InterconnectionRequests-posted

VIEWS: 11 PAGES: 1

									                                                                       Generation Interconnection Requests




                                                                                                                                                Last Updated 08/30/2012 MTL


                                      Max
                         Request    Summer Max Winter                                                                                Facility
Queue Number               Date    MW Output MW Output           Location                   Interconnection Facility        COD       Type                                    Status
 070302000001   Q01    03/02/07       200       200    Beaver Cty, Utah         (I) IPP 345kV Switchyard                   Mar-11     Wind      Request being processed
 070302000002   Q02    03/02/07       200       200    Beaver Cty, Utah         (I) IPP 345kV Switchyard                   Jul-11     Wind      Request being processed
 070910000000   Q03    09/10/07       250       250    Kern County, CA          Barren Ridge 230 kV Sw Station             May-14     Solar     Facilities Study completed
 080214000000   Q05    02/14/08       300       300    Kern County, CA          Barren Ridge - Castaic 230kV Line          Nov-16     Wind      Need to redo Feasibility Study due to change by IC.
 080317000001   Q06    03/12/08       350       350    Baker, CA                (M) Marketplace-Adelanto 500kV Line        Mar-13     Solar     Facilities Study in progress
 080930000000   Q07    09/30/08       300       300    California City, CA      Barren Ridge 230 kV Sw Station             Oct-16     Solar     Feasibility Study completed. Final report transmitted.
 090326000000   Q08    03/26/09       150       150    Boulder City, NV         (J) McCullough 230kV Substation            Aug-11     Solar     Feasibility Study Completed (on hold)
 091105000000   Q09    11/03/09       200       200    Owens Valley, CA         (DWP) Owens Gorge - Rinaldi 230kV Line     Dec-15     Solar     Draft Feasibility Study Report provided
 100122000000   Q10    01/22/10        90        90    California City, CA      Barren Ridge 230 kV Sw Station             Apr-16     Solar     Feasibility Study completed. Final report transmitted.
 100301000000   Q11    03/01/10        60        60    Kern County, CA          Barren Ridge 230 kV Sw Station             Jun-15     Solar     Facility Study Agreement executed.
 100615000002   Q13    06/15/10       150       150    Kern County, CA          Owens Gorge - Rinaldi 230kV Line           Sep-16     Solar     Feasibility Study completed. Final report transmitted.
 100819000001   Q14    08/19/10      200.1     200.1   Lancaster, CA            Owens Gorge - Rinaldi 230kV Line           Dec-12     Wind      Interconnection Request withdrawn by IC 8/23/12
 101007000000   Q15    10/07/10       100       100    Kern County, CA          (DWP) Owens Gorge - Rinaldi 230kV Line     Jul-16     Solar     Scoping Meeting held
 101012000000   Q15A   10/12/12       150       150    Mojave, CA               (DWP) Pine Tree 230kV Substation           Dec-18     Wind      Scoping Meeting held
 101018000000   Q16    10/18/10      199.5     199.5   Hamblin Valley, UT       Gonder - Intermountain 230kV Line          Nov-13     Wind      Feasibility Study in progress
 101216000000   Q17    12/16/10       300       300    Kern County, CA          Barren Ridge - Rinaldi 230kV Line          Dec-14     Solar     Feasibility Study in progress
 110907000000   Q18    09/07/11       100       100    Kern County, CA          Barren Ridge 230 kV Sw Station             Jun-15     Solar     Feasibility Study in progress
 110919000000   Q19    09/19/11       250       250    Kern County, CA          Barren Ridge 230 kV Sw Station             Jun-15     Solar     Feasibility Study in progress
 111003000000   Q20    10/03/11       200       200    Independence, CA         Owens Gorge - Rinaldi 230kV Line           Nov-14     Solar     Feasibility Study Agreement executed.
 111116000000   Q22    11/16/11      200.1     200.1   Barstow, CA              Mead-Victorville 287kV                     Mar-16     Wind      Feasibility Study completed
 111130000000   Q23    11/30/11      243.2     243.2   Victorville, CA          Victorville Substation                     Dec-17     Wind      Scoping Meeting held
 122112000000   Q24    02/21/12       250       250    Boulder City, NV         (M) Marketplace Substation                 Dec-13     Solar     System Impact Study in progress
 120314000000   Q25    03/14/12       150       150    Los Angeles County, CA   Barren Ridge - Rinaldi 230kV Line          Jul-16     Solar     Feasibility Study in progress
 120330000000   Q26    03/30/12       150       150    Kern County, CA          Barren Ridge 230 kV Sw Station             Sep-15     Solar     Feasibility Study Agreement in progress
 120417000000   Q27    04/17/12       515       515    Victorville, CA          Victorville-Rinaldi 500 kV line            Dec-16     Solar     Feasibility Study Agreement executed 7/18/12
 120518000000   Q28    05/18/12       150       150    Baker, CA                Mead-Victorville 287kV                     Nov-16     Solar     Scoping Meeting held
120607000000    Q29    06/07/12       300       300    Boulder City, NV         (J) McCullough 230kV Substation            Sep-14     Solar     Scoping Meeting held
120612000000    Q30    06/12/12       300       300    Rosamond, CA             Barren Ridge - Rinaldi 230kV Line          Apr-14     Solar     Scoping Meeting held
 120726000000   Q31    07/26/12       750       850    Victorville, CA          Victorville Substation                     Dec-15   Gas/Steam   Request being processed
 120801000000   Q32    08/01/12       200       200    Victorville, CA          Victorville Substation                     Oct-15     Solar     Request being processed

                                                                                (I) Intermountain Power Project Facility
                                                                                (J) Other Jointly-Owned Facility
                                                                                (M) Mead-Adelanto Project Facility
                                                                                (DWP)- LADWP Project

								