					                          LIST OF STAFF
S.N   Name of           Designati                        Work Load
o.    Employee          on
                                    Name of      Sanction     Work         Remainin
                                    Work         Cost (in     Executed     g work
                                                 Lacs)        up to date
1.    Sh. A.B. Pandey   Resident    Const. of    1875.00      115.44       1759.56
                        Engineer    ROB at
                                    Tijara
                                    Phatak
2.    Sh. R.K. Mali     Asstt.      Const.       88.65        63.53        25.12
                        Resident    CFC
                        Engineer    Building
                                    Gola ka
                                    bas
3.    Sh. N.K.          Accounta
      Bhatnagar         nt

                                       Total =
A/R to Chanduki under PMGSY
ALWAR BHIWADI ROAD (BOT)
A/R TO AKBARPUR (RMUP)
RAC BARRACK 100MEN (PHASE-I)
RAC BARRACK 100MEN (PHASE-I&II)
PRESENT SCENARIO
FUTURE SCENARIO
               PROJECT AT A GLANCE
• Name of Work :- Construction of RoB at L.C. No. 111 ( Tizara
  Phatak) on Alwar – Bhiwadi Road ( T.P. No. 71/3-4 B.G.)
• Name of Client :- UIT, Alwar
• A & F Sanction :- Vide No. P.8(1) UDH/1/2006 Dated 17th Sept.
  2008 for Rs. 20.55 Crores.
• Technical Sanction :- Rs. 20.55 Crores on dated 06.01.2009
• St date of start :- 01-09.2008
• St. date of completion :- 08.01.2010
• Expected dated of completion: 31.12.2011
• Funds received from client upto 4th Dec. 2009 :- Rs. 150.00
  Lacs
• Expenditure as on 4th Dec. 2009 :- Rs. 115.44Lacs.
                                             ( including liabilities)
       Land marks :-
• GAD approved by Railway :-
  01.05.08
• Pile foundation work is in progress
• Funds Received from client :-
• (a) Rs. 25.00 Lacs on 29.05.07 for
  preparation of DPR
• (b) Rs. 75.00 Lacs on 02.07.09
• (c) Rs. 50.00 Lacs on 20.11.09
                   Hindrances :-
• Encroachment removed by UIT on 19.06.09 but matter
  is pending in the Rajasthan High Court, Jaipur for
  Payment of Compensation for land & Buildings.
• Shifting of utilities such as:-
• (a) Water supply lines shifting are still in process
• (b) Electric poles are still in process
• (c) Removing of trees- Application for permission
  submitted by UIT, Alwar
• (d) The traffic is not diverted till date from LC No. 111
• Agitation by local citizens for land and building
  compensation since 16.07.09 to 22.10.09.
CFC BUILDING AT GOLA KA BAS
CFC BUILDING AT GOLA KA BAS
               PROJECT AT A GLANCE
• 1.Name of Work :- Construction of Common Facility Center for Murtikala
  Cluster Gola ka Bas, Tehsil-Rajgarh District- Alwar (Raj.)
• 2. Name of Client :- DIC, Alwar
• 3. A & F Sanction :- Rs. 88.65 Lacs
• 4. Technical Sanction (Revised) :- Rs. 88.65Lacs
• 5. St. date of start :- 02-11-07
• 6. St. date of completion :- 22-01-10
• 7. Funds received from client as on 31th Oct. 2009 :- Rs. 88.65 Lacs
• 8. Expenditure as on 04TH Dec. 2009 :- Rs. 63.53 Lacs.
• 9. Bottlenecks:-Revised funds received late as on 09-03-09.
   – Plate form Drawing received as on 09-06-09.
   – Encroachment on land for Culvert and approach road has not yet been
      cleared till today as on 04.12.09.
PROPOSED
ROAD
  WIDENING OF ALWAR –BHIWADI
ROAD (SH-25)KM 146/0 TO 225/0 FROM 2
 LANE TO 4LANE DEVIDED HIGHWAY
LENGTH              :   79.00KM
PROJECT COST           :   222.26 Crores
PERIOD OF
CONSTRUCTION           :   18 Months
PERIOD OF CONCESSION   :   19 YEARS
Total Period           :   20 Years 6 Mths
Toll Booth             :   2 Nos. Booth
                           1. on KM 160
                           2. on KM 211

				