WP1 Presentation Zschau FAM by 6vKsxv84

VIEWS: 5 PAGES: 14

									             SAFER
     Seismic EArly Warning
         For EuRope

   Introduction to the 1st year`s meeting
                   and
project management (WP1) progress report


                Athens, 27 June
   Jochen Zschau, GeoForschungsZentrum Potsdam
  1st Year`s SAFER Meeting Agenda
              Wednesday, 27th Electra Hotel
9:00 Registration
9:30 Welcome Gerassimos Papadopoulos
9:40 Introduction, WP1 progress report Jochen Zschau
10:00 SEW progress in California Richard Allen
10:30 Coffee Break
10:45 WP2 progress report Aldo Zollo
11:45 WP3 progress report Gaetano Manfredi
12:05 WP4 progress report Claus Milkereit
13:05 WP5 progress report Jochen Woessner
13:30 Lunch
14:30 WP6 progress report Gerassimos Papadopoulos/Paolo Trautteur
14:50 WP parallel meetings
17:30 Steering Committee meeting
1st Year`s SAFER Meeting Agenda
           Thursday, 28th Electra Palace Hotel
9:00 Continuation of WP parallel meetings
11:00 Coffee Break
11:30 SeaHellArc presentation Joanna Papoulia
12:00 NERIES presentation Alberto Michelini
12:30 TRANSFER presentation Alberto Armigliato
13:00 Discussion of possible synergies between EU projects
13:30 Lunch
14:30 Results of WP meetings and plans for next period
17:30 Executive Committee meeting

              Friday, 29th Electra Palace Hotel
9:30 Round table discussions with end users
11:30 Conclusions
12:30 End of meeting
    WP1: Project Management
           Steering Committee                                SAFER Office
       Jochen Zschau Coordinator (GFZ)
                                                    Alfonso Rossi Filangieri (AMRA)
   Paolo Gasparini Co-coordinator (AMRA)
                                                         Kevin Fleming (GFZ)
Gerassimos Papadopoulos Co-coordinator (NOA)




                              Executive Committee
                                   Jochen Zschau
                                  Paolo Gasparini
                             Gerassimos Papadopoulos
                            George Marmureanu (NIEP)
                              Mustafa Erdik (KOERI)
                          Aldo Zollo, WP2 leader (AMRA)
                       Gaetano Manfredi, WP3 leader (AMRA)
                         Claus Milkereit, WP4 leader (GFZ)
                        Stefan Wiemer, WP5 leader (ETHZ)



                  WP1                  WP2                    WPn
            WP1-Activity
         General Coordination
                 Project Begin: 15 June 2006
                  Project End: 15 Dec. 2008

 Core Contract with EC:
  14 August 06    GFZ-signature
   23 October 06 All signed accession forms with the EC
   Mid Dec. 06    Contract signed by EC
   End of Dec. 06 Payment by EC
 Consortium Agreement: Finalized by Nov. 06
 First Payment to the Partners: End of Jan. 07
 First Year`s Scientific and Financial Report: 31 July 07
 First Year`s Scientific Audit: 31 July 07
 First Year`s Financial Audit: ???
             WP1-Activity
              Meetings
 General:
  2-4 July 2006, Capri:      Kick-off meeting
  27-29 June 2007, Athens:   First year`s general meeting
 Steering Committee:
  6 Dec. 2006, Potsdam
  19 April 2007, Vienna
  27 June 2007, Athens
 Executive Committee: 28 June 2007, Athens
 Special: 5-9 June 2007, Cairo
             Jochen Zschau (general coordination)
             Kevin Fleming (shake map)
             Max Wyss (real-time damage assessment)
             Klaus Winkenwerder (decision support system)
         WP1-Activity
Major Decisions and Clerifications
 Scientific Advisory Board: Nomination of candidates
   Raul Madariaga (seismologist, France)
   Kyriazis Pitilakis (civil engineer, Greece)
   Scientific advice and external scientific audit!
 Amount of First Payment:
  100% of the first year`s budget (1.5 million Euros)
  from 85% of the first 18 months` budget (1.9 million Euros)!
  Problem of the 70% rule!
 Interim Management Report: Necessary and possible!
 Deliverables and Milestones:
   Time can be shifted within the 30 months project duration!
   But indicate new deadlines and explain!
Shift Between Financial Categories: person., travel, consum., ..
  Is possible, but you have to explain!
          WP1-Activity
Website (in Association with WP6)
    General Project Information
    Management Circulars
    Minutes of Meetings
   Available Deliverables, Reports, Presentations
    Handbook of Administrative Management
   Publications
   PR-Activities
   Participant Coordinates (…Photos?...)
   Communication?
        WP1-Activity
Synergies with other EU-Projects
 Special SAFER-Organized Meeting: 19 April 2007, Vienna
  SAFER participants:   Steering Committee, Office
  EC:                   Denis Peter
  NERIES:                Torild van Eck
  TRANSFER:              Stefano Tinti
  SeaHellArc:            Joanna Papoulia, Jannis Makris
 First Year`s NERIES-Meeting: 11-13 June 2007, Zürich
  SAFER-representative:       Bogdan Enescu
 First Year`s SeaHellArc-Meeting: 26 June 2007, Athens
  SAFER-representatives: Jochen Zschau, Gerassimos Papadopoulos
Special Session at SAFER Meeting: 28 June 2007, Athens
 with NERIES, TRANSFER and SeaHellArc
 Joint “SAFER WP3/WP4“-“NERIES JRA3“- Meeting:
  30-31 August 2007, Oslo
        WP1-Activity
After One Year: Where Are We?


     The Bad News: On average ½ year delay!
      Late payment!
      Hiring problems!


     The Good News:
      1/3 of the first year`s deliverables ready!
      10% of the first year`s deliverables nearly ready!
      We have 30 months instead of 24 months!
        Completed Deliverables: 14/43
D1.1  Kick-off meeting –Report
D6.1  Web page of the project (AMRA)
D6.2  Initial report by EUG (NOA)
D2.24 Evaluation of the existing tools on EEWS in Bucharest (NIEP)
D5.3  Clustering properties for Italy (INGV)
D2.1  Report and code on methodologies for earthquake location (AMRA)
D2.14 Software packages for generating data consistent accelerograms (UNIKAR)
D2.18 Evaluation scheme and results for optimizing seismic networks for early
      warning and rapid response (UNIKARL)
D3.10 Report and publication demonstrating the developed method (NORSAR)
D4.1 Generation of area-specific relationships between ground motion parameters
      (PGA, PGV) (GFZ)
D4.2 Development of magnitude calibrated intensity attenuation relations for target
      areas (GFZ)
D4.8 Report on local attenuation relations analysing real and simulated strong
      motion data (AMRA)
D4.9 Report on methodologies for real-time adjusting of attenuation relations and
      shake map computation (AMRA)
D6.5 Special report about the status of civil protection as regards seismic early
      warning (NOA)
    Almost Completed Deliverables:
               5/43
D3.1    Report on the needs into development of an EWS from the perspective
        of infrastructural/structural control. (AMRA)

D2.2    Report on analysis of high quality strong motion data base for
        exploring the optimal real-time observable for magnitude estimation
        (AMRA)

D3.16 Critical review of the different solutions for an integrated safe
      transmission system for EWS in urban areas. (Selex)

D3.2    Report on the development of control algorithms and control devices.
        (AMRA)

D3.6    Report on the empirical model of landslide prediction and validation
        against case histories. (NGI)
        Delayed Deliverables: 24/43
D4.34   MMI(PGA) and MMI(PGV) relations valid for SW Iceland. (IMO)
D5.1    Alpha Version of RAFT distributed (ETHZ)
D2.8    Calibration of VS parameters for Switzerland (ETHZ)
D2.10   Performance evaluation and code improvements ((ETHZ)
D2.20   Demonstration of real-time processing algorithms. (NORSAR)
D2.27   Results of the application of automatic fault mapping procedure (IMOR)
D2.29   Implementation of real-time fault mapping at in Iceland. (IMOR)
D2.31   Report on evaluation of the procedures for real time monitoring (INGV)
D2.37   Prototype hybrid network design and implementation (NKUA)
D2.9    First Installation of test VS system (ETHZ)
D4.12   Selection of target area where to achieve the shake map (NIEP)
D4.20   Sensor Node Prototype of Low Cost Sensor (UBER)
D4.25   Network Optimisation simulator development and testing (UBER)
D4.27   Operation of spare early warning network in the Istanbul area (KOERI)
D4.32   An automated system for the evaluation a earthquake sequence (NOA)
D4.35   Analysis of the applicability of using station alerts in SW Iceland. (IMO)
D4.37   Development of software code for QUAKELOSS (WAPMERR)
D4.39   Development of software modules for shake map generation (NRIAG)
D4.4    Development of the seismological analysis software (with UBER) (GFZ)
D4.5    Development of seismogram analysis of single station/network trigger (GFZ)
D5.2    Improve PGA- and VGA-distance relations for SW Iceland (IMOR)
D5.5    RAFT test system Italy online (INGV)
D5.8    New tool for the calculation of shear and Coulomb stress changes (GFZ)
D6.6    General software frame of a DDSM (cedim AG)
           WP1-Activity
        Some Future Actions

 Vision Paper for EC: State of the art and
                             future potential of SEW
   By the end of the year!
   As basis for possible post SAFER projects!
   Together with other EU-projects or separately?


 AGU Special Session on SEW: 12-14 Dec, San Francisco
  Convenor: Richard Allen
  Co-Convenors: Paolo Gasparini
               Representative from Japan

								
To top