     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                               Unit     NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       1.0       Excavations, Backfilling, and Site Works
        1.1      Excavation for foundations; in any kind of soil to the
                 dimensions and levels shown in the drawings.
                                                                                m3                   420
        1.2      Backfilling with Selected Imported approved materials
                 up to bottom of base course underneath slab on grade,
                 and where directed by the Engineer, removal of extra and
                 unsuitable soil. Back filling shall be on layers of 200 mm
                 thick with watering and compacting to min 95% to comply
                 with modified AASHTO F.D.T. (T-80). All imported fill
                 shall be preapproved by engineer on a truck by truck
                 basis and prior to entering the site.
                                                                                m3                  1,000
        1.3      Supply and Well Compact Base Course, average 15cm.
                 Thick, for under plain concrete layer. Price includes
                 leveling, watering, compacting to 99%, leveling and
                 compacting of ground (sub-base) under base Course to
                 min 95% according to Field Density Test.

                 15 cm thick under Plain Concrete Layer                         m2                   520




                 Total For Section 1.0




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                               Unit     NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       2.0       Concrete Works
                 Preamble.
                 Rates of Concrete Works shall include:-

                  1.All form works and shuttering in any form, shape and
                 size. Making chamfered and curved edges, allowing for
                 and making grooves and sleeves and the like; removal of
                 forms and cleaning of all exposed tie wires and rods;
                 making good the harmed surfaces and edges and all
                 surface finishing.
                  2.Supplying, Casting, vibrating and curing as per
                 specifications.

                  3.Approved additives and admixtures.

                  4.Incurred costs on Concrete Mix Designs, Sample
                 taking, testing and providing test results certificates,
                 storing and saving of samples, and preparation of bar
                 bending schedules and workshops.

                  5.Supplying reinforcement of any grade, size and length
                 as detailed in the drawings, storing on site including
                 cutting, bending and fixing in position and providing all
                 tying wires, spacers, shop drawings, testing and bar
                 bending schedules

                  6.Painting of exposed surfaces of underground
                 reinforced concrete elements with two coats of hot
                 bituminous paint (75/25) , the strokes of each layer to be
                 opposite to each other.
                  7.Steel bars used for alignment and fixing of
                 reinforcement works, and extra steel added to assure
                 proper detailing and safety.

                 Measurement of Concrete elements shall be the net
                 dimensions as detailed in the drawings. All recesses
                 openings and voids shall be deducted.

                 Measurement shall be only for the seen surfaces of
                 elements. Overlapping and measuring items twice under
                 separate headings shall not be allowed.

                 Slabs are measured from the edge of external walls. (All
                 beams, drop beams, projection including fair face sun
                 breakers and any part casted together with the slab will
                 be included in the price of the slab). Columns are to be
                 measured from the top level of the slab to the bottom
                 level of the beam or dropped beam.

                  8.All wooden form work for any structural element and
                 slabs shall be made with all new wood parts.




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                               Unit     NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       2.0       Concrete Works
        2.1      Supply and Cast Plain Concrete;
                 Blinding Concrete f'c150 under foundations, footings &
                 tie beams. Thickness should be according to drawings.
                                                                                m3                    25
        2.2      Supply and Cast Reinforced Concrete Class 'f'c 250'.
                 With a minimum cement content of 300 Kg. per cubic
                 meter. Price to include for painting with two coats of hot
                 bitumen (75/25), the strokes of each layer to be opposite
                 to each other (for the buried parts).
                 Foundations and Wall Footings.                                 m3                   137
        2.3      Supply and Cast Reinforced Concrete Class 'f'c 300'.
                 With a minimum cement content of 350 Kg. per cubic
                 meter. Price to include for painting with two coats of hot
                 bitumen (75/25), the strokes of each layer to be opposite
                 to each other (for the buried parts).
       2.3.a     Tie Beams.                                                     m3                    25
       2.3.b   Walls under Slab on grade                                        m3                    3
        2.4      Supply and Cast Reinforced Concrete B200, with a
                 minimum cement content of 250 Kg, For Plain concrete
                 slab on hard core underneath tiling in ground floor and
                 where needed, 5cm thick, including 6mm steel mesh,
                 polyethylene sheets 500microns, and all related work,
                 rate to include manual smooth trowel finish and all
                 requirements as per specifications, drawings and
                 Engineer's instruction.                                        m2                   591
        2.5      Supply and Cast Reinforced Concrete Class 'f'c 300'
                 with a minimum cement content of 350 Kg. per cubic
                 meter for:
                 Stairs, landings, flights and steps and where
                                                                                m3                    3
                 required.
        2.6      Supply and Cast Reinforced Concrete Class 'f'c 300'
                 with a minimum cement content of 350 Kg. per cubic
                 meter for the following, Price to include for painting with
                 two coats of hot bitumen (75/25), the strokes of each
                 layer to be opposite to each other (for the buried parts).

       2.6.a   Column portions. (Necks).                                        m3                    8
       2.6.b   Columns.                                                         m3                    29
        2.7      Supply and Cast Reinforced Concrete Class 'f'c 300' with
                 a minimum cement content of 350 Kg. per cubic meter
                 for 32 cm thick suspended ribbed slabs. Price to
                 include for projected and drop beams, other beams and
                 projections including fair face sun breakers, supply, lay
                 and arrange hollow concrete blocks 'Grade 35' for ribbed
                 slabs, using closed end blocks as required by the
                 engineer at all ends, edges, openings, services location
                 etc. Price also include sleeves 4" and 2" required for
                 electrical or mechanical prefix works. measurement for
                 slab to be from outside edge of slab to the opposite
                 outside edge.
                                                                                m2                   531

                 Total For Section 2.0




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                               Unit     NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       3.0       Stone Works
                 Preambles
                 All Stone works shall be of local white stone of First
                 Choice.
                 Stone material, size, and texturing shall be in accordance
                 with detailed drawings and Engineer’s instructions and
                 approval.
                 Stones shall be of not less than (5 cm. thick, 25 cm. high
                 and of length ranging from 1.5 to 3 times the height.)

                 Stones shall be homogeneous in color and texturing and
                 free of any defects.
                 Cutting, shaping and building of stone shall be in straight
                 angles, no twisting, distortion or uneven sizes shall be
                 allowed.
                 All cuttings shall be made using Manjal.
                 Measurement of all types shall be in Meter Square, for
                 the net dimensions of the vertical plan of the elevations
                 excluding openings of any area.
                 No measurement will be made for any recesses,
                 projections or sides of stone pieces.
                 Measurement of door and window jambs and reveals,
                 corner peaces, and the like is not applicable.
                 No allowances shall be made for stone pieces in any
                 shape.
                 No allowances or extra rates shall be considered for
                 stone courses in lintels, overhanging slabs and roof slab
                 courses.
                 Taking all the above-mentioned into account,
                 measurement for stone cladding works will follow the
                 shape of the clad element.
                 Rates of stone works shall include:-
                 Supplying , storing, protection and removal of rejected
                 and surplus materials.
                 Shaping, cutting and fitting.
                 Mortar and backing concrete (plain concrete and/or
                 cement blocks and plain concrete).
                 Galvanized steel ties, dowels, hangers, steel mesh and
                 all tying tools.
                 Erecting and dismantling of scaffoldings.
                 Pointing and pointing materials of any type, and cleaning
                 of walls.
                 Lintels and other reinforced concrete elements
                 embedded in the stonewalls including reinforcement.
                 2Cm Polystyrene boards for insulation between concrete
                 and concrete blocks.




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                               Unit     NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       3.0       Stone Works
        3.1      Supply and Build Stone Walls;
                 Supply and build stone walls to the full length and height
                 as shown in the drawings ,Jamma` in first class and first
                 quality rough textured “Mulattash” for facades, and
                 smooth matabbah for jambs and reveals :

       3.1.a     34 cm with plain concrete (B-200), 3cm thermal insulation
                 polyester boards and cement (concrete) block backing           m2                   255
                 Grade 35 (10*20*40cm).

       3.1.b     Ditto but 40cm overall wall thickness .                        m2                    30
        3.2      Supply and Stone cladding facades over reinforced
                 concrete walls, walls between tie beams and slab on hard
                 core, slab beams. Columns ( As shown on AD00)
                 according to Palestine Standards Institution (NO.
                 113). Price to include concrete filling of plain concrete
                 Grade B-250, steel mesh and all ancillaries.
                 Price not to include for the reinforced concrete elements
                 to be caddied, which is to be measured under another
                 item.                                                          m2                   120
        3.3      Supply, Build stone coping for parapets, head of
                 columns, and balcony wall parapets as shown on details.

                 Parapet walls.                                                 m2                    31




                 Total For Section 3.0




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                                Unit    NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       4.0       Electrical Works
        4.1      GROUNDING AND BONDING
                 Supply, Install, test and commission complete earthing
                 system including earthing pits, copper rods, copper
                 conductor from earthing pit to main earthing bus as
                 specified and according to drawings.
                 30/30 mm Galvanized steel strip welded each meter to
                 foundation reinforcement and connected directly to             MR                   140
                 arbitrary main earth bus in MDB location
        4.2      CONDUITS/FIRST FIX ONLY
                 Supply and install as shown on drawings and as per
                 specifications conduits with pull wire that are required for
                 proper installation and operation of cables

       4.2.a   Ø 4" UPVC conduits from manhole to DB - LAU                      MR                    15

       4.2.b   Ø 2" UPVC conduits from manhole to DB - AC                       MR                    10

       4.2.c   Ø 4" Flexible Cobra conduits from manhole to DB - 41             MR                    40

       4.2.d   Ø 2" Flexible Cobra conduits from manhole to COMP                MR                    40




                 Total For Section 4.0




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                 Skeleton Works Package

                                                                                    Unit   NIS        Original BOQ
      Item                              Description
                                                                                                     Qty      Amount
       5.0       Mechanical Works
                 Preambles
                 All mechanical works items mentioned in here and after
                 for all project facilities and Units shall include installation,
                 adjustment, testing commissioning, and all required
                 materials, equipment and workmanship to execute the
                 items of construction in accordance with the
                 specifications, drawings, and supervising engineers
                 instructions, complete in place and ready for handing
                 over. Measurements for items with MR or MS units will
                 be based on net linear distance or net area of the
                 products
        5.1      Sleeves for Galvanized Steel Pipes
                 Supply and install Ø 3" pvc sleeves through external walls
                 for main water pipes that supply water collectors in bath
                 rooms. Locations are shown in the drawings.
                                                                                    NO                2
        5.2      Floor Traps
                 Supply and install of 4" Floor Traps in Ground Floor slab.
                 Price include also all drainage piping up to main pipe or
                 manhole                                                            NO                14
        5.3      Clean Out

       5.3.a     Supply and install 4" clean out in ground floor slab as
                 shown in the drawings.                                             NO                9
       5.3.b     Ditto but 6" Clean Out                                             NO                4
        5.4      Internal Sanitary Pipes

                 Supply and install of Drainage and storm UPVC for
                 burried network and vertical vents for both gray and black
                 system up to external manholes with all required fittings
                 and testing, all shown in the drawings.

       5.4.a     Diameter 100mm (4")                                                MR                75

       5.4.b     Diameter 150mm (6")                                                MR                30

                 Total For Section 5.0 Page -1-




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
     Operational excellence for results that matter

     Project: Police Training Facility - F41 Multipurpose Buildings
     Contract No:CON/JMOC/PTF/2010/XXX
                                                Skeleton Works Package

                                                                                 Unit   NIS           Original BOQ
      Item                             Description
                                                                                                     Qty      Amount
       5.0       Mechanical Works
        5.5      Rain Water Pipes
                 Supply, install UPVC rain water pipes down to free
                 discharge above ground level, with all required digging,
                 plastering, fittings, and vent caps, all as shown in the
                 drawings, specifications, and approval of Engineer
                 Diameter 100mm (4")                                             MR                   30
        5.6      Rain Drain
                 Supply, installation and commissioning of UPVC
                 rainwater roof drain 20cm × 20cm (quality approved). The
                 price includes horizontal 4" UPVC pipe to connect with
                 the vertical rain pipe. Locations are shown in drawings
                                                                                 NO                   5
        5.7      Sleeves for Extract Fan
                 Supply and install pvc sleeves through external walls for
                 bath rooms in order to use for the wall type extract fans.
                 Locations are shown in drawings.

       5.7.a     Ø 4" PVC Pipe                                                   NO                   1

       5.7.b     Ø 6" PVC Pipe                                                   NO                   1

       5.7.c     Ø 8" PVC Pipe                                                   NO                   2
        5.8      Sleeves for Split units connections
                 Supply and install Ø 3" pvc sleeves through external walls
                 for pipes that connect internal units with external units.
                 Locations are shown in the drawings
                                                                                 NO                   6
        5.9      Sleeves for Fire Pipes
                 Supply and install Ø 3" pvc sleeves through external walls or
                 slab for fire pipes. Locations are shown in the drawings.
                                                                                 NO                   1
                 Total For Section 5.0 Page -2-

                 Total For Section 5.0 Page 1-2




UNOPS, Jerusalem Operations Centre (JMOC), 8 Nour Ad-Din Street, East Jerusalem, oPT,| Tel: +972 2 626 1881 | Fax: +972 2 262 7586 |
Operational excellence for results that matter


                              Summary Sheet for BoQ Schedule

Project:                  Police Training Faciliy (PTF), Jericho         Contractor:

Work Area:                F41 Skeleton Works                         Contract Value:

Contract No:              CON/JMOC/PTF/2010/XXX


                                         CONTRACT SUMMARY- BSP-(B)

 Item                      Description                      Amount       Value Cpltd         % Cptd
  1.0      Excavation, Backfilling, and Site Works     ILS 0.00
  2.0      Concrete Works                              ILS 0.00
  3.0      Stone Works                                 ILS 0.00
  4.0      Electrical Works                            ILS 0.00
  5.0      Mechanical Works                            ILS 0.00




             FORECAST CONTRACT VALUE                 ILS 0.00          % Change =      #DIV/0!

				