Safer Work Zones Through ITS by jr8z8OX

VIEWS: 3 PAGES: 9

									Safer Work Zones Through ITS

      Interim Traffic Management System
      Florida Department of Transportation
                 Tahira Faquir
The Problem
 Eight year construction of I-95
  (extending for 46 miles)
 I-95 experiences substantial peak
  hours congestion
 No existing Interstate traffic
  management system
Solution Criteria: The
Management System
 Rapidly deployable
 Mobile and reconfigurable with little
  effort
 Supports development of safety
  Measures of Effectiveness
 Supports assessment of work
  zone/non-work zone safety
Solution Composition
 Traffic Management
 Maintenance of Traffic
 Information System
Description of Components
   Traffic Management
    – Function
       • Dissemination of information to the
         traveling public
   Maintenance of Traffic
    – Function
       • Enhancement of existing MOT
       • Real Time Construction Information
Description of Components
   Information System
    – Function
       • Capture and recording of data
   Main Equipment
       •   Smart Zones
       •   Trailered Dynamic Message Signs
       •   Pole Mounted Dynamic Message Signs
       •   Traffic Management Office
       •   Website
       •   Incident Tracking Database
System Overview
                                                           Existing
                       Traffic                           Maintenance of
                     Management                             Traffic
                     Component



                                                                      FHP
 Incident Tracking                Traffic Management
     Database                            Office



             Signal
             System
                                                       Construction
                                     Road
                                    Rangers
    Safety Impacts (Goals)
System    Work Zone                     Non-Work Zone          Non-Work
Component                               (Interstate)           Zone
                                                               (Arterial)
Traffic       Reduced secondary         Incident information   Advanced
Management    accidents, reduced        dissemination,         warning of
System        incident response         accident reduction,    conditions on
              times, incident           advanced warning       the Interstate,
              information               of conditions in       Construction
              dissemination             work zones             information
Maintenance   Real-time construction    Not applicable         Not applicable
of Traffic    information in advance
              of work zones,
              reduction of
              construction related
              accidents
Information   Incident time recording   Incident time          Incident time
System        and dissemination         recording and          recording and
                                        dissemination          dissemination
Evaluation
   Elements
    – Assessment of Public’s view on effectiveness
      of system
    – Assessment of partner agencies perception of
      ITMS
    – Assessment of decision-maker’s perception of
      ITMS
    – Assessment of ITMS’s operational
      effectiveness
      • Effects of ITMS on travel delay during construction
      • Effects of ITMS on crash occurrence during
        construction and on incident response time

								