The future…

W
Shared by: ert554898
Categories
Tags
-
Stats
views:
1
posted:
8/21/2012
language:
Unknown
pages:
9
Document Sample
scope of work template
							                    Craig Cottrill
                RESERVE ASSETS MANAGER
                   HUTT CITY COUNCIL

•   Sports Fields – Horticultural Parks - Reserves
•   Beaches and Wharves
•   Tracks and Walkways
•   Playgrounds
•   Bush Reserves
•   City Reserves
The future…
• Feb 2010 CPG ‘Report on Surveys of Hutt
  City Wharves’
• Point Howard, Petone, Days Bay & Rona
  Bay Wharves + Lowry Bay Jetties
• Point Howard Wharf ‘Heads’ closed as a
  result of the report’s findings
• Report to Council on all Wharves
  recommended further public consultation
  of the future of Point Howard Wharf
• Option One – As is; Maintain entire wharf




• 25yr Cost $1,260,000 - Future risk: HIGH
• Option Two - Remove North Head




• 25yr cost $790,000.00 - Future risk: Medium
• Option Three - Remove South Head




• 25yr Cost $928,000 - Future risk: medium
• Option Four - Remove Both Heads




• 25yr Cost $639,000 - Future risk: Low
• Option Five - Remove Wharf




• 25yr Cost $530,000.00 - Future risk: Minimal
• Maintain Entire Wharf   $1,260,00*
• Demolish North Head     $790,000*
• Demolish South Head     $928,000*
• Demolish both Heads     $639,000*
• Demolish entire wharf   $530,000*

 * 25 year discounted total cost

						
Related docs
Other docs by ert554898
Coral Reefs - Judas World
Views: 37  |  Downloads: 1
3D VIRTUAL REALITY CAMERAS
Views: 49  |  Downloads: 0
designz360.comdocumentsdesignz_20blue.ppt
Views: 0  |  Downloads: 0
DARWINS NIGHTMARE
Views: 78  |  Downloads: 0
PS401- Lec. 3
Views: 2  |  Downloads: 0
Slide 1 - Maryknoll Convent School
Views: 26  |  Downloads: 0
Introduction to Lobe Pumps
Views: 35  |  Downloads: 0
Provisional Registration Training _PRT_
Views: 128  |  Downloads: 0