      October 14, 2009


Rio Hondo Community College District
      Board of Trustees Meeting
                Construction Update
Completed
•   Pedestrian Bridge
•   Fire Training Facility Ph I and II
•   Building Panels
•   Maintenance Facility Addition
Occupied
•   Learning Resource Center
•   Central Plant
•   Applied Technology – Building A
•   Santa Fe Springs Fire Training Facility Ph III
In Construction
•   Infrastructure
•   Applied Technology Renovation – Building B
•   South Whittier Educational Center
•   Administration of Justice
•   Mass Grading
    Learning Resource Center
                                 •   Punchlist work is nearly
                                     complete
                                 •   Building systems
                                     commissioning is in
                                     progress
                                 •   DSA final approval in
                                     process




•   Contract closeout
    underway
•   As-Built drawings received
•   Warranties received
    Central Plant/Infrastructure
                               •   DSA final approval in
                                   process
                               •   Contract closeout
                                   underway
                               •   AQMD permits will be
                                   issued in January



•   Administration Building
    chilled water connection
    installation is underway
              Applied Technology
            Building “B”
•   Construction of equipment pits
    and wall framing is underway
•   Project will be completed in
    December
    Fire Training Facility Phase III
•   Facility can be occupied
    and used
•   Delivery of training props
    is underway
•   DSA light fixture review
    is ongoing
South Whittier Educational Center
                 •   Steel framing is 80%
                     complete
                 •   Installation of concrete
                     block walls is underway
          Administration of Justice
•   Agreement with General
    Contractor has been
    signed, bonds have
    been received




                             •   Pre-construction
                                 meetings were held
                             •   NTP issued for October
                                 15, 2009. On site work
                                 to begin.
               Mass Grading

•   Site preparation for the Student Services and
    Student Union Building projects.
•   Excavation and preparation of building sites
•   Installation and relocation of underground utility
    lines.
                        Design Update
•   Physical Education Complex – State Authorization to bid received, Site re-
    design to has begun.
•   Student Services and Student Union Building – Submitted to DSA,
    Comments Received, Backcheck meetings are underway
•   Campus Quad Landscaping – Submitted to DSA, Comments Received,
    Backcheck meetings are underway
•   El Monte Center – Property in escrow, due diligence inspections have
    been conducted.
•   Terraced Walks – Stamped by DSA, RHPMT evaluating construction
    schedule
•   South Whittier Educational Center Annex – Planning has been completed,
    preparation of construction documents will begin.
•   Blue Light Phone System – Engineering to begin.
•   Campus Wide Directional and Emergency Signage – planning underway
Questions