Subject: Professional Practice(5520)

Time Duration: 3 Hrs.                                    Max. Marks: 75
Instructions: 1) All Questions are compulsory.
              2) Figures to the right indicate full marks.
              3) Assume suitable additional data if required.

Q.No.1. Answer any three:                                                    3 x 5 = 15
     a) What is the scope of work between the client and the Architect?
     b) Explain the different attributes of an Architectural Assistant in
        an Architectural firm.
     c) Explain what is a zoning map. Explain the different types of
        zones with the help of different colour codes.
     d) What are the different types of Contract? Explain any three types
        of contract.

Q.No.2. Answer any two:                                                      2 x 6 = 12
     a) Write on advertisement for tenders and information to be
        submitted in a tender notice.
     b) Which are the areas to be notified as conservation zones and why
        is it necessary to have special regulation for this type of zone,
        explain.
     c) What are Architectural competitions? Explain any three types in
        brief.

Q.No.3. Answer any two:                                                      2 x 6 = 12
     a) What is the purpose of valuation? Explain different types of
        valuation.
     b) What are Tenders? What are the different types of documents
        that are required while submitting Tender form?
     c) What constitutes contract documents? Briefly explain each of
        them.

Q.No.4. Answer any two:                                                      2 x 6 = 12
     a) Write in detail on functions of a good Architect.
     b) Which are the various authorities with their specific names and
        the sanction required for starting the construction work.
     c) Write in detail the office structure in an Architects office and
        their responsibilities.

Q.No.5. Answer any two:                                                      2 x 6 = 12
     a) Define the terms: i) Valuation ii) Contract.
     b) Explain the various drawings prepared in an Architectural firm
        and to whom it is submitted in the order of progress of work of a
        building project.
     c) Write a note on CPM and Bar Chart.

Q.No.6. Answer the following:                                                2 x 6 = 12
     a) Which are the different approving Authorities required in order to
        get the planes approved in a Muncipal area.
     b) What are the different regulations to be studied by a student
        inorder to get approval of a building plan?

                                        ***********

				