2000-03-22                                                          Trench Excavating and Backfilling

Use this Section to specify requirements which apply specifically to excavating, backfilling, and
compacting trenches required for installation of underground services, occurring within and outside
perimeter of buildings or structures. Underground services may include pipes, ducts, ductbanks,
conduit, cable, wire, etc.

This Master Specification Section contains:

.1       This Cover Sheet

.2       Specification Section Text:

         1.        General
         1.1       Intent
         1.2       Section Includes
         1.3       Related Requirements
         1.4       Related Work Specified in Other Sections/Divisions
         1.5       Coordination
         1.6       Unit Prices

         2.        Products
         2.1       Fill Materials

         3.        Execution
         3.1       Excavation
         3.2       Placement and Compaction of Fill Material
         3.3       Utility Crossings
         3.4       Pipe Trench Width
         3.5       Pipe Trench Width Schedule
         3.6       Backfilling Schedule




BMS Basic Master Specification
Alberta Infrastructure                                                                           Page 0
Master Specification System
                                                                                   Section 02319
Plan No:                                                        Trench Excavating and Backfilling
Project ID:                                                                               Page 1

1.            General

1.1           INTENT

       .1     Read this Section in conjunction with:

              .1     [Earthwork Testing:                                               Section 02010.]
              .2     Fill Materials:                                                    Section 02056.
              .3     Earthwork General Requirements:                                    Section 02305.

1.2           SECTION INCLUDES

       .1     This Section includes requirements for excavating, backfilling, and compacting trenches
              required for installation of underground services, occurring within and outside perimeter
              of buildings or structures. Underground services may include pipes, ducts, ductbanks,
              conduits, cable and wire.

1.3           RELATED REQUIREMENTS

       .1     Mechanical and Electrical
              Service Connections:                                                          Division 1.

1.4           RELATED WORK SPECIFIED IN OTHER SECTIONS/DIVISIONS

       .1     Pipe bedding for pipe utility systems:                                    Section [02 ]
       .2     Pipe bedding for mechanical services:                                      Division 15.
       .3     Pipe bedding for electrical services:                                      Division 16.

1.5           COORDINATION

       .1     Coordinate work specified in this Section with pipe bedding and other related work
              specified in other Sections.

1.6           UNIT PRICES

       .1     Trench Excavating And Backfilling:

              .1     Unit Description: Temporary access, excavating, dewatering, sheathing and
                     shoring, [support, of existing utilities], backfilling and disposal of excess and
                     waste material.

              .2     Unit of Measurement: Metre length of trench.
                                                                                     Section 02319
Plan No:                                                          Trench Excavating and Backfilling
Project ID:                                                                                 Page 2

SPEC NOTE: Include following paragraph for gravity sewer or other graded utility lines where
payment is to be made for different depth ranges.

              .3      Method of Measurement: Where depth of utility line varies, depth shall be
                      measured from original grade elevation at centre line of utility to utility invert.
                      Three depth measurements, one at each manhole and one at mid-point between
                      manholes, will be taken for each section of line. A section is defined as the
                      centreline distance between successive manholes. The average of the three
                      measurements shall be the depth for that section.

SPEC NOTE: Include the following, Topsoil Excavation, when no other site work is being carried
out.

       .2     Topsoil Excavation:

              .1      Unit Description: Stripping and [stockpiling] [disposal off-site].

              .2      Unit of Measurement: [Cut measure] [truck measure] [stockpile measure].

       .3     [    ] Fill Material:

              .1      Unit Description: [    ] material as specified in Section 02056].

              .2      Unit of Measurement: [Excavated quantity, measured by [cubic metre] [truck]
                      [tonne].] [Compacted in-place quantity, measured by [cubic metre] [truck] [tonne]
                      [square metre measured parallel to surface for specified thickness].]

       .4     [    ] Fill Material:

              .1      Unit Description: [    ] material as specified in Section 02056].

              .2      Unit of Measurement: [Excavated quantity, measured by [cubic metre] [truck]
                      [tonne].] [Compacted in-place quantity, measured by [cubic metre] [truck] [tonne]
                      [square metre measured parallel to surface for specified thickness].]

2.            Products

2.1           FILL MATERIALS

       .1     Refer to Section 02056 for fill material product specifications.
                                                                                      Section 02319
Plan No:                                                           Trench Excavating and Backfilling
Project ID:                                                                                  Page 3

3.            Execution

3.1           EXCAVATION

       .1     Excavate trenches to alignment and depth indicated or required and to uniform width,
              sufficiently wide to provide adequate working room. For pipe trenches, comply with Pipe
              Trench Width Schedule.

       .2     Grade and shape pipe trench to give uniform and even bearing for each length of pipe.
              Dig bell holes at each joint as required.

3.2           PLACEMENT AND COMPACTION OF FILL MATERIAL

       .1     Backfill trenches using fill materials as specified in Backfilling Schedule.

       .2     Place fill materials in layers not exceeding loose thickness specified in Backfilling
              Schedule.

       .3     Uniformly compact each layer of fill to minimum percentages of Standard Proctor
              Density specified in Backfilling Schedule.

       .4     Use care in backfilling to avoid damage or displacement of services.

3.3           UTILITY CROSSINGS

       .1     Install crossings as indicated on Drawings.

       .2     Comply with requirements [of crossing permit issued by utility company] [and]
              [requirements of utility company].

3.4           PIPE TRENCH WIDTH

       .1     Except as otherwise specified, minimum and maximum trench widths, up to a point
              300 mm above top of pipe [or top of highest pipe in the case of multiple pipes], shall be
              as specified in Pipe Trench Width Schedule.

       .2     Maximum trench widths indicated in Pipe Trench Width Schedule exclude an allowance
              for shoring.

       .3     Minimum trench width for "Rock Excavation in Trenches" shall be 1 m.

       .4     Trench width at any point shall not be less than trench width at any depth below such
              point.
                                                                                  Section 02319
Plan No:                                                       Trench Excavating and Backfilling
Project ID:                                                                              Page 4

3.5              PIPE TRENCH WIDTH SCHEDULE


                                 Minimum                         Maximum
No. of Pipes                     Trench Width                    Trench Width


Single pipe,                     300 mm greater than             450 mm greater than external
850 mm diameter                  external pipe                   pipe diameter or 750 mm total
or less                          diameter                        trench width, whichever is
                                                                 greater

Single pipe,                     300 mm greater than             600 mm greater than
greater than                     external pipe                   external pipe diameter
850 mm diameter                  diameter

Multiple pipes,                  300 mm greater than             600 mm greater than horizontal
side by side                     horizontal dimension            dimension across outer edges of
                                 across outer edges of pipes     pipes


3.6              BACKFILLING SCHEDULE


                                                                        Max. Lift      Minimum
Location                Fill Material                                   Thickness     Compaction


Under interior          [                              ]                 [   ] mm         [   ]%
slabs-on-grade

Under exterior          [                              ]                 [   ] mm         [   ]%
slabs-on-grade

Under landscaped        [                              ]                 [   ] mm         [   ]%
areas

Under paved areas       [                              ]                 [   ] mm         [   ]%

[          ]            [                              ]                 [   ] mm         [   ]%

Other locations         [                              ]                 [   ] mm         [   ]%



                 END OF SECTION

						
Related docs
Other docs by HC120807021435
Case Dionysia Team Registration Form
Views: 1  |  Downloads: 0
Deaths fell between 1995 181 of 1454 cases
Views: 1  |  Downloads: 0
2007 GRADUATE STUDENT
Views: 2  |  Downloads: 0
The Musculo Skeletal Centre
Views: 4  |  Downloads: 0
puoidirloqui@libero - DOC
Views: 0  |  Downloads: 0
IN CASE
Views: 0  |  Downloads: 0
CASE, GENDER & NUMBER
Views: 0  |  Downloads: 0
American Standard
Views: 5  |  Downloads: 0
bloom09 birs
Views: 0  |  Downloads: 0