                                      Procurement Plan
I.         General

1.       Project information: Zambia, Government of the Republic of Zambia, Irrigation
        Development Support Project, P102459, Loan/Credit No………., Project Implementing Agency
        (PIA): Ministry of Agriculture and Cooperatives.

2.      Bank’s approval Date of the Procurement Plan January 21, 2011

3.      Date of General Procurement Notice: TBA

4.      Period covered by this Procurement Plan: January, 2011 to July, 2012.

II. Goods and Works and Non-Consulting Services.

1.         Prior Review Threshold:
                                                    Contract Value            Contracts Subject to
     Expenditure
                          Procurement Method           Threshold                   Prior Review
      Category
                                                         (US$)                    (US$ millions)
1. Works                       ICB                 >=3,000,000               All Contracts
                               NCB                  >=50,000 - <3,000,000   As in procurement plan
                          Shopping                     <50,000                        None
                     Direct Contracting             All values               All Contracts
                     Commercial Practices           All values                        None
2. Goods                        ICB                 >=500,000                All Contracts
                               NCB                   >=50,000 < 500,000     As in procurement plan
                          Shopping                     <50,000                        None
                     Direct Contracting             All values               All Contracts
                     Commercial Practices           All values                        None



2.         Prequalification. Bidders for works and goods maybe prequalified in accordance with
           the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3.         Proposed Procedures for CDD Components (as per paragraph. 3.17 of the
           Guidelines: Use of CDD is anticipated under ISF grant subcomponent [C. 3.2].
           Modalities of implementation of CDD are described in the Project Implementation
           Manual (PIM), including how technical and procurement audits would be carried out.

4.         Reference to (if any) Project Operational/Procurement Manual: YES, a Module on
           procurement procedures of the PIM has been developed by MACO for use under the
           IDSP Project.

     5. Any Other Special Procurement Arrangements: The financing, design, .construction
        operation and maintenance of the bulk water supply infrastructure and Tier 3 farms are
        likely to involve public private partnerships. The consultant-Transaction Adviser will be
        appointed by MACO and will be involved in determining how the private sector would be
        involved. The consultant will also develop an outreach program and related events.

                                                                                                     1
                Management contracts will be let for both the bulk water supply and the Tier 3 farms.
                These will be handled following an ICB procedure and will be subject to prior review by
                IDA in line with provisions of paragraph 3.13 of the Procurement guidelines.

         5.        Procurement Packages with Methods and Time Schedule

     1               2             3               4            5           6              7         8                   10

Ref.             Contract        Estimate    Procurement   Prequa      Domestic     Review      Expected             Comments
No.             Description          d         Method      lificati   Preference    by Bank       Bid-
                                   Cost                       on       (yes/no)     (Prior /    Opening
                                (US$'000)                  (yes/no                   Post)        Date
                                                               )
Goods
1             4x4 vehicles          212      NCB           No         No           Post        21st April,     Nil
                                                                                               2011
2             4x4 vehicle           40       Shopping      No         No           Post        18th March,     Nil
                                                                                               2011
3             Motorcycles           12       Shopping/U    No         No           Post        4th March,      Nil
                                             N                                                 2011
4             Furniture for         15       Shopping      No         No           Post        1st April,      Nil
              decentralized                                                                    2011
              offices
5             Computers and         32       Shopping      No         No           Post        1st April,      Nil
              printers                                                                         2011
6             Photocopiers          21       Shopping      No         No           Post        1st April,      Nil
                                                                                               2011
7             LCD                   2        Shopping      No         No           Post        1st April,      Nil
              Projectors                                                                       2011
8             Scanners              4        Shopping      No         No           Post        6th May,        Nil
                                                                                               2011
9             Meteorological        15       Shopping      No         No           Post        15thApril,      Nil
              data logger                                                                      2011
10            Specialized           10       Shopping      No         No           Post        21stApril,      Nil
              photocopier                                                                      2011
11            Specialized           52       NCB           No         No           Post        27th May,       Nil
              equipment                                                                        2011
12            Supply and               873   Direct        No         No           Prior       10th October,   Subject to ZESCO
              installation of                Contracting                                       2012            capacity contracts
              Power                                                                                            may be let out
              transmission                                                                                     competitively to
              Lusitu                                                                                           private sector using
                                                                                                               ICB
13            Supply and           1,592     Direct        No         No           Prior       10th October,   Subject to ZESCO
              installation of                Contracting                                       2012            capacity contracts
              Power                                                                                            may be let out
              transmission                                                                                     competitively to
              Mwomboshi                                                                                        private sector using
                                                                                                               ICB
14            Supply and               269   Direct        No         No           Prior       10th October,   Subject to ZESCO
              installation of                Contracting                                       2012            capacity contracts
              Power                                                                                            may be let out
              transmission                                                                                     competitively to
              Musakashi                                                                                        private sector using
                                                                                                               NCB
Works
1             Construction of      4,774     ICB           Yes        Yes          Prior       19hOctober,     May be implemented
              civil works at                                                                   2012            using private sector
              Lusitu                                                                                           arrangements
2             Construction of     23,679     ICB           Yes        Yes          Prior       24thNovembe     May be implemented
              civil works at                                                                   r, 2012         using private sector

                                                                                                                                      2
             Mwomboshi                                                                                                   arrangements
3            Construction of        7,637     ICB             Yes           Yes          Prior           14thDecembe     May be implemented
             civil works at                                                                              r, 2012         using private sector
             Musakashi                                                                                                   arrangements
4            Environmental            707     Shopping        No            No           Post            12thOctober,    Minor various small
             implementation                                                                              2012            works all
                                                                                                                         >US$50,000
5            Decentralized            67      Shopping        No            No           Post            27th January,   Minor various small
             project offices                                                                             2012            works all
             set up                                                                                                      >US$50,000

      III. Selection of Consultants

      1.  Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in
      Appendix 1 to the Guidelines Selection and Employment of Consultants:

                                                                            Contract Value Threshold            Contracts Subject to Prior Review
           Expenditure Category             Procurement Method
                                                                                      (US$)                              (US$ millions)
                                                  QCBS                         >=100,000                                   >=200,000
                                            CQS, LCS, QBS, FBS                   <100,000                                     None
      Consulting Services (Firms)
                                                    SSS                        All values                                 All Contracts
                                            Commercial practices               All values                                     None
      Consulting Services                   Competitive selection                >=50,000                                 All Contracts
      Individual consultants (IC)                 SS (IC)                      All values                                 All contracts


      2. Short list comprising entirely of national consultants: Short list of consultants for services,
      estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national
      consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.

      3.   Any Other Special Selection Arrangements: Established private /commercial practices
      which have been found acceptable to the Association.

      4.       Consultancy Assignments with Selection Methods and Time Schedule

 1                              2                                 3                4                 5              6                 7
Ref         Description of Assignment                         Estimate       Selection          Review by      Expected         Comments
No.                                                           d Cost         Method             Bank           proposals
                                                              (US$'00                           (Prior/Post    submission
                                                              0)                                )              date

1           Dam safety panel;
            Engineering geologist/geotechnical                       33      IC                 Prior          4th December,
            engineer                                                                                           2010
            Civil/Dam Engineer                                       36      IC                 Prior          4th December,
                                                                                                               2010
            Hydrologist                                              33      IC                 Prior          4th December,
                                                                                                               2010
2           Transaction Advisory Services                           1,545    QCBS               Prior          29thApril,
                                                                                                               2011
3           Prefeasibility studies (Group 2 sites),                 1,485    QCBS               Prior          17th June,
            feasibility studies, participatory planning,                                                       2011
            detailed designs, tender documentation
            (Group 1 sites)
4           Construction supervision (group 1 sites)                 400     QCBS               Prior          13th April,
                                                                                                               2012
5           Consultant services for establishing                     118     QCBS               Prior          4thJuly, 2011


                                                                                                                                                3
             monitoring and evaluation/development of
             an MIS system
     6       Baseline study for impact assessment                    258    QCBS         Prior             8th April,
                                                                                                           2011
     7       Study on agricultural financing sector and              231    QCBS         Prior             7th April,
             strengthening financial capacity of selected                                                  2012
             banks
     8       ICT-related technical assistance to financial           614    QCBS         Prior             7th April,
             institutions.                                                                                 2012
     9       Study on safeguards policy issues &                     82     IC           Post              13th April,
             technical assistance                                                                          2011
     10      Consultants' services for study on WUA                  276    QCBS         Prior             17th April,
             policy                                                                                        2012
     11      Consultant services for risk assessment,                132    QCBS         Prior             17th April,
             annual participatory performance evaluation                                                   2012
             & dissemination of lessons learnt
     12      Study on value chain analysis & preparation             300    QCBS         Prior             5th October,
             of site specific action plans (Groups 1 & 2)                                                  2012
     13      External audit                                          21     LCS          Post              12th October,
                                                                                                           2011.
     14      Community participation & capacity                     1,900   QCBS         Prior             22ndMarch,
             building for Group 1 sites, including:                                                        2011
             Training for Transformation; capacity
             building for women; Training of Trainers in
             participatory M&E; support to land
             demarcation, titling and consolidation;
             support to legalization of producers'
             organizations; capacity building for WUAs
             and other farmers' organizations; capacity
             building for processing & marketing
             development; as well as professional
             facilitation for the participatory planning
             process - Including EIA & Resettlement
             Action Plan Group 1 sites

          IV. Implementing Agency Capacity Building Activities with Time Schedule

          1. In this section the agreed Capacity Building Activities (some items could be from
          CPAR recommendation) are listed with time schedule
No         Expected outcome /                                                     Estimated      Estimated         Start Date    Comments
.          Activity Description                                                   Cost           Duration
                                                                                  (US$'000)
1          EIA Training and sensitization                                               61       3 Months          30th June,
                                                                                                                   2011
2          Various training/capacity building courses for project                       12       3 Months          30th June,
           implementers                                                                                            2011
3          Sampling and testing (safeguards)                                            21       6 months          30th June,
                                                                                                                   2011
4          Website development & maintenance                                            15       8 weeks           14th April,
                                                                                                                   2011


          Note: All training will be based on agreed training plan that will be prepared by the Government
          of the Republic of Zambia (GoZ) and approved by the Bank and will include at the least the
          justification of the training identified and the capacity gap, the intended trainees, the name of the
          training provider, the duration and cost of training. After the training, the beneficiaries will be
          requested to submit a brief report indicating what skill have been acquired and how the skills will


                                                                                                                                     4
contribute to enhance his performance and contribute to the attainment of the project objective.
The training plan will be prepared and submitted once a year and updated as required.




                                                                                              5

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:3
posted:8/1/2012
language:English
pages:5