					                                           Project Timeline
            Duration
Start Day              End Day                       Milestone                    Deliverables
             (days)
10/10/11       1       10/11/11 Review Intel-Cornell Cup Rules                   All team members have read all the rules and discussed them
10/11/11       1       10/12/11 Gain Advisor Support                             Ask Faculty members become advisors for the team for the upcoming academic year
                                                                                 List all of potential ideas
10/12/11       1       10/13/11   Create Project Concept                         Make a matrix decision to determine the most appropriate project
                                                                                 Register on website
                                                                                 Create a list of solutions to project challenges with pros and cons for each
10/13/11       1       10/13/11   Challenge Definition                           Address a best way to handle these challenges with originating requirements and explanations
                                                                                 Finishing challenge definition and reviewing by all team members
                                                                                 List of main subsystems, potential feasibility issues, solution description,
                                                                                 function flow diagram, Use case & Requirements, least expensive equipment’s
10/13/11       1       10/14/11   Proposed Solution
                                                                                 Identify potential reviewers
                                                                                 Reviewed and Approved by advisors
                                                                                 Show relation between functionality and challenge needs
10/14/11       1       10/14/11   Performance Measures                           List questions and potential tests, update test list with doable within time and
                                                                                 resources available, approved advisor
                                                                                 List of Potential Milestones, expected outputs for each milestone
10/14/11       1       10/14/11   TimeLine & Milestone Formation                 Assigned an estimated completed days for each task
                                                                                 Determined schedule by Gantt charts
                                                                                 Assigned & update importance and uncertainty rating with greatest effort
10/14/11       1       10/14/11   Concerns Check                                 Adjusted flow diagram, use cases and requirements, added requirements;
                                                                                 Adjusted flow diagram, use cases and requirements, added requirements;
                                                                                 Teammates review sections that they were not the primary author
10/14/11       1       10/14/11   Final Feasibility Check                        Adjusted functional flow diagram, uses cases, requirements and
                                                                                 written solution description; Advisor addressed questions, suggested changes
10/14/11       1       10/14/11   List any remaining concerns                    Adjusted deliverables
                                                                                 Written by at least one team member
10/14/11       1       10/15/11   Complete Application Write-Up
                                                                                 Reviewed by at least one other
                                                                                 Meeting scheduled & conducted
                                  Review Application with Advisor and Team
10/15/11       3       10/17/11                                                  Review sheets completed by all attendees
                                  Reviewer
                                                                                 List of changes needed recorded
10/17/11       1       10/17/11   Submit Application                             Confirmation Email Received
10/17/11       7       10/24/11   Waiting for finalists announcement             Notification Email Received :D
                                                                                 Team members understand basic ideas of image processing
                                                                                 Requirements of CMOS Camera to accomplish the challenge: speed, resolution, focus, brightness
                                                                                 Determine Test for CMOS Camera
                                  Research on image processing algorithm, openCV
10/25/11       13      11/07/11                                                  List of available and compatible CMOS cameras
                                  and CMOS Camera
                                                                                 Completed Decision matrix for CMOS camera
                                                                                 Confirmation in writing with tentative available dates and time
                                                                                 Purchase order placed, Receipts turned into Advisors
                                                                                 Team members understand basic ideas of touch screen interface with Atom processors
                                                                                 Requirements of touch screen
                                                                                 Determine Test for touch screen
11/07/11       7       11/14/11   Research on touch screen interface             List of available and compatible touch screen
                                                                                 Completed Decision matrix for touch screen
                                                                                 Confirmation in writing with tentative available dates and time
11/07/11   7    11/14/11 Research on touch screen interface



                                                                           Purchase order placed, Receipts turned into Advisors
                                                                           List of all possible inputs and respective desired outputs
                                                                           List of memory and runtime requirements, anticipated scale of the challenge, and legacy & code required
                                                                           Determine test bench for algorithms with sample images
11/07/11   20   11/27/11 Create image processing algorithm pseudo-code
                                                                           List of image processing types
                                                                           Image processing algorithms pseudo-code
                                                                           Review with Advisors
                                                                           Create image processing program run on PC to process image and convert to drugs characteristics
                                                                           Test program on PC with sample images
11/27/11   20   12/24/11 Design image processing program
                                                                           Review Results with Advisors
                                                                           Written report including pseudo-code, UML diagrams, test data, and conclusions
12/25/11   8    01/02/12 Noel and New Year break                           Noel and New Year break
                                                                           Research on Intel Atom processors environment
                                                                           Determine OS running on Atom processors
                                                                           Test touch screen
                           Implement Touch screen to Intel Atom            OS installed on Atom processors
01/02/11   14   01/16/12
                           development board                               Completed interface between touch screen and Atom processor
                                                                           Test touch screen on Intel Atom development board
                                                                           Review Results with Advisors
                                                                           Documentation for touch screen interface
                                                                           Test CMOS Camera
                                                                           Completed interface between CMOS Camera and Atom processor
                           Implement CMOS Camera to Intel Atom
01/16/12   7    01/23/12                                                   Test CMOS Camera on Intel Atom development board with results shown on touch screen
                           development board
                                                                           Review Results with Advisor
                                                                           Documentation for touch screen interface
                                                                           Change in image processing program if needed to install on Atom processors
                                                                           Image processing algorithms implemented into Atom processor
                           Test CMOS Camera and image processing
01/23/12   7    01/30/12                                                   Test image processing algorithms functionality in combination with CMOS Camera
                           algorithm combination
                                                                           Review Results with Advisors
                                                                           Documentation for touch screen interface
                                                                           Research on SQL server
                                                                           Determine database requirements
01/30/12   4    02/03/12 Create sample database
                                                                           Sample database with varies types of drugs
                                                                           Documentation for sample database
                                                                           Team members understand basic ideas of wi-fi technology and micro SD card interface
                                                                           Requirements of Wi-fi module and micro SD card
                                                                           Determine Test for Wi-fi module and micro SD card
                           Research on Wi-fi interface and micro SD card
02/03/12   7    02/10/12                                                   List of available and compatible Wi-fi module and micro SD card
                           interface
                                                                           Completed Decision matrix for Wi-fi module and micro SD card
                                                                           Confirmation in writing with tentative available dates and time
                                                                           Purchase order placed, Receipts turned into Advisors
                                                                           Research on searching algorithms
                                                                           Create suitable searching algorithms pseudo-code and review with Advisors
                                                                           Design searching program
02/10/12   24   03/05/12 Create searching algorithms                       Design test for searching program
                                                                           Test searching program
                                                                           Review results with Advisors
                                                                           Documentation for searching program include algorithm, psedo-code, source code
                                                                           Test Wi-fi module
                                                                           Completed interface between Wi-fi module and Atom processor
                           Implement Wi-fi module to Intel Atom
03/05/12   7    03/12/12
                           development board
                                 Implement Wi-fi module to Intel Atom
03/05/12       7      03/12/12                                                   Test Wi-fi module on Intel Atom development board with results shown on touch screen
                                 development board
                                                                                 Review Results with Advisor
                                                                                 Documentation for Wi-fi module
                                                                                 SQL Server installed on Server
                                                                                 Database installed
03/12/12       3      03/15/12 Create Online SQL database                        Test connection between Atom processor and Online database
                                                                                 Review Results with Advisor
                                                                                 Documentation for SQL server
                                                                                 Test micro SD Card
                                                                                 Completed interface between micro SD card and Atom processor
                                 Implement micro SD card on Intel Atom           Test micro SD Card on Intel Atom development board
03/15/12       4      03/19/12
                                 development board and create offline database   Offline database installed on micro SD Card
                                                                                 Review Results with Advisor
                                                                                 Documentation for SQL server
                                                                                 Change in searching program if needed to install on Atom processors
                                                                                 Test searching program with inputs from CMOS Camera and offline database
03/19/12       7      03/26/12 Test searching program on Atom processor          Test searching program with inputs from CMOS Camera and online database
                                                                                 Review Results with Advisors
                                                                                 Documentation for searching program
                                                                                 Determine GUI requirements
                                                                                 Combine subsystem programs into GUI
                                                                                 Completed GUI with device required features
03/26/12      10      04/05/12 Create GUI                                        Install GUI on Atom processor
                                                                                 Test GUI
                                                                                 Review Results with Advisors
                                                                                 Documentation for GUI
                                                                                 Review timeline and schedule for Competition event
04/05/12       1      04/05/12 Book tickets to Exp
                                                                                 Book tickets and plan for next month trip
                                                                                 Test the whole device with all the test plan
                                                                                 Acquire results from test plan
04/05/12      14      04/19/12 Test and review device                            Review the device
                                                                                 Get advices from ER doctors on using device and make changes if needed
                                                                                 Documentation test process
                                                                                 Final reports
04/19/12      11      04/30/12 Finish documentation and presentation             Presentation
                                                                                 Finished device for showing in Expo
           May 2012              Attend Competition event at Walt Disney World

				