									                               ADDENDUM NO. 1 – April 27, 2012

                          ACCELERATED BRIDGE PROGRAM- PHASE 1B

                                PIN SABP.01, Contract D900006

                                PIN SABP.07, Contract D900007

                                PIN SABP.08, Contract D900008

                                PIN SABP.09, Contract D900009


The following Sections of the DB Contract Documents are amended as follows:

A.      DB Contract Documents, Part 2, DB Section 100, General Provisions

Section DB 102-7.4 Civil Rights Monitoring and Reporting

Is modified by adding the following paragraph:

     F) Federal-Aid Highway Construction Contractors Annual EEO Report. The Design-Builder
        shall submit all required data to produce an annual Form FHWA 1391 Federal-Aid
        Highway Construction Contractors Annual EEO Report to the Department not later than
        the second Friday in August covering the last payroll period worked in July, for all
        ongoing Federal-Aid contracts. The data shall indicate the number of minority men,
        minority women, nonminority men, and non-minority women employees currently
        engaged in each trade.

B.      DB Contract Documents, Part 3, Project Requirements

Section 3.7.5 Backwall Reconfiguration

Is modified by adding the following paragraph:

A construction joint shall be made between the approach slab and the deck. Pouring a
continuous slab and saw-cutting a joint will not be permitted. See BD-SS5E for reference.

C.      DB Contract Documents, Part 3, Project Requirements

Applicable to Zone 4 ONLY

Is modified as follows:

Sections 4.2.2.3 C. Utilities and 4.2.5.3. D. Utilities

Are modified by adding the following sentence:

Install two new 4” spare PVC conduits in the sidewalk.


                                                 1
D.       DB Section 108-7 Subcontracting or Assigning the Contract

Is modified as follows:

The first paragraph is modified by adding the following:

The Design Firm cost, the Construction Inspection cost, and the Materials Testing cost will be
excluded from the calculation of the 51%.

E.       The following definition is added to Part 2 – DB Section 100 General Provisions-

Resident Engineer – A licensed, experienced Engineer from the Independent
Construction Inspection professional firm whose scope of work includes the
organization and coordination of the inspection and the on-site inspection of the
execution of the construction by the Contractor. He ensures that the construction is
executed in accordance with the approved designs, drawings and specifications related
to the work under construction.


F.       DB Section 111-12.1.2 is modified by adding the following:

As-Built drawings shall be submitted in digital format and as paper copies.

G.       Computer and Networking requirements

These requirements are:

Notebook PC, 2/HM65 Chipset, and Intel HD Graphics 3000 (or equivalent).

        2nd Generation Intel Core i5 2620M Processor, 2.70GHz (Turbo up to 3.40GHz),
         1333MHz, 4MB L3 Cache
        Mobile Intel HM65 Chipset
        14” diagonal LED-backlit HD anti-glare (1366x768)
        Intel HD Graphics 3000
        4 GB 1333 MHz DDR3 SDRAM – Dual Channel Active
        250 GB 7200 RPM 2.5 inch hard drive – or 120 GB Intel SSD
        DVD R/W SuperMulti DL Drive
        Full Keyboard
        Broadcom 4313 GN 802.11 g/b/n 1x1 WiFi Adapter
        65W Hardware Kit
        6 cell Li-ion Battery
        Integrated Gigabit Ethernet




                                                2
H. DB Contract Documents, Part 3, Project Requirements – Zone 2

Section 3.6.1.2 - BIN 1040560, Route 208 over Otter Creek

Bearing work is not anticipated. The 5% will be included in the demolition and removal
of deck. That payment will increase from 15% to 20%.

I. DB Contract Documents, Part 3, Project Requirements – Zone 2

Section 3.6.1.8 - BIN 1044870, Ridge Street over I-287:

Bearing work is not anticipated. The 5% will be included in the demolition and removal
of deck. That payment will increase from 10% to 15%.

J. DB Contract Documents, Part 4, Special Provisions

Activity ID M00025, Contract Award Process – 45 days is inconsistent with May 30,
2012 date in the instruction to proposers.

The date in the Instructions to Proposers is correct and supersedes Part 4.