					 Access Timeline for Pole Attachment in the
          Communications Space
                                                   Stage
                         Survey                 Estimate        Acceptance             Make-Ready
         Day:    0                        45               59           73                              133-148
Stage in days:               45                      14            14                       60-75

                 • Conduct engineering                                       • Give existing attachers 60 days
Owner Duty                                     • Provide
                 survey.                                                     notice.
                                               cost estimate
                                                                             • Prepare poles if necessary.
                                               for make-
                                                                             • Work with existing attachers’
                                               ready.
                                                                             contractors.


  Attacher       • Hire contractor to          • File
  Remedy         conduct survey (for           complaint                     • Hire contractor to perform
                 attachments in the            with                          make-ready.
                 communications space).        Commission



                                               • Parties may
                                                                             • Pole owner may stop clock for
                                               stop clock if
Clock                                                                        good and sufficient cause.
                                               no master
                                               agreement.
        Access Timeline for Wireless Pole
     Attachment Above the Communications
                     Space
                                                  Stage
                          Survey               Estimate        Acceptance             Make-Ready
         Day:    0                       45               59           73                              163-178
Stage in days:                45                    14            14                       90-105

                 • Conduct engineering                                      • Give existing attachers 90 days
Owner Duty                                    • Provide
                 survey.                                                    notice.
                                              cost estimate
                                                                            • Prepare poles if necessary.
                                              for make-
                                                                            • Work with existing attachers’
                                              ready.
                                                                            contractors.


  Attacher                                    • File                        • File complaint with Commission.
  Remedy         • File complaint with        complaint
                 Commission.                  with
                                              Commission.



                                              • Parties may
                                                                            • Pole owner may stop clock for
                                              stop clock if
Clock                                                                       good and sufficient cause.
                                              no master
                                              agreement.

				