Template of Contract

Reviews
CONTRACT DRILLING OF WELLS IDENTIFICATION NUMBER: (DACAAR-PUT13/2009) This contract is between DACAAR and “ “ hereafter referred as the contractor for Drilling of two wells in Jalaier area of Faryab province. Article 1 Details of works to be done: Boring should be drilled by Rotary Rig with 4 inches diameter drilling rod. The drilling diameter of well should not be less than 12 inches diameter to a depth of 200 m. The contractor should do Karataj (well logging geophysics) under the following conditions a) Perform Karataj after drilling of wells under the supervision of DACAAR field engineer b) Should record the most important parameters like SP, SPR , EC and resistively with long and short improvement c) Identify intervals of each layer(strata) according to the well logging record d) Identify intervals of fresh and saline water (aquifers) according to the well logging record (electrical conductivity) e) Provide comprehensive well log design according to the well logging record Permanent 6-inch PVC casing & filter will be installed in the wells. The casing & filter will be supplied by DACAAR. The contractor will be responsible for lowering and installation. The contractor should also monitor and record salinity of water (Electrical Conductivity) during drilling The contractor should provide sorted sand and gravel (2 to 5mm) for back filling of pipe and filters and also provide available suitable clay for sealing around the pipe The contractor should clean the well by compressor and carry out pumping test for seven hours for each well to find its hydraulic properties. Provide a compete soft and hard copy of report Article 2 RESPONSIBILITIES OF DACAAR 2.1 DACAAR/WSP shall be responsible for timely supplying of 6 inches diameter PVC pipe and filter. 2.2 DACAAR/WSP is responsible to monitor drilling processes according to the Work details in Article 1. 2.3 DACAAR/WSP shall be responsible for well site selection in Jalaier area of Shireen Tagab district of of Faryab province. 2.4 Payments will be made against receipt of the bill of the CONTRACTOR by DACAAR at the end of the job after successful completion of bored wells. Verification on well completion is needed from the DACAAR/WSP monitoring engineer. 2.5 DACAAR shall not be responsible for transportation and accommodation Article 3 3.1 The cost of drilling mentioned in table (I) of page no.5 shall be the sole remuneration Page 1 of 6 owed by the Contracting Authority to the Supplier under the contract. It shall be fixed and not subject to revision. 3.2 Payments shall be made with 15 days after completion of work. Article 4 The contract is made up of the following documents, in order of precedence: this Contract agreement; copy of Invitation to Bid copy of your offer The documents making up the contract shall be deemed to be mutually explanatory; in case of ambiguity or divergence, they should be read in the order in which they appear above. For all matters not covered by the above provisions, the law applicable shall be Afghanistan law. Article 5 Any written communication relating to this Contract between the Contracting Authority, on the one hand, and the Supplier, on the other, must state the contract title and identification number, and must be sent by e-mail or by hand to the following addresses: For the Contracting Authority: Name: Address: Telephone: e-mail: Dr. Arif Qaraeen/ Director DACAAR Main office, Paikob-e-Naswar, Wazirabad, PO Box 208 Kabul, Afghanistan 93 (0) 20 22 01 750 / 0797011002 dir@dacaar.org, procurement@dacaar.org For the Supplier: Name: Address: Telephone: e-mail: Article 6 This contract shall be automatically terminated, and the Supplier shall have no right to any form of compensation if there are any changes in quality or if it emerges that the award or execution of the contract has given rise to unusual commercial expenses. Such unusual commercial expenses are commissions not mentioned in the main contract or not stemming from a properly concluded contract referring to the main contract, commissions not paid in return for any actual and legitimate service, commissions remitted to a tax haven, commissions paid to a recipient who is not clearly identified or commissions paid to a company which has every appearance of being a front company. Article 7 The Contracting Authority may under no circumstances be held responsible for damages caused by the contractor, their employees or a third party in connection with the performance of this contract. Page 2 of 6 Article 8 8.1 10% of total contract value will be deposited to DACAAR account as contract performance guarantee before sign of contact. The mentioned amount of guarantee shall be deposited to DACAAR USD Account No 100 120 100 73 80 in Kabul bank. If termination results from inaction or fault on the part of the Supplier, the Contracting Authority shall be entitled to compensation up to a maximum of 10% of the total Contract value. In the case of delay in completion of drilling, the contactor shall be liable to pay damages calculated from the expiry date of the contractual period. For each day of delay in implementation of the project of drilling wells, the damage is fixed at 0.5% of the total value of incomplete work. 8.2 8.3. Article 9 The contracting parties shall make every effort to settle amicably any dispute which may arise between them but in case it is not resolved then the case can be referred to local court. Article 10 All required machineries and other accessories plus transportation and accommodation will be provided by the contractor. Article 11 Contractor should provide report on each well and all works must be completed within 45 days after sign of contract. Article 12 The bank account of the Supplier into which payments shall be made is: Account number Account name Swift Code Sort Code Bank name & address Page 3 of 6 The contract is being written in English in two originals, one original being for the Contracting Authority and one original being for the Supplier. For the Supplier Name: Function: Signature: Date: Name: Function: Signature: Date: For the Contracting Authority Dr. Arif Qaraeen Director Page 4 of 6 Table (I) Cost Details ARTICLE QUANTITY DESCRIPTION UNIT COST PER METER/TEST TOTAL (AFN) 1 2 400 meter 400 meter Boring of wells (depth of well is 200 meter) Lowering of PVC 6” casing pipes & Filter cost/m (depth of wells is 200 m) Gravel packing around the pipe and filters and clay sealing around the pipe (depth of well is 200 meter) Cleaning of wells by compressor and pumping Test for7 hours cost/wells Well logging by Karataj (well logging geophysics) cost/well. Complete Soft copy and hard copy of report cost/well (AFN) INCLUDING GOVERNMETN TAXES 3 400 meter 4 02 5 6 02 02 Total Price Page 5 of 6 Table (II) Tentative Work Plan ARTICLE QUANTITY DESCRIPTION START OF CONTRACT COMPLETION 1 2 3 4 5 6 400 meter 400 meter 400 meter 02 02 02 Boring of wells (depth of well is 200 meter) 11/10/2009 Lowering of PVC 6” casing pipes & Filter cost/m (depth of wells is 200 m) 11/10/2009 Gravel packing around the pipe and filters and clay sealing around the pipe (depth of well is 200 meter) Cleaning of wells by compressor and pumping Test for7 hours cost/wells 11/10/2009 Well logging by Karataj (well logging geophysics) cost/well. 11/10/2009 Complete Soft copy and hard copy of report cost/well 11/10/2009 26/11/2009 26/11/2009 26/11/2009 11/10/2009 26/11/2009 26/11/2009 26/11/2009 Page 6 of 6

Related docs
contract template
Views: 2146  |  Downloads: 53
Contract Template
Views: 1531  |  Downloads: 31
Contract Template
Views: 1368  |  Downloads: 17
Contract Template
Views: 231  |  Downloads: 3
A Contract Template
Views: 218  |  Downloads: 2
Contract of Employment Template
Views: 1243  |  Downloads: 72
Independent Contractor Contract Template
Views: 3515  |  Downloads: 293
service contract template
Views: 4735  |  Downloads: 52
CONTRACT TEMPLATE
Views: 22  |  Downloads: 0
Sample assignment of contract form template
Views: 192  |  Downloads: 0
Construction Contract Template
Views: 8867  |  Downloads: 466
General Contract Template
Views: 94  |  Downloads: 4
Consignment Contract Template
Views: 63  |  Downloads: 2
Other docs by Alamance
OSHA Form 174
Views: 458  |  Downloads: 14
Form 6251 Alternative Minimum Tax-Individuals
Views: 1167  |  Downloads: 6
pos020
Views: 110  |  Downloads: 0
BUSINESS THANK YOU LETTER
Views: 2844  |  Downloads: 64
Evolution and Ethics
Views: 478  |  Downloads: 4
Inst W-2C and W-3C (PDF) Instructions
Views: 328  |  Downloads: 3
Blockbuster Inc Ammendments and By laws
Views: 275  |  Downloads: 1
Code of Ethics for Homeopathy
Views: 388  |  Downloads: 13
ASSIGNMENT OF MONEY DUE
Views: 259  |  Downloads: 2
CHECK REGISTER
Views: 364  |  Downloads: 20
MONTHLY CALENDAR TEMPLATE
Views: 838  |  Downloads: 12