					                      STATEMENT OF WORK
                             FOR
                         CONSTRUCTION




                         Requisition #: 246168


                                   Title:
105-KE SAFE STORAGE ENCLOSURE (SSE) CONSTRUCTION




                          Revision Number: 0

                               Date: 5-4-12




                                   i of ii
                            Requisition Number: 246168
           Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                Date: 5-4-12
                             TABLE OF CONTENTS


DIVISION 1 – GENERAL REQUIREMENTS

Section 01010   Summary of Work

Section 01019   Items Furnished for Construction (Government-Furnished Materials
                [GFM])

Section 01036   Request for Clarification (RCI) and Changes

Section 01040   Coordination

Section 01050   Field Engineering

Section 01065   Permits

Section 01110   Occupational Safety / Industrial Hygiene

Section 01130   Environmental, Radiological, and Nuclear Safety

Section 01150   Training and Qualifications

Section 01200   Project Meetings

Section 01300   Submittals

Section 01315   Project Schedules, Project Controls, and Project Performance Milestones

Section 01400   Quality Assurance and Control

Section 01500   Construction Facilities and Temporary Controls

Section 01610   Material and Equipment Delivery, Storage, and Handling

Section 01630   Product Options and Substitutions

Section 01670   Construction Acceptance Testing

Section 01720   Project Record Documents




                                         ii of ii
                                  Requisition Number: 246168
                 Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                      Date: 5-4-12
                                      SECTION 01010
                                    SUMMARY OF WORK

PART 1 – GENERAL

1.1        INTRODUCTION / BACKGROUND

As a prime contractor to the U.S. Department of Energy (DOE), CH2MHILL Plateau
Remediation Company (CHPRC) is focusing on the safe, environmental cleanup of the Central
Plateau of DOE’s Hanford Site. CHPRC’s scope of work includes treatment and disposal of
various radioactive waste streams and groundwater, management of spent nuclear fuel, disposal
or disposition of nuclear materials and non-reactor nuclear facilities, and environmental
remediation activities currently funded through DOE’s Office of Environmental Management.

This Statement of Work (SOW) identifies the Contractor’s scope as it relates to the construction
of the 105-KE Reactor Safe Storage Enclosure (SSE) and 162-K Utility Building associated with
the 105-KE Interim Safe Storage (ISS) Project at the 100K Area of the Hanford Site.


1.2        DESCRIPTION OF WORK - GENERAL

The Contractor shall construct the free-standing 105-KE Reactor SSE over the existing 105-KE
Reactor building, including associated lighting, handrailing, guardrailing; install temperature
monitoring and water detection systems in the 105-KE Reactor building; and construct the 162-K
Utility Building with electrical and control monitoring equipment.

The Contractor shall provide technically qualified person(s) to perform the tasks described in this
SOW. The Contractor will work as part of an integrated project team under the general
supervision of CHPRC. Unless otherwise approved, the Contractor shall work in accordance
with CHPRC contract requirements, operating policies and procedures and shall be responsible
for execution of the work in accordance with the quality standards and requirements specified for
assigned project and facility.

1.2.1      Work is in the 100K Area of the Hanford Site and is located approximately 40 road
           miles north of Richland, Washington.

1.2.2      Work consists of supplying, fabricating, erecting, constructing, and installing the 105-
           KE SSE, 162-K Utility Building, and associated systems.

1.3        DESCRIPTION OF WORK - SPECIFIC

The Contractor shall construct the 105-KE SSE, which will be a free-standing enclosure structure
over the existing 105-KE Reactor building. The SSE will consist of a structural steel framing
system with metal roofing and siding panels, and a reinforced concrete grade beam foundation
system. The SSE will be approximately 151 ft. x 158 ft. x 123 ft. tall (approx. 23,300 sq. ft.).


                                              01010-1
                                         Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                      SECTION 01010
                                    SUMMARY OF WORK

The Contractor shall supply and install handrailing/guardrailing and a surveillance lighting
system and receptacles within the SSE. The Contractor shall also supply and install a
temperature monitoring system and a water leak detection system in the 105-KE Reactor
building with remote annunciation to the new 162-K Utility Building, which shall be constructed
by the Contractor as part of this work scope. The 162-K Utility Building will contain equipment
to transmit (wireless) the temperature monitoring and leak data to a centralized location within
the Hanford Site. 162-K will also house electrical equipement (e.g. breakers, switches, etc.)
supporting the SSE. The work scope also includes installation of an exhaust duct in the SSE for
future connection to a portable ventilation system that can evacuate stagnant air within the
reactor prior to performing surveillance and monitoring activities. The Contractor shall also
perform quality assurance inspection and testing.

The Contractor shall furnish all necessary labor, supervision, materials, tools, services,
equipment, consumables, and payment of any applicable taxes to perform the work as defined in
this SOW. Labor includes participation of Contractor’s employees in training and medical
examinations required by Contract. The Contractor shall procure/lease all equipment unless
identified as supplied by others. The Contractor shall verify and validate field conditions in
accordance with design drawings and technical specifications.

1.3.1      Included Work: The following identifies major work elements only.

a.         Provide and manage labor, equipment, material, and services required to complete
           work. Labor includes participation of Contractor’s employees in training and medical
           examinations required by Contract.

b.         Specific tasks to be performed under this work scope include the following:

            1.   Training and qualification of personnel

            2.   Preparation of required plans

            3.   Mobilization of equipment, tools, material, and temporary facilities

            4.   Earthwork including excavation of existing terrain; excavation, loading, and
                 hauling of borrow pit material; and backfill, and compaction to grade level,
                 including excavation, backfill, and compaction for building foundations.

            5.   Soil material excavated from existing terrain has the potential to be
                 contaminated. Consequently, the Contractor shall load all soil material
                 excavated from exisiting terrain into Environmental Restoration Disposal
                 Facility (ERDF) waste containers and move the loaded containers to a nearby
                 staging area, the Container Transfer Area (CTA), for transport by others. The
                 CTA is located approximately ¼ mile north of the 105-KE Reactor building.

                                              01010-2
                                         Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                  SECTION 01010
                                SUMMARY OF WORK

        6.   Prior to start of excavation, the Contractor shall verify existing ground
             elevations to elevations as shown on existing site topography survey SK-11-
             0001 Rev. D, As-built of Well Locations Phase 2. Any discrepancies between
             the drawing and the existing conditions are to be reported to CHPRC.

        7.   Supply and construction of foundations for the SSE and 162-K Utility Building.

        8.   Installation of a fencing system around the construction site prior to
             construction of the superstructure to establish control of personnel accessing the
             site.

        9.   Preparation of construction drawings and calculations as required for temporary
             bracing of columns and other structural members during construction.

        10. Supply, fabrication and erection of the SSE structural steel.

        11. Supply and installation of the SSE ventilation exhaust duct.

        12. Supply and installation of handrailing and guardrailing in the 105-KE Reactor
            building.

        13. Supply and installation of the surveillance lighting system and receptacles in the
            105-KE Reactor building.

        14. Supply and construction of the separate 162-K Utility Building, 240/120V
            single phase distribution system, electrical power equipment, lighting, and
            monitoring station instruments and equipment.
        15. Supply and installation of the remote leak detection monitoring system for
            flooding and temperature monitoring system in the 105-KE Reactor building
            with readouts to control monitoring equipment in the 162-K Utility Building.
        16. Quality assurance inspection and testing, functional testing, and construction
            acceptance testing of work. Performance acceptance testing of leak and
            temperature monitoring system locally and at the remote monitoring location.
        17. Demobilization of equipment, tools, material, and temporary facilities

1.3.2   The Contractor is responsible for providing all equipment, tools, materials, supplies,
        and each and every item of expense. The following equipment and materials shall be
        provided at a minimum by the Contractor and shall not be considered an all-inclusive
        list:
         All industrial safety equipment for Contractor personnel (e.g., eye protection, hard
             hats, steel-toed footwear, welding hood, face shields, splash protection)


                                          01010-3
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                                   SECTION 01010
                                 SUMMARY OF WORK


           All radiological protection and respiratory protection equipment (tyvek suits,
            booties, gloves, hoods, masks, cartridges), as required
           Appropriate hearing protection for all contractor personnel
           Signs, t-posts, ropes, fencing, and other approved barricades for posting zone.
            Traffic revision barriers and signing
           Fire extinguishers
           Cellular telephone or other communication device capable of initiating emergency
            notifications at remote work sites.
           Disposal containers for clean trash
           All permanent construction materials
           Wash water and drinking water
           Sanitary facilities
           Portable lighting/power for work

1.3.3   Excluded Work: The following are not part of this Contract.

        Work package preparation and daily work release

        Radiological protection and industrial health surveys

        Waste (including excavated soil) characterization, designation, profiling,
        transportation and disposal

        Items shown on the Drawings to be done by others:

        1) Construction of 105-KE Reactor Building at-grade, above-grade, and below-grade
           penetration pourbacks, curbs, coverings, and berms as depicted on Drawing H-1-
           97141, Sheet 1, 105KE Safe Storage Enclosure, Structural Pourback Plan and as
           detailed on Drawings H-1-97142, Sheets 1-5, 105KE Safe Storage Enclosure,
           Structural Pourback Sections & Details, and Drawing H-1-97150, Sheet 3,
           105KE Safe Storage Enclosure, Structural Standard Connection Details will be
           performed by others.

        2) Backfill and compaction of existing excavations to elevation – (minus) 20’-0”
           will be performed by others.

        3) Over-excavation of existing terrain on the north side of th 105-KE Reactor
           building to the Elev. – (minus) 20’ level as depicted on Section B on Drawing H-
           1-97132, Sheet 1, 105KE Safe Storage Enclosure,Civil Grading Sections will be
           performed by others.




                                           01010-4
                                      Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                  SECTION 01010
                                SUMMARY OF WORK

1.4     DRAWINGS, SPECIFICATIONS, AND EXHIBITS

        All Work shall be performed in strict accordance with requirements, design criteria,
        codes and standards, specifications, drawings, exhibits, and any other documents,
        which by this reference are made a part of the Statement of Work.

1.4.1   Drawings

a.      Drawings that show Work are listed below.

               Drawing No.            Rev.                          Title
                                               105KE Safe Storage Enclosure, General Title
             H-1-97120 Sht. 1           0
                                               Sheet
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97121 Sht. 1           0
                                               Floor Plan – El. -17’-6”
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97121 Sht. 2           0
                                               Floor Plan – El. -51’-7”
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97121 Sht. 3           0
                                               Floor Plan – El. -66’-0”
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97121 Sht. 4           0
                                               Stair Sections and Details
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97122 Sht. 1           0
                                               Exterior Elevations
                                               105KE Safe Storage Enclosure Architectural
             H-1-97122 Sht. 2           0
                                               Exterior Elevations
                                               105KE Safe Storage Enclosure Architectural
             H-1-97122 Sht. 3           0
                                               Exterior Elevations
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97122 Sht. 4           0
                                               Roof Plan
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97123 Sht. 1           0
                                               Roofing and Siding Details
                                               105KE Safe Storage Enclosure, Architectural
             H-1-97124 Sht. 1           0
                                               Utility Building
                                               105KE Safe Storage Enclosure, Civil Site
             H-1-97131 Sht. 1           0
                                               Grading Plan
                                               105KE Safe Storage Enclosure, Civil Site
             H-1-97132 Sht. 1           0
                                               Grading Sections
                                               105KE Safe Storage Enclosure, Structural
             H-1-97141 Sht. 1           0
                                               Pourback Plan

                                            01010-5
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                     SECTION 01010
                   SUMMARY OF WORK


                                 105KE Safe Storage Enclosure, Structural
H-1-97142 Sht. 1          0
                                 Pourback Sections & Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97142 Sht. 2          0
                                 Pourback Sections & Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97142 Sht. 3          0
                                 Pourback Sections & Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97142 Sht. 4          0
                                 Pourback Sections & Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97142 Sht. 5          0
                                 Pourback Sections & Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97150 Sht. 1          0
                                 General Notes
                                 105KE Safe Storage Enclosure, Structural
H-1-97150 Sht. 2          0
                                 Abbreviations, Legend and Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97150 Sht. 3          0
                                 Standard Connections Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97151 Sht. 1          0
                                 Foundation Plan
                                 105KE Safe Storage Enclosure, Structural
H-1-97152 Sht. 1          0
                                 Roof Framing Plan
                                 105KE Safe Storage Enclosure, Structural
H-1-97153 Sht. 1          0
                                 Truss Elevation and Bracing
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 1          0
                                 Framing Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 2          0
                                 Framing Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 3          0
                                 Framing Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 4          0
                                 Framing Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 5          0
                                 Girt Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 6          0
                                 Girt Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97154 Sht. 7          0
                                 Girt Elevation
H-1-97154 Sht. 8          0      105KE Safe Storage Enclosure, Structural

                              01010-6
                       Requisition Number: 246168
      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                           Date: 5-4-12
                     SECTION 01010
                   SUMMARY OF WORK


                                 Girt Elevation
                                 105KE Safe Storage Enclosure, Structural
H-1-97155 Sht. 1          0
                                 Foundation Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97155 Sht. 2          0
                                 Foundation Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97155 Sht. 3          0
                                 Foundation Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97156 Sht. 1          0
                                 Roof Framing Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97156 Sht. 2          0
                                 Roof Framing Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97157 Sht. 1          0
                                 Wall Framing Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97157 Sht. 2          0
                                 Wall Framing Details
                                 105KE Safe Storage Enclosure, Structural
H-1-97158 Sht. 1          0
                                 Girt Framing Details
                                 105KE Safe Storage Enclosure, Mechanical
H-1-97161 Sht. 1          0
                                 Ventilation Plan
                                 105KE Safe Storage Enclosure, Mechanical
H-1-97162 Sht. 1          0
                                 Details
                                 105KE Safe Storage Enclosure, Electrical
H-1-97170 Sht. 1          0
                                 General Notes and Legend
                                 105KE Safe Storage Enclosure, Electrical
H-1-97171 Sht. 1          0
                                 Site Plan
                                 105KE Safe Storage Enclosure, Electrical
H-1-97172 Sht. 1          0
                                 Site Details & Elevations
                                 105KE Safe Storage Enclosure, Electrical
H-1-97173 Sht. 1          0
                                 Arrangement Plan
                                 105KE Safe Storage Enclosure, Electrical
H-1-97173 Sht. 2          0
                                 Arrangement Plan
                                 105KE Safe Storage Enclosure, Electrical
H-1-97173 Sht. 3          0
                                 Arrangement Plan
                                 105KE Safe Storage Enclosure, Electrical
H-1-97173 Sht. 4          0
                                 Arrangement Plan
                                 105KE Safe Storage Enclosure, Electrical
H-1-97173 Sht. 5          0
                                 Arrangement Plan

                              01010-7
                       Requisition Number: 246168
      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                           Date: 5-4-12
                                   SECTION 01010
                                 SUMMARY OF WORK


                                               105KE Safe Storage Enclosure, Electrical
              H-1-97173 Sht. 6          0
                                               Arrangement Plan
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97173 Sht. 7          0
                                               Arrangement Plan
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97173 Sht. 8          0
                                               Arrangement Plan
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97173 Sht. 9          0
                                               Arrangement Plan
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97174 Sht. 1          0
                                               Monitoring System Panel
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97174 Sht. 2          0
                                               Monitoring System Panel
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97174 Sht. 3          0
                                               Monitoring System Panel
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97174 Sht. 4          0
                                               Monitoring System Panel
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97175 Sht. 1          0
                                               One-Line Diagrams
                                               105KE Safe Storage Enclosure, Electrical
              H-1-97175 Sht. 2          0
                                               Panel Schedule

1.4.2   Specifications and Work Processes

a.      The Specifications applicable to this Scope are shown below:

               Specification No.      Rev.                          Title
                                                Technical Specifications for CH2M HILL
                                                Plateau 105KE ISS Associated Penetration
           Project No. 11-6729          0
                                                Sealing and Safe Storage Enclosure (SSE)
                                                Design


b.      Major CHPRC work processes applicable to this Scope are shown below. Refer to
        GP 2.0, “Order of Precedence.”

        No.                                 Title

        CHPRC-00263                  Offsite Vendor Instructions for the Preparation and Control of
                                     Engineering Drawings

                                            01010-8
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                                   SECTION 01010
                                 SUMMARY OF WORK

        MSC-RD-8589                  Hanford Fire Marshal Permits
        PRC-GD-EN-40256              Engineering Codes & Standards
        PRC-PRO-EN-097               Engineering Design and Evaluation (Natural Phenomena Hazard)
        PRC-PRO-EN-286               Testing of Equipment and Systems
        PRC-PRO-EN-440               Engineering Documentation Preparation and Control
        PRC-PRO-EN-8016              Design Change Notice Process
        PRC-PRO-EN-8017              As-Built Verification Process
        PRC-PRO-EN-8336              Design Verification
        PRC-PRO-EN-20050             Engineering Configuration Management
        PRC-PRO-EN-40271             Engineering Design Process
        PRC-PRO-SH-40078             Contractor Safety Processes – Appendix F, Safety Program
                                     Specification for Contractors
        PRC-PRO-SH-40435             CHPRC Electrical Safety Progran
        PRC-PRO-WKM-12115            Work Management
        PRC-PRO-WM-40223             Environmental Restoration Disposal Facility Waste Process
        PRC-RD-EN-1819               CHPRC Engineering Requirements
        PRC-RD-WKM-8524              Supervision of Field Work
        PRC-STD-FP-40404             Fire Protection Program

1.4.3   Codes and Standards

        The following latest version of the codes, standards, and requirements included
        below, are hereby incorporated into and made a part of this SOW, as applicable.
        They shall have the same force and effect as if written into the body of the SOW, and
        are in addition to codes, standards and requirements in the FDC.
         Document No.                   Title
         29 CFR 1910.120                Hazardous Waste Operations and Emergency
                                        Response
         ANSI Z535.1                    American National Standard for Safety Color Code
         CRD 420.1.B, Chg 1             Facility Safety
         (Supplemented Rev. 0)
         DOE -0344                      Hanford Site Excavating, Trenching and Shoring
         DOE-0346                       Hanford Site Fall Protection Program
         DOE-0336                       Hanford Site Lockout/Tagout
         DOE O 413.3B                   Program and Project Management for the Acquisition
                                        of Capital Assets
         DOE/RL-92-36                   Hanford Hoisting and Rigging Manual.
         DOE STD 1088                   Fire Protection for Relocatable Structures
         NFPA 241                       National Fire Protection Association (NFPA)
                                        (Standard for Safeguarding Construction, Alteration
                                        and Demolition Operations)


                                          01010-9
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                                  SECTION 01010
                                SUMMARY OF WORK


         Document No.                   Title
         NFPA 51B                       Standard for Fire Prevention During Welding,
                                        Cutting, and Other Hot Work
         NFPA 70                        National Electrical Code (NEC)


1.4.4   Exhibits

        The exhibits applicable to the Scope are included below:

               Exhibit No.            Rev.                          Title
              SK-11-0001                D          As-built of Well Locations Phase 2
                                                      (Existing Site Topography Survey)



                                                   105-KE_Reactor_Fin
                                                        alCivil.pdf

              105KE South                n/a       105KE Aerial Photo (South View)
                 View.pdf


                                                      105KE SOUTH
                                                        VIEW.pdf

              105KE North                n/a       105KE Aerial Photo (North View)
                 View.pdf
                                                          105KE NORTH
                                                            VIEW.pdf

              105KE East                 n/a       105KE Aerial Photo (East View)
                 View.pdf
                                                          105KE EAST
                                                           VIEW.pdf

             105KE Framing.pdf           n/a       105KE Safe Storage Enclosure (Internal
                                                      Framing)



                                                     105KE FRAMING.pdf




                                          01010-10
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                                   SECTION 01010
                                 SUMMARY OF WORK


           105KE Enclosure.pdf           n/a       105KE Safe Storage Enclosure (External
                                                      Cladding)



                                                         105KE
                                                     ENCLOSURE.pdf

           DD-49286                      4         105KE Reactor Interim Safe Storage
                                                      (ISS) Project Functional Design
                                                      Criteria

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                    END OF SECTION




                                          01010-11
                                     Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                                    SECTION 01019
                       ITEMS FURNISHED FOR CONSTRUCTION
                         (Government-Furnished Materials [GFM])

PART 1 – GENERAL

1.1        GOVERNMENT- FURNISHED MATERIALS

1.1.1     The following materials and equipment will be furnished by CHPRC at no cost to the
           Contractor:

1.1.1.1    Necessary permits to perform work on-site (as applicable and unless otherwise
           specified)

1.1.1.2    On-site HAMMER Training courses required to execute work in accordance to SOW
           requirements (does not include contractor labor cost or employee “seat” time to attend
           training classes)

1.1.1.3     ERDF waste containers, tarps, and tie-down cords for the loading and transfer of
           excavated soil for disposal

1.2        ITEMS FURNISHED FOR CONSTRUCTION

1.2.1      CHPRC will furnish the following materials for construction as shown in the table
           below. To arrange transfer, notify CHPRC 5 working days before need.


                                                                Delivery
                      Date    Specification Section or Storage     to     Miles to
            Item
                   Available     Drawing Number        Location Worksite Worksite
                                                                  by
                             Technical Specifications
                             for CH2M HILL Plateau
                             105KE ISS Associated
                             Penetration Sealing and
                             Safe Storage Enclosure
          Borrow 5 days (SSE) Design, Section
          material after     312000 and Attachment A                      Approx. 5
                                                        Pit 23 Contractor
          for      contract – Geotechnical                                 miles
          backfill award     Engineering Study

                            Drawings H-1-97131, H-
                            1-917132, and SK-11-
                            0001




                                             01019-1
                                        Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                   SECTION 01019
                      ITEMS FURNISHED FOR CONSTRUCTION
                        (Government-Furnished Materials [GFM])

1.2.2     The Contractor shall provide equipment and labor for loading, transporting, unloading
          stockpliling, and handling borrow material for backfill in accordance with
          arrangements for transfer.

1.2.3     Contractor shall protect and handle government-furnished items in accordance with
          SP-12.

1.2.4     Provide access to furnished items during storage.

1.2.5     Pit run gravel and sand are available at no cost from natural deposits at Pit 23 located
          approximately five (5) miles southeast of the worksite. Use of gravel and sand sites is
          non-exclusive; others may also enter to excavate material required for other work.

1.2.5.1   Selection, gradation, placement and compaction of backfill shall comply with the
          requirements of Technical Specifications for CH2M HILL Plateau 105KE ISS
          Associated Penetration Sealing and Safe Storage Enclosure (SSE) Design, Section
          312000 and Attachment A – Geotechnical Engineering Study

1.2.5.2   Screening of the pit run material may be required by the Contractor to achieve
          required gradation.

1.2.5.3   Selection, gradation, placement and compaction of pit run material for structural
          backfill will be observed by the Engineer-of-Record.

1.2.5.4   If the Contractor elects to utilize available gravel and sand sites, the Contractor shall
          furnish equipment and labor to excavate, process, load, transport, and place material.

1.2.5.1   Confine removal of overburden and top soil to CHPRC-designated areas. After
          surface has been disturbed, stabilize blowing sand areas with ballast or other
          approved method to prevent wind erosion.

1.2.5.2   Excavate in accordance with DOE-0344 and the Excavation Permit.

1.2.5.3   Use roads designated by CHPRC to access gravel and sand sites and to travel
          between gravel and sand sites and worksite. If oversize loads are utilized, comply
          with Section 01500.

1.2.5.4   Upon completion of operations, remove debris, temporary structures, and equipment.
          Grade excavated area, properly slope banks, and stabilize area to prevent wind
          erosion. Grade excavated area, and properly slope banks (4:1 horizontal/vertical).

1.2.5.5   Right to use gravel and sand sites may be terminated by CHPRC for failure to meet
          Contract requirements and for abandonment of operations under this Contract. Right

                                             01019-2
                                        Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                    SECTION 01019
                       ITEMS FURNISHED FOR CONSTRUCTION
                         (Government-Furnished Materials [GFM])

           to use gravel and sand sites will be terminated without notice upon completion and
           acceptance of Work under this Contract.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                       END OF SECTION




                                             01019-3
                                        Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                              SECTION 01036
               REQUEST FOR CLARIFICATION (RCI) AND CHANGES

PART 1 – GENERAL

1.1       REFERENCES

          Not Used

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal procedures.

1.2.2     Approval Required: None

1.2.3     Approval Not Required: Before starting work, submit name of person responsible for
          receiving changes to design media in accordance with 1.4.2.

1.3       REQUEST FOR CLARIFICATION (RCI)

1.3.1     This Section covers preparation of Contractor-originated Request for Clarification or
          Information (RCI) (Form A-6004-833). RCI forms will be supplied during
          Preconstruction Conference (see Section 01200).

1.3.2     RCIs are used by the Contractor to receive clarification from CHPRC at any time
          during construction. The RCI form is not used to document a contract modification,
          engineering change, or nonconformance. CHPRC’s response to an RCI does not
          constitute authorization to perform a change to the Contract.

1.3.3     The Contractor may proceed in accordance with the response only on the basis that
          the Contractor agrees that it is not a contract change. If the Contractor believes the
          response constitutes a change, the Contractor shall immediately process a Contract
          Change form (A-6004-820) and await receipt of additional written instruction from
          the Contract Specialist.

1.3.3.1   Limit each request to a single issue. Date each request and assign a unique reference
          number.

1.3.3.2   Provide pertinent information including Contract number, subject, Drawing numbers,
          Specification number and paragraph references, date by which response is requested,
          cost and schedule impacts, site location, descriptive text, and originator’s name and
          signature.

1.3.3.3   Correspondence and inquiries from lower tier subcontractors addressed to CHPRC
          will be returned to originator or referred to Contractor.


                                             01036-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                               SECTION 01036
                REQUEST FOR CLARIFICATION (RCI) AND CHANGES

1.3.4      RCIs shall be prepared in accordance with the form’s instructions.

1.4        CHANGES

1.4.1      Authorized changes to design media will be provided to the Contractor via an
           approved redline field change drawing, a Design Change Notice (DCN), or a contract
           modification. No change work shall be performed without written authorization from
           the Contract Specialist.

1.4.2      Contractor shall designate a single-point-of-contact responsible for receiving changes
           to drawings, specifications, and other design media. The designee shall be
           responsible for maintaining documents and ensuring the most current revision is
           being used for the performance of work. Documents shall be stored in a manner that
           minimizes the risk of loss or damage.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                       END OF SECTION




                                             01036-2
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                      SECTION 01040
                                     COORDINATION


PART 1 – GENERAL

1.1     COMMUNICATIONS

1.1.1   Written communications between CHPRC and Contractor shall be sent to the
        representatives identified under “Notices” in the Contract Signature Document. The
        Contractor may interface with various CHPRC (and other) organizations through
        CHPRC Contract Specialist (or designee), as required.

1.1.2   Site Coordination and Interface Requirements include interface with CHPRC Field
        Work Supervisor (CHPRC FWS), Project Engineer, CHPRC’s Technical
        Representative (BTR), or designated representative on a daily basis.

1.1.3   Applicable interfaces that the Contractor may interact with, include the following:

            Radiological Control technicians

            Electrical Utilities representatives

            Waste Management representatives

            Safety and Industrial Health representatives

             D&D representatives

            Soil Remediation representatives

1.1.4   Daily construction activity shall be coordinated with CHPRC as identified in the
        General Provisions for Construction Services entitled “Technical Representative
        Responsibilities.”

1.1.5   The BTR designated for the Contract is Edward Jacobs, phone: 376-2859. The BTR
        is responsible for monitoring and providing technical guidance for this Contract and
        should be contacted regarding questions or problems of a technical nature. The BTR
        is also responsible for appropriate surveillance of the Contractors representative while
        on site. In no event, however, will an understanding or agreement, modification,
        change order, or any deviation from the terms of this Contract be effective or binding
        upon CHPRC unless formalized by proper Contract documents executed by the
        Contract Specialist prior to completion of this Contract. On all matters that pertain to
        Contract terms, the Contractor shall contact the Contract Specialist specified within
        this Contract. When in the opinion of the Contractor, the BTR requests or directs
        efforts outside the existing scope of the Contract; the Contractor shall promptly notify
        the Contract Specialist in writing. The BTR does not possess any explicit, apparent

                                           01040-1
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                        Date: 5-4-12
                                     SECTION 01040
                                    COORDINATION

        or implied authority to modify the contract. No action should be taken until the
        Contract Specialist makes a determination and/or modifies the contract.

1.1.6   The Contractor shall work with the CHPRC FWS to coordinate construction activities
        with on-going demolition and remediation activities at the project location.

1.2     PREPARATION ACTIVITIES

        The Contractor shall be responsible for the following functions, requirements, and
        preparatory activities:
1.2.1   Complete employee training requirements as specified in Section 01150.

1.2.2   Ensure equipment, materials, and personnel are ready for the execution of the
        applicable contract release.

1.2.3   The Contractor shall ensure that Suspect/Counterfeit items are not brought onto the
        Hanford Site, in accordance with Section 01400.

1.2.4   Ensure all Contractor-supplied tools and equipment are in good working order and
        free from obvious and known defects, malfunctions and disrepair (e.g., oil leaks,
        broken and/or missing parts) upon arrival at the job site.

1.2.5   Prior to Mobilization, submit all Material Safety Data Sheets (MSDS) sheets and
        Chemical Inventory sheets as required.

1.3     SECURITY, BADGES, AND DOSIMETERS

1.3.1   CHPRC will arrange for issuance of security badges and dosimeters required for on-
        site work subject to the requirements identified in SP-5.

1.3.2   As soon as practical after award, the Contractor shall submit a badge request for
        personnel required under the Contract so that they may be scheduled for training and
        medical evaluation to be eligible for work on-site. A badge is required in order to
        obtain an HID number, which is needed before training and medical evaluations can
        be coordinated and scheduled. A minimum of two working days advanced notice is
        required for a Site badge. Contractor personnel shall wear CHPRC-issued security
        indentification badges.

1.3.3   Contractor employees will be required to submit to vehicle searches and not
        personally carry or transport prohibited articles.




                                          01040-2
                                Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                       Date: 5-4-12
                                        SECTION 01040
                                       COORDINATION

1.4       WORK HOURS

1.4.1     Work will be done on an 8-9's schedule. The standard workday shall consist of nine
          (9) hours of work from 7:00 AM to 4:30 PM, with one-half hour designated as an
          unpaid period for lunch. An eight (8)-hour workday is substituted on alternate
          working Fridays, and no work occurs on the alternate non-working Friday. No work
          occurs on Facility Closure Days. If schedule alternative is required, BTR will
          communicate to Contractor contact.

1.4.2     The Contractor will have access to the job site based on the terms of the Contract.

1.5       WORK MANAGEMENT REQUIREMENTS

1.5.1     Work shall be performed in accordance with CHPRC procedures, policies, and
          guidance documents. No work shall be performed that is out of scope to the contract.
          If work is determined to be out of scope or questionable, work shall be stopped,
          issue/concern defined and evaluated, and a revision to contract shall be prepared, as
          necessary, prior to resuming work.

1.5.2     Performance of Work on other than regular day shift, movement of equipment,
          electrical system tie-ins, and equipment tie-ins requires special coordination and prior
          approval.

1.5.3     Hazard Identification and Mitigation

1.5.3.1   The Contractor shall develop and maintain a work site Job Safety Analysis in
          accordance with PRC-PRO-SH-40078 - Contractor Safety Processes, Appendix F –
          Safety Program Specifications for Contractors, Section 2.2.

1.5.4     Work Control Requirements
1.5.4.1   The Contractor shall use CHPRC work control documents and procedures per PRC-
          PRO-WKM-12115, Work Management. Work Planning Requirements are required
          for work activities to be performed on site. Planning documentation will be provided
          to the Contractor for review and concurrence.

1.5.4.2   Work instructions provided by CHPRC are written specifically to control work scope
          and hazards, and to implement mitigating hazard controls described in this SOW and
          the corresponding Job Safety Analysis (JSA)/Job Hazards Analysis (JHA). The work
          instructions will be placed in a work package that will include the necessary permits
          and associated project documentation needed to safely complete the work scope.

1.5.4.3   Hazard identification and control requirements are included in the work planning
          documents.


                                             01040-3
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                         SECTION 01040
                                        COORDINATION

1.5.4.4   Work performance requirements and limitations shall be clearly communicated to the
          work crew to ensure the individual worker does not place themselves or others into an
          unsafe configuration.

1.5.5     Work Planning

1.5.5.1   The Contractor and/or its lower-tier contractors (or representatives) shall provide
          competent person(s) to support the preparation of all required work documents and
          shall actively participate in the planning and preparation of the work instructions,
          Enhanced Work Planning (EWP) and Job Hazard Analysis (JHA) in accordance with
          PRC-PRO-WKM-079, Job Hazard Analysis.
1.5.5.2   In conjunction with CHPRC, the Contractor’s qualified competent person(s) shall be
          responsible for providing input that supports the writing and revising of work steps that
          describe the work to be conducted and to enumerate the safety hazards associated with
          conducting the work. In conjunction with the Job Safety Analysis, the Contractor shall
          provide input that supports the inclusion within the work instructions the mitigating
          procedures for avoiding inherent hazards.
1.5.5.3   Work scope described in this SOW shall be performed following the preparation and
          approval of a work package prepared by CHPRC D&D Project Work Control following
          the requirements of PRC-PRO-WKM-12115 including but not limited to earthwork,
          foundations, structural erection, electrical systems tie-ins, equipment installation, testing,
          etc.

1.5.6     Work Release Requirements

1.5.6.1   Daily release of work packages and approval to work shall be performed using the
          Work Release for Construction/Services Organization process.

1.5.6.2   A Work Release for Construction/Service Organizations Form (WRCSOF) (Form
          BC-6001-394) is provided in the work package. The Contractor shall complete the
          work release form and provide it to the CHPRC FWS , each day on the afternoon, for
          review and approval by the CHPRC FWS prior to performing the next day’s work.
          The project requires release each day prior to start of work, then again prior to the end
          of shift for signoff by the CHPRC FWS. Activities worked each day are limited to
          items listed on the work release unless additions are approved by the CHPRC FWS to
          facilitate unforeseen changes to work scope. The end-of-the-day meeting may be a
          conference call to plan the following day’s work activities at a time to be determined
          by the CHPRC FWS.
1.5.6.3   The WRCSOF shall provide a description of the work including a brief work scope
          statement, location, required permits, any support required from the Owner including
          inspections or hold points, special precautions about the planned work, and potential
          impacts such as contamination and service interruption. The form must describe all
          activities and deliveries at the jobsite.

                                              01040-4
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                                        SECTION 01040
                                       COORDINATION

1.5.6.4    The WRCSOF will be used to obtain daily work release approval from the 105-KW
           Shift Operations Manager (SOM). The SOM is the Release Authority (RA) for the
           105-KE SSE Project.

1.5.6.5    Only work scope identified in this SOW may be released.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                       END OF SECTION




                                             01040-5
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                    SECTION 01050
                                 FIELD ENGINEERING

PART 1 – GENERAL

1.1     CONTROL POINTS

1.1.1   Basic reference points, bench marks, and other survey data are shown on the
        Drawings.

1.2     QUALITY CONTROL

1.2.1   Quality Controls (e.g., inspections, tests, material identification, nonconformance
        control, etc.) shall be established, implemented, and documented using a graded
        approach to verify that design requirements are appropriately satisfied during
        construction. The specific controls shall be specified in Quality Assurance Plans and
        implemented through a combination of project procedures, drawings, specifications,
        and inspection/test plans. See Section 01400.

1.2.2   Structural alignment, support location, and grades: For surveying Work, use of a land
        surveyor licensed in the state of Washington is required. Proof of professional license
        shall be submitted to CHPRC.

1.2.3   Layout: Use personnel who are trained, skilled, and experienced in construction
        staking.

1.2.4   Deliverable Documentation: Deliver field notes, records and documentation for
        Work under this Section in accordance with Section 01720.

1.3     PROCEDURE

1.3.1   Before construction activity and in field, verify control points provided by this
        section. Verification shall include horizontal coordinates and elevations. Report
        discrepancies to CHPRC before proceeding with construction.

1.3.2   Using control points, establish reference points for structural alignment, support
        location, grades, layout and other construction activity. Record horizontal and
        vertical data for reference points.

1.3.3   Preserve control points, reference points, stakes and other established markers until
        either removal is authorized by CHPRC or Work is completed.

1.3.4   Refer to SP-4’s reference clause FAR 52.236-17, “Layout of Work.”




                                           01050-1
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                   SECTION 01050
                                FIELD ENGINEERING

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used
                                    END OF SECTION




                                          01050-2
                                Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                              SECTION 01110
                 OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

PART 1 – GENERAL

1.1       REFERENCES

1.1.1     The following documents and others referenced herein form part of Contract to extent
          designated in this section. Referenced documents are those current as of the date of
          this section unless otherwise indicated.

1.1.1.1   Department of Energy (DOE)

          DOE-0344, Hanford Site Excavating, Trenching and Shoring

          DOE-0346, Hanford Site Fall Protection

1.1.1.2   Washington State Department of Ecology (Ecology)

          State Waste Discharge Permit

1.1.1.3   National Fire Protection Association (NFPA)

          1, Fire Code

          70, National Electrical Code (NEC)

1.2       SUBMITTALS

          Not Used

1.3       SUMMARY

1.3.1     Work elements requiring Hanford Site permits are identified in this section. Permits
          will be provided by CHPRC at no cost, unless otherwise stated.

1.3.2     Notify CHPRC 15 working days in advance of work requiring permit (unless
          otherwise stated) and furnish requested information. Post permit in a conspicuous
          location and ensure employees' awareness of permit contents. Meet the requirements
          set forth in permit.

1.3.3     Permits identified in this section and other sections of the Contract may require use or
          approval of forms and requests that are not titled as permits but generically referred to
          as permits. Contractor shall comply with requirements identified on those forms and
          requests.

1.3.4     It is anticipated that Work performed under this SOW will require a Radiological
          Work Permit (RWP).

                                               01110-1
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                            SECTION 01110
               OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

1.3.5   It is not anticipated that cultural materials or protected plants or animals will be
        encountered during project activities in previously disturbed areas. However, the
        Contractor shall watch for bones or possible historic artifacts, especially during
        excavation. If cultural materials are encountered, stop work within the immediate
        vicinity of the find and notify CHPRC.

1.3.6   Migratory birds may be present at this site and nesting activities shall not be
        disturbed. If field work is to be initiated during active nesting season (i.e., between
        mid-March through end of July), Contractor shall contact CHPRC to initiate a review
        of the area where the work is to be performed to make sure no nesting is occurring
        within the affected area). Workers are to be instructed to watch for active nests. If
        active nests and/or any nesting birds are encountered, or birds exhibit defensive
        behavior, the Contractor shall stop work in the immediate vicinity of the nest and
        shall contact CHPRC for additional review and required action.

        Ground-disturbing activities have the potential to spread and increase noxious plants.
        Vehicles should stay on existing roadways, graveled areas, and bare areas to the
        extent possible.

1.4     PERMITS

        CHPRC will coordinate and obtain the Hanford Site work permits as necessary for
        performance of the Work. The Contractor shall notify CHPRC fifteen (15) days in
        advance of work being performed and maintain a copy of all CHPRC-provided
        permits. The following permits may be applicable depending on the Contractor’s
        installation techniques. Once permits and requirements are obtained by CHPRC, the
        Contractor shall comply with all CHPRC-issued permits.
1.4.1   Confined Space Entry Permit (Form A-6004-724): Required prior to entry into any
        area determined to be classified as a Confined Space, and containing conditions
        detrimental to employee safety.

1.4.2   Construction/Demolition Permit: In accordance with MSC-RD-8589.

1.4.3   Critical Lift Plan: In accordance with DOE-RL- 92-36.

1.4.4   Electrical Installation Permit (Form BC-6001-777): In accordance with DOE-0336.
        One permit covers new electrical installation work governed by the National
        Electrical Code (NFPA 70). Electrical wiring/installations require NEC compliance
        inspection by qualified electrical inspector approved by the Hanford Electrical Codes
        Board.

1.4.5   Electrical Utilities Disconnect Request: In accordance with MSC-PRO-066.


                                           01110-2
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                             SECTION 01110
                OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

1.4.6    Energized Electrical Work Permit (Form A-6004-799): In accordance with DOE-
         0336. Required for work on existing electrical systems.

1.4.7    Excavation Permit (Form A-6004-751): In accordance with DOE-0344. Required for
         excavation involving hand digging greater than 12 inches in depth, or machine
         digging. Excavations shall also comply with 29 CFR 1926 Subpart P, Excavations.

1.4.8    Fall Protection Permit for Portable Ladders (Form A-6004-762): In accordance with
         PRC-STD-SH-40314. Required when fall exposure is 6 feet or greater and the use of
         conventional fall protection is infeasible or creates a greater hazard. Permit to be
         accessible during performance of work.

1.4.9    Fall Protection Work Permit (Form A-6004-286): In accordance with DOE-0346.

1.4.10   Fire Marshall Permit: Notify CHPRC Fire Protection Engineer or Deputy Fire
         Marshal in accordance with SP-4. Required for work associated with fire hydrants
         taken out of service; for any new construction or demolition activity; when using
         combustible chemicals, compressed gas, explosives, and flammable/combustible
         liquids; when performing cutting/welding or outdoor burning; and for any activity
         falling under the scope of NFPA 1. Flammable/combustible liquids storage shall be
         per NFPA 30, and permitted in accordance with MSC-RD-8589.

1.4.11   Flammable/Combustible Liquids Storage: Shall be per NFPA 30, and permitted by a
         Fire Marshal Permit in accordance with MSC-RD-8589.

1.4.12   Hanford Site Oversize/Overweight Permit (Form A-6003-609): Required for each
         vehicle and/or non-reducible load that exceeds the dimensions or weights shown in
         SP-4. Verify route suitability and limitations before applying for the permit.

1.4.13   Hot Work Permit (Form A-6006-115): In accordance with PRC-PRO-FP-40421.
         Required prior to performing any work which may involve open flames or producing
         heat and/or sparks including brazing, cutting, grinding, soldering, arc or gas welding,
         plasma welding, or torch-applied roofing. Cutting and grinding classified as Hot
         Work is limited to operations that produce significant sources of heat or spraying
         sparks such that they are considered ignition sources to surrounding combustibles on
         the Hanford Site.

1.4.14   Nonemergency Hydrant Tie-In Permit (Form A-6005-120): In accordance with PRC-
         STD-FP-40404. Required for any water being obtained through an existing hydrant.
         Contractor shall notify CHPRC a minimum of 2 weeks prior need, in accordance with
         SP-4.




                                            01110-3
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                               SECTION 01110
                  OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

1.4.15     Radiological Work Permit (Form A-6004-602): Required prior to performing any
           work within radiologically posted areas (e.g. CAs and RAs).

1.4.16     Re-locatable Structure Permit: In accordance with MSC-RD-8589.

1.4.17     State Waste Discharge Permit: CHPRC has already obtained the required permit. No
           discharges of water are allowed or authorized within 300 horizontal feet of any
           known crib, catch basin, infiltration trench, or underground disposal area.

1.4.18     Utility/System Outage Permit (Form A-7600-672): Required prior to Lock/Tag
           isolation of facility equipment, systems, and utilities in accordance with SP-5. Utility
           outages also require a Fire Marshal Permit. Notify CHPRC 5 days prior to need.

1.4.19     The Contractor shall comply with all current or existing Hanford Fire Marshal
           Permits issued to support the 105KE Safe Storage Enclosure Project.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used



                                        END OF SECTION
PART 1 – GENERAL

1.1        REFERENCES

1.1.1      The following documents and others referenced therein form part of Contract to
           extent designated in this section. Referenced documents are those current as of the
           date of this section unless otherwise indicated.

1.1.1.1    Code of Federal Regulations (CFR)

           Title 29                            Labor

                Part 1910                      Occupational Safety and Health Administration
                                               (OSHA)

1.1.1.2    Department of Energy, Richland Operations (DOE-RL)



                                              01110-4
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                               SECTION 01110
                  OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

          92-36                              Hoisting and Rigging Manual

1.1.1.3   Institute of Electrical and Electronics Engineers (IEEE)

          C2                                 National Electrical Safety Code (NESC)

1.1.1.4   National Fire Protection Association (NFPA)

          70                                         National Electrical Code (NEC)

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal procedures.

1.2.2     Approval Required

1.2.2.1   Safety and health program: PRC-PRO-SH-40078, Appendix F is the preapproved
          safety and health procedure; however, Contractor may submit, with proposal, an
          alternate safety program. The alternative program shall comply with federal, state,
          and local codes and PRC-PRO-SH-40078, Appendix F.
1.2.2.2   Designated Safety Representative: Before starting work, submit name of individual
          identified as the “Designated Safety Representative,” if the Contractor has more than
          one employee working on site in performance of this contract, in accordance with
          Special Provisions – On-Site Services (SP-5). Contractor shall notify the Contract
          Specialist if the name of the Designated Safety Representative changes.

1.2.2.3   Job Safety Analysis (JSA) / Job Hazard Analysis (JHA): Prior to on-site work,
          submit JSA/JHA identifying safety hazards as required by this Section.

1.2.2.4   Critical Lift Plan (DOE-RL-92-36): Prior to on-site work, submit a Critical Lift Plan
          in accordance with Paragraph 1.3.11.2B.

1.2.2.5   Task-Specific Job Safety Analysis: Prior to on-site work, submit a detailed Task-
          Specific Job Safety Analysis in accordance with 1.3.6.

1.2.2.6   Contractor Employee Job Task Analysis (EJTA): Prior to starting work, submit
          EJTA forms as required in 1.5.1.

1.2.2.7   Material Safety Data Sheets and Chemical Inventory Worksheets: Prior to
          mobilization or moving equipment on site, provide Material Safety Data Sheets
          (MSDS) for all chemical products that will be used during the work activity for pre-
          approval by CHPRC Project Safety. These shall be summarized as required, on Form
          A-6004-750, “Chemical Inventory Worksheet,” prior to mobilization. This will
          require a CHPRC MSDS number for each chemical to be brought on site. Contact

                                            01110-5
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                            SECTION 01110
               OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

        CHPRC Safety for assistance if needed. This shall be coordinated with the BTR and
        CHPRC Safety in the field and accurately maintained during fieldwork

1.2.3   Approval Not Required: None

1.3     SAFETY

1.3.1   All services under the management of the Contractor shall be performed in
        accordance with PRC-PRO-SH-40078, Contractor Safety Processes, Appendix F,
        Safety Program Specifications for Contractors, Section 3.3, which flows down the
        requirements of 10 CFR 851 and Hanford site requirements to the Contractor.

1.3.2   The Contractor shall comply with the on-site provisions identified in SP-5 of the
        Contract.

1.3.3   The Contractor shall perform work safely, in a manner that ensures adequate
        protection for employees, the public, and the environment, and shall be accountable
        for the safe performance of work. The Contractor shall comply with, and assist
        CHPRC in complying with all applicable laws, regulations and directives.

1.3.4   The Contractor and its lower-tier subcontractors shall take all reasonable precautions
        in the performance of the work to protect the safety and health of employees and of
        members of the public. Where there is a difference in regulations or requirements,
        the most stringent shall apply.

1.3.5   Contractor on-site fall protection shall be in accordance with DOE-0346, Hanford
        Site Fall Protection Program.

1.3.6   The Contractor shall prepare a detailed Task-Specific Job Safety Analysis for
        performing structural steel erection and roofing/siding installation at elevated heights,
        protection of personnel, equipment and hardware from falling materials, worker heat
        and cold stress, working in confined/limited work areas, large excavation work, and
        other hazards as identified.

1.3.7   The Contractor shall perform analysis of temporary construction configuration
        loading on the SSE as it is erected and design to provide temporary support as
        necessary to ensure structural stability of the SSE during erection. Calculations and
        drawings for shall be approved and stamped by a Registered Professional Engineer in
        the state of Washington.

1.3.8   While working within a facility or remote area, Contractor shall participate in
        emergency drills. Exemptions may be requested by Contractor; however exemptions
        might not be granted.


                                           01110-6
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                               SECTION 01110
                  OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

1.3.9      Contractor shall utilize gloves that are rated as cut/puncture-resistant for all activities
           that present the potential for a cut or puncture to the hand. Leather gloves are not
           rated as cut/puncture-resistant, and are not permitted. Contractors shall still use
           gloves (e.g., leather, canvas, cotton, etc. as appropriate for the work activity) to
           prevent and/or protect the hand from abrasions and contusions. Cut-resistant gloves
           come in different performance strengths; the Contractor needs to exercise the right
           amount of care to ensure they have selected the proper type of gloves for the hazard
           to be encountered. CHPRC does not specify or recommend any brand-name gloves;
           but does require these gloves to be rated as cut/puncture resistant.

1.3.10     Worker Exposure Monitoring for Hazardous Agents (i.e. Industrial Hygiene)

1.3.10.1   CHPRC will be responsible for providing industrial hygiene technical support. Daily
           industrial hygiene technician checks may be performed. Such support will include
           establishing exposure controls and limits, and conducting sampling and monitoring
           for hazardous agents associated with the activities and evolutions performed by the
           Contractor. These exposure controls and limits for hazardous agents (i.e. chemical;
           not radiological) will be specified in the Site-Specific Health and Safety Plan and/or
           the JSA. Results of all industrial hygiene surveys and monitoring will be provided to
           both the Contractor's Safety Representative and the Contractor's on-site Project
           Manager. CHPRC Industrial Hygienists will discuss exposure monitoring results
           with the respective Contractor Representatives and, as necessary, recommend or
           specify actions and controls to reduce or prohibit employee exposure to hazardous
           agents. The Contractor and CHPRC shall collaborate to implement these controls and
           ensure their effectiveness.

1.3.11     Hoisting and Rigging Requirements
1.3.11.1   Contractor on-site hoisting and rigging shall be performed in strict accordance with
           DOE-RL-92-36, Hanford Site Hoisting and Rigging Manual, Revision 1.
1.3.11.2   The following requirements are consistent with PRC-PRO-SH-40078, Contractor
           Safety Processes, Appendix F, which flows down the 10 CFR 851 and Hanford site
           requirements to the Contractor.
           A. For cranes and forklifts the requirements of the Hanford Site Hoisting and
           Rigging Manual (DOE/RL-92-36) are followed exclusively.
           B. The Contractor shall submit a Critical Lift Plan(s) (as required) that addresses the
           following requirements:
                  1. Structural calculations demonstrating the design factor of safety of all
                  below-the-hook lifting devices (e.g., ASME B30.20 certification, or
                  Professional Engineer certification of design load with a safety factor of three
                  based on yield strength of the material).


                                              01110-7
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                SECTION 01110
                   OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

                  2. Proof of load test certification to 1.25 times the rated load.
                  3. Written designation of a responsible equipment custodian.
                  4. A written schedule of planned maintenance, lubrication, and inspection
                  program for forklift trucks (maintained by equipment Contractor or Contractor
                  as appropriate).
            C. In addition, the following shall be maintained and shall be available on the job
            site for review, but are not a part of the hoisting and rigging submittal:
                  1. A current periodic inspection and current monthly wire rope inspection shall
                  be made available upon request for all mobile cranes (in accordance with
                  ASME B30.5) and drill rigs (in accordance with manufacturer’s
                  recommendations) in use. Complete, documented inspections shall be
                  performed monthly to no less than annually, depending upon activity, severity
                  of service, and environment.
                   2. Maintaining required inspection documentation for all hoisting and rigging
                  hardware and equipment as indicated in the above referenced chapters.
            D. In addition, daily and periodic maintenance and inspections shall be performed as
            required and will include maintaining records and documentation current.
1.3.12      Electrical Safety Requirements
1.3.12.1    For the purpose of worker safety, electrical equipment shall be in accordance with
            PRC-PRO-SH-40435, CHPRC Electrical Safety Program.

1.3.12.2     All electrical control panels and electrical equipment (a general term including
            material, fittings, devices, appliances, luminaries [fixtures], apparatus, and the like
            used as a part of, or in connection with, an electrical installation) delivered or brought
            on to the site in performance of the contract shall be labeled by an organization
            currently recognized by OSHA as a Nationally Recognized Testing Laboratory
            (NRTL).

1.3.12.3     All electrical equipment installed as part of the contract shall comply with the
            National Electric Code (NEC) and, where applicable, IEEE C2 (NESC).

1.3.12.4.   The Contractor shall use the Hanford Site Electrical Service Request (ESR) and
            CHPRC’s NEC inspectors for all permanent and temporary electrical power
            connections. The Contractor shall perform all electrical work in accordance with
            NFPA 70. The ESR normally requires a 10-day lead time for onsite processing.
            CHPRC will complete the ESR using information supplied by the Contractor.
1.3.12.10 The Contractor shall coordinate with CHPRC for de-energizing activities prior to
          making electrical connections or working with other forms of hazardous energy.
          Lockout and tagout activities will be required.

                                               01110-8
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                               SECTION 01110
                  OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

1.3.12.11 The Contractor shall not perform any work within 10 feet of an energized feed line
          without the written concurrence of CHPRC.
1.3.13     Fire Protection Requirements

1.3.13.1   All work activities must comply with PRC-STD-40404, Fire Protection Program.
1.4        HAZARD IDENTIFICATION

1.4.1.1    Prior to performing any other activities, Contractor shall submit a JSA/JHA for the
           construction activities to be performed.

1.4.1.2    JSAs/JHAs are prepared by the Contractor to address specific work activities and
           hazards associated with the specific work and to identify the controls necessary to
           eliminate or control the hazards. The JSA/JHA shall be written in such a manner as
           to be understood and usable by Contractor personnel in order to aid them in the
           identification, control, and response of potential hazards; it is not just a compliance
           document. To achieve the level of coordination desired, approval of the JSA/JHA is
           required to ensure proper safety planning and communication prior to the start of
           work. The JSA/JHA shall be prepared in a format provided by CHPRC, and the
           Contractor shall submit a JSA/JHA for approval prior to work on each release.

1.5        MEDICAL EXAMINATIONS

1.5.1      Medical examinations and Employee Job Task Analysis (EJTA) evaluation forms
           may be required for Contractor personnel prior to starting work on the Hanford Site.
           See SP-5. EJTAs drafted by the Contractor (form available on the CHPRC web site)
           shall be submitted to CHPRC for approval by CHPRC Health and Safety. Approved
           EJTAs will be forwarded to the Hanford Site Occupational Medical Provider (CSC)
           for required medical examination(s) identification and scheduling.

1.5.2      The Contractor shall immediately notify the BTR and the Contract Specialist of any
           injuries or incidents; to include damage to Contractor-owned property or equipment.

1.5.3      Contractor shall take appropriate action, up to and including stopping work, and
           immediately notify CHPRC if an unplanned risk or hazard is discovered that is not
           covered by directions provided by CHPRC. This action includes notifying CHPRC if
           the work exposes their workers to hazards that require medical monitoring.

PART 2 – PRODUCTS

Not Used




                                              01110-9
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                            SECTION 01110
               OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

PART 3 – EXECUTION

3.1     Specific unique work environment/conditions/circumstances that may be encountered
        during execution of the work scope include working in radiological environments,
        performing work in tight and limited space conditions, working at elevated heights on
        scaffolds, elevated work platforms, performing steel erection, hoisting and rigging
        activities, walking and working surfaces that are uneven, sharp corners and general
        construction hazards associated with equipment, lighting, noise, etc.

3.2     CHPRC will provide Hanford Site Occupational Medical Provider medical facilities
        for emergency or life-threatening injury situations (those requiring immediate
        medical attention). All injuries, accidents, fires, and near misses shall be reported
        immediately to CHPRC, including fires that are extinguished without causing
        damage.

3.3     The Contractor shall use the Hanford Site Occupational Medical Provider, CSC for
        first aid treatment and return-to-work evaluations, and the Hanford Fire Department
        for ambulance service for urgent medical situations requiring care and transport.

3.4     If chemical contamination is encountered, work shall be stopped immediately and the
        BTR contacted; an appropriate chemical monitoring plan is prepared by CHPRC.

3.5     To ensure worker safety, work or portions of work may be temporarily and
        incrementally shut down due to high winds, lightning, or other inclement weather as
        determined by CHPRC. Contractor shall not be additionally compensated in terms of
        cost or schedule for weather-related shutdowns. CHPRC issues the following
        warnings via radio system, public announcement, or in person. The Contractor shall
        ensure that subcontractor personnel are apprised of the warnings and take the required
        actions as stated below.

            Sustained winds greater than 15 mph – the necessity for crane operations shall
             be closely scrutinized.

            Excavation of radioactive material shall cease if sustained winds exceed
             20 mph. Depending on dust hazard, personnel may be relocated or directed to
             shelter. If sustained winds of 20 mph are predicted during the work shift,
             excavation of radioactive material will not be allowed to start.

            Sustained winds greater than 25 mph and/or gusts greater than 40 mph – all
             crane operations shall cease and be secured. No breach of radioactive systems
             or vessels will be allowed. All loose outdoor material shall be secured. The
             subcontractor’s Health and Safety representative shall review work on roofs and
             elevated surfaces before continuing. All personnel working outdoors are

                                          01110-10
                                Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                   SECTION 01110
      OCCUPATIONAL SAFETY / INDUSTRIAL HYGIENE

     required to wear safety goggles. Depending on dust hazards, work may be
     stopped. Personnel may be directed to shelter. Dust masks may be required

    Sustained winds greater than 30 mph and/or gusts greater than 45 mph – all
     outdoor work activities may be stopped. Personnel may be directed to shelter.
     Dust masks may be required.

    Sustained winds greater than 50 mph – outdoor work activities shall be curtailed
     and limited to those approved by CHPRC and subcontractor’s Health and Safety
     representative. Personnel will be directed to shelter. Site closure may be
     implemented and all work activities ceased.

    Thunderstorm/lightning advisory based on lightning activity within 30 mile
     vicinity of the Site. Subcontractor personnel shall not work on roofs or elevated
     surfaces. Personnel shall stay away from construction equipment such as
     drilling rigs, cranes, boom trucks, or elevated work platforms. These protective
     actions shall remain in place until CHPRC cancels the warning.

NOTE: Contractor shall provide personal protective equipment to meet the above
conditions.

In addition to these warnings, CHPRC also provides the following:

    Snow and ice removal is provided on Site roads. The Contractor shall provide
     snow removal and ensure safe walking and transfer conditions for walkways
     and access points around their offices and work areas and the job-site within the
     project boundaries.

    In response to winter storm conditions, CHPRC may close the Site or release
     Contractor's employees early. If so, CHPRC will make appropriate
     announcements and coordinate the closure or early dismissal.

    The Contractor shall be responsible for freeze protection in all areas turned over
     to the Contractor by CHPRC.



                            END OF SECTION




                                  01110-11
                        Requisition Number: 246168
            Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                 Date: 5-4-12
                           SECTION 01130
          ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

PART 1 – GENERAL

1.1       REFERENCES

1.1.1     DOE/RL 2005-26, Revision 1, Removal Action Work Plan for 105KE/105KW
          Reactor Facilities and Ancillary Facilities.
1.1.3     The following documents and others referenced therein form part of Contract to
          extent designated in this section. Referenced documents are those current as of the
          date of this section unless otherwise stated.

1.1.1.1   Code of Federal Regulation (CFR)

          Title 10                           Energy

               Part 820                      Procedural Rules for DOE Nuclear Activities

               Part 830.122                  Quality Assurance Criteria

               Part 835                      Occupational Radiation Protection

          Title 29   Labor

               Part 1910                     Occupational Safety and Health Standards

               Part 1926                      Safety and Health Regulations for Construction

          Title 40                           Protection of Environment

               Part 247                      Comprehensive Procurement Guideline for Products
                                             Containing Recovered Materials

1.1.1.2   Washington State Department of Ecology (Ecology)

          State Waste Discharge Permit

1.1.1.3   National Fire Protection Association (NFPA)

          30                                 Flammable and Combustible Liquids Code

1.1.1.4   Revised Code of Washington (RCW)

          Title 46                           Motor Vehicles

               Chapter 46.16                 Vehicle Licenses

                                            01130-1
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                           SECTION 01130
          ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.1.1.6   Resource Conservation and Recovery Act (RCRA)

          Section 6002                        Solid Waste Disposal Act

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal procedures.

1.2.2     Approval Required

1.2.2.1   Waste management information: Five work days before starting work, submit a
          Waste Management Plan, in accordance with the Special Provisions 4 and 5, for
          managing waste generated during work.

1.2.2.2   Material safety data sheets (MSDS): Before starting work, submit MSDS for
          hazardous chemicals (1.12.21.12.21.11.2).

1.2.2.3   Chemical sources: Ten (10) work days before starting work, submit detailed
          information relative to any anticipated process involving the application of volatile
          chemicals (use of a volatile cleaning agent, application of polyurethane coating,
          etc.)(1.12.31.12.31.11.3).

1.2.2.4   Chemical inventory: Ten (10) work days before starting work, submit inventory of
          chemicals that will be brought to the worksite in accordance with SP-4, SP-5, and this
          Section.

1.2.2.5   Air emissions: Before starting work on-site, submit inventory of air emission sources
          to be used in accordance with 1.131.131.12.

1.2.2.6   Dust control plan: Before starting work on-site, submit a Dust Control Plan in
          accordance with the Benton Clean Air Authority (1.13.2.11.13.2.11.12.2.1).

1.2.2.7   Radioactive sources: Four (4) work days before starting work on-site, submit a list of
          all radioactive sources to be brought on-site in accordance with 1.9.3.

1.2.2.8   Waste reduction plan: Before starting work on-site, submit a plan to ensure waste
          reduction in all work performed in accordance with 1.4.

1.2.3     Approval Not Required: None

1.3       WASTE MINIMIZATION

1.3.1     The Contractor is responsible to minimize waste generation. Minimize waste in
          accordance with the following waste management hierarchy.


                                             01130-2
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                           SECTION 01130
          ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

          a.   Source reduction
          b.   Reuse
          c.   Recycling
          d.   Compliant disposal

1.3.2     Source Reduction

1.3.2.1   Material substitution: Minimize number of chemicals used to perform same or
          similar tasks. Where practical, replace hazardous materials with non-hazardous or
          less hazardous substitutes. Before substitution, obtain approval in accordance with
          Section 01630.

1.3.2.2   Inventory reduction: Minimize product inventory to reduce accumulation of partially
          used and unused materials requiring disposal. Remove partially used lots and unused
          materials from worksite at Contract completion.

1.3.2.3   Packaging: Minimize packaging brought on worksite. Whenever feasible, return
          empty containers to vendor.

1.3.2.4   Waste segregation: Separate wastes to avoid creating additional wastes and mixtures
          that cannot be recycled, or that may be more difficult to manage.

1.3.2.5   Process modification: Streamline processes for more efficient operation and less
          waste generation.

1.3.2.6   Reuse/Recycling: Ensure that materials are reused, if possible, rather than discarded
          as waste.

1.4       The Contractor shall establish a program to promote cost-effective waste reduction in
          all operations and facilities covered by this contract. The Contractor’s program shall
          comply with applicable federal, state, and local requirements, specifically including
          Section 6002 of the Resource Conservation and Recovery Act and implementing
          regulations (40 CFR Part 247).

1.5       DISPOSAL OF INERT/DEMOLITION AND NONHAZARDOUS WASTE

1.5.1     Handle and dispose of waste in accordance with applicable federal, state, and local
          laws, regulations and requirements, SP-5 and this Section. Notify CHPRC prior to
          shipment of inert/demolition waste for radiological survey by others if removing from
          contaminated area.




                                            01130-3
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                         SECTION 01130
        ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.5.2   Non-hazardous: Excavated soil and waste generated by the Contractor shall be
        packaged in accordance with waste packaging requirements provided by the CHPRC.
        CHPRC will provide waste containers, liners, absorbent socks/pads, tarps and tie-
        down cords, transportation, and waste treatment and disposal. Waste will be disposed
        of at the Environmental Restoration Disposal Facility (ERDF) or other approved
        disposal facility. CHPRC Waste Management will deliver roll-off waste containers to
        a central location for Contractor use. Hoppers or bins will be provided by 100K
        Facilities for lunchroom and office trash. Contractor shall be responsible to properly
        load and package waste containers according to CHPRC-provided direction included
        in work packages.

1.5.3   Soil excavated from existing terrain has the potential to be contaminated.
        Consequently, the Contractor shall load all soil material excavated from existing
        terrain into ERDF waste containers in accordance with PRC-PRO-WM-40223,
        Environmental Restoration Disposal Facility Waste Process and move the loaded
        containers to a nearby staging area, the Container Transfer Area (CTA), for transport
        by others. The CTA is located approximately ¼ mile north of the 105-KE Reactor
        building.

1.5.4   Any nonradioactive inert waste (i.e. broken asphalt, broken concrete, glass, brick,
        aluminum, stainless steel, wood, and overburden/spoils material such as rock and
        earth) may be disposed at no charge to Contractor at Pit 9 located in 200 West Area.
        Notify CHPRC at least 24 hours prior to need for entry.

1.5.5   Other waste generated on the Hanford Site such as demolition rubble, construction
        debris, trash, and solid waste not included in other waste categories specifically
        mentioned in the contract shall be dispositioned by Contractor.

1.6     HAZARDOUS WASTE

1.6.1   Hazardous materials shall be managed in accordance with SP-5. Promptly report all
        spills of hazardous waste.

1.6.2   Flammable/combustible liquid storage shall be in accordance with NFPA 30.

1.7     DISPOSAL OF ASBESTOS

1.7.1   Contractor shall not perform any work that would disturb asbestos-containing
        material nor remove any load-bearing structures of any building without first
        notifying the BTR.




                                          01130-4
                                Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                           SECTION 01130
          ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.8       DISPOSAL OF DANGEROUS AND MIXED WASTE

1.8.1     Handle and dispose of waste in accordance with applicable federal, state, and local
          laws, regulations and requirements and CHPRC procedures. Hanford-specific
          requirements also apply to dangerous and mixed waste generated on the Hanford Site.

1.8.1.1   Notify CHPRC at least five days before generation of waste and immediately after
          spill and other unforeseen waste generation. Notification shall identify waste stream
          and provide an estimated quantity of waste to be generated.

1.8.1.2   Upon notification by Contractor, CHPRC will establish waste accumulation
          containers within the building footprint area and/or ab approved CERCLA Waste
          Management Area. CHPRC will provide labeled containers affixed with tracking
          numbers. Contractor shall provide a digital fish scale or comparable weighing device
          area and shall ensure personnel responsible for the waste accumulation area are
          properly trained.

1.8.2     Separately accumulate waste from each waste stream in accordance with the
          substantive requirements of applicable federal, state, and local laws, regulations and
          requirements.

1.8.2.1   During spill cleanup and waste accumulation, cumulatively record waste inventory on
          Waste Container Log (A-6004-995).

1.8.2.2   Containers are set up and managed by CHPRC. Manage waste in accordance with
          SP-5.

1.8.3     CHPRC will coordinate pick up and disposal of properly sealed dangerous waste after
          notification by Contractor.

1.9       RADIOLOGICAL CONTROL

1.9.1     If work is deemed Radiological, the Contractor shall be subject to 10 CFR 835,
          CHPRC RADIOLOGICAL CONTROL Manual, CHPRC-00073, and this Section.

1.9.2     Contractor shall not utilize vacuum trucks or HEPA-filtered vacuums, or set up
          enclosures with exhausters or similar emission units at any radioactively
          contaminated location on the Hanford Site without the express written approval of
          CHPRC.

1.9.3     The Contractor shall obtain written approval from CHPRC prior to bringing a
          radioactive source on-site. This includes any source or equipment that contains
          sources (e.g. soil densitometers) that are governed under a U.S. Nuclear Regulatory
          Commission (NRC) license or a license by an NRC-agreement state.

                                             01130-5
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                         SECTION 01130
        ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.9.4   Contractor’s equipment utilized to perform radiological work shall be subject to an
        initial radiological baseline survey prior to use on-site. This survey is expected to
        take approximately one hour (per piece of equipment) to complete. The survey will
        be conducted by CHPRC-provided Radiological Control Technicians (RCTs) and/or
        Health Physics Technicians (HPTs). Contact CHPRC to schedule the required survey
        upon arrival of the equipment on-site.

1.9.5   Contractor’s equipment utilized to perform radiological work shall be subject to
        intermittent radiological surveys approximately 2 to 3 times per work day.
        Radiological surveys are expected to take between 30 – 45 minutes each. Contractor
        shall make equipment available for intermittent radiological surveys at the request of
        CHPRC-provided RCT/HPT.

1.9.6   Removal of the following requires a contamination release survey for each removal.
        Contractor will not be charged for survey. CHPRC will arrange for survey upon
        request by Contractor. Allow two (2) working days for processing request and four
        (4) hours for survey.

        a.   Material from radiological contamination areas and radiological buffer areas

        b.   Foreign materials and discolored soil discovered during excavation

        c.   Equipment from radiological contamination areas and radiological buffer areas

1.9.7   During any work disturbing the existing ground surface, a CHPRC-provided
        RCT/HPT will be present to conduct intermittent radiological surveys of the
        excavated or disturbed material, if deemed necessary by CHPRC. The radiological
        surveys will be conducted on the spoils removed during any soil excavation as well as
        on the equipment being utilized for this excavation. These radiological surveys are
        not expected to significantly disrupt the Contractor’s ability to perform the required
        work. Contractor shall provide three (3) work days prior notice to CHPRC of need
        for RCT/HPT coverage of any excavation or work activity that will significantly
        disturb the existing ground surface.

1.9.8   If at any point, radioactive materials above specified action levels are encountered,
        work shall be stopped immediately. A Radiological Work Permit will be prepared by
        CHPRC to cover working with radiological contaminated soils and materials.

1.9.9   If radiological contamination is encountered during excavation or other work
        activities, Contractor shall place equipment in a safe condition and remove all
        personnel from area as directed by the RCT/HPT. Radiological controls shall be
        evaluated by the RCT/HPT organization to the encountered conditions and modified



                                           01130-6
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                          SECTION 01130
         ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

         as may be required. Contractor shall seek direction from CHPRC prior to resuming
         work activities.

1.9.10   A release survey is required to be conducted by CHPRC provided RCTs/HPTs of all
         equipment utilized in excavation. Release survey shall be conducted prior to
         equipment being removed from the project site. The release survey is expected to
         take approximately one hour per piece of equipment. Contractor shall provide two
         (2) work days prior Notice to CHPRC of need for RCT/HPT coverage to conduct
         required release surveys.

1.9.11   Contractor may additionally request a contamination release survey for each removal
         of equipment or material from if a radiological buffer area is declared. Contractor
         will not be charged for survey.

1.9.12   If survey reveals that equipment or material is not radiologically contaminated,
         dispose of material as planned.

1.9.13   If survey reveals that equipment or material is radiologically contaminated, dispose in
         accordance with direction from CHPRC. CHPRC will determine if release back to
         the Contractor is possible. If not possible, the Contractor will be compensated for
         items taken.

1.10     Soil excavated from existing terrain has the potential to be contaminated.
         Consequently, the Contractor shall load all soil material excavated from existing
         terrain into ERDF waste containers in accordance with PRC-PRO-WM-40223,
         Environmental Restoration Disposal Facility Waste Process and move the loaded
         containers to theCTA for transport by others (per to 1.5.3).

1.11     NUCLEAR AND CRITICALITY SAFETY

1.11.1   This work is deemed nuclear-related; the Contractor shall be subject to
         10 CFR 830.122, and the enforcement actions under 10 CFR 820.

1.12     LIQUID EFFLUENTS

1.12.1   In accordance with SP-4, SP-5, and PRC-PRO-SH-40078, Contractor Safety
         Processes, when the Contractor brings chemicals on site, the activity is subject to
         CHPRC’s Chemical Management System Program. The Contractor shall complete
         Form A-6004-750, Chemical Inventory Worksheet and submit to CHPRC for
         approval prior to mobilization. The Contractor shall keep Chemical Inventory
         Worksheets current and manintain copies on-site.




                                            01130-7
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                          SECTION 01130
         ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.12.2   Material Safety Data Sheets (MSDS) for hazardous chemicals (as defined by
         29 CFR 1910.1200) that will be used during the work activity shall be kept current.
         The Contractor shall provide the list to the assigned BTR when list has been updated.

1.12.3   The Contractor shall submit detailed information relative to any anticipated process
         involving the application of volatile chemicals (e.g., use of a volatile cleaning agent,
         application of polyurethane coating, etc.).

1.12.4   Concrete rinsate discharge locations require approval by CHPRC. Concrete rinsate
         discharge authorization forms shall be completed and approved prior to discharge.

1.12.5   Liquid discharge for hydrotesting, flushing, or other construction operation other than
         dust control, requires pre-approval by CHPRC and shall be performed in accordance
         with the State Waste Discharge Permit.

             No water shall be discharged within 300 horizontal feet of any known crib,
              catch basin, infiltration trench, or underground disposal area.

             No discharge shall be allowed within a surface contaminated area (areas with
              dangerous waste and/or radioactive contaminants), unless discharge is an
              approved incidental release.

             Other restrictions identified in the State Waste Discharge Permit and the
              accompanying conditions include the need to reuse/recycle and the need to
              discharge to the Treated Effluent Disposal Facility; discharge rate, volume,
              additives, source water, contaminants, and logging are also covered in permit
              conditions (Pollution Prevention and Best Management Practices section).

1.13     AIR EMISSIONS

1.13.1   The following emissions are regulated and shall comply with applicable federal, state,
         and local laws, regulations and requirements:

         a.   Fugitive emissions and dust
         b.   Abrasive blasting
         c.   Ozone-depleting substances
         d.   Non-routine (unplanned) emissions
         e.   Radioactive airborne emissions (from disturbing contaminated soil)

1.13.2   Contractor shall take reasonable precautions to minimize fugitive dust during
         performance of this work.




                                            01130-8
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                            SECTION 01130
           ENVIRONMENTAL, RADIOLOGICAL, AND NUCLEAR SAFETY

1.13.2.1   A dust control plan prepared in accordance with Benton Clean Air Authority
           guidelines shall be submitted by the Contractor and shall be approved by
           CHPRCprior to commencement of work activities.
1.13.3     Contractor shall not conduct open burning without the express written approval of
           BTR or CM.
1.13.4     Air emission sources also include non-road internal combustion engines for power
           generator or air compressor, loader, backhoe, welder, chain saw, etc. Licensed motor
           vehicles, pursuant to RCW 46.16 are exempt from the inventory. However, mounted
           internal combustion engines not used to propel the vehicle (e.g.; mounted generator)
           shall be inventoried.

1.13.5     The Contractor shall comply with PRC-PRO-SH-40078 - Contractor Safety
           Processes, Appendix F, Section 3.15, for controlling exposures to airborne hexavelent
           chromium. These requirements are specifically applicable to welding, grinding,
           torch-cutting, metal buffing and metal polishing, and spray painting activities.

1.14       CONTINGENCIES

1.14.1     Isolate and secure spill area in a manner that protects human health and the
           environment. Take direct action if nature of spilled or unforeseen waste material is
           known and if material can be immediately and safely absorbed, neutralized, or
           otherwise controlled. Report spills immediately to CHPRC.

1.14.2     Notify CHPRC upon occurrence or discovery of hazardous substances and
           non-hazardous material spills and of unforeseen dangerous waste generation.
           Notification shall identify waste stream if known and include identification and
           quantity of waste. Clean up areas contaminated by spilled material and manage spill
           residues in accordance with this Section.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

Not Used

                                       END OF SECTION




                                             01130-9
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                  SECTION 01150
                           TRAINING AND QUALIFICATIONS

PART 1 – GENERAL

1.1       REFERENCES

1.1.1     The following documents and others referenced therein form part of Contract to
          extent designated in this section. Referenced documents are those current as of the
          date of this section unless otherwise stated.

1.1.1.1   Department of Energy, Richland Operations (DOE-RL)

          92-36                               Hoisting and Rigging Manual

1.1.1.2   Washington Administrative Code (WAC)

          Title 296                           Department of Labor and Industries

               Chapter 46B                    Electrical Safety Standards, Administration, and
                                              Installation

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal procedures.

1.2.2     Approval Required

1.2.2.1   Prior to start of work, the Contractor shall submit documentation of successful
          completion of training requirements and certification that all training is current.

1.2.3     Approval Not Required

1.2.3.1   Hoisting and rigging: Prior to start of work, the Contractor shall complete and submit
          the OJE required for hoisting and rigging operations as required in 1.3.3.4.

1.2.3.2   Competent Persons: Before starting work, submit names of designated Competent
          and Qualified Persons in accordance with 1.3.1.1.

1.3       REQUIREMENTS

1.3.1     General

1.3.1.1   The Contractor shall appoint and identify the following fulltime professional
          positions to the project: Construction Superintendent, Safety & Health
          Representative, Field Engineer, Quality Assurance Representative, and Field Work
          Supervisor.


                                             01150-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                  SECTION 01150
                           TRAINING AND QUALIFICATIONS

1.3.1.2   Contractor shall provide appropriately trained and qualified staff to perform the type
          of work associated with their trade at the Hanford Site.

1.3.1.3   Task- and facility-specific training is required in this Statement of Work, the Contract
          Provisions, and other documents referenced herein. The training listed may not be
          all-inclusive of training required.

1.3.1.4   CHPRC will provide task- or facility-specific training required for the Hanford Site,
          which includes the class, instructor, and required training material. Contractor is
          responsible for cost of labor to complete all required training.

1.3.1.5   When offsite equivalent training is available, the Contractor is responsible for all
          training costs.

1.3.1.6   Contractor personnel shall be trained and qualified to CHPRC requirements for
          performing services. Personnel assigned to enter radiation zones within CHPRC
          areas of responsibility shall be fully qualified to perform work in such zones.
          Additional task specific or unique training or qualifications required for a specific
          task as delineated below. Personnel will be individually identified for specific
          training. Activities defined below are a composite of all training activities. The BTR,
          Contractor and 100K Training will determine training requirements for specific
          personnel/job classification.

1.3.1.7   The following types of training/qualifications are required and will be communicated
          by the BTR in work instructions driven by Employee Job Task Analysis (EJTA):
          a. CHPRC General Employee Training (CGET) or Hanford Site Orientation
          b. Special hazard training as applicable (i.e., GERT, Radiological Worker I/II
             Training, Hazardous Material Transportation)
          c. Facility-specific training
          d. Any special certifications (i.e., welding, engineering, NDE, CDL)
          e. Job-specific training (i.e., journey electrician, journeyman pipefitter, heavy duty
             operator)
          f. “Competent and/or Qualified Person” (Validation of assignment will be through
             completion of the appropriate Training Completion Record for the subject area.)
          g. Occupational Safety and Industrial Hygiene Training (See PRC-PRO-SH-40078)
          h. CHPRC or equivalent Fire Watch Training

1.3.1.8   CHPRC will provide for on-the-job evaluations (OJE) when they are required by
          Contract.
1.3.1.9   For previous training to be acceptable for Hanford Site qualification, documented
          evidence shall include type and class of equipment. For qualifications not related to



                                             01150-2
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                   SECTION 01150
                            TRAINING AND QUALIFICATIONS

           equipment operation, personnel shall have documented evidence of training and
           experience related to an activity covered under this Contract.

1.3.1.10 The Contractor shall maintain copies of personnel training records at the jobsite.

1.3.1.11 As soon as practical after award, the Contractor shall submit a badge request for
         personnel required under the various releases so that they may be scheduled for
         training and medical evaluation so that crews will be eligible for work on site. The
         badging request is required, because without it an HID number cannot be assigned,
         and therefore training and medical evaluations cannot be easily coordinated and
         scheduled.
1.3.1.12   The Contractor shall arrange for their and subcontract employees to obtain the
           following regulatory-required occupational medical examinations, which may be
           triggered by the activities of this contract:
                                    Asbestos
                                    Noise (>85 dbA)
                                    Paints/Resins
                                    Particulates
                                    Solvents-Other
                                    Welding Fumes


1.3.1.13   Anticipated work assignments:

                            Crane Operator
                            Driver With CDL
                            Hazardous Waste Worker
                            Quality Control Inspector


1.3.2      Site-Required Training

1.3.2.1    CHPRC General Employee Training (CGET): Mandatory for all Contractor and sub-
           tier Contractor personnel performing CHPRC work on the Hanford Site. Previous
           CGET training may be acceptable.

1.3.3      Qualification Training

1.3.3.1    The Contractor shall provide a trained and qualified FWS for field work activities.
           The FWS shall meet qualifications as required in PRC-RD-WKM-8524, Supervision
           of Field Work, and complete 100K D4 FWS Qualification Cards requirements.


                                              01150-3
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                  SECTION 01150
                           TRAINING AND QUALIFICATIONS

1.3.3.2   Electrical scope of work shall be performed by certified electrical journeymen, with
          qualifications meeting WAC 296-46B.

1.3.3.3   Hoisting and Rigging

1.3.3.4   Hanford Site Hoisting and Rigging Manual (DOE-RL-92-36) provides qualification
          for rigging operations. The Contractor may submit employee record of equivalency
          (i.e., experience and union affiliation), but is required to pass a written or oral
          examination; operators of cranes, forklifts, and aerial lift personnel performing
          rigging activities shall also satisfactorily complete an OJE.

          Prior to the start of work, the Contractor shall submit documentation of successful
          completion of the training requirements of any applicable activities covered in DOE-
          RL-92-36 Rev 1, and certification that all training is current. Training to include:
          hoisting and rigging operations, hoisting and rigging equipment inspection, fork truck
          operations, critical lifts, and mobile cranes, as required.

          Specifically, for Hanford Site Hoisting and Rigging Manual qualifications for rigging
          operations, the Contractor may submit employee record of equivalency (i.e.,
          experience and union affiliation), but must pass a written or oral examination.
          Operators of cranes, forklifts, and aerial lift personnel performing rigging activities
          shall also satisfactorily complete an on-the-job-evaluation (OJE).

             Basic Crane & Rigging Safety (Course #040784, 16 hrs) or new class
             Forklift Operational Safety (Course #044470, 6 hrs) or equal such as training
              from Star or Sunbelt or new class
             Forklift On-The-Job Evaluation (OJE) (Course #044671, A, B, C, D, E, or F,
              2 hrs) (Depending on type of forklift used)
             When applicable, Mobile Crane Operation & Setup (Course #042321, 4.5 hrs) or
              equal (i.e., experience and union affiliation)
             When applicable, Mobile Crane On-The Job Evaluation (OJE) (Course #044621,
              22, 23 or 24, 2-4 hrs) (Depending on type of crane used)
             When applicable, Aerial Lift Operator Course (Course#042720 or #043920 for
              class 1-4, or #043830 for class 5-6 Aerial Lifts) and (Course #044674 for LPG
              change out on class 1-3). (4.5 hrs)
             Aerial Lift Operator OJE (Course #044681, or #04468A-E, 2hrs) as appropriate.
          The Contractor shall identify and assign a Competent and Qualified person to service
          as the Assembly/Disassembly (A/D) Director for mobile crane operations. The
          Contractor must comply with Washington Administrative Code (WAC) 296-155 Part
          L, Crane Certifier Accreditation and Certification.



                                             01150-4
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

1.3.3.5    The following training/qualifications, as applicable, may be required in support of
           this scope:

                                Occupational Safety-Related Training
                                                           Off-site
 Hanford
                                            CHPRC          training
 Course              Course Title                                      Comments
                                            Documents     acceptable
 Number
                                                          (Yes / No)
           CHPRC General Employee
 000006                                        N/A            N                          -
           Training
           Advanced Rigging Activities On    DOE-RL-
 042865    the Job Evaluation (OJE)                           N                          -
                                              92-36
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
                                                                          Must complete a site specific
           Advanced Rigging Techniques       DOE-RL-
 042310                                                       Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          3 yr retrain period.
                                                                          United Brotherhood of Carpenters
                                                                           class accepted; MSA Letter
                                                                           CPL600000-08-02.
                                             DOE-RL-
 040784    Basic Crane & Rigging Safety                       Y           Must complete a site specific
                                              92-36
                                                                           examination.
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
           Cab Operated Overhead Cranes      DOE-RL-
 044701    (OJE)                                              N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 1 Floor Operated            DOE-RL-
 044691    Overhead Cranes (OJE)                              N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 1 Floor Operated            DOE-RL-
 04469A    Overhead Cranes (OJE)                              N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 1 Floor Operated            DOE-RL-
 04469B    Overhead Cranes (OJE)                              N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 1 Floor Operated            DOE-RL-
 04469C    Overhead Cranes (OJE)                              N        Complete a Hanford Site specific OJE.
                                              92-36
           Forklift Class 1 & 2 Operator     DOE-RL-
 044672    Qualification (OJE)                                N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 1 Lattice Boom Truck        DOE-RL-
 044621    Mobile Crane (OJE)                                 N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 2 Lattice Boom Crawler      DOE-RL-
 044622    Mobile Crane (OJE)                                 N        Complete a Hanford Site specific OJE.
                                              92-36
           Class 3 Aerial Lift Self          DOE-RL-
 04468B    Propelled Platform (OJE)                           N        Complete a Hanford Site specific OJE.
                                              92-36

                                               01150-5
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                       SECTION 01150
                                TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                             CHPRC         training
Course              Course Title                                       Comments
                                             Documents    acceptable
Number
                                                          (Yes / No)
          Class 3 Forklift – Electric        DOE-RL-
04467B    Motor, Hand Trucks (OJE)                            N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 3 Small Telescopic           DOE-RL-
044623    Mobile Crane (OJE)                                  N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 4 Aerial Lift Manually       DOE-RL-
04468C    Propelled Elevating (OJE)                           N        Complete a Hanford Site specific OJE.
                                              92-36
          Forklift Class 4 & 5 Operator      DOE-RL-
044673    Qualification (OJE)                                 N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 4 Large Telescopic           DOE-RL-
044624    Mobile Crane (OJE)                                  N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 5 Aerial Lift Vehicle        DOE-RL-
04468D    Mounted Boom Supported (OJE)                        N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 6 Aerial Lift Vehicle        DOE-RL-
04468E    Mounted Articulated (OJE)                           N        Complete a Hanford Site specific OJE.
                                              92-36
          Class 6 Forklift - Electric &
          Internal Combustion Engine         DOE-RL-
04467E                                                        N        Complete a Hanford Site specific OJE.
          (OJE)                               92-36
          Class 7 Forklift - Rough Terrain   DOE-RL-
04467F    Vehicle (OJE)                                       N        Complete a Hanford Site specific OJE.
                                              92-36
                                                                          Prerequisite 044470.
                                                                          Must complete a site specific
          Class -8 Forklift-Setup,           DOE-RL-                       examination.
044475                                                        Y
          Operation & Load Charts             92-36                       Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
          Class 8 Forklift Operator          DOE-RL-
044676    Qualification (OJE)                                 N                          -
                                              92-36
                                                                          3 yr retrain period.
                                                                          Must complete a site specific
          Forklift Inspectors                DOE-RL-                       examination.
041885                                                        Y
                                              92-36                       Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          3 yr retrain period.
                                                                          United Brotherhood of Carpenters
                                                                           class accepted; MSA Letter
                                                                           CPL600000-08-03.
                                             DOE-RL-
044470    Forklift Operational Safety                         Y           Must complete a site specific
                                              92-36
                                                                           examination.
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.


                                                01150-6
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                            CHPRC          training
Course              Course Title                                       Comments
                                            Documents     acceptable
Number
                                                          (Yes / No)
          Hoisting and Rigging Manual        DOE-RL-
170664    (DOE-RL-92-36) Overview                             N                          -
                                              92-36
          Incidental Rigging Activities      DOE-RL-
042860    (OJE)                                               N                          -
                                              92-36
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Load Charts & Load Movement                                     Must complete a site specific
                                             DOE-RL-
042327    Indicators                                          Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          Prerequisite 040784 and 042820.
                                                                          3 yr retrain period.
                                                                          Must complete a site specific
          Mobile Crane Inspection            DOE-RL-
042930                                                        Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
                                                                          Must complete a site specific
          Mobile Crane Inspection-Vendor     DOE-RL-
101010                                                        Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
          Mobile Crane (OJE)                 DOE-RL-
044710                                                        N        Complete Hanford Site specific OJE.
                                              92-36
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Mobile Crane Operation and                                      Must complete a site specific
                                             DOE-RL-
042321    Setup                                               Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Overhead Crane Electrical                                       Must complete a site specific
                                             DOE-RL-
043010    Inspection                                          Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.




                                               01150-7
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                    SECTION 01150
                             TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                            CHPRC          training
Course              Course Title                                       Comments
                                            Documents     acceptable
Number
                                                          (Yes / No)
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Overhead Crane Manual /                                         Must complete a site specific
                                             DOE-RL-
101100    Electric Hoist Inspection                           Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Overhead Crane Mechanical                                       Must complete a site specific
                                             DOE-RL-
42830     Inspection                                          Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          Prerequisite 040784.
                                                                          3 yr retrain period.
          Wire Rope/Rigging Hardware                                      Must complete a site specific
                                             DOE-RL-
042820    Inspection                                          Y            examination.
                                              92-36
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
          Fire Extinguisher Training for                                  3 yr retrain period.
          Mobile/Cab Operated Crane         PRC-RD-T                      Present journeyman card,
170661                                                        Y
          Operators                          Q-11061                       certificate of completion or
                                                                           training record.
          Facility Emergency &
          Hazardous Info Checklist –         PRC-RD-
03E500                                                        N                           -
          FEHIC                              EM-7647

                                                                          Training maintains a database of
          16-Hour Hazardous Waste                                          accepted vendors or other DOE
                                             PRC-MP-
031230    Operations – Upgrade                                Y            sites.
                                              TQ-011
                                                                        Present certificate of completion
                                                                           or training record.
          1-Day Supervised Field             PRC-MP-                   Must complete a Hanford Site field
031410    Experience                                          N
                                              TQ-011                   experience.
                                                                        Training maintains a database of
                                                                           accepted vendors or other DOE
          24-Hour Hazardous Waste Site                                     sites.
                                             PRC-MP-
031210    Worker                                              Y         Present certificate of completion
                                              TQ-011
                                                                           or training record.

                                                                       Provide site specific information.




                                               01150-8
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                            CHPRC          training
Course              Course Title                                       Comments
                                            Documents     acceptable
Number
                                                          (Yes / No)
                                                                          Training maintains a database of
          24-Hour RCRA TSD Hazardous                                       accepted vendors or other DOE
                                             PRC-MP-
031110    Waste                                               Y            sites.
                                              TQ-011
                                                                        Present certificate of completion
                                                                           or training record.
          3-Day Supervised Field             PRC-MP-                   Must complete a Hanford Site field
031420    Experience                                          N
                                              TQ-011                   experience.
                                                                        Training maintains a database of
                                                                           accepted vendors or other DOE
          40-Hour Hazardous Waste                                          sites.
                                             PRC-MP-
031220    Worker – Field                                      Y         Present certificate of completion
                                              TQ-011
                                                                           or training record.

                                                                       Provide site specific information.
                                                                        Training maintains a database of
          8-Hour Manager / Supervisor                                      accepted vendors or other DOE
                                             PRC-MP-
031310    Hazardous Waste                                     Y            sites.
                                              TQ-011
                                                                        Present certificate of completion
                                                                           or training record.
          OSHA 10-Hour Health and                                       Present certificate of completion
026100    Safety                               N/A            Y
                                                                           or training record.
                                                                        United Brotherhood of Carpenters
                                                                           class accepted; MSA Letter
          Fall Protection Personal Fall      PRC-RD-                       RML46000-09-02.
020146                                                        Y
          Arrest System (PFAS) Users         SH-8801                    Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                        3 yr retrain period.
                                                                        Labors International Union of
                                                                           North America class accepted;
                                            PRC-PRO-
044400    Fire Watch Training                                 Y            MSA Letter RML46000-09-03.
                                            FP-40421
                                                                        Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                        3 yr retrain period.
                                                                        Must complete a site specific
                                            PRC-RD-                        examination.
041886    Aerial Lift Inspection                              Y
                                            SH-10972                    Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.




                                               01150-9
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                            CHPRC          training
Course              Course Title                                       Comments
                                            Documents     acceptable
Number
                                                          (Yes / No)
                                                                          3 yr retrain period.
                                                                          United Brotherhood of Carpenters
                                                                           class accepted; MSA Letter
                                                                           RML46000-09-01.
                                            PRC-RD-
042720    Aerial Lift Operator Training                       Y           Must complete a site specific
                                            SH-10972
                                                                           examination.
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
          Class 1 Aerial Lift Self
                                             DOE-RL-
044681    Propelled Boom Supported                            N        Complete a Hanford Site specific OJE.
                                              92-36
          (OJE)
          Class 2 Aerial Lift Self           DOE-RL-
04468A                                                        N        Complete a Hanford Site specific OJE.
          Propelled Articulated (OJE)         92-36
                                                                          3 yr retrain period.
                                                                          Must complete a site specific
          Vehicle Mounted Aerial Lift        DOE-RL-                       examination.
043830                                                        Y
          Operator Class                      92-36                       Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                            PRC-RD-                       Present certificate of completion
044391    Portable Ladder Safety - CBT                        Y
                                            SH-24243                       or training record.
                                                                          United Brotherhood of
                                                                           Carpenters/Occupational Safety
                                                                           and Health Association
                                                                           Scaffolding Training class
                                            PRC-PRO-
044373    Scaffold Safety Erector/Dismnt                      Y            accepted; MSA Letter
                                             SH-095
                                                                           CPL600000-08-01.
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.
                                                                          United Brotherhood of
                                                                           Carpenters/Occupational Safety
                                                                           and Health Association
                                                                           Scaffolding Training class
                                            PRC-PRO-
044372    Scaffold Safety for Inspectors                      Y            accepted; MSA Letter
                                             SH-095
                                                                           CPL600000-08-01.
                                                                          Present journeyman card,
                                                                           certificate of completion or
                                                                           training record.




                                               01150-10
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                      SECTION 01150
                               TRAINING AND QUALIFICATIONS

                                                             Off-site
Hanford
                                              CHPRC          training
Course                Course Title                                       Comments
                                              Documents     acceptable
Number
                                                            (Yes / No)
                                                                            United Brotherhood of
                                                                             Carpenters/Occupational Safety
                                                                             and Health Association
                                                                             Scaffolding Training class
                                              PRC-PRO-
044371    Scaffold Users                                        Y            accepted; MSA Letter
                                               SH-095
                                                                             CPL600000-08-01.
                                                                            Present journeyman card,
                                                                             certificate of completion or
                                                                             training record.
                                              PRC-RD-                       Present certificate of completion
020049    Compressed Gas Cylinder Safety                        Y
                                              SH-11198                       or training record.
          LPG/Propane Gas Bottle Change       PRC-RD-
044674                                                          N                          -
          Out (OJE)                           SH-11198
                                                                            3 yr retrain period.
          OSHA Electric Cord and Power         PRC-RD-                      Present electrician license,
044480                                                          Y
          Tool Safety                          SH-7769                       journeyman card, certificate of
                                                                             completion or training record.
                                                                            Present certificate of completion
041680    Batteries                           DOE-0336          Y
                                                                             or training record.
                                              PRC-PRO-                      3 yr retrain period.
          Breaker Operation Electrical         SH-066                       Present electrician license,
043820                                                          Y
          Safety                              PRC-RD-                        journeyman card, certificate of
                                              SH-11827                       completion or training record.
                                              PRC-PRO-                      3 yr retrain period.
                                               SH-066                       Present journeyman card,
042870    Equipment Custodian Training                          Y
                                              PRC-RD-                        certificate of completion or
                                              SH-11827                       training record.
                                                                            Present electrician license,
          Equipment Operation Near            PRC-RD-
044605                                                          Y            journeyman card, certificate of
          Power Lines                         SH-28954
                                                                             completion or training record.
                                                                            3 yr retrain period.
                                              PRC-RD-                       Present electrician license,
043692    NEC – Grounding                                       Y
                                              SH-11827                       journeyman card, certificate of
                                                                             completion or training record.
                                                                            3 yr retrain period.
                                              PRC-RD-                       Present electrician license,
043694    NEC – Over Current Protection                         Y
                                              SH-11827                       journeyman card, certificate of
                                                                             completion or training record.
                                                                            3 yr retrain period.
                                              PRC-RD-                       Present electrician license,
043696    NEC – Wiring Methods                                  Y
                                              SH-11827                       journeyman card, certificate of
                                                                             completion or training record.




                                                 01150-11
                                       Requisition Number: 246168
                           Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                Date: 5-4-12
                                    SECTION 01150
                             TRAINING AND QUALIFICATIONS

                                                          Off-site
Hanford
                                           CHPRC          training
Course              Course Title                                      Comments
                                           Documents     acceptable
Number
                                                         (Yes / No)
                                                                         International Brotherhood of
                                                                          Electrical Workers class accepted;
          NFPA-70E Standards for           PRC-RD-                        MSA Letter RML46000-09-06.
043870                                                       Y
          Electrical Safety                SH-11827                      Present electrician license,
                                                                          journeyman card, certificate of
                                                                          completion or training record.
                                                                         Labors International Union of
                                                                          North America class accepted;
                                                                          MSA Letter RML46000-09-04.
                                                                         International Union of Operating
          Basic Medic First Aid/            PRC-RD-
170500                                                       Y            Engineers class accepted; MSA
          CPR/AED                           SH-7769
                                                                          Letter RML46000-09-05.
                                                                         Present journeyman card,
                                                                          certificate of completion or
                                                                          training record.
                                                                         SMART MARK class accepted;
                                                                          MSA Letter CPL600000-08-04.
          Fall Hazard Recognition and       PRC-RD-
020147                                                       Y           Present journeyman card,
          Prevention                        SH-8801
                                                                          certificate of completion or
                                                                          training record.
                                           PRC-RD-
                                                                         1 yr retrain period.
                                           SH-15097
02006L    Asbestos Awareness                                 Y           Present certificate of completion
                                           PRC-RD-
                                                                          or training record.
                                           SH-15245
                                                                         1 yr retrain period.
                                           PRC-RD-
020194    Hearing Conservation
                                           SH-11812
                                                             Y           Present certificate of completion
                                                                          or training record.
                                                                         2 yr retrain period.
                                           PRC-PRO-
020193    Heat Stress Training – CBT                         Y           Present certificate of completion
                                            SH-121
                                                                          or training record.
                                                                         1 yr retrain period.
          Air Purifying Respirator (APR)   PRC-PRO-                      Present certificate of completion
02I062                                                       Y
          Initial – Standalone              SH-120                        or training record.
                                                                         Medical clearance through CSC.
                                                                         1 yr retrain period.
                                           PRC-PRO-                      Present certificate of completion
020510    MSA Hood - PAPR Initial                            Y
                                            SH-120                        or training record.
                                                                         Medical clearance through CSC.
                                                                         1 yr retrain period.
          MSA PAPR (Full Facepiece)        PRC-PRO-                      Present certificate of completion
020035                                                       Y
          Initial                           SH-120                        or training record.
                                                                         Medical clearance through CSC.




                                              01150-12
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                            CHPRC          training
Course              Course Title                                       Comments
                                            Documents     acceptable
Number
                                                          (Yes / No)
                                                                          1 yr retrain period.
          PAPR (Hood) Initial –             PRC-PRO-                      Present certificate of completion
02I510                                                        Y
          Standalone                         SH-120                        or training record.
                                                                          Medical clearance through CSC.
                                                                          1 yr retrain period.
          Respiratory Knowledge-Based       PRC-PRO-                      Present journeyman card,
020066                                                        Y
          Initial                            SH-120                        certificate of completion or
                                                                           training record.
                                                                          1 yr retrain period.
                                                                          Prerequisite 020066
                                            PRC-PRO-
020044    Quantitative Mask Fit
                                             SH-120
                                                              Y           Present certificate of completion
                                                                           or training record.
                                                                          Medical clearance through CSC.
                                                                          1 yr retrain period.
                                            PRC-PRO-                      Present certificate of completion
020041    Respiratory Protection Initial                      Y
                                             SH-120                        or training record.
                                                                          Medical clearance through CSC.
                                             PRC-RD-
170648    Bloodborne Pathogens – Initial                      N
                                             SH-7769
                                                                          1 yr retrain period.
                                            PRC-RD-
020130    Confined Space Entry                                Y           Present certificate of completion
                                            SH-11258
                                                                           or training record.
                                                                          1 yr retrain period.
                                                                          Prerequisite 020066.
                                            PRC-PRO-
020030    SCBA Initial Training                               Y           Present certificate of completion
                                             SH-120
                                                                           or training record.
                                                                          Medical clearance through CSC.
                                                                          1 yr retrain period.
                                                                          Prerequisite 020066.
                                            PRC-PRO-
02I030    SCBA Initial Training                               Y           Present certificate of completion
                                             SH-120
                                                                           or training record.
                                                                          Medical clearance through CSC.
                                                                          1 yr retrain period.
                                                                          Prerequisite 020066.
          Scott SKA-PAK Airline System      PRC-PRO-
020032                                                        Y           Present certificate of completion
          – Initial                          SH-120
                                                                           or training record.
                                                                          Medical clearance through CSC.
                                                                          1 yr retrain period.
                                                                          Prerequisite 020066.
          Scott SKA-PAK Airline System      PRC-PRO-
02I032                                                        Y           Present certificate of completion
          – Initial                          SH-120
                                                                           or training record.
                                                                          Medical clearance through CSC.




                                               01150-13
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                     SECTION 01150
                              TRAINING AND QUALIFICATIONS

                                                           Off-site
Hanford
                                             CHPRC         training
Course               Course Title                                      Comments
                                             Documents    acceptable
Number
                                                          (Yes / No)
                                                                          3 yr retrain period.
 042730    Flagging and Traffic Control
                                             PRC-RD-
                                                              Y           Present journeyman card,
                                             SH-9237                       certificate of completion or
                                                                           training record.
           Hanford Site Lockout/Tagout for
 00310I    Controlling Organization –        DOE-0336         N                           -
           Initial
           Hanford Site Lockout/Tagout for
 00310R    Controlling Organization –        DOE-0336         N                           -
           Retraining
           Hanford Site Lockout/Tagout for
 00311I                                      DOE-0336         N                           -
           Authorized Worker – Initial
           Hanford Site Lockout/Tagout for
 00311R                                      DOE-0336         N                           -
           Authorized Worker - Retraining
           Spotter Training for Electrical   PRC-RD-                      Present certificate of completion
 044606                                                       Y
           Hazards                           SH-11827                      or training record.
           Beryllium Associate Worker –      PRC-PRO-
 004104                                                       N                           -
           CBT                                SH-6155

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

Not Used

                                          END OF SECTION




                                               01150-14
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                    SECTION 01200
                                  PROJECT MEETINGS

PART 1 – GENERAL

1.1     SUMMARY

1.1.1   General purposes of conferences and meetings addressed in this Section are
        coordination, control, and direction of the Work. In addition to meetings addressed
        by this Section, Contractor may be required by other Sections and other Contract
        documents to conduct special-purpose meetings and various safety meetings and
        briefings.

1.1.2   CHPRC will issue meeting notices and prepare an agenda and minutes for each
        conference and meeting addressed in this Section. When applicable, minutes will
        identify action items, assigned actionees, and due dates.

1.2     SITE LABOR CONFERENCE

1.2.1   Before start of Work, the Contractor shall conduct a site labor conference in
        accordance with the Site Stabilization Agreement (Article X, Section 6) at a time and
        Hanford Site location agreed upon by the Contractor and the Labor Organization
        representatives.

1.2.2   Invited attendees shall include CHPRC, Contractor, subcontractors, Labor
        Organizations representing utilized crafts, and others having an interest in Hanford
        Site labor requirements.

1.2.3   Purpose of the conference is familiarization of project participants with Hanford Site
        labor requirements. The conference shall last approximately one hour and shall
        include a presentation by the Contractor of the proposed craft utilization and work
        plan.

1.3     PRECONSTRUCTION CONFERENCE

1.3.1   After contract award, the Contractor shall participate in a Project Kickoff Meeting to
        be held at CHPRC’s Site. The time, date, and location of the meeting will be provided
        to the Contractor by CHPRC.

1.3.2   Invited attendees will include CHPRC, Contractor, subcontractors and others having
        an interest in the Work

1.3.3   Purpose of the conference is the coordination of Work startup and familiarization of
        project participants with the Work and worksite. The conference will last
        approximately two (2) hours and will include the following agenda.

        a.   Certified payrolls

                                           01200-1
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                             SECTION 01200
                           PROJECT MEETINGS

b.   Construction Progress Meetings

c.   Forms required by the Contract. CHPRC will provide reproducible masters

         Construction Daily Activity Report (A-6004-822)
         Work Release for Construction Service Organization (A-6004-967)
         CHPRC – Change Form (A-6004-820)
         Chemical Inventory Worksheet (A-6004-750)
         CHPRC Contractor Document Submittal Form (A-6004-757)
         Request for Clarification or Information (RCI) (A-6004-833)
         Craft-Specific Job Safety Analysis/Position Hazard Analysis (K-1
          JSA/PHA) (A-6004-783)
         Job Safety Analysis/Activity Hazard Analysis (K-2 JSA/AHA)
          (A-6004-784)
         Task-Specific Job Safety Analysis (K-3 JSA) (A-6004-785)

         Significant Discharge Log (A-6002-294)

         RO/RO Container Pre-Use Inspection Form (A-6005-661)

         PRC ERDF Container Verification Data Sheet (A-6005-414)

         Fall Protection Work Permit (A-6004-286)

d.   Material and equipment lists

e.   Points of contact and key personnel representing the Contractor and CHPRC.
     Areas covered will include safety, quality assurance and quality control, Price
     Anderson Amendment Act (PAAA), acceptance inspection, and construction
     engineering

f.   Quality requirements

g.   Report requirements

h.   Safety

i.   Schedule requirements, schedule constraints, and work limitations

j.   Submittals

                                    01200-2
                          Requisition Number: 246168
              Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                   Date: 5-4-12
                                      SECTION 01200
                                    PROJECT MEETINGS

1.4        CONSTRUCTION PROGRESS MEETINGS

1.4.1      Every week, CHPRC will conduct a progress meeting at time and Hanford Site
           location determined during the Preconstruction Conference.

1.4.2      Invited attendees will include CHPRC, Contractor, and subcontractor representatives.
           Attendance by the Construction Superintendent or Contractor Project Manager is
           required.

1.4.3      The purpose of the meetings is the exchange of Work-related information. Average
           meeting will last approximately 1 hour and will include the following agenda items:

           a.   Safety
           b.   Quality Assurance
           c.   Progress
           d.   Submittal Status
           e.   Schedule, Cost and Construction Status
           f.   Requests For Information – Status
           g.   Design and Scope Changes
           h.   Material and Equipment Status
           i.   Problem Areas

1.4.4      Contractor to provide six (6) copies of 3-week look-ahead schedule for review during
           the meeting. Refer to Section 01315 for level of detail required on 3-week look-
           ahead schedule.

1.4.5      In addition, the Contractor shall provide CHPRC with a Daily Activity Report
           identifying the work performed for the day; craft, supervision, and subcontractor
           manpower; problems, issues, or delays; safety, etc. Daily Activity Report shall be
           provided to CHPRC by 8:00 am each work day documenting the previous work day’s
           activities.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used


                                       END OF SECTION



                                             01200-3
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                      SECTION 01300
                                       SUBMITTALS

PART 1 – GENERAL

1.1     SUMMARY

        This Section provides the general procedures and requirements for preparing and
        processing submittals. Required submittals are identified in other Specification
        sections, other Contract sections, and CHPRC OS/IH Manual. Required submittals
        are also summarized by CHPRC on the Master Submittal Register. The submittal
        register may not be all-inclusive, and identifies documents required with proposal
        submittal, post-award / prior to Notice-To-Proceed (NTP), and post NTP.

1.1.1    Submittals will be considered valid for all contract releases unless a contract release
        specifically stipulates otherwise, or until changes occur that would invalidate the
        submittal.

1.1.2   Requests for substitutions are prepared in accordance with Section 01630 and
        processed in accordance with this Section. Deliverable documents differ from
        submittals and are processed in accordance with Section 01720. Deliverable
        documents are Quality Assurance documents and are required by technical sections of
        the Specification.

1.2     CLARIFICATIONS

1.2.1   Contract documents take precedence if a conflict exists between Contract documents
        and the submittal register. Immediately notify CHPRC of discrepancies in the
        submittal register.

1.2.2   Approval of a specific item does not constitute approval of a system or assembly of
        which an item is a component.

1.2.3   Materials and equipment that differ from approved submittals are subject to rejection
        and replacement at Contractor’s expense.

1.2.4   Delays arising from failure to provide required submittals in a timely manner will not
        constitute excusable delays for extension.

1.2.5   Standard processing time of submittals by CHPRC is under 2 weeks and is measured
        from date of submittal’s receipt by CHPRC to date of return mailing.

1.3     SUBMITTAL BY CONTRACTOR

1.3.1   The Contractor submittals identified herein on the submittal register shall be
        submitted to CHPRC EPC Document Control by the Contractor using the Contractor
        Document Submittal (A-6004-757) (available at

                                           01300-1
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                         SECTION 01300
                                          SUBMITTALS

           http://www.plateauremediation.hanford.gov/index.php/page/10/). Instructions for
           completion of the submittal are included with the form.

1.3.2      The quantity, frequency, and type of submittal shall agree with the requirements set
           forth on the submittal register. The submittal number shall be entered on the
           submittal form by the Contractor in accordance with the submittal register. This
           number is used to identify each submittal.

1.3.3      When any submittal is returned to the Contractor with a request to resubmit (i.e.,
           marked as: “B-yes” “Minor Comments – Approved With Exceptions as Corrected
           Re-submittal Required”; or “C” “Not Approved Revise and Resubmit”) the
           Contractor shall resubmit all corrected documents within the time specified on the
           returned submittal form, or if no time is specified, within 5 working days from the
           disposition date.

1.3.4      Contact the Contract Specialist if additional submittal numbers are required.

1.3.5      Changes to a Contractor’s deliverables that have not been accepted by CHPRC as
           complete shall be re-submitted using the submittal form and in accordance with the
           Contractor’s CHPRC-approved Quality Assurance Program.

1.4        MASTER SUBMITTAL REGISTER

1.4.1      Required submittals are listed in the Master Submittal Register in Section 1300A.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used


                                        END OF SECTION




                                              01300-2
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                                              SECTION 01300A
                                                        MASTER SUBMITTAL REGISTER

               The Contractor shall meet the required schedule and provide the documents specified in accordance with the
               following submittals.
Contract Number and Name:                                                                                   Revision:
   1               2              3           4                              5                       6                    7           8             9
                                                                                                                                   CHPRC
                                                                                                                                                Contract
                                                                                              Submittal Due         Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                            Paragraph or
 No.                                                        Description / Document Title        (Calendar            Approver       Time
             Copies, Format   Submittal   Information                                                                                         Requirement
                                                                                                  Days)            Organizations   (Work
                                                                                                                                               Reference
                                                                                                                                    Days)
                                                          105KE SSE Construction SOW Sections
                                                        Individual responsible for receiving
   1     INF,1E,MFC                                                                          BSW                 BTR/ENG           3        01036/1.2.3
                                                        changes
   2     INF,1,PDF                                      Professional Land Surveyor License    BSW                ENG               5        01050/1.2.2
                                                        Safety and Health Program, or use
   3     AP1E,MFC                                                                             w/ Proposal        Safety            7        01110/1.2.2.1
                                                        CHPRC
   4     INF,1E,MFC                                     Designated Safety Representative      BSW                Safety            3        01110/1.2.2.2
   5     AP,1E,MFC                                      JSA/JHA                               BSW                Safety            5        01110/1.2.2.3
   6     APW,1E,MFC             Yes                     Critical Lift Plan                    BSW                Safety            7        01110/1.2.2.4
                                                        Task-Specific Job Safety Analysis -
   7     APW,1E,MFC                                                                           BSW                Safety/ENG        7        01110/1.2.2.5
                                                        Structural Steel Erection
   8     INF,1E,MFC                                     EJTA                                  BSW                Safety            7        01110/1.2.2.6
   9     AP,IE,MFC                                      Waste Mgmt Information                BSW                Env               5        01130/1.2.2.1
  10     AP,1E,PDF                                      MSDS                                  BSW                Env               5        01130/1.2.2.2
  11     AP,1E,MFC                                      Chemical Sources                      10d BSW            Env               3        01130/1.2.2.3
  12     AP,1E,MFC                                      Chemical Inventory                    10d BSW            Env               5        01130/1.2.2.4
  13     AP,1E,MFC                                      Air Emissions                         /BSW               Env               3        01130/1.2.2.5
  14     AP,1E,MFC                                      Dust Control Plan                     /BSW               Env               5        01130/1.2.2.6


                                                                             01300A-1
                                                              Requisition Number: 246168
                                                  Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                       Date: 5-4-12
                                                              SECTION 01300A
                                                        MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                    Revision:
   1                2            3            4                            5                           6                   7           8             9
                                                                                                                                    CHPRC
                                                                                                                                                 Contract
                                                                                               Submittal Due         Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                             Paragraph or
 No.                                                        Description / Document Title         (Calendar            Approver       Time
             Copies, Format   Submittal   Information                                                                                          Requirement
                                                                                                   Days)            Organizations   (Work
                                                                                                                                                Reference
                                                                                                                                     Days)
  15     APW,1E,MFC                                     Radioactive Sources                    4d BSW             RadCon            3        01130/1.2.2.7
  16     AP,1E,MFC                                      Waste Reduction Plan                   BSW                Env               5        01130/1.2.2.8
  17     AP,1E,MFC                                      Completion of Training Certification   BSW                CM/Safety         5        01150/1.2.2.1
  18     INF,1E,PDF                                     Hoisting & Rigging OJE                 BSW                Safety            5        01150/1.2.3.1
  19     INF,1E,MFC                                     Competent/Qualified Persons            BSW                Safety            3        01150/1.2.3.2
  20     AP,1E,P6                                       Startup Project Schedule               A+10d              BTR/PM            5        01315/1.2.2.1
  21     AP,1E,P6                                       Project Schedule                       A+30d              BTR/PM            5        01315/1.2.2.2
  22     AP,1E,P6                                       Cost Baseline by WBS                   w/ Proposal        BTR/PM            3        01315/1.2.2.3
  23     AP,1E,P6                                       Critical Path Schedule                 w/ Proposal        BTR/PM            5        01315/1.2.2.4
  24     AP,1E,GEN                                      Weekly Work Schedules                  Weekly             BTR/PM            3        01315/1.2.2.5
  25     AP,1E,P6                                       Revised Schedules                      As Required        BTR/PM            5        01315/1.2.2.6
  26     AP,1E,PDF                                      Downtime/Delay Reports                 As Required        BTR/PM            3        01315/1.2.2.7
  27     INF1E,MFC                                      Weekly Status Reports                  Weekly             BTR/PM            3        01315/1.2.3.1
  28     INF,1E,MFC                                     Monthly Progress Reports               A+60d,Monthly      BTR/PM            5        01315/1.2.3.2
  29     INF,1E,MFC                                     Weekly Labor Cost Reports              Weekly             BTR/PM            5        01315/1.2.3.3
  30     AP,1E,MFC                                      Quality Assurance Plan                 w/ Proposal        QA                7        01400/1.2.2.1
  31     AP,1E,MFC                                      Quality Assurance Inspection Plan      w/ Proposal        QA                7        01400/1.2.2.2
  32     INF,1E,PDF                                     Item Stmt "genuine, new, unused"       w/Proposal         QA                3        01400/1.2.3.1


                                                                           01300A-2
                                                              Requisition Number: 246168
                                                  Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                       Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                   Revision:
   1               2             3              4                         5                           6                 7              8             9
                                                                                                                                   CHPRC
                                                                                                                                                 Contract
                                                                                               Submittal Due        Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                             Paragraph or
 No.                                                        Description / Document Title         (Calendar           Approver        Time
             Copies, Format   Submittal   Information                                                                                          Requirement
                                                                                                   Days)           Organizations    (Work
                                                                                                                                                Reference
                                                                                                                                     Days)
  33     AP,1E,MFC                                      Formal NCR Punchlist                  Job Completion     QA                5         01400/1.2.3.2
  34     AP1E,DWG                                       Work Area Layout                      BSW                BTR/CM            5         01500/1.2.2.1
  35     INF1E,PDF                                      Equipment Information                 BSW                CM                5         01500/1.2.2.2
  36     APW,1E,MFC                                     Radiological Equipment List           BSW                CM/RadCon         5         01500/1.2.2.3
  37     AP,1E,MFC                                      Filler Metal Control Procedure        BSW                ENG/QA            7         01610/1.4.5
  38     APW,1E,MFC                                     Substitution Approval Request         As Required        BTR/ENG           5         01630/1.1.2.1
  39     APW,1E,MFC             Yes                     Construction Acceptance Test          BSW                ENG/QA/CM         7         01670/1.3.2
                                                         105KE ISS Technical Specification Sections
  40     AP,1E,PDF                        Yes           Product Data – Concrete                                  ENG                   5     033000/1.2A
  41     APW,1E,PDF             Yes                     Design Mixtures                                          ENG                   5     033000/1.2B
  42     APW,1E,DWG             Yes       Yes           Shop Drawings Steel Reinf.                               ENG                   5     033000/1.2C
  43     INF,1E,PDF                                     Manufacturer's Qualifications                            ENG                   5     033000/1.2D
                                                        Concrete Testing Agency's                                ENG
  44     INF,1E,PDF                                                                                                                    5     033000/1.2E
                                                        Qualifications
  45     INF,1E,PDF             Yes       Yes           Material Certificates                                    ENG                   5     033000/1.3A
  46     INF,1E,PDF              Yes                    Material Test Reports                                    ENG                   5     033000/1.3B
                                                        Field Quality Control Reports-                           ENG/QA
  47     AP,1E,PDF                                                                                                                     5     033000/1.3C
                                                        Concrete
  48     AP,1E,PDF                                      Field Quality Control Reports from                       ENG/QA                5     033000/1.3D


                                                                          01300A-3
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                 Revision:
   1               2             3              4                          5                         6                7             8            9
                                                                                                                                 CHPRC
                                                                                                                                              Contract
                                                                                               Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                          Paragraph or
 No.                                                        Description / Document Title         (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                       Requirement
                                                                                                   Days)         Organizations   (Work
                                                                                                                                             Reference
                                                                                                                                  Days)
                                                        Test Agency

  49     INF,1E,MFC/PDF                                 Conveying Equipment Info                               ENG                 5      033000/1.3E
  50     INF,1E,PDF                                     Temperature Measurements                               ENG                 5      033000/1.3F
  51     AP,1E,MFC                                      Hot and Cold Concreting Procedures                     ENG                 5      033000/1.3G
  52     AP,1E,PDF                        Yes           Product Data - Structural Steel                        ENG                 5      051200/1.4A
                                                        Shop Drawings – Structural Steel                       ENG
  53     APW,1E,DWG             Yes       Yes                                                                                      5      051200/1.4B
                                                        Fabrication and Erection
                                                                                                               ENG
                                                                                                                                          051200/1.4C
                                                        Welding Procedure Specs, Welder
                                                                                                                                          055000/1.2C
  54     APW,1E,MFC/PDF                                 Performance Qual Records,                                                  5
                                                                                                                                          055100/1.2D
                                                        Procedure Qualification Records
                                                                                                                                          055213/1.2C

  55     INF,1E,PDF                                     Professional Engineer Qualifications                   ENG                 5      051200/1.4D
                                                                                                               ENG                        051200/1.4E
  56     INF,1E,PDF                                     Installer Qualifications                                                   5
                                                                                                                                          055000/1.2D
                                                                                                               ENG                        051200/1.4F
  57     INF,1E,PDF                                     Fabricator Qualifications                                                  5
                                                                                                                                          055000/1.2E
                                                                                                               ENG/QA                     051200/1.4G
                                                        Str Steel Testing Agency's                                                        055000/1.2F
  58     INF,1E,PDF                                                                                                                5
                                                        Qualifications                                                                    055100/1.2C
                                                                                                                                          055213/1.3A



                                                                           01300A-4
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                 Revision:
   1               2             3              4                         5                          6                7             8            9
                                                                                                                                 CHPRC
                                                                                                                                              Contract
                                                                                               Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                          Paragraph or
 No.                                                        Description / Document Title         (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                       Requirement
                                                                                                   Days)         Organizations   (Work
                                                                                                                                             Reference
                                                                                                                                  Days)
                                                                                                               ENG/QA                     051200/1.4H
  59     APW,1E,MFC                                     Welding Inspection Plan                                                    5
                                                                                                                                          055000/1.2G
                                                                                                                                          051200/1.4I
  60     APW,1E,MFC                                     NDE Procedures and Techniques                          ENG/QA              5
                                                                                                                                          055000/1.2H
  61     APW,1E,MFC                                     Grout Plan                                             ENG                 5      051200/1.4J
  62     AP,1E,PDF                                      Delegated-Design Analysis Data                         ENG                 5      051200/1.4K
                                                                                                                                          051200/1.4L
  63     INF,1E,MFC                                     Identification Markings                                ENG                 5
                                                                                                                                          055000/1.3A
  64     INF,1E,PDF                       Yes           Warranty of Quality Document                           ENG/QA              5      051200/1.5A
                                                                                                               ENG/QA                     051200/1.5B
  65     INF,1E,PDF                                     Mill Test Reports for Str Steel                                            5
                                                                                                                                          055100/1.3A
  66     INF,1E,PDF                                     Product Test Reports - Str. Steel                      ENG/QA              5      051200/1.5C
                                                                                                               ENG/QA                     051200/1.5D
  67     INF,1E,PDF                                     Source Quality Control Reports                                             5
                                                                                                                                          055100/1.3B
                                                                                                               ENG/QA                     051200/1.5E
                                                        Field Quality Control Reports - Str
  68     INF,1E,PDF                                                                                                                5      055100/1.3C
                                                        Steel
                                                                                                                                          055213/1.3C
                                                        Minutes of Preinstallation                             ENG
  69     INF,1E,MFC                                                                                                                5      051200/1.5F
                                                        Conference
  70     AP,1E,PDF                        Yes           Product Data - Metal Framing                           ENG                 5      054000/1.2A



                                                                          01300A-5
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                 Revision:
   1               2             3              4                         5                          6                7             8            9
                                                                                                                                 CHPRC
                                                                                                                                              Contract
                                                                                               Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                          Paragraph or
 No.                                                        Description / Document Title         (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                       Requirement
                                                                                                   Days)         Organizations   (Work
                                                                                                                                             Reference
                                                                                                                                  Days)
  71     AP,1E,DWG              Yes       Yes           Shop Drawings - Metal Framing                          ENG                 5      054000/1.2B
                                                        Product Test Reports - Metal                           ENG
  72     INF,1E,PDF                                                                                                                5      054000/1.3A
                                                        Framing
  73     AP,1E,PDF                        Yes           Product Data - Paint/Grout                             ENG                 5      055000/1.2A
  74     AP,1E,DWG              Yes       Yes           Shop Drawings - Metal Fabrication                      ENG                 5      055000/1.2B
  75     INF,1E,PDF                                     Field Quality Control Test Results                     ENG/QA              5      055000/3.4
  76     AP,1E,PDF                        Yes           Product Data - Metal Stairs                            ENG                 5      055100/1.2A
  77     AP,1E,DWG              Yes       Yes           Shop Drawings - Metal Stairs                           ENG                 5      055100/1.2B
                                                        Product Data -                                         ENG
  78     AP,1E,PDF                        Yes                                                                                      5      055213/1.2A
                                                        Railings/Grout/AnchorCement/Paint
  79     AP,1E,DWG               Yes      Yes           Shop Drawings – Railings                               ENG                 5      055213/1.2B
  80     AP,1E,PDF                        Yes           Product Data - Thermal Insulation                      ENG                 5      072100/1.2A
                                                        Product Test Reports - Thermal                         ENG/QA
  81     INF,1E,PDF                                                                                                                5      072100/1.3A
                                                        Insulation
                                                        Research/Evaluation Reports -                          ENG
  82     INF,1E,PDF                                                                                                                5      072100/1.3B
                                                        Thermal Insulation
  83     AP,1E,PDF                        Yes           Product Data - Roof Panels                             ENG                 5      074113/1.3A
  84     AP,1E,DWG              Yes       Yes           Shop Drawings - Roof Panels                            ENG                 5      074113/1.3B
  85     AP                                             Samples - Roof Panel Exposed Finish                    ENG                 5      074113/1.3C
  86     INF,1E,DWG                                     Coordination Drawings - Roof Plans                     ENG                 5      074113/1.4A


                                                                          01300A-6
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                 Revision:
   1               2             3              4                        5                           6                7             8            9
                                                                                                                                 CHPRC
                                                                                                                                              Contract
                                                                                               Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                          Paragraph or
 No.                                                        Description / Document Title         (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                       Requirement
                                                                                                   Days)         Organizations   (Work
                                                                                                                                             Reference
                                                                                                                                  Days)
  87     INF,1E,PDF                                     Product Test Reports - Roof Panels                     ENG/QA              5      074113/1.4B
                                                        Field Quality Control Reports - Roof                   ENG/QA
  88     INF,1E,PDF                                                                                                                5      074113/1.4C
                                                        Panel
                                                        Warranties - Sample of Special                         ENG
  89     INF,1E,PDF                       Yes                                                                                      5      074113/1.4D
                                                        Warranties
  90     INF,1E,PDF                       Yes           Maintenance Data - Roof Panels                         ENG                 5      074113/1.5A
  91     AP,1E.PDF                        Yes           Product Data - Wall Panels                             ENG                 5      074213/1.3A
  92     AP,1E.DWG              Yes       Yes           Shop Drawings - Wall Panels                            ENG                 5      074213/1.3B
  93     AP                                             Samples - Wall Panel Exposed Finish                    ENG                 5      074213/1.3C
  94     INF,1E,DWG                                     Coordination Drawings - Wall Panels                    ENG                 5      074213/1/4A
  95     INF,1E,PDF                                     Product Test Reports - Wall Panels                     ENG/QA              5      074213/1.4B
                                                        Warranties - Sample of Special                         ENG
  96     INF,1E,PDF                       Yes                                                                                      5      074213/1.4C
                                                        Warranties
  97     INF,1E,PDF                       Yes           Maintenance Data - Wall Panels                         ENG                 5      074213/1.5A
  98     AP,1E,PDF                        Yes           Product Data - Flashing/Trim                           ENG                 5      076200/1.2A
  99     AP,1E,DWG               Yes      Yes           Shop Drawings - Flashing/Trim                          ENG                 5      076200/1.2B
 100     AP                                             Samples - Flashing/Trim                                ENG                 5      076200/1.2C
                                                        Warranties - Sample of Special                         ENG
 101     INF,1E,PDF                       Yes                                                                                      5      076200/1.3A
                                                        Warranties
 102     INF,1E,PDF                           Yes       Maintenance Data - Flashing/Trim                       ENG                 5      076200/1.4A



                                                                         01300A-7
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                  Revision:
   1               2             3              4                         5                          6                 7             8            9
                                                                                                                                  CHPRC
                                                                                                                                               Contract
                                                                                                Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                           Paragraph or
 No.                                                        Description / Document Title          (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                        Requirement
                                                                                                    Days)         Organizations   (Work
                                                                                                                                              Reference
                                                                                                                                   Days)
 103     AP,1E,PDF                        Yes           Product Data - Joint Sealants                           ENG               5        079200/1.2A
 104     AP,1E,PDF                                      Joint Sealant Schedule                                  ENG               5        079200/1.2B
 105     INF,1E,PDF                                     Product Test Reports - Joint Sealants                   ENG/QA            5        079200/1.3A
 106     INF,1E,PDF                       Yes           Warranties                                              ENG               5        079200/1.3B
                                                        Product Data - Hollow Metal                             ENG
 107     AP,1E,PDF                        Yes                                                                                     5        081113/1.3A
                                                        Door/Frame
                                                        Shop Drawings - Hollow Mtl                              ENG
 108     AP,1E,DWG            Yes         Yes                                                                                     5        081113/1.3B
                                                        Door/Frame
 109     AP,1E,PDF                                      Hollow Metal Door/Frame Schedule                        ENG               5        081113/1.3C
 110     AP,1E,PDF                        Yes           Product Data - Door Hardware                            ENG               5        087100/1.2A
 111     AP,1E,PDF                                      Schedule - Door Hardware                                ENG               5        087100/1.2B
 112     AP,1E,PDF                                      Schedule – Keying                                       ENG               5        087100/1.2B
                                                        Warranties - Copy of Manuf                              ENG
 113     INF,1E,PDF                       Yes                                                                                     5        087100/1.5A
                                                        Warranty
 114     AP,1E,PDF                        Yes           Product Data – Painting                                 ENG               5        099113/1.3A
 115     AP                                             Samples – Paint                                         ENG               5        099113/1.3B
 116     AP,1E,MFC                                      Product List – Painting                                 ENG               5        099113/1.3C
 117     N/A                                            Extra Paint-5% or >1gal of ea                           ENG               N/A      099113/1.4A
 118     AP,1E,PDF                        Yes           Product Data – Signage                                  ENG               5        101400/1.2A
 119     AP,1E,DWG            Yes         Yes           Shop Drawings – Signs                                   ENG               5        101400/1.2B


                                                                          01300A-8
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                               SECTION 01300A
                                                         MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                                  Revision:
   1               2             3              4                         5                          6                 7             8            9
                                                                                                                                  CHPRC
                                                                                                                                               Contract
                                                                                                Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                           Paragraph or
 No.                                                        Description / Document Title          (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                        Requirement
                                                                                                    Days)         Organizations   (Work
                                                                                                                                              Reference
                                                                                                                                   Days)
 120     AP,1E,PDF                                      Samples – Signs                                         ENG               5        101400/1.2C
                                                        Equipment Used for Panel                                ENG
 121     INF,1E,MFC                                     Fabrication (if not on Material/Parts                                     5        275125/1.5A
                                                        List)
                                                                                                                ENG
                                                        Original Product Data
                                                        - Manuals from Manufacturer
 122     AP,1E,PDF                        Yes                                                                                     5        275125/1.5B
                                                        - Maintenance Requirements & Plan
                                                        - Spare Parts List

 123     INF,1E,PDF                       Yes           Warranty Information                                    ENG               5        275125/1.5C
 124      AP,1,DWG            Yes                       Red-Lined Drawings                      EC              ENG               7        275125/1.5D
                                                        Supplier's Statement of Genuine
 125     INF,1E,PDF                       Yes                                                                   ENG               5        275125/1.5E
                                                        Materials
 126     AP,1E,MFC                                      Quality Control Inspection Plan                         ENG/QA            5        275125/3.5A

                                                        Material Information
                                                        - Lab Report
                                                        - Test Reports Max Dry Density
                                                        - Test Reports Top Course
 127     AP,1E,PDF            Yes                                                                               ENG/QA            5        312000/1.2A
                                                        - Test Reports Base Course
                                                        - Mix Design, Control Density Fill
                                                        - Tested Strengths, CDF
                                                        - Bedding Course Material

 128     APW,1E,MFC                                     Excavation/Shoring Safety Plan                          ENG/Safety        5        312000/1.2B


                                                                          01300A-9
                                                                Requisition Number: 246168
                                                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                         Date: 5-4-12
                                                              SECTION 01300A
                                                        MASTER SUBMITTAL REGISTER

Contract Number and Name:                                                                               Revision:
   1               2             3            4                          5                         6                7             8            9
                                                                                                                               CHPRC
                                                                                                                                            Contract
                                                                                             Submittal Due      Reviewer/      Review
            Type, Number of   Technical     Vendor                                                                                        Paragraph or
 No.                                                        Description / Document Title       (Calendar         Approver       Time
             Copies, Format   Submittal   Information                                                                                     Requirement
                                                                                                 Days)         Organizations   (Work
                                                                                                                                           Reference
                                                                                                                                Days)
                                                        Excavation/Shoring Safety Plan >20
 129     APW,1E,MFC                                                                                          ENG               5        312000/1.2C
                                                        Ft
                                                        Field Quality Control Reports
                                                        - Trip Tickets for CDF
 130     INF,1E,PDF           Yes                                                                            ENG/QA            5        312000/1.3A
                                                        - Compaction Test Reports for
                                                        Subgrade
                                                                 END OF SUBMITTALS

   1. Typically a numerical sequence (i.e., 1, 2, 3). However, other numbering systems may also be used.
   2. Submittal type, number of copies and format:
         APW =          Approval Required Prior to Work (CHPRC must approve the Contractor’s submittal prior to the Contractor being
         authorized to proceed with any activity/work associated with the submittal).
         AP = Approval Required (CHPRC must approve the Contractor’s submittal. However, work associated with the submittal may
         proceed prior to CHPRC approval).
         Format: Describes the type of submittal required (electronic or printed):
         DWG An AutoCAD (Version 2011) drawing using the Hanford standard formatting (see CHPRC-00263, Off-Site Vendor
         Instructions for the Preparation and Control of Engineering Drawing)
         MFC Microsoft Format Compatible application (Word, Excel, Access, PowerPoint)
         P6      A Primavera Project Planner schedule
         GEN General or Open Format/Media
         PDF Adobe Acrobat (Portable Document Format)




                                                                        01300A-10
                                                              Requisition Number: 246168
                                                  Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                       Date: 5-4-12
                                                        SECTION 01300A
                                                  MASTER SUBMITTAL REGISTER

3. Technical submittals are Engineering or Quality affecting submittals. A Yes in this column designates the need for formalized
   comments, and a formalized comment disposition process by the Contractor. Examples of Technical Submittals would include
   Engineering or Fabrication Drawings, or Certificates of Conformance.
4. Vendor information is for project record purposes.
5. Description / Document Title. Describe submittal.
6. Required submittal date or its relationship to project milestones. Per detailed construction execution schedule, unless noted otherwise.
   Examples are July 14, 2009, or Award + 15 days, Contract Completion +30 days.
      A              Date of Award
      BSW            Before Start of Work
      M              Mobilization
      SC             Start of Construction
      EC             End of Construction
7. Approver Organization. Examples are Construction Manager, Safety, Quality, Radiation Protection, Waste Management.
8. The number of Work Days required for review of the submittal.
9. Contract Reference: Cross reference to the Contract requirement that defines this submittal: SOW 5.1




                                                                  01300A-11
                                                         Requisition Number: 246168
                                             Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                                  Date: 5-4-12
                                SECTION 01315
                    PROJECT SCHEDULES, PROJECT CONTROLS,
                    AND PROJECT PERFORMANCE MILESTONES

PART 1 – GENERAL

1.1       SCHEDULES

1.1.1     Schedule Preparation

1.1.1.1   Prepare schedules using commercial project planning software. Preferred software
          (used by CHPRC) is Primavera Project Planner (P6). Other project planning software
          may be used if Contractor provides software translation capability to and from
          Primavera.

1.1.1.2   The Contractor shall propose a specific level within the Work Breakdown Structure
          (WBS) to be used for monthly reporting purposes. A sample P6 Activity Code
          Structure and WBS will be provided to the Contractor in order to assist in the
          preparation of the Construction Schedule, which will enable communication and
          downloading of the Contractor’s schedule with CHPRC schedule system.

1.1.1.3   Identify initial project schedule as Revision 0. This schedule, when approved, is the
          baseline project schedule.

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal procedures.

1.2.2     Approval Required

1.2.2.1   Start-Up Project Schedule: 10 days after Notice of Award, submit a schedule
          covering activities for the first 60 days of Contract, starting with receipt of Notice to
          Proceed, as specified in 1.3.

1.2.2.2   Project Schedule: 30 days after Notice of Award, submit a resource-loaded schedule
          covering activities and budget for duration of Contract. Schedule shall show cost of
          each major element such that earned value can be determined.

1.2.2.3   The Contractor shall provide a Cost Baseline by WBS showing planned expenditures
          by month through the contract period. The baseline shall provide costs by cost
          element (labor, materials, other direct costs, etc.).

1.2.2.4   The Contractor shall provide a critical path schedule to be used as the Schedule
          Baseline showing logic interfaces and all contract milestones and deliverables by
          WBS element.



                                             01315-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                               SECTION 01315
                   PROJECT SCHEDULES, PROJECT CONTROLS,
                   AND PROJECT PERFORMANCE MILESTONES

1.2.2.5   Weekly Work Schedules: Provide a 2-week “look ahead” schedule, updated weekly,
          one day prior to each scheduled Weekly Progress Meeting (1.5.1).

1.2.2.6   Revised Schedules: When required, submit revised project schedules as specified in
          1.4.

1.2.2.7   Downtime/delay reports: On a daily basis or on the working day of an occurrence,
          submit downtime/delay reports.

1.2.3     Approval Not Required

1.2.3.1   Weekly Status Report: A weekly status report of major activities, accomplishments,
          safety, issues, and items of concern shall be submitted by the close of business
          Wednesday of each work week.

1.2.3.2   Monthly Progress Reports: Submit monthly as specified in 1.6.

1.2.3.3   Weekly labor cost reports: No later than the second day of the following week,
          submit weekly labor cost reports. Cost reports shall be budget- and quantity-based,
          and reflect each work element in the WBS. The cost reports shall be updated each
          week with the progress and variances for each work element. The weekly cost
          reports shall indicate names and hours for all people charging their time to the
          project.

1.3       SCHEDULE PREPARATION

1.3.1     The schedule submittal shall include a time-phased performance measurement
          baseline schedule (PMBS) for completing the individual construction work activities.

1.3.2     The schedule shall be in the form of a progress chart of suitable scale to indicate
          appropriately the percentage of work scheduled for completion by any given date
          during the contract period of performance. Identify critical path activities, including
          logical sequence and relationship of activities for engineering, design, submittals,
          procurement, fabrication, delivery, erection, installation, and testing for work covered
          by Contract.

1.3.3     See submittal register for quantity of copies to be submitted and approval code.

1.4       SCHEDULE REVISIONS

1.4.1     Whenever CHPRC determines that there are significant variances between actual and
          scheduled progress, endangering completion of the Contract Work within the


                                             01315-2
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                               SECTION 01315
                   PROJECT SCHEDULES, PROJECT CONTROLS,
                   AND PROJECT PERFORMANCE MILESTONES

          scheduled time, the Contractor may be required to prepare and submit revised project
          schedules including corrective action plan(s).

1.4.2     Make schedule revisions in accordance with the following:

1.4.2.1   Show progress to date of submittal and projected completion dates for each activity.

1.4.2.2   Identify activities modified since the previous submittal, major changes in scope, and
          other identifiable changes.

1.4.2.3   Provide a narrative report defining the problem areas, anticipated delays, and
          schedule impacts.

1.4.2.4   Describe corrective action taken, or proposed, and its effect, including changes in
          schedules of subcontractors.

1.4.3     Send copies of revised schedules to CHPRC. Notify subcontractors, suppliers, and
          other concerned entities, instructing them to promptly report, in writing, problems
          anticipated due to revisions.

1.4.4     Upon approval, a revised schedule becomes the new baseline.

1.5       WEEKLY WORK SCHEDULE PREPARATION

1.5.1     Each week, prepare a detailed schedule of next 2-week’s work. Base weekly work
          schedules on the activity schedule. Electronic generation of these schedules is not
          required. Include the following:

          a. Work Description
          b. Location of the Work.
          c. Work involving outages, overtime, weekends, etc.

1.6       PROGRESS REPORT PREPARATION

1.6.1     A summary progress report with cost and schedule status reported by WBS shall be
          submitted monthly with actual progress and cost performance indicated against the
          cost and schedule baseline.

1.6.2     A variance analysis shall be prepared on the current month and cumulative to-date.
          Deviations of more than +/- 5% per WBS reporting element shall require a narrative
          variance analysis with explanations to adequately address cause, impact, planned
          corrective action, and expected outcome. If schedule impacts occur as the result of


                                             01315-3
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                SECTION 01315
                    PROJECT SCHEDULES, PROJECT CONTROLS,
                    AND PROJECT PERFORMANCE MILESTONES

           cost impacts, the Contractor shall so indicate in a narrative write-up in the monthly
           report. An estimate at completion (EAC) shall be included in each monthly report.

1.6.3      Develop and include a line graph (“S” curve) to show cumulative actual progress
           versus cumulative scheduled progress. Progress shown shall be consistent with that
           indicated by the reports.

1.6.4      Update project schedule each reporting period, or more frequently if requested by
           CHPRC, when progress report is prepared. Include an updated data disk and a hard
           copy of updated schedule with the progress report.

1.6.5      Progress of scheduled activities will be used to determine monthly progress payments
           made to the Contractor. Requests for progress payments shall be directly related to
           progress shown in relation to the approved baseline project schedule.

1.6        MILESTONES

1.6.1      The specific Milestones the Contractor must meet for this contract are as follows.

           Construction Completion, Acceptance and Demobilization: May 1, 2014

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                        END OF SECTION




                                              01315-4
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

PART 1 – GENERAL

1.1       REFERENCES

1.1.1     The following documents and others referenced therein form part of Contract to
          extent designated in this section. Referenced documents are those current as of the
          date of this Section unless otherwise indicated.

1.1.1.1   American Society of Mechanical Engineers (ASME)

          NQA-1: 2008 with 2009 Addenda           Quality Assurance Program Requirements for
                                                  Nuclear Facility Applications. Include
                                                  Requirements 1 through 18, subparts 2.7 and
                                                  2.14 as applicable for the scope of work being
                                                  performed (see 1.3.3.1).

1.1.1.2   American Society for Quality (ASQ)

          E4                                      Specifications and Guidelines for Quality
                                                  Systems for Environmental Data Collection
                                                  and Environmental Technology Programs

1.1.1.3   Code of Federal Regulations (CFR)

          Part 830, Subpart A                     Quality Assurance Requirements

1.1.1.4   Department of Energy (DOE)

          DOE G 414.1-2B                          Quality Assurance Program Guide

          DOE O 414.1D                            Quality Assurance

1.1.1.5   Factory Mutual (FM)

          Approval Guide

1.1.1.6   Institute of Electrical and Electronics Engineers (IEEE)

          C2                                      National Electrical Safety Code (NESC)

1.1.1.7   International Standards Organization (ISO)

          ISO 9000:2000                           Quality Management and Quality Assurance
                                                  Standards


                                            01400-1
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                                  SECTION 01400
                         QUALITY ASSURANCE AND CONTROL

1.1.1.8    Intertek Testing Services NA, Inc. (ITSNA)

           ETL, Section 1                           Electrical Products/Gas/Oil Fueled Products

1.1.1.9    National Electrical Manufacturers Association (NEMA)

           MG-1                                     Motors and Generators

1.1.1.10   National Fire Protection Association (NFPA)

           70                                       National Electrical Code (NEC)

1.1.1.11   Underwriters Laboratories (UL)

           Electrical Appliance and Utilization Equipment Directory

           Electrical Construction Materials Directory

1.2        SUBMITTALS

1.2.1      See Section 01300 for submittal procedures.

1.2.2      Approval Required

1.2.2.1    With proposal, submit a Quality Assurance Program (QAP) meeting the requirements
           of the Contract and this Section. Include subcontracted work and work performed off
           of the Hanford Site. If QAP is based on a consensus national standard or other
           quality management system, furnish a matrix showing the cross-references between
           the QAP and the standard or system.

1.2.2.2    With proposal, submit a Quality Assurance Inspection Plan (QAIP) for the
           performance of all inspection and testing activities as specified in the SOW, the
           Technical Specifications, and drawings.

1.2.3      Approval Not Required

1.2.3.1    With proposal, submit a written statement warranting that all items supplied under
           Contract are genuine, new, and unused in accordance with 1.4.

1.2.3.2    The Contractor shall maintain and submit a formal punchlist that tracks NCR items
           through final work acceptance.




                                              01400-2
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

1.3       QUALITY ASSURANCE PROGRAM REQUIREMENTS

1.3.1     The Quality Assurance Program (QAP) requirements imposed by this Specification
          are under the authority of the Price Anderson Amendments Act (PAAA) of 1988.
          Quality assurance provisions are developed from U.S. Department of Energy Nuclear
          Safety Management Regulation 10 CFR 830.120. QAPs developed from other
          national standards (e.g., ASME NQA-1, 10 CFR 50, 10 CFR 72, ISO 9000, ASQ E4)
          may be used as a basis for satisfying the criteria specified, and should be
          supplemented and submitted as necessary to satisfy the requirements.

1.3.2     When subcontracting any portion of this Contract, the Contractor is required to
          invoke all of the above quality assurance program requirements on its subcontractor.

1.3.3     The Contractor shall be responsible for performing quality workmanship and shall
          conduct the quality control measures necessary to ensure work conforms to
          requirements included in this SOW.

1.3.3.1   Applicable plans, procedures, and documentation shall be prepared, reviewed,
          approved, and controlled in accordance with the approved QAP. Applicable quality
          requirements from NQA-1 (including 2009 Addenda) include:

             Requirement 1, Organization: Sections 100, (all 200 Subsections), 300
             Requirement 2, Quality Assurance Program: Sections 100, all 200 Subsections
             Requirement 4, Procurement: Sections 100, 200, 201 thru 206, 300, 400
             Requirement 5, Instructions, Procedures, and Drawings: Section 100
             Requirement 6, Document Control: Sections 100,200, all 300 Subsections
             Requirement 11, Test Control: Sections 100, 200, 300
             Requirement 12, Control of M&TE: All Sections
             Requirement 14, Inspection, Tests, and Operating Status: Section 100
             Requirement 15, Control of Nonconforming Items: All Sections
             Requirement 16, Corrective Action: Section 100
             Requirement 17, Quality Assurance Records: Sections 100, 200, 300


1.3.3.2   Contractor shall be responsible for the performance of all inspection and testing
          activities as specified in the Contractor’s Quality Assurance Inspection Plan, (QAIP)
          submittal to CHPRC for approval. The QAIP will detail the inspection requirements
          that are identified in the specifications and drawings. CHPRC will use this submittal
          to identify key activities/witness points for the BTR or designee and establish
          notification requirements prior to performance of those inspections, such as NEC
          inspections prior to backfill, compaction records, concrete placement, high hazard
          activities, etc.

                                            01400-3
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

1.3.3.3   At the conclusion of construction activities, the Construction Manager/ BTR will
          conduct a Final Acceptance Walkdown, during which time work will be inspected for
          compliance with contract requirements and the Construction Completion Document
          (CCD).

1.3.4     The QAP shall apply to all activities, including subcontracted activities and for work
          performed off the Hanford Site. The QAP shall include provisions for the following
          activities, which shall be documented on the Supplier Quality Assurance Program
          Requirements Data Sheet provided by CHPRC:

1.3.4.1   Management: Program, training/qualification, discrepancy identification,
          document/records.

          a.   Quality documents shall describe the organizational structure, functional
               responsibilities, levels of authority and interfaces for those managing and
               performing the Work.

          b.   Personnel shall be trained and qualified to ensure they are capable of
               performing their assigned work. Plans shall address specific training,
               qualification, and certification requirements.

          c.   Items and processes that do not meet the requirements shall be identified,
               controlled, and corrected. Identify items or materials that do not meet specified
               requirements and control them to prevent inadvertent use, shipment, or
               intermingling with acceptable materials or items.

          d.   Documents shall be prepared, reviewed, approved, issued, revised and
               maintained. Approved and current issues of design documents, applicable
               submittals, procedures, procurement documents and instructions shall be used.
               Records shall be legible, identifiable, and retrievable.

1.3.4.2   Performance: Work Processes, Procurement, Inspection, and Testing

          a.   Items shall be identified and controlled to ensure proper use. Items shall be
               maintained to prevent their damage, loss or deterioration.

          b.   Purchased items and services shall meet established requirements and perform
               as specified. Procurement controls shall include actions to prevent the use of
               suspect or counterfeit products (1.4). The Contractor shall ensure inspections
               are performed to identify, control, and disposition suspect counterfeit items.
               Minimum inspection criteria shall be per CHPRC procurement quality clauses
               B73 and B76. Copies of these clauses will be provided by CHPRC.



                                             01400-4
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                      SECTION 01400
             QUALITY ASSURANCE AND CONTROL

c.   The Contractor shall be responsible for the performance of all inspection and
     testing activities as specified in Quality Assurance Inspection Plan. The
     Contractor shall retain the services of an independent, certified inspection and
     testing agency to perform inspections and testing as specified in the Quality
     Assurance Inspection Plan and the “Technical Specifications for CH2M HILL
     Plateau 105 KE ISS Associated Penetration Sealing and Safe Storage Enclosure
     (SSE) Design.” Inspection and testing of specified items and processes shall be
     conducted using established acceptance and performance criteria.

     1.   Perform and document inspections and testing required by the Quality
          Assurance Inspection Plan and the technical specifications. Documented
          inspections shall report the true and physical/functional condition of the
          inspection activity. As a minimum prepare daily reports when inspections
          and testing are performed. Reports shall provide sufficient detail to
          describe inspections and testing performed, with applicable requirements
          referenced, and results and determinations of inspections and tests shown.

     2.   Test procedures, when required, shall include the reference test objectives,
          prerequisites, and acceptance criteria. Test procedures shall also identify
          test configuration, safety instructions, instrumentation requirements,
          required monitoring, and environmental conditions. Test procedures from
          standards, codes, supplier manuals and equipment maintenance
          instructions may be used in lieu of specially prepared test procedures.

     3.   Complete required inspections and tests and have documentation available
          for review, before requesting overview inspection by CHPRC.

     4.   Measuring and Test Equipment (M&TE) shall be properly calibrated
          maintained, accounted for and used when required. Calibration shall be
          traceable to National Institutes of Standards and Technology Calibration
          (NIST) Standards. Perform calibration at specified intervals based on the
          type of equipment, required accuracy, and frequency of use, stability
          characteristics, and other conditions affecting performance. Maintain
          records and mark equipment to show calibration status.

     5.   When M&TE is found to be out of calibration, specify means to identify
          its use since the last calibration and methods to re-verify acceptability of
          items previously tested.

     6.   Calibration shall have accuracy traceable to national standards (where they
          exist), and calibration standards shall have the accuracy to ensure that the
          M&TE has the required tolerances.


                                  01400-5
                        Requisition Number: 246168
            Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                 Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

1.3.5     Welding/Non-Destructive Examination

1.3.5.1   The Contractor shall conform with American Welding Society requirements and as
          defined in design and specifications. The Contractor shall submit all welding
          documentation to CHPRC for approval prior to the start of work. The Contractor shall
          coordinate with CHPRC should any welding/non-destructive examination need to be
          performed on the Hanford Site. All hot work activities shall be conducted in
          compliance with MSC-RD-9900.

1.3.6     Electrical/Electronic Product Acceptability

1.3.6.1   Electrical control panels and electrical equipment (a general term to include material,
          fittings, devices, appliances, luminaries [fixtures], apparatus, and the like used as part
          of or in connection with an electrical installation) delivered or brought onto the
          Hanford Site in performance of this Contract shall be listed or labeled by an
          organization currently recognized by OSHA as a nationally recognized testing
          laboratory (NRTL).

1.3.6.2   Electrical equipment installed as part of this contract shall comply with the NEC and,
          where applicable, the NESC. CHPRC reserves the right to inspect electrical
          equipment and installations. Contractor shall notify CHPRC when installations are
          available for NEC inspection.

1.3.6.3   Electric motors shall be manufactured and testing in accordance with NEMA MG-1
          as applicable, or listed by an organization currently recognized by OSHA as an
          NRTL. Documentation of NEMA MG-1 compliance shall be made available to
          CHPRC on request.

1.3.6.4   Electrical equipment and devices for which there is a UL category code identifying
          product categories shall be listed or labeled by an OSHA-recognized NRTL.

1.3.6.5   The Canadian Standard Association (CSA) marking is currently recognized by OSHA
          as an NRTL when the label includes “US” or “NRTL” subscript.

1.3.6.6   The Council of the European Communities “CE” marking, Directive 93/68EEC, is
          not currently recognized by OSHA as an NRTL marking.

1.3.6.7   The International Electrotechnical Commission (IEC) Standard 60529 for enclosures
          (IPxx) is not currently recognized by OSHA as an NRTL label.

          NOTE: Access http://www.osha.gov/dts/otpca/nrtl/ for a list of approved NRTLs.

1.3.6.8   Electrical equipment for which there is no listing category shall be evaluated or tested
          using a method submitted to and approved by CHPRC prior to delivery of the

                                             01400-6
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                  SECTION 01400
                         QUALITY ASSURANCE AND CONTROL

           equipment. A field evaluation performed by an NRTL prior to delivery is the
           preferred method.

1.3.6.9    Electrical equipment is subject to the “Counterfeit Suspect Item Program.”

1.3.6.10   Each product shall be listed for intended use in one of the following and shall bear
           listing organization’s label (label shall be attached to the product for verification).

           a.   FM Approval Guide
           b.   UL Electrical Appliance and Utilization Equipment Directory.
           c.   UL Electrical Construction Materials Directory.
           d.   ETL Testing Laboratories, Section 1 (ITSNA).

1.3.6.11   If the product is not listed in the above directories or guide, provide the product which
           has been tested and certified by a Nationally Recognized Testing Laboratory (NRTL)
           in accordance with 29 CFR 1910.7. Provide the following:

           a.   OSHA documentation that demonstrates recognition.

           b.   Laboratory documentation that verifies testing in accordance with national code
                or standard.

1.3.6.12   If the product is not listed by UL, FM, or ETL, and if an NRTL is not available,
           submit descriptive literature to CHPRC. Literature shall include the product
           specification and description of the intended application.

1.4        EXCLUDING SUSPECT AND MISREPRESENTED PRODUCTS

1.4.1      Contractor warrants that items provided to CHPRC are genuine, new, and unused
           unless otherwise specified in writing by CHPRC. Contractor further warrants that
           items used during the performance of the Work include genuine, original, and new
           components, or are otherwise suitable for the intended purpose. The Contractor
           indemnifies CHPRC, its agents, and third parties for any financial loss, injury, or
           property damage resulting directly or indirectly from material, components, or parts
           that are not genuine, original, and unused, or otherwise suitable for the intended
           purpose. This includes materials that are defective, suspect, or counterfeit; materials
           that have been provided under false pretenses; and materials or items that are
           materially altered, damaged, deteriorated, degraded, or result in product failure.

1.4.2      Types of material, parts, and components known to have been misrepresented include
           fasteners; hoisting, shackles, turnbuckles, cable clamps, wire rope, rigging, and lifting
           equipment; cranes; hoists; valves; pipe and fittings; electrical equipment and devices;
           plate, bar, shapes, channel members, and other heat-treated materials and structural
           items; welding rod and electrodes; and computer memory modules. The Contractor’s

                                              01400-7
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

          warranty shall also extend to labels and trademarks or logos affixed, or designed to be
          affixed, to items supplied or delivered to CHPRC. In addition, because falsification
          of information or documentation may constitute criminal conduct, CHPRC may reject
          and retain such information or items, at no cost; and identify, segregate, and report
          such information or activities to the DOE.

1.4.3     Fasteners

1.4.3.1   The provisions stated below are the minimum DOE requirements for high-strength
          graded fasteners produced in compliance with national consensus standards (e.g.,
          ASTM, ASME, IEEE).

1.4.3.2   Fasteners shall exhibit grade marks and manufacturer’s identification symbols
          (headmarks).

1.4.3.3   Fasteners supplied with headmarks matching those displayed on the Suspect Fastener
          Headmark List (see Part 2 below) shall be unacceptable under the terms of this SOW.

1.4.3.4   Fasteners shall be inspected to verify compliance with the Contract requirements.
          Additionally, fasteners may also be subjected to destructive testing.

1.4.3.5   When requested by the CHPRC, the Contractor and sub-Contractors shall provide a
          Certificate of Conformance, which must certify conformance and traceability of
          supplied materials to the subject Contract Order. The document must be legible and
          reproducible. This Certification of Conformance shall meet the following
          requirements:

1.4.3.6   Identify the appropriate Purchase Order/Contract Order number under which the
          material, equipment, item, or service is being supplied.

1.4.3.7   The Supplier/Manufacturer shall warrant that all items furnished meet the
          requirements of the Purchase Order/Contract Order.

1.4.3.8   The certificate shall include a statement ensuring no suspect/counterfeit fasteners,
          electrical components, or other items were used in this fabrication and that all items
          are genuine (i.e., not counterfeit) and match the quality, test reports, markings, and
          fitness for use required by the Contract. The statement shall be on Contractor
          letterhead and signed by an authorized agent of Contractor.

1.4.4     Any materials furnished as part of this Contract that have been previously found to be
          suspect/counterfeit by the DOE will not be accepted.




                                             01400-8
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                               SECTION 01400
                      QUALITY ASSURANCE AND CONTROL

1.5     INSPECTION AND TESTING

1.5.1   Inspection and testing shall be performed in accordance with this Statement of Work.

1.5.2   CHPRC may perform oversight and inspections to verify compliance to requirements.

1.5.3   CHPRC reserves the right to verify the quality of work at the Contractor’s facility,
        including any subcontractor’s facility. Access to a subcontractor’s facility shall be
        requested through the Contractor and verification may be performed jointly with the
        Contractor.

1.5.4   Verifications shall be performed for specific verification points as scheduled in the
        Inspection Plan.

1.5.5   Prerequisites to verification points: Ensure that personnel have completed inspections
        of, and approved portions of, work in accordance with the Specification requirements
        before notifying CHPRC.

1.5.6   Specific verification points are defined as follows:

            QA Hold Point: A type of signature step in a technical work document that
             satisfies established criteria for designation of Hold Points at which specific
             personnel are required to sign for the specified action. Hold Points consist of an
             action; acceptance criteria for Hold Point completion; and blocks for signature
             of performer, printed name of performer, and date.

             QA Hold points are placed at those steps where omission or incorrect
             accomplishment of the step could result in a significant problem or hazard. The
             completion and documentation of a Hold Point shall occur prior to proceeding
             to the next working step.

            Verification Point: A step in an inspection plan, procedure, or other work
             document that requires inspection personnel to review, inspect, test, check, or
             otherwise determine and document whether or not items, processes, services, or
             documents conform to specified requirements.

            Witness Point: A step in an inspection plan, procedure, or other work document
             that requires inspection personnel to observe an activity (e.g., examination or
             test).

        NOTE:      "Verification" may be performed after the fact; "witness" is performed
                   during the work process.



                                           01400-9
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

              Radiological Control Hold Point: A hold point that is used when the potential
               exists in which incorrect implementation of radiological controls could exceed
               one or more of the following criteria:

               -     Radiation exposures in excess of Administrative Control Levels
               -     High airborne radioactivity concentrations without protection or controls
               -     The uncontrolled release of radioactive contamination

1.6       NONCONFORMANCE REPORTING

1.6.1     The Contractor shall utilize a nonconformance reporting system to document
          deviations from requirements. Nonconformance reports (NCR) shall be prepared with
          a recommended disposition and shall be formally submitted to CHPRC within
          48 hours of discovery.

1.6.2     Dispositions of NCRs shall be documented in one of the following categories:
          Accept -As-Is; Repair; Rework; or Reject.

             Accept-As-Is: A final disposition for a nonconforming item that is satisfactory
              for its intended use

             Repair: A disposition requiring the correction of a nonconforming item so that it
              can function reliably and safely

             Rework: A disposion requiring the correction of a nonconforming item to
              conform to original requirements

             Reject: A final disposition that the nonconforming is not acceptable for its
              intended use

1.6.2.1   All nonconformances identified with a proposed disposition of "Accept-As-Is" or
          "Repair" shall be approved by CHPRC before any corrective action is taken by the
          Contractor on the nonconformance. Reject and Rework deficiencies shall be
          submitted for information. After the recommended disposition has been evaluated by
          CHPRC, the form will be returned to the Contractor with a disposition of “Approved”
          or “Rejected.” The Contractor shall take corrective action on the nonconformance
          only after the disposition is approved. The completed NCR shall be shipped with the
          affected item.

1.6.2.2   Nonconforming items described by the report shall be physically tagged with a
          nonconformance tag or segregated, when feasible.




                                             01400-10
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                 SECTION 01400
                        QUALITY ASSURANCE AND CONTROL

1.6.2.3    Nonconformance tagging shall remain intact during correction of deficient conditions,
           unless tagging inhibits directed corrective action. If removal of tag is necessary to
           accomplish directed corrective action, removal shall be performed or delegated by the
           initializing organization.

1.6.2.4    Clearance of nonconformance tags shall be performed or delegated by the initializing
           organization.

1.6.2.5    The Contractor shall maintain and submit a formal punchlist that tracks NCR items
           through final work acceptance.

PART 2 – PRODUCTS

Not Used




                                             01400-11
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
          SECTION 01400
 QUALITY ASSURANCE AND CONTROL

  SUSPECT FASTENER HEAD MARK LIST




                      01400-12
            Requisition Number: 246168
Title: 105-KE Safe Storage Enclosure (SSE) Construction
                     Date: 5-4-12
          SECTION 01400
 QUALITY ASSURANCE AND CONTROL




                      01400-13
            Requisition Number: 246168
Title: 105-KE Safe Storage Enclosure (SSE) Construction
                     Date: 5-4-12
                              SECTION 01400
                     QUALITY ASSURANCE AND CONTROL

PART 3 – EXECUTION

Not Used

                                 END OF SECTION




                                       01400-14
                             Requisition Number: 246168
                 Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                      Date: 5-4-12
                           SECTION 01500
          CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 – GENERAL

1.1       REFERENCES

1.1.1     The following documents and others referenced herein form part of Contract to extent
          designated in this section. Referenced documents are those current as of the date of
          this section unless otherwise indicated.

1.1.1.1   National Fire Protection Association (NFPA)

          701                                 Methods of Fire Tests for Flame-Resistant Textiles
                                              and Films

1.1.1.2   Washington State Department of Transportation (WSDOT)

          M 41-10                             Road, Bridge, and Municipal Construction

1.2       SUBMITTALS

1.2.1     See Section 01300 for submittal process

1.2.2     Approval Required

1.2.2.1   Work Area Layout: Before starting work, submit a proposed operational work area
          layout in accordance with 1.3.4.1.

1.2.2.2   Equipment: Before moving equipment to the Site, submit list of equipment to be
          used and confirmation equipment meets OSHA standards in accordance with 1.3.6.2.

1.2.2.3   Radiological Equipment: Before working in radiological area, submit list of
          equipment to be used in accordance with 1.3.6.3.

1.2.3     Approval Not Required: None.

1.3       ACCESS AND PARKING

1.3.1     CHPRC will make available parking for a limited number of Contractor’s company
          vehicles near the worksite, outside of any Limited Area. “No Parking” signs are
          posted to show fire and emergency lanes. No on-street parking will be permitted.

1.3.2     A minimum of 20 feet clear driving width shall be maintained to all relocatable
          structures. Relocatable structures shall not be places closer than 50 feet to a fire
          hydrant and no further than 300 feet.



                                             01500-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                           SECTION 01500
          CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

1.3.3     First Aid: Facilities for first line medical attention are available on-site and are
          located at the 2719WB building located in the 200 West Area of the Hanford Site.
          Facilities for radiological decontamination are also available on-site and are located at
          the 272AW building in the 200 East Area.

1.3.4     Operation and Storage Areas: Worksite operations, including storage of materials,
          will be designated by CHPRC during the preconstruction conference.

1.3.5     The worksites shall be set up in accordance with the Contractor’s Job Safety Analysis
          as specified in PRC-PRO-SH-40078 – Contractor Safety Processes, Appendix F,
          Safety Program Specifications for Contractors, Section 2.1, and requires concurrence
          from CHPRC.

1.3.5.1   Contractor’s proposed operational work area layout shall define trailer locations,
          laydown yard, parking area, location of cranes, etc.

1.3.5.2   Post a visible sign at the project site that identifies the work zone, to include points of
          contact to allow entrance.

1.3.5.3   Post/enclose the work area as a construction area so visitors or unauthorized
          personnel do not enter into the construction work zone without proper notification.

1.3.5.4   Post appropriate signs (e.g., hard hat, safety glasses, hearing protection, and footwear)
          for the jobsite.

1.3.5.5   Comply with all radiological postings established by CHPRC.

1.3.5.6   Control access to the worksite.

1.3.5.7   Coordinate site setup with BTR to ensure compliance with traffic area restrictions
          around the sites.

1.3.5.8   The work area shall be maintained in a clean and orderly fashion during all
          Contractor work activities. This includes all site areas within the Contractors control
          including the SSE structure. Accumulation of trash, debris or water in work areas is
          not acceptable and shall be removed by the Contractor for waste minimization and
          cross contamination purposes.

1.3.6     Equipment




                                             01500-2
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                           SECTION 01500
          CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

1.3.6.1   For property control purposes, the Contractor shall provide CHPRCwith a listing of
          equipment to be brought on site. The Contractor shall update the equipment listing as
          additional equipment is brought on or removed from site.

1.3.6.2   The Contractor shall submit certification to CHPRC that equipment delivered to the
          site is OSHA compliant and uncontaminated. Equipment brought to the site shall be
          in good working condition, free of any residual dirt, oil, and grease. Equipment glass
          shall be free of cracks.

1.3.6.3   The Contractor shall provide a list to CHPRC of all equipment to be utilized in
          radiological areas for an initial radiological survey (performed by CHPRC) prior to
          entry.

1.4       FIELD OFFICE

          Re-locatable structures shall be NFPA 101 compliant and approved by the
          responsible Fire Protection Engineer in addition to being permitted for location and
          occupancy through the Hanford Fire Marshal.
          Portable fire extinguishers shall be mounted on hangers or stored in cabinets (except
          wheeled types) and are to be positioned within all occupied work areas.
          Portable heaters shall be listed or approved by a Nationally Recognized Testing
          Laboratory (such as UL or FM) or American Gas Association (AGA) certified for
          their intended use, and shall not be modified for other applications. The use of electric
          heaters over 1500 watts and fuel-fired heaters shall be approved by the Hanford Fire
          Marshal. A Fire Marshal Permit shall be obtained from the Project Fire Protection
          Engineer prior to utilizing fuel-fired and liquid petroleum gas-fired heaters. Fuel fire
          heaters shall not be placed in an enclosure. The heater and fuel supply shall be located
          outside the heated air duct into the enclosure.
          The Contractor shall designate break and smoking areas. Smoking areas will not be
          allowed within 50 feet of any facility or combustible source. Designated smoking
          areas shall be approved by the Fire Protection Engineer and provided with the
          appropriate signage.
1.4.1     Sufficiently anchor or tie down portable and re-locatable structures, including field
          offices and storage, to prevent overturning and lateral movement in 70-mph winds.
          Enclose or skirt under the floor area with non-combustible material to prevent the
          accumulation of wind-blown debris. Complete the anchoring and enclosure within
          14 days after its arrival at the worksite.




                                             01500-3
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                          SECTION 01500
         CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

1.5     TEMPORARY UTILITIES

1.5.1   Electric Power: Not available. The Contractor shall provide approved mobile
        temporary power systems (e.g. generators) for construction power, as needed.

1.5.2   All generator operations shall be approved by the responsible Fire Protection
        Engineer and permitted through the Hanford Fire Marshal, as applicable.

1.5.3   Telephone: Utilities for telephone service are not available. Contractor shall provide
        cellular phone for emergencies and communication with CHPRC.

1.5.4   Water: Drinking water is not available. Provide employees with adequate drinking
        water that meets health and safety requirements.

1.5.5   All nonemergency fire hydrant tie-ins shall be approved and permitted through the
        100K Area Water Purveyor, the Fire Protection Engineer, and the Hanford Fire
        Department.

1.6     TEMPORARY CONTROLS

1.6.1   Dust Control: Maintain work areas to prevent hazard or nuisance to others.
        Accomplish dust control by sprinkling or other methods approved by CHPRC.
        Repeat sprinkling at necessary intervals to keep disturbed area damp at all times.
        Keep sufficient equipment on worksite to accomplish dust control as work proceeds
        and whenever dust nuisance or hazard occurs. No separate or direct payment will be
        made for dust control and cost shall be considered incidental to and included in the
        Contract price.

1.6.2   Temporary Enclosures: Plastic sheeting materials used to form enclosures shall be
        6 mils minimum thickness, and have fire retardant properties in accordance with
        NFPA 701. Framing lumber shall have been treated with fire retardant or of
        noncombustible construction.

1.6.3   Vehicle and equipment movement

        a.   Slow moving vehicles and equipment shall not travel on the Hanford Site roads
             during heavy traffic periods between 6:30 and 8:00 a.m., and 3:30 and 5:30 p.m.

        b.   Do not block existing roads.

        c.   Do not park on roadway shoulders.

        d.   Vehicles that require a portable fire extinguisher in accordance with PRC-PRO-
             SH-40078, Appendix F, shall have the extinguisher secured in an approved

                                          01500-4
                                Requisition Number: 246168
                    Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                         Date: 5-4-12
                             SECTION 01500
            CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

                manner (vehicle mounting bracket designed for specific extinguisher, or stowed
                in a secured equipment container).

1.6.4      Traffic Control: Temporary traffic control and barricades shall be in accordance with
           WSDOT M 41-10, Section 1-07.23(3).

1.6.5      Oversized vehicles and loads:

           a.   Obtain a Special Motor Vehicle Permit from CHPRC before movement of
                oversize loads. See Section 01065. Verify route suitability and limitations
                before applying for the permit.

           b.   Display oversize load sign on the front of the towing vehicle and on the rear of
                the trailing unit. Attach red flags to each corner.

           c.   Travel between 8:30 a.m. and 2:30 p.m. unless special arrangements are made.
                Comply with escort vehicle requirements in the permit during travel.

           d.   Electrical escort requirements: CHPRC will provide qualified electrical escorts
                when loads reach a height of 14 feet or more from the road surface, or when a
                clearance of at least 6 feet cannot be maintained from overhead electrical or
                signal lines. Notify CHPRC at least three (3) working days before need.
                Contractor will not be charged for electrical escorts.

1.6.6      Fuels and Lubricants:

           a.   Flammable/combustible liquids storage shall be per NFPA 30, and permitted in
                accordance with MSC-RD-8589. Oils, greases and similar materials shall be
                stored in non-combustible metal lidded containers or bins in a fenced compound
                remote from other combustible materials as approved by the CHPRC Fire
                Protection Engineer and Chemical Mangement.

           b.   "No smoking" signs shall be provided by Contractor and prominently displayed
                in areas where flammable or combustible materials are stored. Additionally,
                Contractor shall provide and maintain suitable fire extinguisher in such areas.

           c.   Contractor shall provide all fuel for heating, ventilation and air conditioning of
                Temporary Facilities (unless these are run using free issue power).

PART 2 – PRODUCTS

Not Used



                                             01500-5
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                            SECTION 01500
           CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 3 – EXECUTION

Not Used



                                  END OF SECTION




                                        01500-6
                              Requisition Number: 246168
                  Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                       Date: 5-4-12
                                SECTION 01610
                          MATERIAL AND EQUIPMENT
                      DELIVERY, STORAGE, AND HANDLING

PART 1 – SUMMARY

1.1     SUMMARY

        This section contains requirements for delivery, inspection, marking, storage, and
        handling. Product-unique requirements are contained in other sections. Chemicals
        shall be handled, stored, and tracked in accordance with Section 01130;
        flammable/combustible liquid storage shall be in accordance with Section 01130.

1.2     DELIVERY

1.2.1   The Contractor shall provide equipment and labor required for unloading,
        transporting, and handling delivered material and products.

1.2.2   Regarding deliveries of materials and supplies, and the coordination of
        Subcontractors while on CHPRC Site, the Contractor shall:

           Coordinate work or delivery with CHPRC in advance.
           Arrange for badging through the Contract Specialist.
           Communicate any special hazards associated with the delivery or the work (e.g.,
            safety).
           The individual designated to meet the Contractor is called the DPOC or POC
            (Delivery Point of Contact, or Point of Contact). The DPOC for this Work will be
            defined by the BTR. Meet the DPOC at the designated rendezvous point.
           Comply with DPOC direction to the specified work location.
           Conduct a joint pre-delivery walkdown of the work location with the DPOC prior
            to commencing delivery or work.

        The DPOC must be physically present during the delivery to ensure that it is
        performed safely and in accordance with Contract requirements. Alternate
        arrangements may only be made with the approval and concurrence of CHPRC BTR.

        At completion of the delivery or work, the delivery driver shall exit the Site in a
        timely manner as directed by the DPOC.

1.2.3   The Contractor shall be responsible for providing adequate weather protection during
        delivery to prevent damage or degradation to materials due to environmental
        conditions.

1.2.4   Material Safety Data Sheets (MSDSs) shall be kept accessible at each jobsite where
        material is stored. See Section 01130.


                                           01610-1
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                SECTION 01610
                          MATERIAL AND EQUIPMENT
                      DELIVERY, STORAGE, AND HANDLING

1.3     RECEIVING INSPECTION

1.3.1   Arrange for immediate disposal and replacement of products found to be defective,
        damaged beyond repair, or in otherwise unacceptable condition.

1.3.2   Perform standard inspections and additional inspections required by this Statement of
        Work.

1.3.3   Dry and clean products that have become wet or have accumulated foreign substances
        during shipment, but have not become damaged.

1.3.4   Perform additional identification marking of products when necessary to meet
        requirements of this Statement of Work.

1.3.5   CHPRC may inspect products and product marking and storage methods for
        compliance with this Statement of Work.

1.4     PRODUCT IDENTIFICATION AND SEGREGATION

1.4.1   Provide identification tags or markings for products of similar appearance, or
        intended for similar use, procured to different specifications, or from different
        manufacturers.

1.4.2   As applicable, include following information on tags: Manufacturer's name; product
        brand name; specification number; product type, grade and class; and other
        information required by other sections of this Statement of Work.

1.4.3   Segregate tagged or marked products and provide separate storage for each product.

1.4.4   Preserve identity of bulk and lot products during storage and in-process work.

1.4.5   Control identification and storage of welding materials shall be performed in
        accordance with a written filler metal control procedure which shall be submitted to
        CHPRC. Maintain procedure at jobsite. Procedure shall specify methods for control
        by heat or lot number during storage and in-process work and for disposal of
        contaminated and partially used material.

1.4.6   When pipe and tube is removed from storage and prior to cutting, clearly and
        permanently re-mark remaining pieces with either original markings or field code
        identification symbols. Return pipe and tube to storage after re-marking.




                                           01610-2
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                SECTION 01610
                          MATERIAL AND EQUIPMENT
                      DELIVERY, STORAGE, AND HANDLING

1.4.7   On pipe and tube, use permanent marking methods such as indelible ink, crayon,
        paint, and paint stick. Vibratory etching equipment may be used with approval of
        CHPRC. Marking with steel stamps is not acceptable.

1.5     STORAGE

1.5.1   The Contractor shall use all means necessary to protect construction materials before
        and during installation. All materials shall be secured so not to become a hazard
        during high winds, damage from heat, cold or other abnormal condition.The
        Contractor shall properly store and stage materials and equipment to maintain
        cleanliness and to prevent foreign material inclusion or damage.

1.5.2   Follow manufacturer's storage recommendations.

1.5.3   Store packaged products in original, unbroken packages and containers. Leave seals
        and labels intact.

1.5.4   Store rolled products in upright position.

1.5.5   Store products with finished surfaces in manner that prevents surface damage.

1.5.6   If contact between products could result in damage or reduction of utility, store
        products far enough apart to prevent contact. If close proximity storage is necessary,
        provide a barrier between products. Care shall be taken to preclude carbon and halide
        contamination of stainless steel products.

1.5.7   Keep ports, nozzles, ends, and other openings on equipment, tanks, pipe, and tube
        capped or plugged during storage.

1.5.8   Remove, dispose of, and replace products with expired shelf-life dates. Dispose of
        hazardous products in accordance with Section 01130.

1.6     INDOOR STORAGE

1.6.1   Provide indoor storage for products that can be damaged by, or can deteriorate from,
        changes in temperature and relative humidity.

1.6.2   When required by this Specification, or when recommended by product manufacturer,
        provide environmentally controlled storage. Maintain temperature 60 to 70F,
        relative humidity below 55%, and provide ventilation.




                                           01610-3
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                                  SECTION 01610
                            MATERIAL AND EQUIPMENT
                        DELIVERY, STORAGE, AND HANDLING

1.7        OUTDOOR STORAGE

1.7.1      Avoid ground contact by providing skids, pallets, platforms, and other supports.

1.7.2      Provide sunshade protection for products that can be damaged by, or can deteriorate
           from, exposure to sunlight.

1.7.3      Provide weatherproof covers for products that can be damaged by, or can deteriorate
           from, contact with rain, snow, ice deposits, and blowing sand and debris.

1.7.4      Arrange stacked products so that condensation drains.

1.8        HANDLING

1.8.1      Provide handling tools and equipment, and use methods designed to prevent
           occurrence of following.

           a.   Impact, rubbing, and other contact damage to ends and surfaces of pipe, tube,
                and other cylindrical products, and to edges, corners, and surfaces of panel,
                sheet and other flat products.

           b.   Twisting, racking, and other distortion of prefabricated structures and
                equipment assemblies.

           c.   Tearing, puncturing, and breaking of wrappings, coverings, and seals on
                packages and cartons.

           d.   Surface contamination of stainless steel products.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                       END OF SECTION




                                             01610-4
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                SECTION 01630
                      PRODUCT OPTIONS AND SUBSTITUTIONS

PART 1 – GENERAL

1.1       SUBMITTALS

1.1.1     See Section 01300 for submittal process.

1.1.2     Approval Required

1.1.2.1   Before starting Work or material delivery to the worksite, submit a completed
          Substitution Approval Request to CHPRC for each requested substitution.

1.1.3     Approval Not Required: None

1.2       CONDITIONS

1.2.1     Products include those identified in this Statement of Work, in the Specifications or
          other contract documents, and on the Drawings. References in the Specifications to
          products, or to patented or proprietary processes, by trade name, make, or catalog
          number, shall be regarded as establishing a standard of quality, and shall not be
          construed as limiting competition. The following conditions and limitations apply:

1.2.1.1   A completed Contractor Document Submittal Form shall be submitted for each
          requested material substitution. Submitted data shall show “fit, form and function”
          equivalency, as well as cost savings, if any, to the contractually required item.
          Substitution requires approval of a CHPRC Change Form (A-6004-820) if any of the
          following apply.

              Proposed substitute is more hazardous than the specified product.
              Product callout includes the phrase “or approved substitute.”

1.2.1.2   A substitute may be provided without approval if each of the following apply:

              Product callout does not include the phrase “or approved substitute.”

              Product is identified in this Statement of Work by trade name, make, or catalog
               number.

              Substitute is equivalent in function, maintainability, reliability, durability,
               material content, form, and size.

1.2.1.3   Substitution shall be applied to the total quantity of the product required in the
          Statement of Work. Partial quantity substitutions are not acceptable.



                                             01630-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                 SECTION 01630
                       PRODUCT OPTIONS AND SUBSTITUTIONS

1.2.1.4    Approval of fabrication drawings and other design media does not constitute approval
           of substitute products identified within the media.

1.2.1.5    Submittals required for a specified item are also required for an approved substitute.

1.3        CHANGE FORM PREPARATION

1.3.1      Using CHPRC Change Form, identify addressed product by the Statement of Work or
           Specification section and article or paragraph numbers or by the Drawing number.
           Provide manufacturer’s name and address, trade name, and model or catalog number.
           List fabricators as appropriate.

1.3.2      Attach descriptive information to define the operational and physical characteristics
           of the specified substitute product and to provide a basis for comparison. Include
           drawings, calculations, and data as appropriate.

1.3.3      Provide an itemized comparison between the proposed substitute and the original
           specified product. Include the following information:

1.3.3.1    Applicable Statement of Work or Specification section and article or paragraph
           numbers or applicable Drawing number.

1.3.3.2    Quality and performance comparison. List variations.

1.3.3.3    Cost data. Show the net Contract price change.

1.3.4      List the availability of maintenance service and replacement materials.

1.3.5      State the effect of the substitution on the schedule and identify the changes required
           in other work or products. Submit drawings, calculations, and vendor data to show
           the revisions necessary to accommodate the substitution.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used



                                        END OF SECTION



                                              01630-2
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                 SECTION 01670
                        CONSTRUCTION ACCEPTANCE TESTING


PART 1 – GENERAL

1.1        REFERENCES: Not Used

1.2        SUBMITTALS: Not Used

1.3        SUMMARY

1.3.1      This Section covers preparation and performance of a Construction Acceptance Test
           (CAT) and performance of an Acceptance Test Procedure (ATP).

1.3.2      The objective of the CAT is to ensure equipment is constructed and installed as
           designed and that individual components operate as expected in order to enable
           performance of the ATP. The Contractor shall write CAT procedures and provide them
           to CHPRC for approval prior to performance. The Contractor shall perform the CAT
           procedures, document test discrepancies, and correct deficiencies. All documentation
           shall be provided to CHPRC.

1.3.3      The ojective of the ATP is to demonstrate full system compliance with the Functional
           Design Critieria and that final constructed/installed sytems/sub-systems can operate
           successfully. It includes provisions for recording test results (test reporting). It does
           not cover final adjustments for operation.

1.3.4      CHPRC will prepare an ATP and deliver it to the Contractor for execution. An example
           of an ATP is included in Section 01670, Appendix A.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used

                                         END OF SECTION




                                               01670-1
                                     Requisition Number: 246168
                         Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                              Date: 5-4-12
                                SECTION 01670A
                       CONSTRUCTION ACCEPTANCE TESTING
                                  EXAMPLE

                                           APPENDIX A                             ATP____
                                                                                    Rev 0

ACCEPTANCE TEST PROCEDURE                         REV           DATE

TEST TITLE ________________________________________________________________________

LOCATION__________________________________________________________________________

PROJECT NUMBER __________________________________________________________________

PROJECT TITLE ______________________________________________________________________


Prepared By
[Company Name]


For _____________________________

Contract _________________________


PROCEDURE APPROVAL


Originator                                Date


Checker                                   Date


Project Manager                           Date


CHPRC [APPROVAL] [CONCURRENCE]


Project Manager                           Date




                                             01670A-1
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                                      SECTION 01670A
                             CONSTRUCTION ACCEPTANCE TESTING
                                        EXAMPLE

EXECUTION AND TEST APPROVAL

EXECUTED BY


Test Director/Organization                Date         Test Operator/Organization      Date



Recorder/Organization                     Date

WITNESSES


Witness/Organization                      Date         Witness/Organization            Date


Witness/Organization                      Date         Witness/Organization            Date

A-E APPROVAL
[Company Name]

Without                 With exceptions          With exceptions
exceptions              resolved                 outstanding ____


Design Engineer                           Date


Project Manager                           Date

TEST APPROVAL AND ACCEPTANCE
CH2M Hill Plateau Remediation Company (CHPRC)

Without                 With exceptions          With exceptions
exceptions              resolved                 outstanding ____


[Title or Department]                     Date         [Title or Department]           Date


[Title or Department]                     Date         [Title or Department]           Date



                                                   01670A-2
                                         Requisition Number: 246168
                             Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                  Date: 5-4-12
                                    SECTION 01670A
                           CONSTRUCTION ACCEPTANCE TESTING
                                      EXAMPLE

                                        TABLE OF CONTENTS

                Section                                                              Page

                TITLE/PROCEDURE APPROVAL                                               1

                EXECUTION AND TEST APPROVAL                                            2

                TABLE OF CONTENTS                                                      3

                1    PURPOSE                                                           7

                2    REFERENCES                                                        7

                3    RESPONSIBILITIES                                                  8

                4    CHANGE CONTROL                                                   11

                5    EXECUTION                                                        11

                6    EXCEPTIONS                                                       12

                7    PREREQUISITES, EQUIPMENT/INSTRUMENTS,
                     ABBREVIATIONS, AND ANNUNCIATORS                                  13

                8    FIRE ALARM SYSTEM - EAST WING [example]                          16

                9    [SECOND SYSTEM] [as required]

                10   [THIRD SYSTEM] [as required]

NOTE: At completion of test, enter pages added during performance of test.




                                                01670A-3
                                       Requisition Number: 246168
                           Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                                Date: 5-4-12
                               SECTION 01670A
                      CONSTRUCTION ACCEPTANCE TESTING
                                 EXAMPLE

1       PURPOSE

        [Provide a statement to describe what ATP is expected to accomplish].

        This Acceptance Test Procedure (ATP) has been prepared to demonstrate that
        [Electrical/Instrumentation] [Fire Protection] [HVAC/Instrumentation] [Mechanical]
        [_____________________] systems function as required by project criteria.

2       REFERENCES

2.1     DRAWINGS

        [List Drawings including sheet and revision numbers in numerical order with full title as
        shown in Drawing title block].

2.2     SPECIFICATIONS

        [List Construction Specifications, Procurement Specifications, and Vendor Information
        including revision number or date].

2.3     DESIGN CHANGE NOTICES (DCN)

        Prior to final test approval, enter DCNs written against this ATP.

2.4     OTHER

        [List any other references including revision number or date].

3       RESPONSIBILITIES

3.1     GENERAL

        Each company or organization participating in this ATP will designate personnel to
        assume responsibilities and duties as defined herein for their respective roles. Designees
        shall become familiar with this ATP and systems involved to extent that they can perform
        their assigned duties.

3.2     TEST DIRECTOR

3.2.1   Coordinates testing with CHPRC and directs acceptance testing.

3.2.2   Acts as liaison between participants in acceptance testing.

3.2.3   Distributes approved testing schedule before start of testing.



                                            01670A-4
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                   SECTION 01670A
                          CONSTRUCTION ACCEPTANCE TESTING
                                     EXAMPLE

3.2.4    Schedules and conducts a pretest kickoff meeting with test participants before start of
         testing when necessary.

3.2.5    Notifies persons performing and witnessing test 2 days before start of testing.

3.2.6    Schedules a dry run when necessary.

3.2.7    Notifies concerned parties when a change is made in testing schedule.

3.2.8    Takes necessary action to clear exceptions to test.

3.2.9    Confirms that field testing and inspection of system or portion of system to be tested has
         been completed.

3.2.10   Stops any test that, in his/her judgment, may cause damage to system until problem has
         been resolved.

3.2.11   After verifying there is no adverse impact, may alter sequence in which systems or
         subsystems are tested.

3.2.12   Ensures that required environmental conditions are maintained.

3.2.13   If a test is to be suspended for a period of time, ensures that system is left in a safe mode.

3.2.14   Before restarting suspended test, re-verifies test prerequisites.

3.2.15   Initiates DCNs to document required changes to ATP.

3.2.16   Reviews recorded data, discrepancies, and exceptions.

3.2.17   Obtains information or changes necessary to clear or resolve objections during
         performance of test.

3.2.18   Signs Execution and Test Approval page when test has been performed.

3.2.19   Signs Exception form when exception has been resolved.

3.2.20   Obtains required signatures on ATP Master prior to reproduction and distribution.

3.3      WITNESSES [Provided by Participating Organizations. One witness shall be a Title III
         acceptance inspector].

3.3.1    Witness tests.

3.3.2    Review results of testing.


                                               01670A-5
                                      Requisition Number: 246168
                          Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                               Date: 5-4-12
                               SECTION 01670A
                      CONSTRUCTION ACCEPTANCE TESTING
                                 EXAMPLE

3.3.3   Assist Test Director when requested.

3.3.4   Sign Execution and Test Approval page when test has been performed.

3.3.5   Sign Exception form when exception has been resolved.

3.4     RECORDER

3.4.1   Prepares a Field copy from ATP Master.

3.4.2   Records names of designated personnel on Field copy of ATP prior to start of testing.

3.4.3   Records test instrument identification numbers and calibration expiration dates.

3.4.4   Initials and dates each test step on Field copy as it is completed, next to step number, or
        on a Data Sheet when provided. Records Test Data. On Data Sheets where there is not
        room for both initial and date, date may be entered at bottom of column.

3.4.5   Records objections and exceptions on an Exception form. Transfers information in ink or
        type to an Exception form master. Uses additional Exception forms as needed.

3.4.6   Signs Execution and Test Approval page when test has been performed.

3.4.7   After test is finished, assigns alpha numeric page numbers to added Data Sheets and
        Exception forms. Records page numbers in Table of Contents.

3.4.8   Transfers changes and final test results with Recorder's signature and dates for each step
        to Master in ink or type. Submits completed Master to Test Director for approval
        signature routing. Transmits Field copy to CHPRC when test has been accepted and
        exceptions closed out.

3.4.9   Signs Exception form when exception has been resolved, and transmits to Test Director.

3.5     TEST OPERATOR

3.5.1   Performs test under direction of Test Director.

3.5.2   Provides labor, equipment, and test instruments required for performing tests that have
        not been designated as being provided by others.

3.5.3   Requests, in writing, from CHPRC those services, materials, or equipment that have been
        designated as being supplied by others.

3.5.4   Confirms that equipment required for performing test will be available at start of testing.

3.5.5   Signs Execution and Test Approval page.

                                            01670A-6
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                               SECTION 01670A
                      CONSTRUCTION ACCEPTANCE TESTING
                                 EXAMPLE

4       CHANGE CONTROL

        Required changes to this ATP shall be processed on DCNs in accordance with CHPRC
        procedures. If a need for change is discovered in course of running test, test shall be
        stopped until DCN is approved. However, this does not prevent running of another
        portion of test unaffected by change.

5       EXECUTION

5.1     OCCUPATIONAL SAFETY AND HEALTH

        Individuals shall carry out their assigned work in a safe manner to protect themselves and
        others from undue hazards and to prevent damage to property and environment. Facility
        line managers shall assure safety of activities within their areas to prevent injury,
        property damage, or interruption of operation. Performance of test activities shall always
        include safety and health aspects.

5.2     PERFORMANCE

5.2.1   Use CHPRC-concurred copy of this ATP.

5.2.2   Conduct test meeting responsibility requirements of Section 3 of this ATP.

5.2.3   Perform test in accordance with steps in Section(s) 8 (9, etc) of ATP.

5.2.4   When test has been completed, obtain signatures of test executioners and witnesses.

5.2.5   Submit test report to CHPRC for approval.

        NOTE 1:       At this point, "procedure" becomes a "report."

        NOTE 2:       There may be exceptions outstanding.

5.2.6   Clear exceptions and submit to CHPRC for approval.

        NOTE:         Ideally, cleared exceptions would be submitted with report. Coordinate
                      with CHPRC as to allowable delay between test completion and submittals.

6       EXCEPTIONS

6.1     GENERAL

        Exceptions to required test results are sequentially numbered and recorded on individual
        Exception forms. This enables case-by-case resolution and approval of each exception.

        Errors/exceptions in ATP itself shall NOT be processed as test exceptions (see Section 4).

                                           01670A-7
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                               SECTION 01670A
                      CONSTRUCTION ACCEPTANCE TESTING
                                 EXAMPLE

6.2     RECORDING

6.2.1   Number each exception sequentially as it occurs and record it on Exception Form or
        approved substitute. Copies will be supplied during Preconstruction Conference (see
        134.200.01200).

6.2.2   Enter name and organization of objecting party for each exception.

6.2.3   Enter planned action to resolve each exception when such determination is made.

6.3     RETEST/RESOLUTION

        Record action taken to resolve each exception. Action taken may not be same as planned
        action.

6.3.1   When action taken results in an acceptable retest, sign and date Retest Execution and
        Acceptance section of Exception form.

6.3.2   When action taken does not involve an acceptable retest, strike out Retest Execution and
        Acceptance section of Exception form.

6.4     APPROVAL AND ACCEPTANCE

        CHPRC provides final approval and acceptance of exceptions by checking one of the
        following on Exception form:

6.4.1   Retest Approved and Accepted: Applicable when Retest Execution and Acceptance
        section is completed.

6.4.2   Exception Accepted-As-Is: Requires detailed explanation.

6.4.3   Other: Requires detailed explanation.

6.4.4   CHPRC signs and dates Exception form and obtains their customer approval, as required.

6.5     DISTRIBUTION

        A copy of approved Exception form is distributed to each participant. Signed original is
        attached to ATP Master.




                                           01670A-8
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                               SECTION 01670A
                      CONSTRUCTION ACCEPTANCE TESTING
                                 EXAMPLE

7       PREREQUISITES, EQUIPMENT/INSTRUMENTS, ABBREVIATIONS, AND
        ANNUNCIATORS

7.1     PREREQUISITES

        The following conditions shall exist at start of testing for that portion of system being
        tested.

7.1.1   Systems have been inspected for compliance with construction documents.

7.1.2   Reference documents (including this ATP) have been verified for correct revision
        number and outstanding DCNs.

7.1.3   Power is available.

7.1.4   Annunciator lights have been tested.

7.1.5   Test instruments have a valid calibration stamp attached. Test instrument identification
        numbers and calibration expiration dates have been recorded in 7.2.

7.1.6   Steam and other process lines are valved off.

7.1.7   Water is available to sprinkler system.

7.1.8   Methods of water disposal have been approved by Facilities Management.

7.1.9   Voice communications are available between [list locations].

7.2     EQUIPMENT/INSTRUMENTS

        Supplied by Test Operator unless otherwise noted. [Delete items not required. Add any
        additional necessary items].

7.2.1   Voltohmmeters (VOM): [portable] [give ranges].

        Instrument No.:_____________ Calibration Expiration Date :_______________

7.2.2   Ammeters: [give ranges].

7.2.3   Shorting jumpers: [give lengths].

7.2.4   Shorting jumpers with ON-OFF switch: [give lengths].

7.2.5   Pressure gages: [give ranges].

7.2.6   Variable test pressure source (VTPS):

                                            01670A-9
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                SECTION 01670A
                       CONSTRUCTION ACCEPTANCE TESTING
                                  EXAMPLE

7.2.7    Variable test vacuum source (VTVS):

7.2.8    Container: [to hold water for leak or level detector tests] [give depth].

7.2.9    Thermocouple calibration device: ______________________

7.2.10   Resistance decade box: ______________________

7.2.11   Hygrometer: ______________________

7.2.12   Thermometers: [with waterbath] [give ranges].

7.2.13   Hoses: [give size, length, and end connections].

7.2.14   Radiation test sources: [type of source] Supplied by Operating Contractor.

7.3      ABBREVIATIONS

7.3.1    Abbreviations: [List nonstandard abbreviations used in text].

         DCN        Design Change Notice

         RWP        Radiation Work Permit

         SWP        Special Work Procedure




                                             01670A-10
                                    Requisition Number: 246168
                        Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                             Date: 5-4-12
                              SECTION 01670A
                     CONSTRUCTION ACCEPTANCE TESTING
                                EXAMPLE

7.4     ANNUNCIATORS

7.4.1   Tagging:


           Tagging                                  Location

           1.

           2.

           3.

           4.

7.4.2   Sequence: [Give sequence of annunciator(s) specified].




                                           01670A-11
                                  Requisition Number: 246168
                      Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                           Date: 5-4-12
                             SECTION 01670A
                    CONSTRUCTION ACCEPTANCE TESTING
                               EXAMPLE

                                         EXAMPLE

8       FIRE ALARM SYSTEM - EAST WING

        These tests will verify operation of Pyrotronics fire alarm system.

8.1     PREPARATION

____    8.1.1      Verify that all prerequisites of Subsection 7.1 have been met.

____    8.1.2      Notify building personnel that fire alarm test is in progress; evacuation not
                   required.

8.2     SUPERVISORY TESTS

        These tests will verify supervisory function for HD and MS.

        8.2.1      Heat Detector (HD)

____    8.2.1.1    Lift 1 wire from HD-1.

____    8.2.1.2    Verify that trouble LED on FCP is ON.

____    8.2.1.3    Reattach wire.

____    8.2.1.4    Verify that LED is OFF.

        Record the following steps for items shown on Data Sheet 8.2.2.

        8.2.2      Manual Pull Stations (MS)

        8.2.2.1    Lift 1 wire from MS.

        8.2.2.2    Verify that trouble LED on FCP is ON.

        8.2.2.3    Reattach wire.

        8.2.2.4    Verify that LED is OFF.

END OF SYSTEM 8 TEST


                                          01670A-12
                                 Requisition Number: 246168
                     Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                          Date: 5-4-12
                         SECTION 01670A
                CONSTRUCTION ACCEPTANCE TESTING
                           EXAMPLE

                                    EXAMPLE

DATA SHEET 8.2.2

                                                  Manual Pull Station (MS)
STEP      PERFORM/VERIFY
                                                  1-1            1-2      2-1   2-2

8.2.2.1   Lift wire

8.2.2.2   LED is ON.

8.2.2.3   Reattach wire

8.2.2.4   LED is OFF




                               END OF APPENDIX




                                     01670A-13
                            Requisition Number: 246168
                Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                     Date: 5-4-12
                                 SECTION 01720
                            PROJECT RECORD DOCUMENTS

PART 1 – GENERAL

1.1       SUMMARY

1.1.1     Hanford Site work requires that certain documents, defined herein, be used to record
          construction process and administration of the Contract. CHPRC will assemble
          pertinent data for final disposition.

1.1.2     Some data required for project records shall be delivered to CHPRC during the course
          of construction and contract administration, while other data shall be assembled after
          completion of construction for delivery to CHPRC.

1.1.3     Certain information for project records shall be recorded on CHPRC-provided forms.
          These forms are identified in Specifications sections where required. Copies will be
          supplied during the Preconstruction Conference (see Section 01200).

1.1.4     Project Record Documents, required by Contract, shall be prepared, preserved and
          delivered to CHPRC. These deliverable documents are in addition to submittals
          required by Section 01300.

1.2       PROCEDURE

1.2.1     Identification and Marking: Mark documents that will become project records before
          use for construction. Upon completion, identify documents by title or number.

1.2.1.1   Notes or markings added by hand shall be legible, utilizing permanent non-smearing
          marking media, such as ink or felt tip markers, in contrasting color.

1.2.1.2   Mark items to record actual construction, including changes to dimensions and
          details, manufacturer’s name, catalog number and substitute products.

1.2.2     Availability: Keep copies of Project Record Documents at the Project site, and make
          available to CHPRC during the progress of the Work.

1.2.3     Storage: Store one (1) set at the Project site, apart from documents used in
          construction and maintain in a clean dry and legible condition.

1.2.4     Delivery: Record delivery of documents by retaining copies of letters of transmittal
          itemizing delivered items and reports delivered during the course of the Work. Retain
          until construction completion. An alternate means, acceptable to CHPRC, may be
          used.




                                             01720-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                 SECTION 01720
                            PROJECT RECORD DOCUMENTS

1.3       ACTIVITY AND ADMINISTRATIVE DOCUMENTS

1.3.1     Deliver or retain in accordance with the following:

1.3.1.1   Certified Payrolls: Each week deliver certified payrolls as required by the Contract
          Provisions to CHPRC. Progress payments will not be processed unless certified
          payrolls for work periods have been received by CHPRC.

1.3.1.2   Construction Daily Activity Report (A-6004-822): Before 8:00 am each day, deliver
          to CHPRC one copy of an activity report, covering labor and supervision of
          Contractor and subcontractors for the previous day. The report shall include a general
          description of the Work performed, and a list of major items of equipment that are on-
          site.

1.3.1.3   Weekly Manpower Reports: Prepare weekly manpower reports and deliver to
          CHPRC before 10 a.m. on Monday, for the previous week, during the performance of
          the Contract.

1.3.1.4   Subcontracting Plan Reports: Deliver reports to CHPRC documenting conformance
          with the approved Subcontracting Plan, as required by SP-11.

1.3.1.5   Pre-Job Briefing Checklist: Prepare checklist during each pre-job briefing and post-
          job review. Deliver checklists to CHPRC within 5 days after briefing.

1.3.1.6   Pour Slips: After obtaining CHPRC approval of Concrete Pour Slips, deliver copies
          to CHPRC and retain Contractor copies until Contract closeout. After closeout,
          deliver to CHPRC.

1.3.1.7   Trip Tickets: Deliver copies to CHPRC with each truck load of concrete and retain
          Contractor copies until Contract closeout. After closeout, deliver to CHPRC.

1.4       CONSTRUCTION, QUALITY ASSURANCE AND SUPPORTING DOCUMENTS

1.4.1     Deliver in accordance with the following, when called for in the Specification
          Sections:

1.4.1.1   Significant Discharge Log: Log water discharged each work day and deliver
          discharge log (A-6002-294) to CHPRC.

1.4.1.2   Flushing Records: Deliver to CHPRC one copy of records verifying acceptable
          completion of flushing, before testing.

1.4.1.3   Leak/Pressure Testing Records: Deliver to CHPRC one copy of records verifying
          acceptable completion of leak and pressure testing, within five days after completion.


                                             01720-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12
                                 SECTION 01720
                            PROJECT RECORD DOCUMENTS

1.4.1.4    Calibration Records: Deliver to CHPRC one copy of instrument calibration records
           five days after Contract completion.

1.5        PRODUCT SAMPLES AND MANUFACTURER’S INSTRUCTIONS

1.5.1      In addition to the submittals required in Section 01300, and the requirements of this
           Section, information received by Contractor (from suppliers) that document products
           used and how they were installed shall be delivered to CHPRC as Project Records.

PART 2 – PRODUCTS

Not Used

PART 3 – EXECUTION

Not Used



                                       END OF SECTION




                                             01720-1
                                   Requisition Number: 246168
                       Title: 105-KE Safe Storage Enclosure (SSE) Construction
                                            Date: 5-4-12

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:56
posted:8/8/2012
language:Latin
pages:122