Estuary Actions for Salmon and Steelhead
NOAA 2008 FCRPS Biological Opinion
Estuary Recovery Plan Module Northwest Power and Conservation Council Fish & Wildlife Program
Columbia River Estuary Science Policy Exchange September 10-11, 2009
Progression of FCRPS BiOp
2008 BiOp 2000 BiOp
-
1995 BiOp
-
10 years for implementation of an aggressive nonbreach strategy Was long-term program called for by the 1995 BiOp
10-year implementation of an aggressive nonbreach strategy Based on a broader ESA analysis, similar to 2000 BiOp analysis Offsite habitat mitigation, hatchery, predation control Conclusion: Jeopardy with RPA Court challenge pending in NWF v. NMFS
-
1993 BiOp
-
-
5 years of FCRPS interim operations Transportation vs. dam drawdown study Conclusion: Jeopardy with RPA Upheld in American Rivers v. NMFS
-
-
1 year of FCRPS dam operations only
Conclusion: No Jeopardy Invalidated in IDFG v. NMFS
-
Offsite habitat mitigation
-
-
-
-
Conclusion: Jeopardy with RPA
-
-
-
-
Invalidated in NWF v. NMFS in 2003
2000 FCRPS BiOp Estuary Actions
Program Development
158
Plans and Modeling
159, 162, 194
RM&E
161, 195, 196, 197
Implement Restoration
160
2000 FCRPS BiOp Reasonable Prudent Alternative Actions
Action 158 – Inventory estuary habitat to understand the relationship of that habitat to the needs of ESA-listed salmon and steelhead. Action 159 – BPA and the Corps, working with LCREP and NMFS, shall develop a plan addressing the habitat needs of salmon and steelhead in the estuary.
2000 FCRPS BiOp Reasonable Prudent Alternative Actions
Action 160 – The Corps and BPA, working with LCREP, shall develop and implement an estuary restoration program with the goal of protecting and enhancing 10,000 acres of tidal wetlands and other key habitats. Action 161 – Fund a monitoring and research program acceptable to NMFS and closely coordinated with the LCREP monitoring and research efforts. Action 162 – Develop a conceptual model of the relationship between estuarine conditions and population structure and resilience. Action 163 – Develop a compliance monitoring program.
2000 FCRPS BiOp Reasonable Prudent Alternative Actions
Action 194 – Develop a physical model of the lower Columbia River and plume. Action 196 – Develop appropriate level of funding to support funding studies to develop an understanding of juvenile and adult salmon use of the Columbia River estuary.
Action 197 – Develop appropriate level of funding to support funding studies to develop an understanding of juvenile and adult salmon use of the Columbia River plume.
2008 FCRPS BiOp Reasonable Prudent Alternative Action 36
Estuary Habitat Implementation 2007-2009
–
Action Agencies will provide funding to implement specific actions as part of a 10-year estuary habitat program to achieve the estimated ESU survival benefits of 9.0% and 6.0%, for ocean and stream types, respectively. Projects in an early state of development such that quantitative physical metrics have not been related to estimated survival benefits will be selected per Action 37. If projects identified for implementation in 2007-2009 prove infeasible, the action agencies will implement comparable replacement projects in 20102013. Implementation plans and annual reports.
–
–
–
2008 FCRPS BiOp Reasonable Prudent Alternative Action 37
Estuary Habitat Implementation 2010-2018 – Achieving Habitat Quality and Survival Improvement Targets
–
Action Agencies will actively engage the LCREP Science Work Group to identify project benefits in coordination with other regional recovery planning products and the modified LCREP project selection criteria to identify projects that will benefit salmon considered in this RPA.
–
The Action Agencies will convene an expert regional technical group. This group will use the habitat metrics to determine the estimated change in survival which would result from full implementation.
Project proposals will clearly describe the completed project in terms of quantitative habitat metrics which can be used to quantitatively evaluate progress and completion of individual projects.
–
2008 FCRPS BiOp Reasonable Prudent Alternative Action 37
Estuary Habitat Implementation 2010-2018 – Achieving Habitat Quality and Survival Improvement Targets
–
The expert regional technical group will use the existing approach applied in the FCRPS BA and all subsequent information on the relationship between actions, habitat, and salmon productivity models developed though the FCRPA RM&E to estimate the change in overall estuary habitat and resultant change in population survival. Replacement projects as needed will be developed to achieve equivalent survival benefits, based on input from expert panels, regional recovery planning groups, the Northwest Power and Conversation Council, and NOAA Fisheries. New information can and should be used to review projects and their estimated survival benefits. If benefits are determined to be overstated, replacement projects will be implemented. Implementation plans and annual reports.
–
–
–
2008 FCRPS BiOp Reasonable Prudent Alternative Action 38
Piling and Piling Dike Removal Program
– –
Increase productive habitat and reduce avian predation. In 2008, the Action Agencies will work with LCREP to develop a plan for strategic removal of structures that have lower value to navigation channel maintenance, present low risk to adjacent land use, support increased ecosystem function, and are cost-effective. Implementation plans and annual reports.
–
2008 FCRPS BiOp Reasonable Prudent Alternative Action 58
Monitor and Evaluate Fish Performance in the Estuary and Plume
– – – –
Smolt survival and/or fitness in select reaches from Bonneville Dam through the estuary. Develop and index and monitor and evaluate life history diversity of salmonid populations at representative locations in the estuary. Salmon and growth rates and prey resources at representative locations in the estuary and plume. Implementation plans and annual reports.
2008 FCRPS BiOp Reasonable Prudent Alternative Action 59
Monitor and Evaluate Migration Characteristics and Estuary/Ocean Conditions
– – – – –
Map bathymetry and topography of the estuary as needed for RME. Establish a hierarchical habitat classification system. Develop and index of habitat connectivity and apply it to the eight reaches of the study area. Evaluate migration through and use of a subset of various shallowwater habits from Bonneville Dan to the mouth. Monitor habitat conditions periodically.
–
Implementation plans and annual reports.
2008 FCRPS BiOp Reasonable Prudent Alternative Action 60
Monitor and Evaluate Habitat Actions in the Estuary
– – – –
Reference site development. Evaluate the effects on individual restoration sites. Develop a methodology to estimate the cumulative effects of habitat conservation and restoration projects. Implementation plans and annual reports.
Salmon and Steelhead Estuary Recovery Plan Module
• For NMFS by the Lower Columbia River
Estuary Partnership lower Columbia
• Part of a larger ESA domain plan for the • Consistent estuary application for
upstream recovery plans
• Consistent with NPCC subbasin plans
Extensive Review Process
• First draft in October 2005 • Presentations and feedback from other
recovery planning efforts Conservation Council Register)
• Presentation to Northwest Power and • Formal public review process (Federal
• Review by ISAB (Fall 2007)
Module Elements
• Limiting factors • Threats • Management actions • Cost • Schedule • Monitoring
Management Actions
• 23 comprehensive actions • Actions supported by projects • Project metrics defined (# of acres, etc.)
• Cost
• Schedule • Potential implementers
Estuary Module Status
• Proposed draft submitted to NMFS • Final draft – October 2009
Northwest Power and Conservation Council
• Implementation of habitat actions in estuary, and
2009 Lower Columbia River and Estuary Program
associated M&E, will occur through the CR estuary and Lower Columbia subbasin plans. Salmon and Steelhead will be used to guide actions in lower river and estuary.
• Columbia River Estuary ESA Recovery Plan Module for
Northwest Power and Conservation Council
2009 Lower Columbia River and Estuary Program
Council supports strategies to protect, enhance and restore critical habitat, spawning and rearing grounds, including:
– – – – –
Habitat restoration to reconnect ecosystem functions, e.g., removing dikes/levees, installing tide gates, removing pile dikes Long-term effectiveness monitoring Continued evaluation of salmon/steelhead migration and survival rates in lower Columbia River, estuary, and marine environment Evaluation of impact of flow regulation, dredging, and water quality on habitat Continued partnerships in planning, M&E, and implementation of actions