									                                      Questions & Responses
                                  Received As Of 11 August 2010
                              Joint Base Lewis-McChord, Washington
                                 Solicitation No. FA4479-10-R-0011
                           PQWY 04-1017, AT/FP Grate Fence-Clover Creek

                   The responses in blue text will be incorporated by an amendment.
Duplicate questions were received. Read all the questions and responses that follow. Your question may
 not appear precisely as you wrote it but is contained by similar content from another potential contractor
                                  and addressed by the Government.

                                  Solicitation FA4479-10-R-0011 Attachment 1, Specification 7476
         Reference
                                  Section 01000-1 para 2.2
         Issue                    Construction time frame
                                  Since all on-site construction activities must occur during the dry, low-
         Questions/               flow season from 1 August through 31 October we interpret that to
         Discussion               mean that construction will occur during this time frame in the year
                                  2011. Please verify.
                                  1. Answer will require CES to change the note on the plan sheets that
                                  addresses this construction restriction. The note on the plans is too
                                  restrictive, since the limitation is only on work below the ordinary high
                                  water level outside of the stated dates. Additionally, work must be
                                  done by the end of the calendar year in order to meet the bona fide
                                  need rule.
                                  REVISION: some work must be completed to meet bona fide need.
  1                               The type of work that must be started and how much needs to be
                                  completed within 90 days after October 1 in order to meet the bona
                                  fide need rule will need to be determined by contracting, but there is
         Government               some work that can be performed outside the ordinary high water line
         Response                 at all three locations.
                                  The new note reads:
                                  “CONSTRUCTION ACTIVITIES BELOW THE ORDINARY HIGH
                                  WATER LINE MUST OCCUR DURING A DRY/LOW FLOW PERIOD
                                  OR BETWEEN 15 JULY THROUGH 15 SEPTEMBER. IN ADDITION,
                                  FOLLOW GUIDELINES AND RESTRICTIONS STATED IN THE
                                  JARPA PERMIT PROVIDED BY THE GOVERNMENT.”
                                  Drawing revision will be incorporated in amendment
                                  2. Construction period of performance specifically addressed within
                                  solicitation, FA4479-10-R-0011, Section F, Clause 52.211-10 page 5
                                  of 52

         Reference                Drawing C110
         Issue                    Correction of authorized material
         Questions/               CES DISCUSSION
         Discussion
  2
                                  Also revised was one of the sheets to remove a straw bale barrier that
         Government               was in the main channel and replaced it with filter fabric fences on the
         Response                 sides of the banks. This was done because the straw barrier in the
                                  main stream is not allowed by the HPA

         Reference                Drawings
         Issue                    Difficult to read
         Questions/               Can clearer drawings be provded
  2
         Discussion
         Government               See separate attachment labled BW Drawings 2-17 complete (pdf)
         Response


                                               Page 1 of 1

								