							          Status of the Linac Controls
                    Upgrade

                                        Tom Himel
                                       June 8, 2009




Status of the Linac Controls Upgrade         1   1                  Tom Himel
LCLS FAC review                                       thimel@slac.stanford.edu
                                       Outline

      Review of reasons for upgrade and plan
      Progress
      Problems
      Summary




Status of the Linac Controls Upgrade      2   2                 Tom Himel
LCLS FAC review                                   thimel@slac.stanford.edu
                               Reasons for the Upgrade
      Through retirements and layoffs, have lost most
      people who know how to maintain the SLC
      control system.
      Have decided to upgrade the SLC control
      system to EPICS with a series of AIP projects.
           This will reduce chances of long downtimes due to
           some problem where expertise is lacking causing a
           long MTTR.
           Hardware is old. Upgrade is overdue.
           SLC control system has many years of applications
           being added and fine tuned. Main difficulty of the
           upgrade is to not lose too much this functionality.



Status of the Linac Controls Upgrade      3   3                        Tom Himel
LCLS FAC review                                          thimel@slac.stanford.edu
                                          Phases
      Phase 1 makes LCLS independent of the Alpha and
      multibus micros
           Replaces about 15 micros with VME crates, CPUs, and CAMAC
           interface.
                 1 micro in each of last 10 sectors, few in BSY, few system micros
                 (e.g. MPG)
           Main work is software
      Phase II replaces the CAMAC with more modern
      hardware
           Main expense is hardware
      Phase III-N propagates above upgrades to other regions
      of the accelerator complex
           Little planning here yet
           There are different types of functionality and hardware modules
           in other regions so not just simple replication


Status of the Linac Controls Upgrade             4   4                                  Tom Himel
LCLS FAC review                                                           thimel@slac.stanford.edu
                              “Signed off” List of Tasks

      The June 08 upgrade review
      recommended we make a detailed list of
      functionality and get it “signed off” by
      operations, accelerator physicists, and
      maintenance groups.
      We have made such a list and gone over it
      with above groups at a series of meetings.
      With modifications made at those meeting,
      it was approved, but no formal signatures.


Status of the Linac Controls Upgrade       5   5                         Tom Himel
LCLS FAC review                                            thimel@slac.stanford.edu
                              “Signed off” List of Tasks

                                                         Total
                                          Himel M&S cost labor
      Short description                   priority (K$)  (man-wk) % done resource
      Set up test hardware in bldg 34          1.0              1      100 sheng
      SAM driver                               1.1              4      100 sheng
      PDU driver                               1.1              8          sheng
      Vacuum pressure display                  1.1              6          sonya
      Linac temperature and water display 1.1                   6          sonya
      CamDmp                                   1.2             12       20 judy
      Make EPICS DB from SCP DB                1.2              4       50 judy
      Magnet control                           1.2              8       30 kristi
      Set up test hardware in LI17 and LI18 1.2                 2       20 kristi
      PIOP driver                              1.2             16       20 sass
      sub-booster interface driver             1.2              4        0 sass
      timing control                           1.2             20          sheng
      DAC driver                               1.2              4      100 sheng



Status of the Linac Controls Upgrade        6   6                                Tom Himel
LCLS FAC review                                                    thimel@slac.stanford.edu
                                       AIPs for Upgrade
      Linac dipole correctors to EPICS – 300k - ~approved
      Linac new quadrupole PS + EPICS control – 800k -
      ~approved
      Linac BPMs to EPICS – 700k - approved
      Linac micro -> IOC hardware conversion - ~495k –
      approved long ago
      Linac/BSY unique devices to EPICS – 200k – awaiting
      better cost estimate
      Linac software conversion – 2.03M - ~approved
      Linac gate generator and master trigger generator –
      139k - ~approved
      RF controller upgrade R&D - 1008 k - ~approved



Status of the Linac Controls Upgrade           7   7                    Tom Himel
LCLS FAC review                                           thimel@slac.stanford.edu
                 We DO have documents and Reviews

      6/4/09 LI17/18 test station design review
      5/5/09 Camcom design review
      1/23/09 PIOP initialize and status check
      design review
      11/25/08 SAM and IDIM device support
      design review




Status of the Linac Controls Upgrade   8   8                 Tom Himel
LCLS FAC review                                thimel@slac.stanford.edu
                                       Hardware Progress

      Have 2 crate test setup in lab
      Expect to have IOCs to control LI17 and
      18 by July 1, 2009 for testing purposes
      Have chosen to delay installation of IOCs
      for LCLS sectors until more software
      development and testing is done so can
      be sure we are getting the right stuff.




Status of the Linac Controls Upgrade           9   9                     Tom Himel
LCLS FAC review                                            thimel@slac.stanford.edu
                                       Progress
      VME CAMAC board has had several bugs
      exterminated. In state of no known bugs.
           Still need to test output to multiple branches and
           heavy loading
      SAM, IDIM, and DAC device support are all
      done.
      PIOP image can be downloaded and booted and
      fast status check works.
           Indian problems nearly killed Bob.
      Analog and digital status DBs will be mass
      produced from data in old control system.



Status of the Linac Controls Upgrade       10 10                         Tom Himel
LCLS FAC review                                            thimel@slac.stanford.edu
                                       Progress
      Got more hardware AIP money than originally
      planned
           Don’t have to develop device support for CAMAC
           power supply controllers nor handle bulk+boost
           supplies.
      Have started R&D needed for phase II
      replacement of RF hardware
           Functional requirements partly written (some details
           still need to be filled in)
           Have a microTCA crate, ADC, DAC to test as a
           possible implementation. Starting detailed ADC
           testing. Has been delayed by lack of software person.
           New hire will go here.


Status of the Linac Controls Upgrade       11   11                    Tom Himel
LCLS FAC review                                         thimel@slac.stanford.edu
                                       BSY

      The BSY area has several micros each
      which control some LCLS devices and
      some devices for ESA, PEP, SLC.
           As the last two are obsolete but ESA is
           considering future runs, did not want to break
           ESA by converting micros to IOCs and then
           supporting only the LCLS devices
           Few enough channels for LCLS that have
           decided to just change all of them to EPICS
           style hardware, eliminating the use of CAMAC
           for LCLS in the BSY.


Status of the Linac Controls Upgrade    12 12                   Tom Himel
LCLS FAC review                                   thimel@slac.stanford.edu
                          Slow getting people on board
      As predicted by the June 08 review team, it has
      been difficult to get people on board the upgrade
      project
           At that time, plan was to finish the project by Nov 08.
           In fact, all work stopped after that review
           People were promised first for Nov 08, then Jan 09.
           For software, now have 2 ~80% people and 4 ~40%
           people. More are on the way.
           Not complaining. LCLS had to be finished and there are
           still many important improvements needed.
      That review team was really sharp. Especially the
      chair!!
      With the approval of FACET and plans for LCLS
      upgrades, controls is now hiring many people.

Status of the Linac Controls Upgrade    13 13                          Tom Himel
LCLS FAC review                                          thimel@slac.stanford.edu
                                       Schedule

      There still isn’t a detailed integrated schedule
      for this project
      Task list (with durations) is being used for
      planning. Not many dependencies
      Need to get unique device hardware installed
      during the Jan 10 downtime.
      No other external deadlines.
      (Un)Availability of manpower has been the
      main schedule determinant
      Good to leave obvious reason for the FAC to
      beat me up
Status of the Linac Controls Upgrade       14 14                 Tom Himel
LCLS FAC review                                    thimel@slac.stanford.edu
                                       FACET
      FACET is a newly approved $13M project using S0-
      19 and the damping rings for accelerator physics
      experiments
      Planned to be done Oct 2010.
      Bad timing for controls (busy and in middle of
      upgrade)
      New stuff will be done in EPICS, old, left in legacy
      control system
      Will compete for manpower with advantage of a tight
      deadline
      Fortunately we are now hiring people.


Status of the Linac Controls Upgrade     15 15                 Tom Himel
LCLS FAC review                                  thimel@slac.stanford.edu
                                 Old Worries with status


    1.      As implementation of phase I will take longer than
            originally planned and as expertise in the SLC control
            system is needed until the rest of the linac, damping
            rings, NLCTA, the gun lab, and the test lab are
            converted, people experienced with the SLC control
            system must be kept or new ones trained. - This is
            being done
    2.      If FACET proceeds on its schedule of completion in Oct
            2009, it clearly will not use the new control system and
            that much more expertise in the SLC control system will
            need to be maintained. If FACET proceeds on a slower
            schedule, management will need to decide soon
            whether a controls upgrade is done as part of the
            project, or with operating or AIP funds before the
            project, or if it will use the SLC control system. - chosen


Status of the Linac Controls Upgrade        16 16                         Tom Himel
LCLS FAC review                                             thimel@slac.stanford.edu
                                 Old Worries with status

   3.      This is a large, important project. Even so, many LCLS
           needs discovered during the commissioning process
           will be higher priority. It is better to do this project right
           and, if necessary, slowly, than to rush it to meet a
           schedule deadline and lose too much functionality
           when it is turned on. Delays have happened, project is
           being done slowly (and hopefully right).
   4.      There are 2 steering feedback in the region being
           converted. If they need to run at 120 Hz, then the
           EPICS version of 120 Hz feedback must be done
           before the switchover. (Planned for Jan 2010.) - Still
           planned for Jan 2010, so should be OK.




Status of the Linac Controls Upgrade        17 17                            Tom Himel
LCLS FAC review                                                thimel@slac.stanford.edu
                     Should we go straight to phase II?
      As phase I is going slowly and we are converting
      considerable hardware away from CAMAC (BPMs and
      magnet control), I (and others) periodically ask, should we
      skip phase I and just replace all the CAMAC as soon as we
      can. Pros and Cons
           Would save the work of developing CAMAC device drivers and
           support
           Much of DB and most displays will remain unchanged when we move
           from Phase I to II. Some will change and this is extra work.
           Phase II will cost several $M and needs RF R&D to be completed
           before it can start. Hence would be stuck with VMS and micros for 1-4
           years longer
           With phase I software done, other areas could be converted fairly
           cheaply (BPMs and PSC-II and “unique” devices would need to get
           new CAMAC drivers or new hardware).
           Phase II will require significant downtime and commissioning to
           implement. This will also lead to delays.

Status of the Linac Controls Upgrade       18 18                                Tom Himel
LCLS FAC review                                                   thimel@slac.stanford.edu
                                       Summary

      Upgrade is started, but slowly
      Phase I is mostly planned, but a real
      schedule needs to be developed
      The AIP projects which are tentatively
      approved should allow completion of
      Phase I.




Status of the Linac Controls Upgrade      19 19                 Tom Himel
LCLS FAC review                                   thimel@slac.stanford.edu

						
Related docs
Other docs by HC120809073719
A2A Activity Booking Form
Views: 0  |  Downloads: 0
CHECK ONLY ONE BOX
Views: 0  |  Downloads: 0
SD7 Attachments List
Views: 4  |  Downloads: 0
Enterprise GIS in California
Views: 3  |  Downloads: 0
United Nations
Views: 1  |  Downloads: 0
finalreport
Views: 3  |  Downloads: 0
West County Singles
Views: 1  |  Downloads: 0
Verdana Bold 30
Views: 1  |  Downloads: 0