FAMV000018 2010
Shared by: U6SJEYO6
-
Stats
- views:
- 2
- posted:
- 6/13/2012
- language:
- pages:
- 11
Document Sample


FAMV No.18 of 2010
IN THE COURT OF FINAL APPEAL OF THE
HONG KONG SPECIAL ADMINISTRATIVE REGION
MISCELLANEOUS PROCEEDINGS NO. 18 OF 2010 (CIVIL)
(ON APPLICATION FOR LEAVE TO APPEAL FROM CACV NO. 201 OF 2009)
_____________________
Between:
HAPPY DRAGON RESTAURANT LIMITED Applicant
(Respondent)
- and -
THE DIRECTOR OF LANDS Respondent
(Applicant)
_____________________
Appeal Committee: Chief Justice Ma, Mr Justice Bokhary PJ and
Mr Justice Chan PJ
Hearing and Decision: 4 November 2010
Handing Down of Reasons: 15 November 2010
D ET E R M I NAT I O N
Chief Justice Ma:
1. The background to the present case was a claim for
compensation made by the applicant under the provisions of the Lands
Resumption Ordinance Cap. 124 (“the LRO”). Before this Committee
was an application by the respondent, the Director of Lands, for leave to
appeal to the Court of Final Appeal from the decision of the Court of
- 2 -
Appeal dated 30 March 2010, in which the appeal of the applicant, Happy
Dragon Restaurant Limited, from the decision of the Lands Tribunal was
allowed, with the consequence that compensation was ordered to be paid
to the applicant ($5,337,969 payable immediately and compensation in
relation to another aspect to be assessed). Following submissions from
Mr Edward Chan SC (for the respondent), we dismissed the application
with costs.
2. The facts are contained in the judgments of the Lands Tribunal
handed down on the 28 April 2009 and of the Court of Appeal handed
down on 30 March 2010. Essentially, the applicant operated a restaurant,
occupying (as tenant) 3 properties on Shau Kei Wan Road. A Notice of
Resumption was affixed to the properties on 25 February 2005 (the
properties were part of land that was to be resumed for the purposes of a
development by the Hong Kong Housing Society).
3. In the Lands Tribunal, the applicant claimed compensation
under the LRO on the basis that the resumption had the effect of totally
extinguishing its restaurant business. Compensation was therefore
claimed under two heads: the permanent loss of the business (this was
referred to below as the Extinguishment Claim) and various losses
incurred as a result of the restaurant ceasing business (referred to as the
Disturbance Claim). By the time the matter was dealt with in the Court
of Appeal, the Disturbance Claim consisted only of a claim for the
following items:- the value of the fixtures and fittings of the restaurant,
and also losses from the early termination (through cessation of the
restaurant business at the end of February 2005) of the restaurant’s
general and liquor licences.
- 3 -
4. The Lands Tribunal dismissed both heads of claim. The
Tribunal’s reasoning proceeded mainly along the lines that the applicant
had acted unreasonably in not relocating the restaurant business;
specifically that it had not relocated to certain premises in Kwun Tong
(this was referred to in the Lands Tribunal and the Court of Appeal as the
Wah Do location). The Tribunal’s reasons for concluding that the
applicant had not acted reasonably, as indicated in its judgment dated
28.4.2009, can be summarized as follows:-
(1) The cost of relocation was in the region of $7.25m. With
assets of about $5.58m (this including a sum of $2,649,600
received as provisional compensation from the government),
the shortfall was only about $1.67m.
(2) The Tribunal found that this shortfall could have been made up
by applying to banks for a loan. It was of the view that by not
even attempting to apply for a loan, the applicant had acted
unreasonably.
(3) Another possible means of finance was to seek provisional
compensation from the government for a relocation. The
Lands Tribunal surmised it was more probable than not that the
government would have paid this provisional compensation and
this would have exceeded the provisional compensation that the
government had actually paid (amounting to $2,649,600.00).
(4) In summary, the applicant had acted unreasonably because the
Wah Do location was suitable and the applicant could, if it had
sought financing in the ways just outlined, have had the
financial resources to relocate.
- 4 -
5. Accordingly, the Tribunal dismissed the Extinguishment Claim.
For the same reason, it also dismissed the Disturbance Claim: since the
applicant had acted unreasonably in not relocating, it could not justify
those items claimed under this head of claim.
6. Following this decision, the applicant applied for a review
under s.11A of the Lands Tribunal Ordinance Cap 17. The application
was refused on 27.5.2009 (the reasons for decision were handed down on
26.6.2009). No review was embarked on: the application was simply
not entertained in the first place.
7. The Court of Appeal unanimously allowed the applicant’s
appeal. All 3 judges (Le Pichon JA, Stone and Lam JJ) wrote separate
judgments but there is consistency in their reasoning in allowing the
appeal:-
(1) On the Extinguishment Claim, the Court of Appeal was of the
view that the Tribunal had erred in its consideration of the
question of the applicant’s financial resources to relocate to the
Wah Do location:- first, the Tribunal gave insufficient weight to
the evidence from one of the witnesses called by the applicant
to the effect that it was simply not practicable or possible to
obtain financing; secondly, there was no evidence to suggest
that the government would in fact have given provisional
compensation (in excess of the $2,649,600 actually given) in
the event of a relocation; thirdly, that the shortfall was actually
more in the region of $5m, rather than the $1.67m calculated by
the Tribunal.
- 5 -
(2) On the Disturbance Claim, the Court of Appeal was of the view
in relation to the only items before it that even if the applicant
had acted unreasonably in not relocating, this did not, as
Le Pichon JA put it, “necessarily” mean that the Disturbance
Claim would fail. It was in this respect that the Lands
Tribunal had erred.
(3) The Court of Appeal was of the view that the items claimed
under the Disturbance Claim represented actual losses that the
applicant had suffered as a result of the resumption. It did not
follow even if the applicant had been unreasonable (a view with
which the Court of Appeal disagreed) that its Disturbance
Claim would “necessarily” fail, and in the circumstances of the
present case, these losses could be claimed (presumably on the
basis that they would have been suffered in any event even if
there had been a relocation). The decision of the Court of
Appeal goes no further than this and it is not to be taken that
the Court of Appeal had gone so far as the other extreme,
namely, that where an applicant has acted unreasonably in
relocating, a claim of the type of losses claimed under the
Disturbance Claim would always succeed, regardless of any
unreasonable conduct. One of the guiding principles of
resumption is that compensation for losses may only be
claimed where a claim has acted reasonably: see Director of
Buildings and Lands v Shun Fung Ironworks Ltd [1995] 2 AC
111, at 126F-H.
8. We now come to the application before us for leave to appeal to
the Court of Final Appeal. It was put on 2 bases:-
- 6 -
(1) An appeal as of right under s.22(1)(a) of the Hong Kong Court
of Final Appeal Ordinance Cap. 484 (the HKCFAO).
(2) Alternatively, discretionary leave is sought under s.22(1)(b) on
basis of what were said to be 5 points said to be of great,
general or public importance.
9. Section 22(1)(a) of the HKCFAO states:-
“(1) An appeal shall lie to the Court –
(a) as of right, from any final judgment of the Court of Appeal in any civil
cause or matter, where the matter in dispute on the appeal amounts to or
is of the value of $1,000,000 or more, or where the appeal involves,
directly or indirectly, some claim or question to or respecting property or
some civil right amounting to or of the value of $1,000,000 or more.”
10. The respondent relies on the second limb of this provision.
Mr Chan submitted that the applicant’s claim for compensation under the
LRO was a claim to or question respecting a “civil right”. The civil
right was identified to be the right (presumably as a tenant of premises) to
carry on business on those premises. Reference was made to the
opinion of Lord Nicholls of Birkenhead in Shun Fung in which reference
was made to the value of land as encompassing the ability to conduct
business on it without disturbance: at 125F. Mr Chan further submitted
that the value of this claim or question amounted to over $1m, as shown
by the order for compensation made by the Court of Appeal.
11. In our view, the respondent is not entitled to appeal as of right:-
(1) Although ultimately, it is unnecessary (for the reasons
articulated below) to decide which limb of s.22(1)(a) of the
HKCFAO the applicant’s claim for compensation comes under,
it is likely, in our view, to come within the first limb only.
- 7 -
Mr Chan submitted that the claim for compensation is a claim
to or question respecting a civil right. It is to be noted that a
civil right, for the purposes of s.22(1)(a), is a proprietary right:
see WLK v TMC [2010] 1 HKLRD 495, at 500 (para 12).
However, the nature of the applicant’s claim is in substance and
in reality for monetary compensation. It is more apt to place
the matter under the first limb of s.22(1)(a) than the second.
And if this be the case, it just cannot be said that a claim for
compensation is in the nature of a liquidated claim. Given the
range of considerations that are relevant to an assessment of
compensation, it is more in the nature of an unliquidated claim
(although we accept that it is not, strictly speaking, technically
accurate to refer to a claim for compensation as being either a
liquidated or unliquidated claim). As a number of decisions
have held, the first limb of s.22(1)(a) only covers liquidated
claims.
(2) However, even assuming that the second limb of s.22(1)(a) is
engaged, the difficulty for the respondent to overcome is the
requirement to value the relevant claim or question at the
requisite monetary level. In China Field Ltd v Appeal
Tribunal (Buildings) (No. 1) (2009) 12 HKCFAR 68, this
Committee held that even where a putative appeal involved a
claim to or question respecting property or some civil right, it
was necessary to ascribe a value to that claim or question. At
para 24, Ribeiro PJ said this :-
“Consistently with the strict approach adopted in relation to the first limb
of s.22(1)(a), it is only proper to ascribe a value which qualifies for leave
as of right to the candidate claim or question if (i) on the evidence, such
value is clearly quantifiable as a value of $1 million or more; and (ii) the
court is satisfied that the Court’s order made upon disposing of the
proposed appeal would take effect by immediately conferring or imposing
- 8 -
on the relevant parties a financial benefit or detriment in the quantified
amount. It is not enough that one is able plausibly to say that such a
financial impact is likely eventual result of the appeal.”
(3) Applying this test, we are unpersuaded that the applicant’s
claim for compensation was “clearly quantifiable” at $1 million
or over. As noted above, the exercise in the quantification of
compensation under the LRO is in many ways similar to the
assessment of unliquidated damages. For this reason alone,
this is likely to be a bar in many cases where compensation is
claimed for a resumption. This is all the more so in the
present case where the quantification of the applicant’s claim
was at one stage nil (as the Lands Tribunal found) or substantial
(as the Court of Appeal found). The respondent clearly fails
to satisfy the requisite test.
12. Under s.22(1)(b) of the HKCFAO, 5 questions are identified by
Mr Chan said to constitute points of great general or public importance
(these are taken from counsel’s skeleton submissions) :-
(1) “… whether or not in an appeal against the Tribunal’s original decision, an appellate
court should disregard the Tribunal’s reasons for refusing to review its original
decision?”
(2) “… whether or not an applicant making a disturbance claim under section 10(2)(d) of
the LRO is under a duty to mitigate his loss and whether in discharging his burden of
showing actual loss and damage having been caused by the removal of the business
from the land resumed a claimant for compensation for land resumption has a burden
of discharging the burden that the loss and damage is not caused by any failure in
mitigating the loss and damage?”
(3) “… whether the Court of Appeal is entitled to substitute its own view in contrary to
that of the Tribunal on matter of the licensing practices where there is no evidence
adduced to support of either the view of the Tribunal or that of the Court of Appeal.”
(4) “… how should the Court of Appeal approach a “perversity”ground of appeal?”
(5) “… whether the Lands Tribunal is entitled to use its own knowledge and experience
when reaching its decision on the question of whether the Government would or
would not make an provisional compensation and also how the Government would
have.”
- 9 -
13. On the first question, the respondent sought to argue that the
reasons handed down by the Lands Tribunal on 26 June 2009 for
dismissing the application for a review ought to have formed part of the
reasoned judgment for dismissing the applicant’s claim for compensation,
and that accordingly, the Court of Appeal ought to have looked at not
only the Tribunal’s judgment dated 28 April 2009, but also the reasons for
dismissing the application for review. Contrary to what appeared to be
the respondent’s position in counsel’s skeleton submissions, Mr Chan
frankly acknowledged that the reasons of 26 June 2009 did supplement or
qualify the reasons contained in the original judgment dated 28 April
2009. There would otherwise have been little point in the exercise.
14. The Court of Appeal refused to look at the reasons for refusing
to enter into a review. In para 20 of her judgment, Le Pichon JA said
this: “Where the Tribunal declines to review its decision, the reasons it
gives cannot supplement, alter or qualify the findings of fact made in the
judgment sought to be reviewed”.
15. We agree. If the Tribunal had actually embarked on a review
and made findings, an appellate court would be bound to look at the
reasons in order to decide whether the decision was correct. Where, as
in the present case, the Tribunal did not even enter into a review, the
reasons given in support of the decision not to conduct a review cannot
alter, supplement or qualify findings made in the original judgment or
decision.
16. Mr Chan placed great reliance on the Tribunal not being as a
matter of jurisdiction functus officio when it handed down the reasons for
refusing the review. We accept that the Lands Tribunal was not functus
- 10 -
officio and obviously had the jurisdiction to grant (or refuse) a review.
However, this was not the issue at all and does not take the matter much
further. For the true question in the present case is whether the Court of
Appeal was, in an appeal against the original decision, correct to
disregard the additional reasoning of the Lands Tribunal in dismissing the
application for a review. As is clear from our earlier observation, this is
unarguable. No question of great, general or public importance
therefore arises.
17. On the second question, no point of great, general or public
importance arises either. It is already well settled that compensation for
a resumption of land is payable under the LRO where the claim for losses
caused by the resumption are not too remote and where the applicant has
acted reasonably: see Shun Fung at 126A-H. Mr Chan made no
submissions on the reference in this formulated question to the burden of
proof, but we would observe that, like questions of mitigation that arise in
other legal contexts, the burden is on the party who alleges
unreasonableness.
18. The remaining questions can be quickly disposed of. They are
simply not questions of great, general or public importance: they reflect
merely a dissatisfaction on the part of the respondent with the result
reached by the Court of Appeal.
(Geoffrey Ma) (Kemal Bokhary) (Patrick Chan)
Chief Justice Permanent Judge Permanent Judge
- 11 -
Mr Edward Chan SC and Mr Anthony Ismail (instructed by the
Department of Justice) for the respondent (applicant)
Mr Johnny Mok SC and Mr Richard Leung (instructed by Messrs Lo &
Lo) for the applicant (respondent)
Get documents about "