2012
 Contract Date:          07/05/2012
 W/O Issued:             07/06/2012                                                              Adjusted:
 W/O Effective:          07/07/2012                               Amount Paid:            94  %(         94 %)
 Work Started:           07/07/2012                               Time Passed:            67 % (         67 %)


 22146(07)     Contract: 110015     PK WY.     Residency:       08007           2.17 MI. PK.WY.;GRADE,DRAIN, &
 STP-157A(143)IG                               CRAIG & KEITHLINE, INC.          SURFACE.FROM 41ST AVE., EX- TEND
                                                                                EAST IN TULSA.
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     C&KI                           Adjusted:
 Contract Amount:       $7,781,953.52        (      $7,781,953.52)
 Contract Time:         245                  (  294 )
 Letting Date:          02/17/2011
 Contract Date:         03/17/2011
 W/O Issued:            03/22/2011                                                                  Adjusted:
 W/O Effective:         07/05/2011                                        Amount Paid:          63 %(     63 %)
 Work Started:          07/06/2011                                        Time Passed:         167 %(    139 %)




                                             Construction Status Report                                    Page 121
 22146(04)     Contract: 090662    CT.ST.   Residency:     08007        0.749 MI. CT.ST.;(GILCREASE
 STP-157A(66)(67)IG                         CRAIG & KEITHLINE, INC.     EXPRESSWAY) GRADE,DRAIN,SUR-
                                                                        FACE,BRIDGE & TRAFFIC       SIGNALS.
 Contractor:   PLAINS BRIDGE CONTR./TREAS CONST./UNITED GENERAL CONTR.,INC.
 Engineer:     C&KI                        Adjusted:
 Contract Amount:       $13,091,185.87    (     $13,225,868.69)
 Contract Time:         420               (  873 )
 Letting Date:          12/17/2009
 Contract Date:         01/22/2010
 W/O Issued:            02/02/2010                                                               Adjusted:
 W/O Effective:         03/01/2010                                Amount Paid:           100 % (        99 %)
 Work Started:          03/01/2010                               Time Passed:            210 % (       101 %)


 23130(04)     Contract: 090665     US-60   Residency:     08400        3.048 MI. US-60;GRADE,DRAIN,
 NHY-018N(045)TI                            SAND SPRINGS                SURFACE & BRIDGE/ BEGIN 3.2
                                                                        MINORTH OF SH-11, EXTEND EAST.
 Contractor:   PLAINS BRIDGE CONTR./TREAS CONST./UNITED GENERAL CONTR.,INC.
 Engineer:     Williams, Mark J.           Adjusted:
 Contract Amount:        $10,049,793.43   (     $10,334,331.60)
 Contract Time:          475              (  899 )
 Letting Date:           12/17/2009
 Contract Date:          01/22/2010
 W/O Issued:             02/02/2010                                                            Adjusted:
 W/O Effective:          04/05/2010                              Amount Paid:            94 % (        91 %)
 Work Started:           03/08/2010                              Time Passed:           185 % (        98 %)


 23480(04)     Contract: 110016      CO.RD.   Residency:     08400        2.065 MI. CO.RD.;BRIDGE &
 CIRB-157C(083)RB                             SAND SPRINGS                APPROACHES(E.STREET)OVER THE
                                                                          ARKANSAS RIVER, AT THE
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                            OSAGE/PAWNEE COUNTY LINE.
 Engineer:     Williams, Mark J.             Adjusted:
 Contract Amount:        $6,197,488.90      (      $6,248,752.90)
 Contract Time:          240                (  240 )
 Letting Date:           04/14/2011
 Contract Date:          05/18/2011
 W/O Issued:             05/25/2011                                                               Adjusted:
 W/O Effective:          10/03/2011                                Amount Paid:             57 %(       56 %)
 Work Started:           10/10/2011                                Time Passed:             93 %(       93 %)


 21913(04)     Contract: 120219      SH-18     Residency:       08400           0.037 MI.SH-18:BRIDGE &
 HSIPY-157C(061)                               SAND SPRINGS                     APPROACHES:OVER LOST MAN CR., 2.0
                                                                                MI. NORTH OF SH-60.
 Contractor:   APAC-CENTRAL, INC.
 Engineer:     Williams, Mark J.              Adjusted:
 Contract Amount:        $813,914.87         (        $813,914.87)
 Contract Time:          90                  (   90   )
 Letting Date:           06/21/2012
 Contract Date:          07/11/2012
 W/O Issued:             07/18/2012                                                                 Adjusted:
 W/O Effective:          11/05/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                            Time Passed:           0 %(      0 %)




County:          Ottawa                                       Commissioner District:                                8
Contracts Under Construction




                                             Construction Status Report                                  Page 122
 27812(04)     Contract: 120017      CT.ST.     Residency:       08004           0.238 MI. CT.ST.;BRIDGE &
 STP-158B(182)UR                                                           APPROACHES(EAST CENTRAL AVE.) OVER
                                                JACOBS (AKA - CARTER-BURGESS)
                                                                                 TAR CREEK 0.25 MI. W.   OF ELM ST. IN
 Contractor:   B & B BRIDGE COMPANY, LLC                                         MIAMI.
 Engineer:     JACOBS (AKA - C-B)              Adjusted:
 Contract Amount:        $1,745,041.78        (      $1,745,041.78)
 Contract Time:          120                  (  120 )
 Letting Date:           04/19/2012
 Contract Date:          05/18/2012
 W/O Issued:             05/31/2012                                                                    Adjusted:
 W/O Effective:          08/06/2012                                        Amount Paid:           16 % (     16 %)
 Work Started:           07/23/2012                                        Time Passed:           20 % (     20 %)


 08932(04)     Contract: 100395     SH-10       Residency:       08300           *STPY-58C(240)/3.566 MI. SH-
 BRFY-058C(235)(237)/*                          CLAREMORE                        10/GRADE,DRAIN,SURFACE,BRIDGE
                                                                                 ;FROM THE IS-44 INTERCHANGE,
 Contractor:   BECCO CONTRACTORS, INC.                                           EXTEND EAST.
 Engineer:     Bray, Timothy                   Adjusted:
 Contract Amount:        $19,695,764.93       (     $19,698,389.93)
 Contract Time:          650                  (  701 )
 Letting Date:           11/18/2010
 Contract Date:          12/22/2010
 W/O Issued:             01/04/2011                                                                    Adjusted:
 W/O Effective:          04/04/2011                                        Amount Paid:           86 % (     86 %)
 Work Started:           04/04/2011                                        Time Passed:           77 % (     71 %)


 28476(04)     Contract: 120222     CORD        Residency:       08001           7.60 MI. CO.RD.:RESURFACE
 STP-158D(193)CO                                ENGR. SERV. & TESTING            (ASPHALT)FROM SH-137,EXTEND     EAST
                                                                                 THEN SOUTH TO IS-44.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     EST                             Adjusted:
 Contract Amount:       $1,044,665.10         (      $1,044,665.10)
 Contract Time:         45                    (   45   )
 Letting Date:          06/21/2012
 Contract Date:         07/17/2012
 W/O Issued:            07/18/2012                                                                    Adjusted:
 W/O Effective:         08/06/2012                                         Amount Paid:            0 %(      0 %)
 Work Started:          08/06/2012                                         Time Passed:            0 %(      0 %)




County:          Payne                                         Commissioner District:                                    4
Contracts Under Construction


 20331(06)     Contract: 110177      SH-33   Residency:     04500        7.20 MI. SH-33/GRADE,DRAIN, SURFACE
 STPY-160B(166)(171)                         STILLWATER                  & BRIDGE;FROM THE NEW ALIGNMENT
                                                                         OVER THE CIMARRON RIVER, EXTEND
 Contractor:                                                              JV
               DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCEAST.
 Engineer:     Arps, Jonathan               Adjusted:
 Contract Amount:        $9,829,479.48     (     $10,927,662.59)
 Contract Time:          300               (  431 )
 Letting Date:           03/17/2011
 Contract Date:          04/18/2011
 W/O Issued:             04/27/2011                                                             Adjusted:
 W/O Effective:          06/06/2011                               Amount Paid:           109 %(        98 %)
 Work Started:           06/06/2011                               Time Passed:           141 %(        98 %)




                                              Construction Status Report                                     Page 123
 28225(04)     Contract: 120241      US-177   Residency:     04500        0.950 MI. US-177:RESURFACE
 SSR-160A(206)SR                              STILLWATER                  (ASPHALT)FROM PERKINGS RD. IN
                                                                          STILLWATER, EXTEND WEST.
 Contractor:   THE QUAPAW COMPANY
 Engineer:     Arps, Jonathan                Adjusted:
 Contract Amount:        $267,995.00        (        $267,995.00)
 Contract Time:          30                 (   30   )
 Letting Date:           06/21/2012
 Contract Date:          07/17/2012
 W/O Issued:             07/18/2012                                                              Adjusted:
 W/O Effective:          08/06/2012                                Amount Paid:            45 % (       45 %)
 Work Started:           08/13/2012                                Time Passed:            33 % (       33 %)




County:          Pittsburg                                    Commissioner District:                                   2
Contracts Under Construction


 23145(05)     Contract: 120032     SH-31       Residency:      02200           0.00 MI. JOINT SEAL/REPR.   MULTIPLE
 BRFY-261C(004)                                 HEAVENER                        LOCATIONS IN DIV. II.

 Contractor:   B & B CONSTRUCTION SERVICE    J.T., INC.
 Engineer:     Huddleston, David              Adjusted:
 Contract Amount:       $398,823.53          (          $398,823.53)
 Contract Time:         120                  (    120 )
 Letting Date:          01/19/2012
 Contract Date:         02/24/2012
 W/O Issued:            04/20/2012                                                                    Adjusted:
 W/O Effective:         06/04/2012                                        Amount Paid:           27 % (     27 %)
 Work Started:          06/18/2012                                        Time Passed:            9%(        9 %)


 28128(46)     Contract: 120074      US-270   Residency:     02400        28.920 MI. US-270/SAFETY IM-
 BTOP-261B(002)                               MCALESTER                   PROVEMENT(FIBER OPTIC CABLE) FROM
                                                                          MCALESTER, EXTEND EAST TO
 Contractor:   BEAR COMMUNICATIONS, LLC                                   WILBURTON.
 Engineer:     Plymate, Larry                Adjusted:
 Contract Amount:        $952,036.39        (        $952,036.39)
 Contract Time:          95                 (   95   )
 Letting Date:           02/16/2012
 Contract Date:          03/20/2012
 W/O Issued:             04/23/2012                                                               Adjusted:
 W/O Effective:          05/21/2012                                Amount Paid:            16  %(       16 %)
 Work Started:           06/12/2012                                Time Passed:            43 % (       43 %)


 29436(04)     Contract: 120310      SH-31      Residency:      02400           3.00 MI. SH-31:RESURFACE
 SSR-261C(008)SR                                MCALESTER                       (ASPHALT)BEGIN AT THE SH-31A JCT,
                                                                                EXTEND EAST.
 Contractor:   GLOVER & ASSOCIATES, INC.
 Engineer:     Plymate, Larry                 Adjusted:
 Contract Amount:        $1,944,746.00       (      $1,944,746.00)
 Contract Time:                              (        )
 Letting Date:           07/19/2012
 Contract Date:          08/21/2012                                       Fixed Completion Date: 10/31/2012
 W/O Issued:             08/24/2012                                                                Adjusted:
 W/O Effective:                                                           Amount Paid:         0 %(       0 %)
 Work Started:                                                            Time Passed:         0 %(       0 %)




                                             Construction Status Report                                     Page 124
 28195(04)     Contract: 120226      SH-113   Residency:     02400        *(247)SB / 0.00 MI. SH-113; BRIDGE
 SBR-161C(246)SB/SBR-161B*                    MCALESTER                   REHAB.OVER ROCK CR., 11.2 MI. N. OF
                                                                          US-69.SH-9A, OVER GAINES CR.,0.92
 Contractor:   C-GAWF CONSTRUCTION, INC.                                  MI. E.
 Engineer:     Plymate, Larry                Adjusted:
 Contract Amount:        $2,376,239.74      (      $2,376,239.74)
 Contract Time:          240                (  240 )
 Letting Date:           06/21/2012
 Contract Date:          07/17/2012
 W/O Issued:             07/18/2012                                                                Adjusted:
 W/O Effective:          11/05/2012                                Amount Paid:               0%(          0 %)
 Work Started:                                                     Time Passed:               0%(          0 %)


 21746(04)     Contract: 110359      US-270   Residency:     02400        0.616 MI. US-270:BRIDGE &
 BRFY-161B(141)                               MCALESTER                   APPROACHES/OVER COAL CREEK, 13.2
                                                                          MI. EAST OF THE HUGHES C/L.
 Contractor:   C-GAWF CONSTRUCTION, INC.
 Engineer:     Plymate, Larry                Adjusted:
 Contract Amount:        $2,747,402.53      (      $2,809,285.77)
 Contract Time:          180                (  180 )
 Letting Date:           07/21/2011
 Contract Date:          08/09/2011
 W/O Issued:             08/18/2011                                                               Adjusted:
 W/O Effective:          12/05/2011                                Amount Paid:           101 % (       99 %)
 Work Started:           09/15/2011                                Time Passed:           187 % (      187 %)




County:          Pontotoc                                     Commissioner District:                           3
Contracts Under Construction


 21842(04)     Contract: 100610       SH-99   Residency:     03100        0.254 MI. SH-99,GRADE,DRAIN
 BRFY-162B(118)                               ADA                         ,SURFACE & BRIDGE.OVER CLEAR
                                                                          BOGGY CR., 1.54 MI. S. OF  THE SH-3
 Contractor:   PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV)
                                                                          JUNCTION.
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $1,634,999.97     (      $1,637,749.97)
 Contract Time:           180               (  188 )
 Letting Date:            10/21/2010
 Contract Date:           11/23/2010
 W/O Issued:              11/29/2010                                                               Adjusted:
 W/O Effective:           03/07/2011                               Amount Paid:            99  %(         98 %)
 Work Started:            03/01/2011                               Time Passed:           126 % (       121 %)


 21843(04)     Contract: 110310       SH-99   Residency:     03100        0.056 MI. SH-99:BRIDGE &
 BRFY-162B(121)                               ADA                         APPROACHES:OVER BOIS D' ARC CR.,
                                                                          4.57 MI. SOUTH OF THE SH-3
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                            JUNCTION
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $1,020,063.41     (      $1,045,283.41)
 Contract Time:           90                (  117 )
 Letting Date:            06/16/2011
 Contract Date:           07/22/2011
 W/O Issued:              07/29/2011                                                              Adjusted:
 W/O Effective:           11/07/2011                               Amount Paid:            99  %(       97 %)
 Work Started:            11/07/2011                               Time Passed:           182  %(      140 %)




                                             Construction Status Report                             Page 125
 22973(10)     Contract: 120167      SH-48     Residency:       03200           0.00 MI. SH-48/IS-35/SH-9/
 SSP-162C(226)SS                               PURCELL                          SH-76/SH-4;BRIDGE WATERPROOF
                                                                                SEAL. MULTIPLE LOCATIONS IN DIV. III.
 Contractor:   GARY A. CRAIN, INC.
 Engineer:     Riemer, Caleb                  Adjusted:
 Contract Amount:        $106,709.17         (        $106,709.17)
 Contract Time:          80                  (   80   )
 Letting Date:           04/19/2012
 Contract Date:          05/21/2012
 W/O Issued:             05/24/2012                                                                 Adjusted:
 W/O Effective:          08/06/2012                                       Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)


 21926(04)     Contract: 120166       SH-3    Residency:     03100        0.00 MI.:SH-3:JOINT SEAL/
 BRFY-162C(225)                               ADA                         REPAIR:US-270/SH-18:AT MUL- TIPLE
                                                                          LOCATIONS IN DIV. III.
 Contractor:   C-P INTEGRATED SERVICES, INC.
 Engineer:     Russell, Julie                Adjusted:
 Contract Amount:         $261,403.96      (         $261,403.96)
 Contract Time:           120              (   120 )
 Letting Date:            04/19/2012
 Contract Date:           05/18/2012
 W/O Issued:              05/23/2012                                                              Adjusted:
 W/O Effective:           09/04/2012                               Amount Paid:              0%(         0 %)
 Work Started:                                                     Time Passed:              0%(         0 %)


 28174(04)     Contract: 110522       SH-1   Residency:     03100        0.00 MI. SH-1;BRIDGE REHAB. /OVER
 SBR-162A(219)SB                             ADA                         18TH ST., JUST SOUTH OF ADA.

 Contractor:   SCR CONSTRUCTION CO., INC.
 Engineer:     Russell, Julie               Adjusted:
 Contract Amount:         $1,340,399.50    (      $1,359,689.10)
 Contract Time:           210              (  210 )
 Letting Date:            11/17/2011
 Contract Date:           12/20/2011
 W/O Issued:              01/27/2012                                                             Adjusted:
 W/O Effective:           05/07/2012                              Amount Paid:             93 %(        92 %)
 Work Started:            02/20/2012                              Time Passed:             74 %(        74 %)




County:          Pottawatomie                                 Commissioner District:                                    3
Contracts Under Construction


 28128(31)     Contract: 120075     IS-40      Residency:       03003           26.500 MI. IS-40;SAFETY IM-
 BTOP-263N(001)                                COBB ENGINEERING CO., INC.       PROVEMENTS(FIBER OPTIC CABLE)
                                                                                BEGIN AT THE OKLA. C/L,     EXTEND
 Contractor:   ROHL NETWORKS, LP                                                EAST TO US-377.
 Engineer:     COBB                           Adjusted:
 Contract Amount:       $865,555.90          (        $865,555.90)
 Contract Time:         70                   (   70   )
 Letting Date:          03/15/2012
 Contract Date:         04/10/2012
 W/O Issued:            05/09/2012                                                                  Adjusted:
 W/O Effective:         06/04/2012                                        Amount Paid:          78 %(     78 %)
 Work Started:                                                            Time Passed:         104 %(    104 %)




                                             Construction Status Report                                    Page 126
 29318(04)     Contract: 120263      US-177   Residency:     03300        0.00 MI. US-177:TRAFFIC
 HSIP-263B(005)TR                             WEWOKA                      SIGNALS:AT ACME RD. IN SHAWNEE3.5
                                                                          MI. S. & 4.0 MI. E.  OF THE I-40 JCT.
 Contractor:   TRAFFIC SIGNALS, INC.
 Engineer:     Moore, Archie (Act.)          Adjusted:
 Contract Amount:        $132,014.34        (        $132,014.34)
 Contract Time:          120                (  120 )
 Letting Date:           07/19/2012
 Contract Date:          08/21/2012
 W/O Issued:             08/24/2012                                                               Adjusted:
 W/O Effective:          12/03/2012                                Amount Paid:               0%(           0 %)
 Work Started:                                                     Time Passed:               0%(           0 %)




County:          Pushmataha                                   Commissioner District:                                2
Contracts Under Construction


 26233(04)     Contract: 110447     US-271   Residency:     02200        .164 MI. US-271 OVER HARDY CREEK, 1.0
 BRFY-164B(146)SS                            HEAVENER                    MI. N OF SH-144 JCT.

 Contractor:   C-GAWF CONSTRUCTION, INC.
 Engineer:     Huddleston, David            Adjusted:
 Contract Amount:       $1,425,016.88      (      $1,425,016.88)
 Contract Time:         180                (  180 )
 Letting Date:          09/15/2011
 Contract Date:         10/12/2011
 W/O Issued:            10/19/2011                                                              Adjusted:
 W/O Effective:         05/21/2012                                Amount Paid:             18 % (       18 %)
 Work Started:          06/11/2012                                Time Passed:             46 % (       46 %)


 26232(04)     Contract: 120264     US-271   Residency:     02200        0.325 MI. US-271:BRIDGE &
 BRFY-164B(143)                              HEAVENER                    APPROACHES/OVER HURD CREEK 2.4MI.
                                                                         SOUTH OF SH-2.
 Contractor:   PARADIGM CONSTRUCTION & ENGINEERING, INC
 Engineer:     Huddleston, David            Adjusted:
 Contract Amount:       $1,809,840.70      (      $1,809,840.70)
 Contract Time:         180                (  180 )
 Letting Date:          07/19/2012
 Contract Date:         08/21/2012
 W/O Issued:            08/24/2012                                                               Adjusted:
 W/O Effective:         12/03/2012                                Amount Paid:              0 %(        0 %)
 Work Started:                                                    Time Passed:              0%(         0 %)


 17045(04)     Contract: 120057      CORD       Residency:      02013           0.38 MI. CO.RD.:BRIDGE &
 BRF-164C(012)CI                                CIRCUIT ENGR. DISTRICT # 3      APPROACHES;OVER TENMILE CR., 1.8
                                                                                MI. NORTH OF JUMBO.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     CED3                           Adjusted:
 Contract Amount:        $809,066.74         (        $809,066.74)
 Contract Time:          150                 (  150   )
 Letting Date:           01/19/2012
 Contract Date:          02/23/2012
 W/O Issued:             02/29/2012                                                                Adjusted:
 W/O Effective:          05/07/2012                                       Amount Paid:         31 %(     31 %)
 Work Started:                                                            Time Passed:         65 %(     65 %)




                                             Construction Status Report                                  Page 127
 27877(04)     Contract: 120225      US-271   Residency:     02100        0.00 MI. US-271 BRIDGE REHAB. :OVER
 SBR-164B(162)(163)SB                         ANTLERS                     UNNAMED CR., 11.3 MI. N.E. OF
                                                                          SH-3.US-271 OVER GAY CR.,13.0 MI N.E.
 Contractor:   LOGOS CONSTRUCTION CO., LLC                                OF SH-3.
 Engineer:     Moy, Ryan                     Adjusted:
 Contract Amount:        $1,318,797.56      (      $1,318,797.56)
 Contract Time:          150                (  150 )
 Letting Date:           06/21/2012
 Contract Date:          07/13/2012
 W/O Issued:             07/18/2012                                                               Adjusted:
 W/O Effective:          11/05/2012                                Amount Paid:              0%(           0 %)
 Work Started:                                                     Time Passed:              0%(           0 %)




County:          Roger Mills                                  Commissioner District:                                    5
Contracts Under Construction


 28590(05)     Contract: 110391      IS-40     Residency:       05100           0.00 MI. IS-40/JOINT SEAL/
 BRFY-165C(122)3B                              CLINTON                          REPAIR:SH-47/ AT VARIOUS
                                                                                LOCATIONS IN DIV. V.
 Contractor:   PBX CORPORATION
 Engineer:     Greer, Randy                   Adjusted:
 Contract Amount:        $292,921.00         (        $292,921.00)
 Contract Time:          70                  (  117 )
 Letting Date:           08/18/2011
 Contract Date:          09/28/2011
 W/O Issued:             10/04/2011                                                                   Adjusted:
 W/O Effective:          03/05/2012                                       Amount Paid:           89 % (     89 %)
 Work Started:           03/19/2012                                       Time Passed:          131 % (     79 %)


 21702(04)     Contract: 110528      SH33    Residency:     05100        .25 MI. SH-33: BRIDGE AND
 BRFY-165C(059)                              CLINTON                     APPROACHES; OVER NINE MILE CREEK
                                                                         11.4 MI. EAST OF US-283.
 Contractor:   REECE CONSTRUCTION CO., INC.
 Engineer:     Greer, Randy                 Adjusted:
 Contract Amount:        $1,556,466.14    (       $1,621,672.09)
 Contract Time:          180              (   193 )
 Letting Date:           10/20/2011
 Contract Date:          11/21/2011
 W/O Issued:             12/28/2011                                                               Adjusted:
 W/O Effective:          03/05/2012                               Amount Paid:             98 %(        94 %)
 Work Started:           01/09/2012                               Time Passed:            106 % (       98 %)




County:          Rogers                                       Commissioner District:                                    8
Contracts Under Construction




                                             Construction Status Report                                      Page 128
 09488(04)     Contract: 090566     US-169   Residency:     08300        5.24 MI. US-169;GRADE,DRAIN
 NHY-030N(011)                               CLAREMORE                   ,SURFACE & BRIDGE;FROM
                                                                         TALALA,EXTEND NORTH TO THE NOWATA
 Contractor:   DONDLINGER & SONS CONSTRUCTION CO., INC.                  COUNTY LINE.
 Engineer:     Bray, Timothy                Adjusted:
 Contract Amount:        $12,216,022.60    (     $12,768,123.89)
 Contract Time:          345               (  802 )
 Letting Date:           10/15/2009
 Contract Date:          11/13/2009
 W/O Issued:             01/19/2010                                                             Adjusted:
 W/O Effective:          02/01/2010                               Amount Paid:            98 % (      94 %)
 Work Started:           03/03/2010                               Time Passed:           273 % (     118 %)


 25744(04)     Contract: 120142     CORD       Residency:       08010           0.235 MI. CO.RD.;BRIDGE &
 BRF-166C(219)CI                               ATKINS (AKA - PBS & J)           APPROACHES/OVER DOG CREEK 1.9 MI.
                                                                                EAST OF SH-66.
 Contractor:   BELK BRIDGE, INC.
 Engineer:     ATKINS (AKA - PBSJ)           Adjusted:
 Contract Amount:       $1,261,116.57       (      $1,261,116.57)
 Contract Time:         120                 (  120 )
 Letting Date:          03/15/2012
 Contract Date:         04/12/2012
 W/O Issued:            04/18/2012                                                                   Adjusted:
 W/O Effective:         07/02/2012                                        Amount Paid:          64 % (     64 %)
 Work Started:          05/14/2012                                        Time Passed:          64 % (     64 %)


 28261(04)     Contract: 120043      SH-266   Residency:     08300        0.26 MI. SH-266;BRIDGE RE-
 SBR-166C(254)SB                              CLAREMORE                   HABILITATION;OVER VERDIGRIS
                                                                          RIVER, 5.6 MI. EAST OF    TULSA C/L.
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Bray, Timothy                 Adjusted:
 Contract Amount:        $1,775,741.30      (      $1,775,741.30)
 Contract Time:          180                (  180 )
 Letting Date:           01/19/2012
 Contract Date:          02/15/2012
 W/O Issued:             02/22/2012                                                               Adjusted:
 W/O Effective:          03/19/2012                                Amount Paid:             69 %(         69 %)
 Work Started:           03/19/2012                                Time Passed:             74 %(         74 %)


 29061(04)     Contract: 120308      I-44      Residency:       08300           *(003)SB/ 0.00 MI. IS-44/SH- 66.
 SBR-266A(002)SB/SBR-266A*                     CLAREMORE                        BRIDGE REHAB.;OVER SH-66 0.6 MI. E.
                                                                                OF TULSA C.L. & SH-66 OVER
 Contractor:   PBX CORPORATION                                                  ABANDONDED TURNPIKE
 Engineer:     Bray, Timothy                 Adjusted:
 Contract Amount:        $326,856.50        (        $326,856.50)
 Contract Time:          60                 (   60   )
 Letting Date:           07/19/2012
 Contract Date:          08/17/2012
 W/O Issued:             08/22/2012                                                                 Adjusted:
 W/O Effective:          10/01/2012                                       Amount Paid:           0 %(      0 %)
 Work Started:                                                            Time Passed:           0 %(      0 %)




County:          Seminole                                     Commissioner District:                                  3
Contracts Under Construction




                                             Construction Status Report                                   Page 129
 28128(32)     Contract: 120076     SH-99      Residency:      03003           11.30 MI. SH-99;SAFETY IM-
 BTOP-267N(001)                                COBB ENGINEERING CO., INC.      PROVEMENTS(FIBER OPTIC CABLE)
                                                                               US-270 FROM SEMINOLE STATE
 Contractor:   BEAR COMMUNICATIONS, LLC                                        COLLEGE IN SEMINOLE E.TO SH-99
 Engineer:     COBB                          Adjusted:
 Contract Amount:       $576,938.70         (        $576,938.70)
 Contract Time:         35                  (   35   )
 Letting Date:          03/15/2012
 Contract Date:         04/10/2012
 W/O Issued:            04/23/2012                                                                  Adjusted:
 W/O Effective:         05/21/2012                                       Amount Paid:           9%(        9 %)
 Work Started:          05/28/2012                                       Time Passed:          54 % (     54 %)


 28128(33)     Contract: 120077     SH-99      Residency:      03003           36.800 MI. SH-99;SAFETY IM-
 BTOP-167N(002)                                COBB ENGINEERING CO., INC.      PROVEMENTS(FIBER OPTIC CABLE)
                                                                               BEGIN S. OF ADA, EXTEND N. TO
 Contractor:   ROHL NETWORKS, LP                                               SEMINOLE STATE COLLEGE.
 Engineer:     COBB                          Adjusted:
 Contract Amount:       $1,279,367.24       (      $1,279,367.24)
 Contract Time:         95                  (   95   )
 Letting Date:          03/15/2012
 Contract Date:         04/10/2012
 W/O Issued:            05/09/2012                                                                  Adjusted:
 W/O Effective:         06/04/2012                                       Amount Paid:          46 % (     46 %)
 Work Started:          06/11/2012                                       Time Passed:          74 % (     74 %)


 28128(34)     Contract: 120078     IS-40      Residency:      03010           40.50 MI. IS-40/SAFETY IM-
 BTOP-267N(003)                                ATKINS (AKA - PBS & J)          PROVEMENTS(FIBER OPTIC CABLE)
                                                                               BEGIN AT THE SH-99 INTER-  CHANGE,
 Contractor:   ROHL NETWORKS, LP                                               EXTEND E.TO HENRYETTA.
 Engineer:     ATKINS (AKA - PBSJ)           Adjusted:
 Contract Amount:       $1,286,282.96       (      $1,286,282.96)
 Contract Time:         140                 (  140 )
 Letting Date:          03/15/2012
 Contract Date:         04/12/2012
 W/O Issued:            05/09/2012                                                                 Adjusted:
 W/O Effective:         06/04/2012                                       Amount Paid:          59 %(     59 %)
 Work Started:          06/18/2012                                       Time Passed:          52 %(     52 %)
 T




County:          Sequoyah                                    Commissioner District:                                 1
Contracts Under Construction


 20910(04)     Contract: 100306    I-40     Residency:     01200        5.86 MI. IS-40:RESURFACE ( P.C.
 IMY-0040-6(346)(367)325                    SALLISAW                    CONCRETE)CABLE BARRIER &
                                                                        BRIDGE;FROM MILE MARKER 325. 06,
 Contractor:                                                             JV
               DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INCEXTEND E. TO MILE MARKER
 Engineer:     Edwards, Carl              Adjusted:
 Contract Amount:       $17,611,219.09   (      $17,809,649.04)
 Contract Time:         500             (    729 )
 Letting Date:          05/20/2010
 Contract Date:         06/16/2010
 W/O Issued:            06/22/2010                                                              Adjusted:
 W/O Effective:         10/04/2010                               Amount Paid:             91 %(         90 %)
 Work Started:          08/30/2010                               Time Passed:            140 %(         96 %)




                                            Construction Status Report                                  Page 130
 28730(04)     Contract: 120150     PKRD       Residency:       01200           5.80 MI. PK.RD.(SEQUOYAH
 PLHD-168E(225)DC                              SALLISAW                         WILDLIFE)RESURFACE(ASPHALT) FROM
                                                                                THE IS-40/SH-10 JCT,  EXTEND S.
 Contractor:   GLOVER & ASSOCIATES, INC.                                        FROM THE IS-40/SH-82
 Engineer:     Edwards, Carl                 Adjusted:
 Contract Amount:       $707,425.77         (        $843,625.77)
 Contract Time:         30                  (   30   )
 Letting Date:          03/15/2012
 Contract Date:         04/16/2012
 W/O Issued:            04/18/2012                                                                  Adjusted:
 W/O Effective:         07/02/2012                                        Amount Paid:        114 % (     96 %)
 Work Started:          06/28/2012                                        Time Passed:         60 % (     60 %)


 29078(04)     Contract: 120186     I-40      Residency:    01200        2.32 MI. I-40;SAFETY IMPROV. (CABLE
 HSIPIG-0040-6(377)308TR                      SALLISAW                   BARRIER) FROM US-59 EXTEND EAST.

 Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:     Edwards, Carl                Adjusted:
 Contract Amount:       $479,114.50        (        $479,114.50)
 Contract Time:         60                (    60   )
 Letting Date:          05/17/2012
 Contract Date:         06/14/2012
 W/O Issued:            06/18/2012                                                                Adjusted:
 W/O Effective:         09/04/2012                                Amount Paid:              0%(           0 %)
 Work Started:                                                    Time Passed:              0%(           0 %)




County:          Stephens                                     Commissioner District:                                 7
Contracts Under Construction


 26847(04)     Contract: 110228       CORD   Residency:     07100         0.283 MI. CO.RD.;BRIDGE &
 BRO-169D(169)CI                             DUNCAN                       APPROACHES/OVER A TRIBUTARY
                                                                          OFLITTLE BEAVER CR., 0.30 MI. S. OF
 Contractor:   PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) GRADY C/L.
                                                                          THE
 Engineer:     Harwell, Jerry M.            Adjusted:
 Contract Amount:         $528,883.38      (        $528,883.38)
 Contract Time:           90               (   90   )
 Letting Date:            03/17/2011
 Contract Date:           04/18/2011
 W/O Issued:              04/27/2011                                                              Adjusted:
 W/O Effective:           07/05/2011                              Amount Paid:              90 %(         90 %)
 Work Started:            07/05/2011                              Time Passed:            103 % (        103 %)


 20952(05)     Contract: 110312     US-70      Residency:       07001           0.00 MI. US-70/US-281/SH-7 :BRIDGE
 BRFY-169C(190)                                ENGR. SERV. & TESTING            JOINT SEAL/REPAIR.AT MULTIPLE
                                                                                LOCATIONS IN DIV. VII.
 Contractor:   PBX CORPORATION
 Engineer:     EST                           Adjusted:
 Contract Amount:       $327,455.00         (        $327,455.00)
 Contract Time:         130                 (  130   )
 Letting Date:          06/16/2011
 Contract Date:         07/26/2011
 W/O Issued:            08/04/2011                                                                 Adjusted:
 W/O Effective:         11/07/2011                                        Amount Paid:         84 %(     84 %)
 Work Started:          01/16/2012                                        Time Passed:        114 %(    114 %)




                                             Construction Status Report                                  Page 131
23125(07)     Contract: 100308       I-35   Residency:     07100        0.00 MI. I-35/I-44/US-62/US
BRFY-169C(173)                              DUNCAN                      -77/US-177/SH-5/SH-7/SH-32/SH
                                                                        -53;MULTIPLE LOCATIONS IN    DIV. VII.
Contractor:   INTERSTATE IMPROVEMENT, INC.
Engineer:     Harwell, Jerry M.            Adjusted:
Contract Amount:         $150,771.50      (        $150,771.50)
Contract Time:           125              (  142 )
Letting Date:            04/15/2010
Contract Date:           05/19/2010
W/O Issued:              07/09/2010                                                              Adjusted:
W/O Effective:           09/07/2010                              Amount Paid:              97 % (       97 %)
Work Started:            09/10/2010                              Time Passed:              37 % (       32 %)


28155(04)     Contract: 110213       SH-7     Residency:       07100           *(91)3P / 6.90 MI. SH-7/
NHY-21N(53)3P/NHY-11N*                        DUNCAN                           RESURFACE(ASPHALT)FROM THE
                                                                               COMANCHE C/L, EXTEND EAST. US-81
Contractor:   T & G CONSTRUCTION, INC.                                         FROM THE SH-7W.
Engineer:     Harwell, Jerry M.              Adjusted:
Contract Amount:         $3,199,135.24      (      $3,460,151.44)
Contract Time:           75                 (   75   )
Letting Date:            02/17/2011
Contract Date:           03/22/2011
W/O Issued:              03/31/2011                                                                  Adjusted:
W/O Effective:           07/05/2011                                      Amount Paid:          104 % (     96 %)
Work Started:            06/20/2011                                      Time Passed:           89 % (     89 %)


26846(04)     Contract: 110524       CORD     Residency:       07100           0.284 MI. CO.RD.;BRIDGE &
BRO-169D(168)CI                               DUNCAN                           APPROACHES/OVER STAGESTAND CR.,
                                                                               6.3 MI. SOUTH OF SH-7.
Contractor:   K & R BUILDERS, INC.
Engineer:     Harwell, Jerry M.              Adjusted:
Contract Amount:         $574,732.10        (        $574,732.10)
Contract Time:           150                (  150   )
Letting Date:            11/17/2011
Contract Date:           12/20/2011
W/O Issued:              12/29/2011                                                                 Adjusted:
W/O Effective:           02/06/2012                                      Amount Paid:           78 %(     78 %)
Work Started:            02/23/2012                                      Time Passed:          100 %(    100 %)


28128(43)     Contract: 120177     US-81      Residency:       07004           20.94 MI. US-81:SAFETY IM-
BTOP-269N(001)                                                           PROVEMENTS(FIBER OPTIC CABLE)
                                              JACOBS (AKA - CARTER-BURGESS)
                                                                               BEGIN 4.7 MI. N. OF US-70,   EXTEND N.
Contractor:   ROHL NETWORKS, LP                                                TO SH-7.
Engineer:     JACOBS (AKA - C-B)             Adjusted:
Contract Amount:       $801,221.37          (        $801,221.37)
Contract Time:         75                   (   75   )
Letting Date:          03/15/2012
Contract Date:         04/10/2012
W/O Issued:            05/09/2012                                                                   Adjusted:
W/O Effective:         06/04/2012                                        Amount Paid:           97 %(     97 %)
Work Started:          05/30/2012                                        Time Passed:          104 %(    104 %)




                                            Construction Status Report                                      Page 132
 28570(04)     Contract: 120243       US-81     Residency:       07100           2.13 MI. US-81:RESURFACE
 MC-269N(005)                                   DUNCAN                           (ASPHALT)FROM BEECH AVE. IN
                                                                                 DUNCAN, EXTEND NORTH.
 Contractor:   T & G CONSTRUCTION, INC.
 Engineer:     Harwell, Jerry M.               Adjusted:
 Contract Amount:         $727,313.95         (        $727,313.95)
 Contract Time:           45                  (   45   )
 Letting Date:            06/21/2012
 Contract Date:           07/17/2012
 W/O Issued:              07/18/2012                                                                Adjusted:
 W/O Effective:           08/06/2012                                       Amount Paid:           0%(      0 %)
 Work Started:                                                             Time Passed:           0%(      0 %)




County:          Texas                                         Commissioner District:                                 6
Contracts Under Construction


 14971(13)     Contract: 100588      US-54   Residency:     06200        5.28 MI. US-54;GRADE,DRAIN &
 NHY-008N(019)                               GUYMON                      SURFACE/FROM 5.5 MI. S.W. OFTHE
                                                                         SH-94 JUNCTION, EXTEND NORTHEAST.
 Contractor:   DOBSON BROTHERS CONSTRUCTION CO.
 Engineer:     Michael, Charles             Adjusted:
 Contract Amount:        $9,958,921.28     (     $10,393,772.96)
 Contract Time:          245               (  460 )
 Letting Date:           10/21/2010
 Contract Date:          11/17/2010
 W/O Issued:             12/07/2010                                                             Adjusted:
 W/O Effective:          03/07/2011                               Amount Paid:            96 % (        92 %)
 Work Started:           03/07/2011                               Time Passed:           209 % (       112 %)


 25483(04)     Contract: 120227      CORD       Residency:       06200           5.30 MI. CO.RD.:GRADE,DRAIN &
 CIRB-170C(140)RB                               GUYMON                           SURFACE:FROM 5.0 MI. N. OF US-64,
                                                                                 EXTEND NORTH.
 Contractor:   J & R SAND COMPANY, INC.
 Engineer:     Michael, Charles                Adjusted:
 Contract Amount:        $3,308,800.95        (      $3,308,800.95)
 Contract Time:          120                  (  120 )
 Letting Date:           06/21/2012
 Contract Date:          07/17/2012
 W/O Issued:             07/18/2012                                                                  Adjusted:
 W/O Effective:          10/01/2012                                        Amount Paid:           0 %(      0 %)
 Work Started:                                                             Time Passed:           0%(       0 %)




County:          Tillman                                       Commissioner District:                                 5
Contracts Under Construction




                                              Construction Status Report                                   Page 133
 23236(04)     Contract: 120188     CORD       Residency:       05005           0.199 MI. CO.RD. BRIDGE &
 BRO-171D(094)CI                               CIRCUIT ENGR. DISTR. # 7         APPROACHES:OVER BLUE CR. 3.1 MI. S.
                                                                                & 2.0 MI. EAST OF US- 70/SH-36 JCT IN
 Contractor:   SEWELL BROS., INC.                                               GRANDFIELD.
 Engineer:     CED7                           Adjusted:
 Contract Amount:       $399,223.65          (        $399,223.65)
 Contract Time:         100                  (  100 )
 Letting Date:          05/17/2012
 Contract Date:         06/15/2012
 W/O Issued:            06/20/2012                                                                  Adjusted:
 W/O Effective:         10/01/2012                                        Amount Paid:            0%(      0 %)
 Work Started:                                                            Time Passed:            0%(      0 %)




County:          Tulsa                                        Commissioner District:                                    8
Contracts Under Construction


 22150(04)     Contract: 110409     CTST       Residency:       08002           0.508 MI. CT.ST.:GRADE,DRAIN &
 STP-172C(278)IG                               TETRA TECH                       SURFACE (91ST ST.) FROM ELM ST.,
                                                                                EXTEND EAST IN THE CITY OF JENKS.
 Contractor:   PARAGON CONTRACTORS, LLC
 Engineer:     TETR                           Adjusted:
 Contract Amount:       $972,972.00          (        $985,097.00)
 Contract Time:         150                  (  150 )
 Letting Date:          08/18/2011
 Contract Date:         09/26/2011
 W/O Issued:            09/30/2011                                                                   Adjusted:
 W/O Effective:         01/16/2012                                        Amount Paid:         100 % (     99 %)
 Work Started:          01/16/2012                                        Time Passed:          97 % (     97 %)


 27401(04)     Contract: 100197     CT.ST.     Residency:       08002           1.855 MI. CT.ST.;RESURFACE
 STP-STIM(512)(513)IG                          TETRA TECH                       (ASPHALT)CITY ST.(E FLORENCE
                                                                                ST.,FROM OLIVE AVE. EXTEND EAST ON
 Contractor:   PARAGON CONTRACTORS, LLC                                         23RD ST.,FROM JASPER.
 Engineer:     TETR                           Adjusted:
 Contract Amount:       $604,067.00          (        $604,067.00)
 Contract Time:         90                   (  269   )
 Letting Date:          03/18/2010
 Contract Date:         04/29/2010
 W/O Issued:            05/06/2010                                                                   Adjusted:
 W/O Effective:         07/05/2010                                        Amount Paid:          92 %(      92 %)
 Work Started:          07/05/2010                                        Time Passed:         266 % (     89 %)


 06374(44)     Contract: 100617     IS-44      Residency:       08100           1.215 MI. IS-44;GRADE,DRAIN, SURFACE
 IMY-0044-2(396)225                            TULSA                            & BRIDGE;FROM RIVER- SIDE DR. TO E.
                                                                                OF PEORIA AVE. IN TULSA.
 Contractor:   BECCO CONTRACTORS, INC.
 Engineer:     Arnold, Bruce                  Adjusted:
 Contract Amount:        $32,439,488.87      (     $33,000,066.25)
 Contract Time:          720                 (  772 )
 Letting Date:           11/18/2010
 Contract Date:          12/22/2010
 W/O Issued:             01/05/2011                                                                  Adjusted:
 W/O Effective:          03/01/2011                                       Amount Paid:           96 %(     94 %)
 Work Started:           03/01/2011                                       Time Passed:           72 %(     67 %)




                                             Construction Status Report                                    Page 134
27382(04)     Contract: 100311     CTST       Residency:       08002           0.259 MI. CT.ST.; RESURFACE
STP-STIM(506)IG                               TETRA TECH                       (ASPHALT)(MAIN ST.) BEGIN AT 4TH ST.,
                                                                               EXTEND W. IN THE     CITY OF JENKS.
Contractor:   BECCO CONTRACTORS, INC.
Engineer:     TETR                           Adjusted:
Contract Amount:       $163,450.00          (        $163,450.00)
Contract Time:         90                   (  244 )
Letting Date:          04/15/2010
Contract Date:         05/12/2010
W/O Issued:            06/24/2010                                                                   Adjusted:
W/O Effective:         08/02/2010                                        Amount Paid:          79 % (     79 %)
Work Started:          08/02/2010                                        Time Passed:         234 % (     86 %)


26604(04)     Contract: 110205     IS-244   Residency:     08100        0.968 MI. IS-244:BRIDGE &
IM-TIGR(497)SS                              TULSA                       APPROACHES.OVER THE ARKANSAS
                                                                        RIVER, IN TULSA.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     Arnold, Bruce                Adjusted:
Contract Amount:        $63,637,567.76    (     $63,637,567.76)
Contract Time:          740               (  740 )
Letting Date:           02/17/2011
Contract Date:          03/16/2011
W/O Issued:             03/18/2011                                                              Adjusted:
W/O Effective:          06/15/2011                               Amount Paid:             78 % (      78 %)
Work Started:           05/13/2011                               Time Passed:             57 % (      57 %)


06374(83)     Contract: 090677      SH-51     Residency:       08100           0.00 MI.;SH-51;US-75:IS-44; IS-244
IMY-0044-2(492)225NI                          TULSA                            /SART WORK ZONE;AT      VARIOUS
                                                                               LOCATIONS IN DIV.    VIII.
Contractor:   ACTION SAFETY SUPPLY CO.
Engineer:     Arnold, Bruce                  Adjusted:
Contract Amount:        $1,310,320.25       (      $1,310,320.25)
Contract Time:                              (        )
Letting Date:           11/19/2009
Contract Date:          12/07/2009                                       Fixed Completion Date: 01/31/2013
W/O Issued:             12/08/2009                                                                Adjusted:
W/O Effective:                                                           Amount Paid:        77 %(      77 %)
Work Started:           12/16/2009                                       Time Passed:       959 %(      83 %)


27929(04)     Contract: 120168      1-244   Residency:     08100        0.260 MI. I-244:BRIDGE RE-
SBR-272N(020)SB                             TULSA                       HABILITATION (E-S RAMP)OVER I-444
                                                                        IN TULSA.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     Arnold, Bruce                Adjusted:
Contract Amount:        $1,298,863.10     (      $1,298,863.10)
Contract Time:          150               (  150 )
Letting Date:           04/19/2012
Contract Date:          05/21/2012
W/O Issued:             06/01/2012                                                              Adjusted:
W/O Effective:          07/09/2012                               Amount Paid:              4 %(        4 %)
Work Started:           07/30/2012                               Time Passed:              1 %(        1 %)




                                            Construction Status Report                                    Page 135
29191(04)     Contract: 120230      I-244     Residency:       08100           0.00 MI. I-244/SH-11:SAFETY
HSIPIG-0244-1(009)000TR                       TULSA                            IMPROVEMENT(CABLE BARRIER)BE- GIN
                                                                               AT MILE MARKER 0, EX-    TEND N. FROM
Contractor:   ACTION SAFETY SUPPLY CO.                                         HARVARD AVE.
Engineer:     Arnold, Bruce                  Adjusted:
Contract Amount:        $1,124,670.55       (      $1,124,670.55)
Contract Time:          140                 (  140 )
Letting Date:           07/19/2012
Contract Date:          08/21/2012
W/O Issued:             08/24/2012                                                                 Adjusted:
W/O Effective:          01/07/2013                                       Amount Paid:            0%(      0 %)
Work Started:                                                            Time Passed:            0%(      0 %)


23185(09)     Contract: 120144      US-75     Residency:       08100           0.00 MI. BRIDGE WATER PROOF
SSP-272C(017)SS                               TULSA                            SEAL/VARIOUS LOCATIONS IN DIV.VIII.
                                                                               /US-75.
Contractor:   JLT CONTRACTING, LLC
Engineer:     Arnold, Bruce                  Adjusted:
Contract Amount:        $334,119.40         (        $334,119.40)
Contract Time:          60                  (   60   )
Letting Date:           03/15/2012
Contract Date:          04/13/2012
W/O Issued:             04/18/2012                                                                  Adjusted:
W/O Effective:          05/14/2012                                       Amount Paid:          90 % (     90 %)
Work Started:           05/14/2012                                       Time Passed:          67 % (     67 %)


24037(04)     Contract: 110525     CT.ST.     Residency:       08001           *172A(396)IG / 1.634 MI. CT.
STP-172A(346)IG/STPG-*                        ENGR. SERV. & TESTING            ST.;GRADE,DRAIN,SURFACE &
                                                                               BRIDGE;(86TH ST.)FROM MEMORIALDR.,
Contractor:   BECCO CONTRACTORS, INC.                                          EXTEND E. TO MAIN ST.
Engineer:     EST                            Adjusted:
Contract Amount:       $6,953,717.61        (      $6,953,717.61)
Contract Time:         275                  (  275 )
Letting Date:          11/17/2011
Contract Date:         12/12/2011
W/O Issued:            12/15/2011                                                                  Adjusted:
W/O Effective:         04/02/2012                                        Amount Paid:          28 %(     28 %)
Work Started:          04/02/2012                                        Time Passed:          49 %(     49 %)


27146(04)     Contract: 110453    I-244   Residency:     08003        4.33 MI. I-244 FROM 73RD ST. EXTEND E
IMY-244-2(499)011/IMY-*                   COBB ENGINEERING CO., INC. TO I-44 INTERCHANGE INCITY OF TULSA.
Contractor:   SHERWOOD CONSTRUCTION CO., INC.
Engineer:     COBB                       Adjusted:
Contract Amount:       $35,057,955.07   (     $35,057,955.07)
Contract Time:         420              (  420 )
Letting Date:          09/15/2011
Contract Date:         10/12/2011
W/O Issued:            10/20/2011                                                             Adjusted:
W/O Effective:         02/06/2012                              Amount Paid:             43 %(          43 %)
Work Started:          02/06/2012                              Time Passed:             42 %(          42 %)
*244-2(500)14




                                            Construction Status Report                                    Page 136
28263(04)     Contract: 120309      I-244       Residency:       08100           0.066 MI. I-244:BRIDGE REHAB. OVER
SBR-172N(518)SB                                 TULSA                            33RD W. AVE., 0.8 MI. N. OF I-44.

Contractor:   BECCO CONTRACTORS, INC.
Engineer:     Arnold, Bruce                    Adjusted:
Contract Amount:        $1,517,217.00         (      $1,517,217.00)
Contract Time:          180                   (  180 )
Letting Date:           07/19/2012
Contract Date:          08/16/2012
W/O Issued:             08/21/2012                                                                   Adjusted:
W/O Effective:          01/07/2013                                         Amount Paid:            0%(      0 %)
Work Started:                                                              Time Passed:            0%(      0 %)


27921(04)     Contract: 110207     SH-20        Residency:       08001           0.634 MI. SH-20;GRADE,DRAIN, &
SAP-172A(511)                                   ENGR. SERV. & TESTING            SURFACE/NEW ALIGNMENT FROM 22ND
                                                                                 ST, EXTEND E. TO 14TH ST., IN
Contractor:   PARAGON CONTRACTORS, LLC                                           COLLINSVILLE.
Engineer:     EST                              Adjusted:
Contract Amount:       $2,080,217.59          (      $2,302,841.46)
Contract Time:         180                    (  226 )
Letting Date:          03/17/2011
Contract Date:         04/15/2011
W/O Issued:            04/22/2011                                                                     Adjusted:
W/O Effective:         05/31/2011                                          Amount Paid:         109 % (     98 %)
Work Started:          05/31/2011                                          Time Passed:         134 % (    107 %)


21901(04)     Contract: 110204       IS-244     Residency:       08002           0.00 MI. IS-244/BRIDGE PAINT -ING &
IMY-NBIP(436)                                   TETRA TECH                       REHAB./AT MULTIPLE     LOCATIONS IN
                                                                                 THE CITY OF     TULSA.
Contractor:   V. H. P. ENTERPRISES, INC.
Engineer:     TETR                             Adjusted:
Contract Amount:         $8,940,379.50        (      $9,560,431.85)
Contract Time:           240                  (  254 )
Letting Date:            03/17/2011
Contract Date:           05/12/2011
W/O Issued:              06/10/2011                                                                  Adjusted:
W/O Effective:           08/01/2011                                        Amount Paid:          94 %(     88 %)
Work Started:            08/01/2011                                        Time Passed:         151 %(    143 %)


23171(04)     Contract: 120143      IS-244   Residency:     08100        0.00 MI. IS-244:BRIDGE REHAB
BRIY-0244-1(006)101                          TULSA                       -ILITATION:I-244 EB RAMP OVER I-244
                                                                         W-N RAMP, APPROX. 5.39 MI. E. OF JCT
Contractor:   PARADIGM CONSTRUCTION & ENGINEERING, INC                   I-244/I-444.
Engineer:     Arnold, Bruce                 Adjusted:
Contract Amount:        $492,453.50        (        $492,453.50)
Contract Time:          90                 (   90   )
Letting Date:           03/15/2012
Contract Date:          04/10/2012
W/O Issued:             04/12/2012                                                               Adjusted:
W/O Effective:          09/06/2012                                Amount Paid:              0 %(           0 %)
Work Started:                                                     Time Passed:              0 %(           0 %)




                                              Construction Status Report                                    Page 137
27633(04)     Contract: 110526      SH-51     Residency:       08100           *(005)SB/ 0.05 MI. SH-51; BRIDGE
SBR-172A(515)SB/SBR-272A*                     TULSA                            REHAB./OVER PITTSBURG AVE. 0.5 MI.
                                                                               E. OF HARVARD AVE.,& OVER MK&T
Contractor:   BECCO CONTRACTORS, INC.                                          R/R.
Engineer:     Arnold, Bruce                  Adjusted:
Contract Amount:        $2,680,788.96       (      $2,680,788.96)
Contract Time:          240                 (  240 )
Letting Date:           01/19/2012
Contract Date:          02/21/2012
W/O Issued:             03/22/2012                                                                  Adjusted:
W/O Effective:          04/23/2012                                       Amount Paid:          40 % (     40 %)
Work Started:           04/23/2012                                       Time Passed:          42 % (     42 %)


21923(04)     Contract: 110451     US-75   Residency:     08007        .107 MI. US-75 OVER MIDDLE DUCK
BRFY-172N(272)                             CRAIG & KEITHLINE, INC.     CREEK, .9 MI. N OF OKMULGEE COUNTY
                                                                       LINE.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     C&KI                        Adjusted:
Contract Amount:       $2,471,973.36     (      $2,471,973.36)
Contract Time:         250               (  250 )
Letting Date:          09/15/2011
Contract Date:         10/12/2011
W/O Issued:            10/20/2011                                                              Adjusted:
W/O Effective:         11/28/2011                                Amount Paid:            95 % (       95 %)
Work Started:          11/28/2011                               Time Passed:             84 % (       84 %)


28593(05)     Contract: 110455     US-75      Residency:       08001           0.00 MI. US-75/I-244/US-64/UNION AVE
BRFY-172A(531)3B                              ENGR. SERV. & TESTING            AT VARIOUS LOCATIONS INDIVISION 8.

Contractor:   PBX CORPORATION
Engineer:     EST                            Adjusted:
Contract Amount:       $700,136.30          (        $700,136.30)
Contract Time:         90                   (   90   )
Letting Date:          09/15/2011
Contract Date:         10/12/2011
W/O Issued:            10/20/2011                                                                  Adjusted:
W/O Effective:         11/28/2011                                        Amount Paid:          99 %(     99 %)
Work Started:          02/16/2012                                        Time Passed:          97 %(     97 %)


06374(47)     Contract: 120228     IS-44   Residency:     08100          0.828 MI. IS-44:GRADE,DRAIN
IMY-0044-2(399)226                         TULSA                         ,SURFACE & BRIDGE/AT LEWIS AVEIN
                                                                         THE CITY OF TULSA.
Contractor:   MANHATTAN ROAD & BRIDGE CO. / ALLEN CONTRACTING, INC. (JV)
Engineer:     Arnold, Bruce               Adjusted:
Contract Amount:        $37,992,362.93   (     $37,992,362.93)
Contract Time:          600              (  600 )
Letting Date:           06/21/2012
Contract Date:          07/17/2012
W/O Issued:             08/21/2012                                                               Adjusted:
W/O Effective:          10/01/2012                              Amount Paid:                0 %(         0 %)
Work Started:                                                   Time Passed:                0 %(         0 %)




                                            Construction Status Report                                    Page 138
17387(04)     Contract: 090587    US-75   Residency:     08007        2.738 MI. GRADE, DRAIN, SURFACE &
NHY-014N(019)SS                           CRAIG & KEITHLINE, INC.     BRIDGE US-75 AT THE 111TH STREET
                                                                      JUNCTION IN THE CITY OF JENKS.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     C&KI                       Adjusted:
Contract Amount:       $11,243,505.70   (     $11,646,841.52)
Contract Time:         365              ( 1,073 )
Letting Date:          09/17/2009
Contract Date:         10/20/2009
W/O Issued:            10/23/2009                                                             Adjusted:
W/O Effective:         03/01/2010                               Amount Paid:          103 % (        100 %)
Work Started:          11/10/2009                              Time Passed:           256 % (         87 %)


23185(08)     Contract: 110254      IS-244     Residency:       08100           0.00 MI. BRIDGE WATER PROOF
BRFY-172B(523)                                 TULSA                            SEAL/VARIOUS LOCATIONS IN   CREEK
                                                                                & TULSA COUNTY.
Contractor:   GARY A. CRAIN, INC.
Engineer:     Arnold, Bruce                   Adjusted:
Contract Amount:        $258,181.60          (        $258,181.60)
Contract Time:          60                   (   60   )
Letting Date:           04/14/2011
Contract Date:          05/12/2011
W/O Issued:             05/18/2011                                                                  Adjusted:
W/O Effective:          09/06/2011                                        Amount Paid:        100 % (    100 %)
Work Started:           04/25/2012                                        Time Passed:         62 % (     62 %)


20925(04)     Contract: 120229      US-64   Residency:     08400        0.074 MI. US-64:BRIDGE REPR. OVER
SSP-172N(355)SS                             SAND SPRINGS                EUCHEE CR.,6.4 MI. S.E. OF THE OSAGE
                                                                        C/L.
Contractor:   MANHATTAN ROAD & BRIDGE COMPANY
Engineer:     Williams, Mark J.            Adjusted:
Contract Amount:        $1,100,714.80     (      $1,100,714.80)
Contract Time:          90                (   90   )
Letting Date:           06/21/2012
Contract Date:          07/11/2012
W/O Issued:             07/18/2012                                                              Adjusted:
W/O Effective:          08/06/2012                               Amount Paid:              0 %(           0 %)
Work Started:                                                    Time Passed:              0 %(           0 %)


26362(05)     Contract: 090329     I-244   Residency:     08100        5.805 MI. PAVEMENT REHAB, BRIDGE,
IM-STIM(048)(49)(50)(47)                   TULSA                       TRAFFIC LIGHTING & TRAFFIC SIGNS
                                                                       I-244 AT VARIOUS LOCATIONS IN
Contractor:   MANHATTAN ROAD & BRIDGE CO. & SHERWOOD CONSTRUCTION CO, INC. 8.
                                                                       DIVISION
Engineer:     Arnold, Bruce               Adjusted:
Contract Amount:        $67,659,720.06   (     $69,905,475.59)
Contract Time:          580              ( 1,004 )
Letting Date:           04/23/2009
Contract Date:          05/13/2009
W/O Issued:             06/01/2009                                                            Adjusted:
W/O Effective:          06/08/2009                              Amount Paid:          102  %(         99 %)
Work Started:           06/08/2009                              Time Passed:          172  %(         99 %)




                                             Construction Status Report                                  Page 139
 24796(04)     Contract: 100569      CTST   Residency:     08100        *(392)(491)SB/ 0.097 MI. CT. ST.;
 SBR-172N(389)SB/SBR-172A*                  TULSA                       BRIDGE REHAB. SH-51;OVER UTICA AVE.
                                                                        & OVER ST.LOUIS ST. ON 12TH
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                          ST.OVER IS-444 IN
 Engineer:     Arnold, Bruce               Adjusted:
 Contract Amount:        $2,291,528.04    (      $2,451,528.04)
 Contract Time:          130              (  461 )
 Letting Date:           10/21/2010
 Contract Date:          11/15/2010
 W/O Issued:             11/19/2010                                                              Adjusted:
 W/O Effective:          01/04/2011                              Amount Paid:             96 % (          90 %)
 Work Started:           01/04/2011                              Time Passed:           314 % (           89 %)
 TULSA.




County:          Wagoner                                      Commissioner District:                           1
Contracts Under Construction


 28100(04)     Contract: 110394     US-69     Residency:    01001         0.00 MI. US-69;SAFETY IMPROV. (CABLE
 NHG-013N(143)TR                              ENGR. SERV. & TESTING       BARRIER)FROM 3.6 MI. S.OF THE MAYES
                                                                          C/L., EXTEND    NORTH.
 Contractor:   MIDSTATE TRAFFIC CONTROL, INC.
 Engineer:     EST                          Adjusted:
 Contract Amount:       $538,478.00        (        $538,478.00)
 Contract Time:         120               (    120 )
 Letting Date:          08/18/2011
 Contract Date:         09/26/2011
 W/O Issued:            09/29/2011                                                                Adjusted:
 W/O Effective:         12/05/2011                                  Amount Paid:            32 % (        32 %)
 Work Started:          12/05/2011                                 Time Passed:           143 % (        143 %)


 10006(07)     Contract: 120174      SH-51   Residency:     01100        0.776 MI. SH-51:GRADE & DRAIN
 STPY-173B(009)                              MUSKOGEE                    (CAUSEWAY AT GRAND RIVER
                                                                         BRIDGE)FROM 7.8 MI. E. OF US- 69,
 Contractor:   MANHATTAN ROAD & BRIDGE COMPANY                           EXTEND EAST.
 Engineer:     Ivy, Steve (Act.)            Adjusted:
 Contract Amount:        $9,218,517.50     (      $9,218,517.50)
 Contract Time:          300               (  300 )
 Letting Date:           04/19/2012
 Contract Date:          05/21/2012
 W/O Issued:             05/31/2012                                                              Adjusted:
 W/O Effective:          08/06/2012                               Amount Paid:            15 %(           15 %)
 Work Started:           07/11/2012                               Time Passed:            12 % (          12 %)




County:          Washington                                   Commissioner District:                           8
Contracts Under Construction




                                             Construction Status Report                             Page 140
 26948(04)     Contract: 110303      CORD      Residency:       08400           0.293 MI. CO.RD./BRIDGE &
 BRO-174D(075)CO                               SAND SPRINGS                     APPROACHES;OVER KEELER CR. 7.0MI.
                                                                                S. & 2.8 MI. W. OF US  -60/US-75 JCT.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     Williams, Mark J.              Adjusted:
 Contract Amount:        $576,535.91         (        $576,535.91)
 Contract Time:          90                  (  107 )
 Letting Date:           11/17/2011
 Contract Date:          01/24/2012
 W/O Issued:             01/26/2012                                                                  Adjusted:
 W/O Effective:          03/05/2012                                       Amount Paid:          67 % (     67 %)
 Work Started:           04/09/2012                                       Time Passed:         143 % (    121 %)


 23170(05)     Contract: 120189      US-60     Residency:       08400           0.174 MI. US-60/SH-123 SAFETY
 SSP-274B(001)SS                               SAND SPRINGS                     IMPROVEMENT (INTERSECTION
                                                                                MODIFICATION)AT THE SH-123
 Contractor:   APAC-CENTRAL, INC.                                               JUNCTION.
 Engineer:     Williams, Mark J.              Adjusted:
 Contract Amount:        $834,070.86         (        $834,070.86)
 Contract Time:          90                  (   90   )
 Letting Date:           05/17/2012
 Contract Date:          06/14/2012
 W/O Issued:             06/18/2012                                                                 Adjusted:
 W/O Effective:          10/01/2012                                       Amount Paid:            0%(      0 %)
 Work Started:           08/22/2012                                       Time Passed:            0%(      0 %)




County:          Washita                                      Commissioner District:                                    5
Contracts Under Construction


 28113(04)     Contract: 120231      SH-44     Residency:       05100           0.00 MI. SH-44:BRIDGE REHAB. OVER
 SBR-175C(125)SB                               CLINTON                          STEEL DUST CR., 0.7 MI. NORTH OF THE
                                                                                KIOWA C/L.
 Contractor:   K & R BUILDERS, INC.
 Engineer:     Greer, Randy                   Adjusted:
 Contract Amount:        $643,945.48         (        $643,945.48)
 Contract Time:          60                  (   60   )
 Letting Date:           06/21/2012
 Contract Date:          07/20/2012
 W/O Issued:             07/24/2012                                                                  Adjusted:
 W/O Effective:          11/05/2012                                       Amount Paid:            0 %(      0 %)
 Work Started:                                                            Time Passed:            0%(       0 %)




County:          Woods                                        Commissioner District:                                    6
Contracts Under Construction




                                             Construction Status Report                                    Page 141
24318(04)     Contract: 120169     US-64    Residency:     06100        0.227 MI. US-64/BRIDGE &
STPY-176B(128)                              BUFFALO                     APPROACHES:OVER UNNAMED CR., 3.1
                                                                        MI. E. OF SH-14.
Contractor:   REECE CONSTRUCTION CO., INC.
Engineer:     Burke, David                 Adjusted:
Contract Amount:       $1,464,780.94     (       $1,464,780.94)
Contract Time:         120               (   120 )
Letting Date:          04/19/2012
Contract Date:         05/21/2012
W/O Issued:            08/07/2012                                                               Adjusted:
W/O Effective:         09/04/2012                                Amount Paid:              0%(         0 %)
Work Started:          08/27/2012                                Time Passed:              0%(         0 %)


24243(04)     Contract: 120190     US-64    Residency:     06100        0.982 MI. US-64:BRIDGE &
BRFY-176B(125)                              BUFFALO                     APPROACHES;OVER WHITE HORSE CR.
                                                                        9.0 MI. EAST OF SH-50.
Contractor:   VENTURE CORPORATION DBA V. C. O. PAVING
Engineer:     Burke, David                Adjusted:
Contract Amount:       $5,222,031.23     (       $5,222,031.23)
Contract Time:         310               (   310 )
Letting Date:          05/17/2012
Contract Date:         06/19/2012
W/O Issued:            07/13/2012                                                               Adjusted:
W/O Effective:         10/01/2012                                Amount Paid:              3%(         3 %)
Work Started:          07/30/2012                                Time Passed:              5%(         5 %)


27753(04)     Contract: 110158     SH-14    Residency:     06002        0.00 MI. SH-14:BRIDGE REHAB
SBR-176C(182)(183)(184)SB                   TETRA TECH                  -ILITATION/OVER EAGLE CHIEF CR., 5.0
                                                                        MI. SOUTH OF THE    US-64 JUNCTION
Contractor:   REECE CONSTRUCTION CO., INC.
Engineer:     TETR                         Adjusted:
Contract Amount:       $1,045,246.69     (       $1,054,117.21)
Contract Time:         120               (   120 )
Letting Date:          07/21/2011
Contract Date:         08/18/2011
W/O Issued:            08/30/2011                                                               Adjusted:
W/O Effective:         09/26/2011                                Amount Paid:            95  %(         94 %)
Work Started:          09/26/2011                                Time Passed:            94  %(         94 %)


20271(04)     Contract: 100409    US-281    Residency:     06100        2.071 MI. US-281;BRIDGE &
BRFY-176B(061)SS                            BUFFALO                     APPROACHES;OVER A SALT FORK OFTHE
                                                                        ARKANSAS RIVER/OVER A     R/R
Contractor:   VENTURE CORPORATION DBA V. C. O. PAVING                   BRIDGE JUST N. OF ALVA.
Engineer:     Burke, David                Adjusted:
Contract Amount:       $11,597,233.63    (      $12,153,757.23)
Contract Time:         380               (   572 )
Letting Date:          07/22/2010
Contract Date:         08/24/2010
W/O Issued:            09/16/2010                                                               Adjusted:
W/O Effective:         11/01/2010                                Amount Paid:           102  %(        97 %)
Work Started:          09/21/2010                                Time Passed:           151  %(       100 %)




                                            Construction Status Report                            Page 142
 27560(04)     Contract: 120233     US-281   Residency:     06100        6.00 MI. US-281:RSURFACE
 SSR-176B(178)SR                             BUFFALO                     (ASPHALT)BEGIN 2.4 MI. NORTH OF
                                                                         US-64, EXTEND NORTH.
 Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
 Engineer:     Burke, David                 Adjusted:
 Contract Amount:       $899,680.00        (        $899,680.00)
 Contract Time:         35                 (   35   )
 Letting Date:          06/21/2012
 Contract Date:         07/12/2012
 W/O Issued:            07/18/2012                                                               Adjusted:
 W/O Effective:         08/06/2012                                Amount Paid:             0%(           0 %)
 Work Started:          08/06/2012                                Time Passed:             0%(           0 %)


 23046(04)     Contract: 110456     CORD       Residency:      06009           .198 MI. CO.RD.(EW-021): BRIDGE AND
 BRO-176D(088)CI                               CIRCUIT ENGR. DISTR. # 8        APPROACHES; OVER LITTLE EAGLE CHIEF
                                                                               CREEK .8 MI. E OF US-281 AND 6.0 MI. S
 Contractor:   SEWELL BROS., INC.                                              OF US-64.
 Engineer:     CED8                          Adjusted:
 Contract Amount:       $400,735.96         (        $400,735.96)
 Contract Time:         90                  (   96   )
 Letting Date:          10/20/2011
 Contract Date:         11/22/2011
 W/O Issued:            11/29/2011                                                                   Adjusted:
 W/O Effective:         02/06/2012                                       Amount Paid:           92 % (     92 %)
 Work Started:          12/27/2011                                       Time Passed:          104 % (     98 %)


 24196(04)     Contract: 110322     CORD       Residency:      06009           .18 MI. CO.RD.(NS-237):BRIDGE AND
 BRF-176C(121)CI                               CIRCUIT ENGR. DISTR. # 8        APPROACHES; OVER UNNAMED CREEK,
                                                                               7.0 MI. W AND 6.5 MI. S OF THE
 Contractor:   SEWELL BROS., INC.                                              US-64/US-281 JCT.
 Engineer:     CED8                          Adjusted:
 Contract Amount:       $410,082.80         (        $432,464.13)
 Contract Time:         105                 (  111   )
 Letting Date:          10/20/2011
 Contract Date:         11/22/2011
 W/O Issued:            11/29/2011                                                                  Adjusted:
 W/O Effective:         02/06/2012                                       Amount Paid:          101 %(     96 %)
 Work Started:          12/29/2011                                       Time Passed:          110 %(    104 %)




County:         Woodward                                     Commissioner District:                                     6
Contracts Under Construction


 17457(14)     Contract: 110316      SH-3    Residency:     06100        1.723 MI. SH-3:GRADE,DRAIN
 NHY-017N(057)                               BUFFALO                     ,SURFACE & BRIDGE:FROM 3.0 MI.SOUTH
                                                                         OF THE SH-50 JUNCTION, EXTEND
 Contractor:   OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV) SOUTHEAST.
 Engineer:     Burke, David                 Adjusted:
 Contract Amount:        $5,801,858.98     (      $6,227,770.23)
 Contract Time:          210               (  300 )
 Letting Date:           06/16/2011
 Contract Date:          07/26/2011
 W/O Issued:             08/01/2011                                                             Adjusted:
 W/O Effective:          11/07/2011                               Amount Paid:            98 %(         91 %)
 Work Started:           11/04/2011                               Time Passed:           134 %(         94 %)




                                            Construction Status Report                                     Page 143
28140(04)     Contract: 120114     US-183   Residency:     06100        1.38 MI. US-183;PAVEMENT RE
NHY-177N(118)3P                             BUFFALO                     -HABILITATION(P.C. CONCRETE) FROM
                                                                        10TH ST. IN WOODWARD, EXTEND
Contractor:   DIAMOND SURFACE, INC.                                     WEST.
Engineer:     Burke, David                 Adjusted:
Contract Amount:       $854,186.73        (        $854,186.73)
Contract Time:         90                 (   90   )
Letting Date:          02/16/2012
Contract Date:         03/15/2012
W/O Issued:            03/29/2012                                                              Adjusted:
W/O Effective:         06/04/2012                                Amount Paid:           100 % (      100 %)
Work Started:          06/04/2012                                Time Passed:            81 % (        81 %)


17457(12)     Contract: 100412     US-183   Residency:     06100        3.183 MI. US-183/US-270/SH-
NHY-017N(055)                               BUFFALO                     3;GRADE,DRAIN & SURFACE;FROM THE
                                                                        SH-50 JUNCTION,EXTEND     SOUTHEAST.
Contractor:   THE CUMMINS CONSTRUCTION CO., INC.
Engineer:     Burke, David                 Adjusted:
Contract Amount:       $9,179,854.29      (      $9,524,294.02)
Contract Time:         300                (  602 )
Letting Date:          06/17/2010
Contract Date:         07/15/2010
W/O Issued:            07/20/2010                                                               Adjusted:
W/O Effective:         11/01/2010                                Amount Paid:            99 % (        96 %)
Work Started:          10/11/2010                                Time Passed:           210 % (       104 %)


25700(04)     Contract: 120191     CORD       Residency:      06009           0.208 MI. CO.RD. BRIDGE &
BRO-177D(098)CI                               CIRCUIT ENGR. DISTR. # 8        APPROACHES:OVER DEEP CREEK 0.3MI.
                                                                              N. & 1.7 MI. W. OF THE US-183/US-270
Contractor:   SEWELL BROS., INC.                                              JCT NW OF SEILIN
Engineer:     CED8                          Adjusted:
Contract Amount:       $677,094.40         (        $677,094.40)
Contract Time:         120                 (  120   )
Letting Date:          05/17/2012
Contract Date:         06/15/2012
W/O Issued:            06/20/2012                                                                 Adjusted:
W/O Effective:         09/04/2012                                       Amount Paid:           0 %(      0 %)
Work Started:                                                           Time Passed:           0 %(      0 %)
G

28128(37)     Contract: 120063     US-412   Residency:     06003        54.30 MI. US-412;SAFETY IM-
BTOP-277N(001)                              COBB ENGINEERING CO., INC. PROVEMENTS(FIBER OPTIC CABLE) FROM
                                                                        THE CITY OF WOODWARD      TO THE
Contractor:   ROHL NETWORKS, LP                                         CITY OF ORIENTA.
Engineer:     COBB                         Adjusted:
Contract Amount:       $1,698,546.26      (      $1,698,546.26)
Contract Time:         160                (  160 )
Letting Date:          01/19/2012
Contract Date:         02/21/2012
W/O Issued:            03/01/2012                                                               Adjusted:
W/O Effective:         03/26/2012                                Amount Paid:           100  %(       100 %)
Work Started:          03/26/2012                                Time Passed:            41  %(        41 %)




                                           Construction Status Report                                   Page 144
 County:          Alfalfa                                      Commissioner District:                                 6
Contracts Awarded - NTP Not Processed

  26958(04)     Contract:    120268  CORD                                  BRO-102D(162)CI
  Contractor:          BELK BRIDGE, INC.                                   0.237 MI. CO.RD.:BRIDGE &
  Contract Amount:      $747,976.88                                        APPROACHES:OVER LITTLE MULE     CR., 4.2
                                               Residency:        06009
                                                                           MI. N. OF SH-11.
  Letting Date:         08/16/2012             CIRCUIT ENGR. DISTR. # 8


 County:          Atoka                                        Commissioner District:                                 2
Contracts Awarded - NTP Not Processed

  28755(04)     Contract:    120373 PKRD                                   SAP-103D(141)
  Contractor:          HUB CONSTRUCTION, INC.                              0.010 MI. PK.RD.;GRADE & RE-
  Contract Amount:      $67,660.00                                         SURFACE(ASPHALT)AT MCGEE CREEKSTATE
                                            Residency:           02100
                                                                           PK., ON MCGEE CR. LAKE ROAD.
  Letting Date:         08/16/2012          ANTLERS


 County:          Beckham                                      Commissioner District:                                 5
Contracts Awarded - NTP Not Processed

  28131(04)     Contract:    120193 SH-34                                  SBR-105C(197)SB
  Contractor:          REECE CONSTRUCTION CO., INC.                        0.00 MI. SH-34:BRIDGE RE-
  Contract Amount:      $552,243.09                                        HABILITATION/OVER FLAT CR.,   4.3 MI.
                                           Residency:            05200
                                                                           SOUTH OF SH-152.
  Letting Date:         06/21/2012         ALTUS


 County:          Bryan                                        Commissioner District:                                 2
Contracts Awarded - NTP Not Processed

  27889(04)     Contract:    120284   CORD                            STP-107C(170)CI
  Contractor:          OVERLAND CORPORATION                           2.023 MI. CO.RD.:GRADE,DRAIN SURFACE &
  Contract Amount:      $2,166,935.18                                 BRIDGE/FROM 6.0 MI. S. OF US-70, EXTEND
                                           Residency:     02013
                                                                      SOUTH.
  Letting Date:         08/16/2012         CIRCUIT ENGR. DISTRICT # 3


 County:          Carter                                       Commissioner District:                                 7
Contracts Awarded - NTP Not Processed

  26849(04)     Contract:    120249 CORD                                   BRF-NBIL(223)CI
  Contractor:          REECE CONSTRUCTION CO., INC.                        0.340 MI. CO.RD./BRIDGE &
  Contract Amount:      $604,283.25                                        APPROACHES:OVER TRIBUTARY OF WALNUT
                                           Residency:            07200
                                                                           BAYOU CR. 4.0 MI.    SO. & 4.6 MI. E. OF
  Letting Date:         07/19/2012         ARDMORE                         US-70.

  28754(04)     Contract:    120374  PKRD                                  SAP-110D(241)
  Contractor:          SILVER STAR CONSTRUCTION COMPANY, INC.              0.22 MI. PK.RD.:RESURFACE  (ASPHALT)AT
  Contract Amount:      $136,900.00                                        MURRAY STATE PK, ON THE ENTRANCE RD.
                                           Residency:     07200
                                                                           IN     FRONT OF THE PRO SHOP.
  Letting Date:         08/16/2012         ARDMORE


 County:          Cimarron                                     Commissioner District:                                 6
Contracts Awarded - NTP Not Processed




                                              Construction Status Report                                   Page 145
  28322(04)     Contract:    120314   CORD                                 ACSTP-113C(087)CI
  Contractor:          HIGHWAY CONTRACTORS, INC.                           2.860 MI. CO.RD.;RESURFACE
  Contract Amount:      $1,210,577.38                                      (ASPHALT)FROM EW-23, EXTEND   NORTH TO
                                           Residency:            06200
                                                                           US-56.
  Letting Date:         08/16/2012         GUYMON


 County:          Cleveland                                    Commissioner District:                                  3
Contracts Awarded - NTP Not Processed

  24112(11)     Contract:    120286 SH-39                           STPY-214B(012)RW
  Contractor:          ROBIN HAUSNER HOUSE MOVERS & DEMOLITION, LLC 0.00 MI. SH-39:RIGHT-OF-   WAY
  Contract Amount:      $28,333.00                                  CLEARANCE:FROM 2.0 MI. E. OF US-77,
                                           Residency:    03200
                                                                    EXTEND EAST.
  Letting Date:         08/16/2012         PURCELL

  20997(17)     Contract:    120285 US-77                           STPY-214C(013)RW
  Contractor:          ROBIN HAUSNER HOUSE MOVERS & DEMOLITION, LLC 0.00 MI. US-77:RIGHT-OF-   WAY
  Contract Amount:      $32,188.00                                  CLEARANCE:FROM 4.05 MI. N.OF
                                           Residency:    03200
                                                                    SH-39,EXTEND NORTH       THROUGH
  Letting Date:         08/16/2012         PURCELL                  SLAUGHTERVILLE.


 County:          Creek                                        Commissioner District:                                  8
Contracts Awarded - NTP Not Processed

  28932(04)     Contract:    120269   US-75                                BRFY-219C(005)
  Contractor:          PBX CORPORATION                                     0.00 MI. US-75/SH-11/SH-18 /SH-99:AT
  Contract Amount:      $1,683,521.80                                      MULTIPLE LOCATIONS IN DIV. VIII.
                                               Residency:        08002
  Letting Date:         08/16/2012             TETRA TECH


 County:          Custer                                       Commissioner District:                                  5
Contracts Awarded - NTP Not Processed

  28473(04)     Contract:    120271 CORD                                   STP-120C(197)CI
  Contractor:          CASWELL CONTRACTING, INC.                           1.523 MI. CO.RD.;GRADE,DRAIN &
  Contract Amount:      $775,444.37                                        SURFACE;FROM AIRPORT RD. IN
                                           Residency:     05005
                                                                           WEATHERFORD EXTEND E. ON EW- 101 THEN
  Letting Date:         08/16/2012         CIRCUIT ENGR. DISTR. # 7        N. ON NS-244.

  24133(04)     Contract:    120270   SH-33                          SSP-120B(124)SS/SBR-120B*
  Contractor:                                                        *(178)SB/SBR-220B(007)SB/
                       OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
  Contract Amount:      $2,561,056.22                                SH-33:BRIDGE & APPROACHES/ BRIDGE
                                             Residency:    05100
                                                                     REHAB./OVER DEER     CR., DRY CR.,&
  Letting Date:         08/16/2012           CLINTON                       LITTLE DEER CR.


 County:          Delaware                                     Commissioner District:                                  8
Contracts Awarded - NTP Not Processed

  10441(04)     Contract:    110422   SH-10                                BRFY-021C(256)
  Contractor:          JENSEN CONSTRUCTION COMPANY                         0.892 MI. SH-10;BRIDGE &
  Contract Amount:      $15,741,148.27                                     APPROACHES/OVER ELK RIVER,    1.35 MI. S.
                                            Residency:           08011
                                                                           OF THE OTTAWA     C/L.
  Letting Date:         08/16/2012          GARVER, LLC.


 County:          Grant                                        Commissioner District:                                  4
Contracts Awarded - NTP Not Processed




                                              Construction Status Report                                  Page 146
  27281(04)     Contract:    120252 CORD                                   BRO-127D(171)CI
  Contractor:          KING CONSTRUCTION CO., INC. & SUBSIDIARIES          0.275 MI. CO.RD.:BRIDGE &
  Contract Amount:      $679,607.00                                        APPROACHES/OVER TRIBUTARY TO SAND
                                           Residency:       04009
                                                                           CR. 2.0 MI.N.& 0.4 MI. E. OF THE
  Letting Date:         07/19/2012         CIRCUIT ENGR. DISTR. # 8        SH-11/SH-132 JCT.


 County:         Harmon                                        Commissioner District:                                5
Contracts Awarded - NTP Not Processed

  24949(04)     Contract:    120253   CORD                                 CIRB-129C(039)RB
  Contractor:          EARTH BUILDERS, L.P.                                0.937 MI. CO.RD.:BRIDGE &
  Contract Amount:      $7,176,530.30                                      APPROACHES:OVER THE RED RIVER 8.0 MI.
                                               Residency:        05005
                                                                           S. & 3.0 MI. W.   OF HOLLIS.
  Letting Date:         07/19/2012             CIRCUIT ENGR. DISTR. # 7


 County:         Haskell                                       Commissioner District:                                1
Contracts Awarded - NTP Not Processed

  27386(04)     Contract:    120287 CORD                                   BRF-131C(103)CI
  Contractor:          HUB CONSTRUCTION, INC.                              0.128 MI. CO.RD.:BRIDGE &
  Contract Amount:      $588,716.00                                        APPROACHES:OVER ELM CR., 0.2 MI. WEST
                                            Residency:           01200
                                                                           OF SH-2
  Letting Date:         08/16/2012          SALLISAW


 County:         Jefferson                                     Commissioner District:                                7
Contracts Awarded - NTP Not Processed

  27474(04)     Contract:    120288   CORD                           BRO-134D(079)CI
  Contractor:                                                        0.376 MI. CO.RD.:BRIDGE &
                       OBC, INC./PLAINS BRIDGE CONTRACTING OF OKLAHOMA, LLC (JV)
  Contract Amount:      $1,049,375.54                                APPROACHES:OVER MUD & COTTON- WOOD
                                             Residency:    07100
                                                                     CR., 0.7 MI. W. OF SH- 89.
  Letting Date:         08/16/2012           DUNCAN


 County:         Latimer                                       Commissioner District:                                2
Contracts Awarded - NTP Not Processed

  21735(08)     Contract:    120375 SH-1                                   MC-239C(006)
  Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.               0.08 MI. SH-1:BRIDGE REHAB . OVER ROCK
  Contract Amount:      $356,081.00                                        CR., 0.16 MI. W. OF THE LEFLORE COUNTY
                                            Residency:       02200
                                                                           LINE.
  Letting Date:         08/16/2012          HEAVENER


 County:         Logan                                         Commissioner District:                                4
Contracts Awarded - NTP Not Processed

  23017(04)     Contract:    120289  CORD                                  BRF-142C(118)CI
  Contractor:          BELK BRIDGE, INC.                                   0.251 MI. CO.RD.:BRIDGE &
  Contract Amount:      $734,485.00                                        APPROACHES:OVER OTTER CR. 3.0 MI. S. &
                                               Residency:        04500
                                                                           1.4 MI. EAST OF    THE SH-51/SH-74 JCT.
  Letting Date:         08/16/2012             STILLWATER

  27729(04)     Contract:    120274 SH-000                                 STPY-242C(001)
  Contractor:          RUDY CONSTRUCTION CO.                               1.55 MI. SH-00:RESURFACE   (ASPHALT) &
  Contract Amount:      $587,140.00                                        PEDESTRIAN IMPROV./ THRU COYLE, FROM
                                           Residency:            04500
                                                                           THE NEW SH-33,EXTEND EAST THEN
  Letting Date:         08/16/2012         STILLWATER                      NORTH.




                                              Construction Status Report                                  Page 147
 County:          Love                                         Commissioner District:                                  7
Contracts Awarded - NTP Not Processed

  28584(04)     Contract:    120257   IS-35                         IMY-0035-1(161)003
  Contractor:                                                       1.50 CO., INC JV
                       DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION MI. IS-35;GRADE,DRAIN, &
  Contract Amount:      $3,526,292.41                               SURFACE;INTERCHANGE @ ROGERSRD. 3.24
                                            Residency:     07200
                                                                    N. OF THE TX STATE LINE (SOUTH HALF)
  Letting Date:         08/16/2012          ARDMORE


 County:          McClain                                      Commissioner District:                                  3
Contracts Awarded - NTP Not Processed

  20212(04)     Contract:    120290 CORD                            BRF-144C(059)CI
  Contractor:          REECE CONSTRUCTION CO., INC.                 0.192 MI. CO.RD.:BRIDGE &
  Contract Amount:      $365,646.68                                 APPROACHES:OVER TRIBUTARY OF
                                           Residency:     03006
                                                                    COLBERT CR., 6.0 MI. & 5.7 MI. W. OF THE
  Letting Date:         08/16/2012         OLLAR & OLLAR ENGINEERINGSH-39/SH-59 JCT


 County:          McIntosh                                     Commissioner District:                                  1
Contracts Awarded - NTP Not Processed

  29151(04)     Contract:    120306   US-69                                SBR-246N(001)SB
  Contractor:          WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES       0.00 MI. US-69:BRIDGE REHAB. :OVER
  Contract Amount:      $1,421,032.80                                      LOCUST ST. IN EUFAULA, 4.71 MI. N. OF THE
                                            Residency:     01100
                                                                           PITTSBURG C/L.
  Letting Date:         07/19/2012          MUSKOGEE


 County:          Murray                                       Commissioner District:                                  7
Contracts Awarded - NTP Not Processed

  29273(04)     Contract:    120299 SH-7                                   HSIPG-250A(001)TR
  Contractor:          MIDSTATE TRAFFIC CONTROL, INC.                      0.00 MI. SH-7;SAFETY IM-  PROVEMENT AT
  Contract Amount:      $158,280.00                                        THE IS-35      INTERCHANGE.
                                            Residency:           07200
  Letting Date:         08/16/2012          ARDMORE


 County:          Noble                                        Commissioner District:                                  4
Contracts Awarded - NTP Not Processed

  20311(07)     Contract:    120275   US-64                                STPY-152B(173)/BRFY-152B*
  Contractor:          DONDLINGER & SONS CONSTRUCTION CO., INC.            *(74) 4.63 MI. US-64, GRADE,DRAIN &
  Contract Amount:      $3,278,241.33                                      BRIDGE FROM 7.0 MI.E. OF BOUNDARY ST.
                                            Residency:   04100
                                                                           IN PERRY, EXT EAST. OVER MULE CR., 7.8
  Letting Date:         08/16/2012          PERRY                          MI.

  23316(04)     Contract:    120277   US-77                                BRFY-NBIP(360)
  Contractor:          V. H. P. ENTERPRISES, INC.                          0.00 MI. US-77/SH-74/BRIDGE PAINTING @
  Contract Amount:      $325,000.00                                        MULTIPLE LOCATIONS IN DIV. IV.
                                               Residency:      04001
  Letting Date:         08/16/2012             ENGR. SERV. & TESTING

  23316(05)     Contract:    120278 US-77                                  BRFY-252C(007)
  Contractor:          B & B CONSTRUCTION SERVICE J.T., INC.               0.00 MI. US-77/SH-74;JOINT
  Contract Amount:      $134,285.00                                        SEAL/REPAIR:AT MULTIPLE LOCA- TIONS IN
                                            Residency:       04001
                                                                           DIV. IV.
  Letting Date:         08/16/2012          ENGR. SERV. & TESTING




                                              Construction Status Report                                   Page 148
 County:          Oklahoma                                     Commissioner District:                                   4
Contracts Awarded - NTP Not Processed

  29274(04)     Contract:    120171 I-44                                   SBR-255A(063)SB
  Contractor:          GIBSON & ASSOCIATES, INC.                           0.00 MI. IS-44:BRIDGE REPR.   :OVER THE
  Contract Amount:      $785,150.40                                        OKLA. RIVER IN OKC.
                                            Residency:           04200
  Letting Date:         07/19/2012          EL RENO

  27591(04)     Contract:    120149 IS-44                           SBR-155N(876)SB
  Contractor:          SCR CONSTRUCTION CO., INC.                   0.050 MI. IS-44:BRIDGE REHAB          /OVER
  Contract Amount:      $657,392.00                                 RENO AVE. IN OKC.
                                           Residency:     04004
  Letting Date:         08/16/2012         JACOBS (AKA - CARTER-BURGESS)

  09033(45)     Contract:    120291  IS-44                                 IMY-0044-1(122)127RW
  Contractor:          K & M DIRT SERVICES, LLC DBA K & M WRECKING         0.00 MI. IS-44:RIGHT-OF-WAY
  Contract Amount:      $29,500.00                                         CLEARANCE/WESTBOUND TO NORTH- BOUND
                                              Residency:     04400
                                                                           RAMPS AT THE IS-44/    I-235 JCT.
  Letting Date:         08/16/2012            EDMOND


 County:          Osage                                        Commissioner District:                                   8
Contracts Awarded - NTP Not Processed

  29232(04)     Contract:    120220   SH-123                               SBR-257C(006)(007)SB
  Contractor:          WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES       0.111 MI. SH-123:BRIDGE RE-
  Contract Amount:      $1,556,260.97                                      HABILITATION/OVER SAND CR., 1.5 MI. S.
                                             Residency:    08400
                                                                           OF US-60. OVER    ELIZA CR., 0.6 MI. S. OF
  Letting Date:         08/16/2012           SAND SPRINGS                  US-60

  29313(04)     Contract:    120280 SH-99                                  SSR-257C(008)SR
  Contractor:          PARAGON CONTRACTORS, LLC                            0.203 MI. SH-99 & SH-20 / INTERSECTION
  Contract Amount:      $120,582.66                                        MODIFICATION SH- 20: INTERSECTION AT
                                          Residency:             08400
                                                                           SH-99    IN HOMINY.
  Letting Date:         08/16/2012        SAND SPRINGS

  28932(05)     Contract:    120261 SH-99                                  BRFY-NBIP(454)
  Contractor:          POSEIDON CONSTRUCTION, INC.                         0.00 MI. SH-99;BRIDGE PAINT- ING;OVER
  Contract Amount:      $112,251.00                                        PENN CR. 0.3 MI. N. OF SH-20.
                                           Residency:            08002
  Letting Date:         07/19/2012         TETRA TECH


 County:          Pawnee                                       Commissioner District:                                   8
Contracts Awarded - NTP Not Processed

  28934(04)     Contract:    120283 SH-18                                  BRFY-NBIP(455)
  Contractor:          POSEIDON CONSTRUCTION, INC.                         0.00 MI. SH-18:BRIDGE PAIN-   TING;OVER
  Contract Amount:      $47,845.00                                         COAL CR., 7.5 MI. N.OF 64.
                                           Residency:      08001
  Letting Date:         08/16/2012         ENGR. SERV. & TESTING


 County:          Pittsburg                                    Commissioner District:                                   2
Contracts Awarded - NTP Not Processed

  23482(11)     Contract:    120298   CORD                            CIRB-261C(007)RB
  Contractor:          MANHATTAN ROAD & BRIDGE COMPANY                0.417 MI. CO.RD.;GRADE,    DRAIN &
  Contract Amount:      $2,318,698.35                                 SSURFACE(CROWDER       BLOCKER RD.)FROM
                                           Residency:     02013
                                                                      CAUSEWAY      OVER LAKE EUFAULA 2.0 MI.
  Letting Date:         08/16/2012         CIRCUIT ENGR. DISTRICT # 3




                                              Construction Status Report                                    Page 149
  28756(04)     Contract:    120378 PKRD                                   SAP-161D(251)
  Contractor:          JOB CONSTRUCTION CO., INC.                          0.380 MI. PK.RD.:RESURFACE (ASPHALT)AT
  Contract Amount:      $108,180.75                                        ARROWHEAD STATE PKON MAIN PK.RD. &
                                            Residency:           02400
                                                                           GOLF COURSE DRIVEWAY.
  Letting Date:         08/16/2012          MCALESTER


 County:          Pottawatomie                                 Commissioner District:                                   3
Contracts Awarded - NTP Not Processed

  22090(04)     Contract:    120295  CORD                                  BRO-163D(337)CI
  Contractor:          K & R BUILDERS, INC.                                0.126 MI. CO.RD./BRIDGE &
  Contract Amount:      $673,401.24                                        APPROACHES:OVER TRIBUTARY TO SALT
                                               Residency:        03100
                                                                           CR., 0.2 MI. W. OF US -177.
  Letting Date:         08/16/2012             ADA


 County:          Sequoyah                                     Commissioner District:                                   1
Contracts Awarded - NTP Not Processed

  26251(04)     Contract:    120296 CORD                                   ACSTP-168C(196)CO
  Contractor:          JOB CONSTRUCTION CO., INC.                          4.26 MI. CO.RD.:RESURFACE  (ASPHALT)
  Contract Amount:      $549,350.16                                        (NS-471)FROM US-64, EXTEND SOUTH.
                                            Residency:           01200
  Letting Date:         08/16/2012          SALLISAW


 County:          Texas                                        Commissioner District:                                   6
Contracts Awarded - NTP Not Processed

  29384(04)     Contract:    120297 SH-95                                  MC-270C(003)
  Contractor:          BEHNE CONSTRUCTION CO., INC.                        0.020 MI. SH-95:RESURFACE  (PC
  Contract Amount:      $118,310.00                                        CONCRETE INTERSECTION) AT 3RD ST. IN
                                           Residency:            06200
                                                                           THE TOWN OF       TEXHOMA.
  Letting Date:         08/16/2012         GUYMON


 County:          Tulsa                                        Commissioner District:                                   8
Contracts Awarded - NTP Not Processed

  15860(04)     Contract:    120265  CORD                             BRO-172D(598)CO
  Contractor:          B & B BRIDGE COMPANY, LLC                      0.099 MI. CO.RD.;BRIDGE &
  Contract Amount:      $325,782.00                                   APPROACHES(HARVARD AVE.)OVER BIRD
                                             Residency:      08014
                                                                      CR. TRIB. 2.8 MI. S. & 1.0 MI. W. OF
  Letting Date:         07/19/2012           SAIC (AKA - THE BENHAM COMPANIES, LLC)
                                                                      US-75.


 County:          Wagoner                                      Commissioner District:                                   1
Contracts Awarded - NTP Not Processed

  16233(08)     Contract:    120300 US-69                                  BRFY-NBIP(464)
  Contractor:          POSEIDON CONSTRUCTION, INC.                         0.00 MI. US-69/BRIDGE PAIN- TING;OVER
  Contract Amount:      $163,327.00                                        UNION PACIFIC R/R, 0.7 MI. & 1.5 MI. N. OF
                                           Residency:            01002
                                                                           SH-51
  Letting Date:         08/16/2012         TETRA TECH




                                              Construction Status Report                                    Page 150
                                                                Resident Directory

Residency: 0X001 - ENGR. SERV. & TESTING                        NORMAN, OK                73072                    3201 S. BERRY ROAD

 Engineer: EST                      Ph:     (405)307-8378     Fx:   (405)329-1914



Residency: 0X002 - TETRA TECH                                   OKLAHOMA CITY, OK         73102               119 N. ROBINSON AVE. - SUITE
                                                                    (405)608-8601                                         700
 Engineer: TETR                     Ph:     (405)606-8600     Fx:


Residency: 0X003 - COBB ENGINEERING CO., INC.                   OKLAHOMA CITY, OK         73122                    4516 NW 36TH STREET

 Engineer: COBB                     Ph:     (405)415-9400     Fx:   (405)415-9410



Residency: 0X004 - JACOBS (AKA - CARTER-BURGESS)                OKLAHOMA CITY, OK         73114               10001 N. BROADWAY EXTENSION

 Engineer: JACOBS (AKA - C-B)       Ph:     (405) 810-8254    Fx:   (405) 810-2980



Residency: 0X005 - CIRCUIT ENGR. DISTR. # 7                     CLINTON, OK               73601                PO BOX 337 - 1779 MARSHALL
                                                                                                                           RD.
 Engineer: CED7                     Ph:     (580)323-8685     Fx:


Residency: 0X006 - OLLAR & OLLAR ENGINEERING                    NORMAN, OK                73070                        PO BOX 5997

 Engineer: O&OE                     Ph:     405-364-0281      Fx:


Residency: 0X007 - CRAIG & KEITHLINE, INC.                      TULSA, OK                 74105               214 E. SKELLY DRIVE, SUITE 100

 Engineer: C&KI                     Ph:     (918)743-6611     Fx:   (918)743-6680



Residency: 0X008 - BRAWLEY ENGINEERING CORP.                    MCALESTER, OK             74501                    521 S SECOND STREET

 Engineer: BEC                      Ph:     (918)420-5500     Fx:


Residency: 0X009 - CIRCUIT ENGR. DISTR. # 8                     ALVA, OK                  73717                   909 WEST LAKES DRIVE

 Engineer: CED8                     Ph:     (580)430-5078     Fx:


Residency: 0X010 - ATKINS (AKA - PBS & J)                       NORMAN, OK                73072                    350 DAVID L. BOREN
                                                                                                                  BOULEVARD, SUITE 1510
 Engineer: ATKINS (AKA - PBSJ)      Ph:     (405)321-2480     Fx:


Residency: 0X011 - GARVER, LLC.                                 TULSA, OK                 74146                    10015 E 51ST STREET

 Engineer: GARV                     Ph:     (919)250-5922     Fx:


Residency: 0X012 - PSA-DEWBERRY                                 TULSA, OK                 74119               1350 SOUTH BOULDER, STE 600

 Engineer: PSAD                     Ph:     (918)587-7283     Fx:


Residency: 0X013 - CIRCUIT ENGR. DISTRICT # 3                   HUGO, OK                  74743                     203 PEPSI COLA AVE

 Engineer: CED3                     Ph:     (580)326-9191     Fx:


Residency: 0X014 - SAIC (AKA - THE BENHAM COMPANIES, LLC)       OKLAHOMA CITY, OK         73114               9400 NORTH BROADWAY, SUITE
                                                                                                                          300
 Engineer: SAIC ( AKA - ZBCL)       Ph:     (405)478-5353     Fx:


Residency: 01100 - MUSKOGEE                                     MUSKOGEE, OK              74401               2800 S. 32ND - US-69 3 MI. S OF
                                                                    (918) 682-2597        sivy@odot.org                   US-62
 Engineer: Ivy, Steve (Act.)        Ph:     (918) 682-9471    Fx:


Residency: 01200 - SALLISAW                                     SALLISAW, OK              74955               P.O. BOX 449 - 113 MCGEE DRIVE

 Engineer: Edwards, Carl            Ph:     (918) 775-2751    Fx:   (918) 776-0285        cedwards@odot.org



Residency: 01700 - DIV. 1 BRIDGE                                MUSKOGEE, OK              74401                2800 S. 32ND - US-69 3 MI. S
                                                                    (918) 682-2597        dobrien@odot.org                US-62
 Engineer: Obrien, Dan              Ph:     (918) 682-9471    Fx:




                                                             Construction Status Report                                    Page 151
Residency: 02100 - ANTLERS                                   ANTLERS, OK               74523                  P. O. BOX DRAWER 628 - US-271
                                                                 (580) 298-6152        rmoy@odot.org                   2 MI. S. TOWN
 Engineer: Moy, Ryan               Ph:   (580) 298-3081    Fx:


Residency: 02200 - HEAVENER                                  HEAVENER, OK              74937                   P.O. BOX 835 - N. HIGHWAY 59

 Engineer: Huddleston, David       Ph:   (918) 653-7896    Fx:   (918) 653-4532        dhuddleston@odot.org



Residency: 02300 - MADILL                                    MADILL, OK                73446                   P. O. BOX 297 - HWY. BLDG. S.
                                                                 (580) 795-7461        jeldridge@odot.org                 MADILL
 Engineer: Eldridge, Jerry         Ph:   (580) 795-3675    Fx:


Residency: 02400 - MCALESTER                                 MCALESTER, OK             74502                     P.O. BOX 3269 - US-270 E.
                                                                 (918) 429-0807        lplymate@odot.org                MCALESTER
 Engineer: Plymate, Larry          Ph:   (918) 423-5443    Fx:


Residency: 02700 - DIV. 2 BRIDGE                             ANTLERS, OK               74523                  P.O. BOX DRAWER 628 - US-271 2
                                                                 (580) 298-6152        mnabors@odot.org                 MI. S TOWN
 Engineer: Nabors, Monte           Ph:   (580) 298-3371    Fx:


Residency: 03100 - ADA                                       ADA, OK                   74820                  P.O. BOX 157 - 3 MI. NW ADA ON
                                                                 (580) 332-2566        jrussell@odot.org                  SH-3W
 Engineer: Russell, Julie          Ph:   (580) 332-2094    Fx:


Residency: 03200 - PURCELL                                   PURCELL, OK               73080                   P.O. BOX 468 - SH-74 2 MI. SW
                                                                 (405) 527-6576        criemer@odot.org                 OF PURCELL
 Engineer: Riemer, Caleb           Ph:   (405) 527-5569    Fx:


Residency: 03300 - WEWOKA                                    WEWOKA, OK                74884                      P.O. BOX 918 - 1.5 MI. N.
                                                                 (405) 257-5003        amoore@odot.org               WEWOKA ON SH-56
 Engineer: Moore, Archie (Act.)    Ph:   (405) 257-3325    Fx:


Residency: 03700 - DIV. 3 BRIDGE                             ADA, OK                   74820                  P.O. BOX 549 - 3 MI. N.W. OF ADA
                                                                 (580) 332-0261        slwilliams@odot.org               ON SH-3W
 Engineer: Williams, Shelly        Ph:   (580) 332-1526    Fx:


Residency: 04100 - PERRY                                     PERRY, OK                 73077                  P.O. BOX 548 - US-77 1/4 M. E. OF
                                                                 (580) 336-7373        tzachary@odot.org                     I-35
 Engineer: Zachary, Ted            Ph:   (580) 336-7374    Fx:


Residency: 04200 - EL RENO                                   Yukon, OK                 73099                         15100 NW 36th St,

 Engineer: Vonfeldt, Cole          Ph:   (405) 350-2331    Fx:   (405) 350-2199        cvonfeldt@odot.org



Residency: 04300 - ENID                                      ENID, OK                  73701                            410 KREMLIN

 Engineer: Crowl, Kenny (Act.)     Ph:   (580) 234-3223    Fx:   (580) 237-3328        kcrowl@odot.org



Residency: 04400 - EDMOND                                    EDMOND, OK                73013                       4105 E. MEMORIAL RD.

 Engineer: Hubbard, Tom            Ph:   (405) 475-2860    Fx:   (405) 478-1126        thubbard@odot.org



Residency: 04500 - STILLWATER                                STILLWATER, OK            74076                      P.O. BOX 1928 - 3613 N.
                                                                 (405) 377-8321        jarps@odot.org                    HUSBAND
 Engineer: Arps, Jonathan          Ph:   (405) 372-5644    Fx:


Residency: 04600 - OKLAHOMA CITY                             OKLAHOMA CITY, OK         73129                           1021 S.E. 59TH

 Engineer: Howell, Terry           Ph:   (405) 636-4044    Fx:   (405) 632-9921        thowell@odot.org



Residency: 04700 - DIV. 4 BRIDGE                             PERRY, OK                 73077                   P.O. BOX 471 - US-77 1/4 MI. E
                                                                 (580) 336-7350        charlin@odot.org                     I-35
 Engineer: Harlan, Chris           Ph:   (580) 336-7340    Fx:


Residency: 05100 - CLINTON                                   CLINTON, OK               73601                  P.O. BOX 818 - US-183 1 MI S. OF
                                                                 (580) 323-3551        rgreer@odot.org                      I-40
 Engineer: Greer, Randy            Ph:   (580) 323-0702    Fx:


Residency: 05200 - ALTUS                                     ALTUS, OK                 73521                         608 S. JACKSON ST

 Engineer: Nedbalek, Will          Ph:   (580) 482-3191    Fx:   (580) 482-0792        wnedbalek@odot.org



                                                          Construction Status Report                                        Page 152
Residency: 05700 - DIV. 5 BRIDGE                             CLINTON, OK               73601                P.O. BOX 1449 - US-183 1 MI. S.
                                                                 (580) 323-1430        mclanton@odot.org                 I-40
 Engineer: Clanton, Mike           Ph:   (580) 323-1431    Fx:


Residency: 06100 - BUFFALO                                   BUFFALO, OK               73834                 P. O. BOX 190 - US-64 1 MI. W
                                                                 (580) 735-2024        dburke@odot.org                  US-183
 Engineer: Burke, David            Ph:   (580) 735-2537    Fx:


Residency: 06200 - GUYMON                                    GUYMON, OK                73942                 P.O. BOX 348 - 504 S. CRUMLEY

 Engineer: Michael, Charles        Ph:   (580) 338-3545    Fx:   (580) 338-5685        cmichael@odot.org



Residency: 06700 - DIV. 6 BRIDGE                             BUFFALO, OK               73834                 P.O. BOX 190 - US-64 1 MI. W
                                                                 (580) 735-2248        wroesner@odot.org                US-183
 Engineer: Roesner, Wayne          Ph:   (580) 735-2561    Fx:


Residency: 07100 - DUNCAN                                    DUNCAN, OK                73534                 P.O. BOX 1107 - 2205 S. US-81
                                                                 (580) 252-6178        jharwell@odot.org                BYPASS
 Engineer: Harwell, Jerry M.       Ph:   (580) 255-7609    Fx:


Residency: 07200 - ARDMORE                                   ARDMORE, OK               73402                P. O. BOX 1826 - 525 INTERSTATE
                                                                 (580) 226-8146        jearp@odot.org                      DR.
 Engineer: Earp, Jay               Ph:   (580) 223-1351    Fx:


Residency: 07300 - ANADARKO                                  ANADARKO, OK              73005                 P.O. BOX 220 - 211 W MAIN ST.

 Engineer: Knight, Reese           Ph:   (405) 247-2462    Fx:   (405) 247-2057        rknight@odot.org



Residency: 07700 - DIV. 7 BRIDGE                             DUNCAN, OK                73533                 P.O. BOX 460 - 2205 S. US-81
                                                                 (580) 255-5064        terrrill@odot.org               BYPASS
 Engineer: Terrill, Tracy          Ph:   (580) 255-7586    Fx:


Residency: 08100 - TULSA                                     TULSA, OK                 74116                  4002 N. MINGO VAL. EXPWY.

 Engineer: Arnold, Bruce           Ph:   (918) 836-7116    Fx:   (918) 832-0383        barnold@odot.org



Residency: 08300 - CLAREMORE                                 CLAREMORE, OK             74018                  25825-B S. HWY. 66 - 729 S.
                                                                 (918) 343-1203        tbray@odot.org                  MORETZ
 Engineer: Bray, Timothy           Ph:   (918) 266-1160    Fx:


Residency: 08400 - SAND SPRINGS                              SAND SPRINGS, OK          74063                   110 E. 41ST (PRATTVILLE)

 Engineer: Williams, Mark J.       Ph:   (918) 245-9531    Fx:   (918) 245-0953        mwilliams@odot.org



Residency: 08700 - DIV. 8 BRIDGE                             TULSA, OK                 74101                 P.O. BOX 660 - 4002 N. MINGO
                                                                 (918) 832-9074        dbutler@odot.org               VAL. EXPWY.
 Engineer: Butler, David           Ph:   (918) 838-9933    Fx:




                                                          Construction Status Report                                     Page 153

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:8
posted:9/27/2012
language:English
pages:153