GBF FundingOffers Round7 by r1STcj

VIEWS: 0 PAGES: 23

									Green Building Fund
Funding offers for Round 7, Stream A



STREAM A: These are retro-fitting and/or retro-commissioning projects aimed at reducing the greenhouse gas emissions of existing commercial office
buildings, hotels and shopping centres by reducing energy consumption.


                                                                                                                            Predicted
                                                                                                                            GHG
                                                                                                                            savings
                                                                                                                            (tonnes         Grant offer
                                                                                                                            CO2(e) per      (GST
State    Building address          Applicant                   Project description                                          annum)          exclusive)

ACT      2 Constitution            ISPT Pty Ltd ATF            The project involves the upgrade of the base building        1,084           $250,776
         Avenue, Canberra          Industry                    services to improve energy efficiency and demonstrate
                                   Superannuation              tangible energy reduction and actively minimise
                                   Property Trust No. 1        ongoing environmental impact by reducing
                                                               consumption of electricity, gas and water. All base
                                                               building services including the mechanical, electrical,
                                                               fire, hydraulics and lift services will be upgraded.
ACT      14 Moore Street,          DEXUS Funds                 The works will include the upgrade/replacement of the        832             $500,000
         Canberra                  Management Limited          Building Management and Control System (BMCS),
                                   AREF DEXUS                  high efficiency chillers, variable speed drives, and
                                   Diversified Trust           damper and control modifications.
ACT      38 Sydney Avenue,         Mirvac Funds Limited        The project will involve the installation of high            511             $500,000
         Forrest                   ATF Mirvac                  efficiency chillers, high efficiency pumps, boiler
                                   Commercial Trust            upgrades, lighting and energy metering systems
                                                               delivered via an energy performance contract.
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                  Predicted
                                                                                                                  GHG
                                                                                                                  savings
                                                                                                                  (tonnes       Grant offer
                                                                                                                  CO2(e) per    (GST
State   Building address       Applicant               Project description                                        annum)        exclusive)

ACT     205 Anketell Street,   GE Real Estate          This project includes the replacement of the chiller and   312*          $500,000
        Tuggeranong            Investments Australia   boiler, Building Management system upgrade, and the
                               Pty Ltd                 installation of Shaw Method of Air Conditioning
                                                       dedicated outdoor air-handling unit.
ACT     11-17 Swanson          GE Real Estate          This project includes the installation of a new air        478*          $500,000
        Court, Belconnen       Investments Australia   handling system, and ventilation system control.
                               Pty Ltd
NSW     Sheraton on the Park   Sheraton On The Park    This project involves replacement of a chiller and        3,594          $500,000
        Hotel, 161 Elizabeth   Pty Ltd                 the installation of variable speed drives, and update of
        Street, Sydney                                 the building management system to allow for energy
                                                       monitoring, reporting and tracking. The project also
                                                       includes the re-fitting of economy cycle on some air
                                                       handling units and installation of LED down lights in
                                                       hotel corridors.
NSW     Park Hyatt Hotel       Daisho Development      The project involves replacing the existing chiller with 775             $308,900
        Sydney, 7 Hickson      Sydney Pty Ltd          one which offers variable speed drive centrifugal
        Road, The Rocks,                               compression, as well as the installation of a new BMS
        Sydney                                         to control and monitor energy consumption. The
                                                       introduction of this advanced technology will achieve
                                                       significant increases in energy efficiency throughout all
                                                       areas of the property.




                                                                                                                               Page 2 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                   Predicted
                                                                                                                   GHG
                                                                                                                   savings
                                                                                                                   (tonnes       Grant offer
                                                                                                                   CO2(e) per    (GST
State   Building address       Applicant                 Project description                                       annum)        exclusive)

NSW     33 Alfred Street,      Kent Street Pty Limited An energy efficiency project which includes the             1,377         $500,000
        Sydney                 ATF Sydney Cove         upgrade of air handling units and new digital BMCS,
                               Trust                   delivering significant energy savings for Sydney's first
                                                       high rise commercial building.
NSW     171 Clarence Street,   Abacus Funds            The works will include improving the building               588           $383,731
        Sydney                 Management Limited      controls, replacing the chillers with the most efficient
                               AREF Abacus 171         on the market and reconfiguring the air distribution
                               Clarence Street Trust   systems to increase the operational efficiency.
NSW     Stockland Green        Stockland Trust         The project involves the installation of solar panels and   911           $400,000
        Hills Shopping         Management Limited      LED lighting (providing renewable energy to the
        Centre, 1 Molly        AREF Stockland Trust shopping centre); intelligent sub-metering to monitor
        Morgan Drive, East                             power consumption; and a building tuning program to
        Maitland                                       optimise building operations.
NSW     Carlingford Court      GPT Funds               Through the improvement of plant, equipment and the         1,250         $262,500
        Shopping Centre,       Management Limited      implementation of innovative technologies GPT Retail
        Corner Pennant Hills   AREF GPT Wholesale will further improve the energy performance of
        & Carlingford Roads,   Shopping Centre Fund Carlingford Court. These improvements include
        Carlingford            No.1                    replacement of metal hallide and dichroic lamps in
                                                       common areas and car parks, chiller controls upgrade
                                                       plus variable speed drive installation. This site has a
                                                       long history of energy conservation and these
                                                       initiatives will further improve the energy
                                                       consumption.




                                                                                                                                Page 3 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                    Predicted
                                                                                                                    GHG
                                                                                                                    savings
                                                                                                                    (tonnes       Grant offer
                                                                                                                    CO2(e) per    (GST
State   Building address       Applicant                Project description                                         annum)        exclusive)

NSW     207 Pacific Highway,   Eureka Funds             This project involves a lighting upgrade and the            490           $109,333
        St Leonards            Management Limited       installation of variable speed drive controls.
                               ATF Alternative
                               Investment (Real
                               Estate) Private
                               Syndicate
NSW     99 Elizabeth Street,   Tackelly No. 8 Pty Ltd   This project involves a major upgrade involving: the        820           $500,000
        Sydney                 ATF Tackelly No. 8       building façade, the base building lighting and air-
                               Trust                    conditioning, a central chilled water plant, a sub-
                                                        metering system and a building management system.
NSW     Four Seasons Hotel,    199 George Street        The project involves an upgrade of incandescent and         1,771         $410,984
        199 George Street,     Hotel Pty Limited        inefficient halogen lamps with energy efficient
        Sydney                                          lighting, as well as the implementation of intelligent
                                                        room air-conditioning and lighting control systems.
NSW     203 Coward Street,     Cromwell Property        This project consists of the installation of on-floor air   1,500         $500,000
        Mascot                 Securities Limited ATF   handling units; heating reticulation system; variable
                               Mascot Trust             speed drive pumps and chilled water pipe work to
                                                        facilitate the installation of a tri-generation system at
                                                        the Qantas corporate centre.
NSW     Chifley Tower &        Reco Bathurst Pty Ltd    The project involves the upgrade of the HVAC system         3,371         $500,000
        Plaza, 2 Chifley                                into a centralised chilled water system, configuration
        Square, Sydney                                  and establishment of zoned air distribution, update of
                                                        the BMS control logic and recommissioning and
                                                        improvement of common area lighting.



                                                                                                                                 Page 4 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                               Predicted
                                                                                                               GHG
                                                                                                               savings
                                                                                                               (tonnes       Grant offer
                                                                                                               CO2(e) per    (GST
State   Building address      Applicant                Project description                                     annum)        exclusive)

NSW     345 George Street,    ISPT Pty Ltd ATF         The project involves a major improvement of the          418          $102,000
        Sydney                Industry                 energy efficiency of the building through total
                              Superannuation           replacement of the Building Management and Control
                              Property Trust No. 1     System, upgrade of the hot water boiler, and
                                                       installation of variable speed drives on heating water
                                                       pumps. The project also includes conversion of the
                                                       condenser water facility to a true variable volume
                                                       system, HVAC air side re-tuning and control strategy
                                                       optimisation.
NSW     Erina Fair Shopping   Lend Lease Real Estate   The project includes the installation of an integrated   1,156        $232,069
        Centre, Eastern Road, Investments Limited      energy management system, an upgrade to the Building
        Erina                 AREF Australian          Management System, air-conditioning
                              Prime Property Fund -    enhancements/upgrades and a comprehensive
                              Retail                   commissioning and tuning process.
NSW     10 Smith Street,      ISPT Pty Ltd ATF         The project involves improvement of the energy           559          $130,500
        Parramatta            Industry                 efficiency of the building through upgrade of the
                              Superannuation           central refrigeration system by introduction of variable
                              Property Trust No. 1     pumping system, upgrade of controls, conversion of the
                                                       condenser water system to variable volume and
                                                       optimum tuning of the variable air volume air side
                                                       system.




                                                                                                                            Page 5 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                              Predicted
                                                                                                              GHG
                                                                                                              savings
                                                                                                              (tonnes       Grant offer
                                                                                                              CO2(e) per    (GST
State   Building address    Applicant                Project description                                      annum)        exclusive)

NSW     477 Pitt Street,    ISPT Pty Ltd ATF         The project involves a major improvement of the           1,527        $361,945
        Sydney              Industry                 energy efficiency of the building through an upgrade of
                            Superannuation           the central refrigeration system by providing high
                            Property Trust No. 2     efficiency chillers and controls as well as an overhaul
                                                     of the entire HVAC air side systems by providing the
                                                     required hardware and software and optimum
                                                     utilisation of plant resources.
NSW     Shangri-La Hotel,   Lilyvale Hotel Pty. Ltd. The project involves the installation of guest room       3,555        $500,000
        176 Cumberland                               management system (which will control heating and
        Street, The Rocks                            lighting and reduce energy consumption when the
                                                     room is unoccupied), common area LED Lighting
                                                     upgrade, a chiller upgrade which includes variable
                                                     speed drives (VSDs), and a chiller plant energy
                                                     optimisation and monitoring system.
NSW     255 Pitt Street,    ISPT Pty Ltd ATF         The project involves rectification of design deficiencies 539          $121,950
        Sydney              Industry                 in relation to delivery of outside air to the central
                            Superannuation           HVAC air handling plant. Improvement of the energy
                            Property Trust No. 2     efficiency of the building through upgrade of the
                                                     central refrigeration system by introduction of variable
                                                     pumping system and controls upgrade and optimum
                                                     tuning of the variable air volume air side system.




                                                                                                                           Page 6 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                      Predicted
                                                                                                                      GHG
                                                                                                                      savings
                                                                                                                      (tonnes       Grant offer
                                                                                                                      CO2(e) per    (GST
State   Building address         Applicant                 Project description                                        annum)        exclusive)

NSW     363 George Street,       ISPT Pty Ltd ATF          The project involves improvement of the energy             1,221         $234,960
        Sydney                   Industry                  efficiency of the building through upgrade of the
                                 Superannuation            central refrigeration system by retrofitting one
                                 Property Trust No. 1      centrifugal chiller with variable speed drive,
                                                           introduction of variable pumping system and controls
                                                           as well as recalibration and tuning of the entire HVAC
                                                           air side system by providing smart algorithms in
                                                           optimising the zoning of the current arrangement.
NSW     Crowne Plaza             Hanz (Coogee) Pty Ltd     This project consists of an upgrade of the Building        1,776         $303,055
        Coogee Beach Hotel,      ATF Hanz (Coogee)         Management System and the installation of networked
        Corner Carr & Arden      Trust                     smart room controllers in all guest rooms.
        Streets, Coogee
NSW     Crowne Plaza             Hanz (Terrigal) Pty Ltd   This project consists of the replacement of the            2,445         $377,000
        Terrigal Hotel, Pine     ATF Hanz (Terrigal)       building's Air Handling Units and an upgrade of the
        Tree Lane, Terrigal      Trust                     Building Management System.
NSW     Holiday Inn Potts        Hanz (Potts Point) Pty    This project consists of an upgrade of the Building        1,067         $338,244
        Point Hotel, 203         Ltd ATF Hanz (Potts       Management System, the installation of networked
        Victoria Street, Potts   Point) Trust              smart room controllers in all guest rooms and a lighting
        Point                                              upgrade.
NSW     Port Central             Gowing Bros Ltd           The project involves the installation of a solar boosted   1,689         $500,000
        Shopping Centre, 40-                               direct fired absorption chiller with a biogas backup
        42 Horton Street, Port                             system along with the introduction of a BMS, LED
        Macquarie                                          lighting, smart metering and variable speed drive
                                                           exhaust motors.



                                                                                                                                   Page 7 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                  Predicted
                                                                                                                  GHG
                                                                                                                  savings
                                                                                                                  (tonnes       Grant offer
                                                                                                                  CO2(e) per    (GST
State   Building address      Applicant                Project description                                        annum)        exclusive)

NSW     Building B,           The Trust Company       This project consists of the installation of energy         702           $352,000
        Macquarie Corporate   Limited as Custodian    efficient chillers; the addition of variable speed drives
        Park, 101 Waterloo    for Goodman Australia   to the chilled and condenser water pumps and the
        Road, North Ryde      Industrial Trust No. 3  cooling water tower fans; a complete building energy
                                                      tune-up and an upgrade of base building lighting and
                                                      lighting controls.
NSW     80 Clarence Street,   Asia Pacific Investment The project involves an upgrade of the chiller water        587           $500,000
        Sydney                T2 Pty Ltd ATF          system and air conditioning, the replacement of cooling
                              Pioneer Clarence        towers, the upgrade of the base building lighting, and
                              Property Trust          the installation of a new building management control
                                                      system.
NSW     Lilianfels Hotel, 1   Lilianfels Hotel Blue   The project involves replacement and relocation of the      1,267         $500,000
        Lilianfels Avenue,    Mountains Pty Ltd       current chiller and water heaters with a high efficiency
        Katoomba                                      unit that allows recovery of waste heat, for use in both
                                                      hotel pools and to provide hot water to the hotel. LED
                                                      lighting will be installed in common areas, and all
                                                      guest rooms will have upgraded air-conditioning, with
                                                      central controls linked to a new building management
                                                      system.
NSW     Westpac Place, 275    Mirvac REIT             The project will involve the installation of a              3,367         $500,000
        Kent Street, Sydney   Management Limited      trigeneration plant as well as an energy sub-metering
                              ATF Mirvac Office       system.
                              Trust




                                                                                                                               Page 8 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                  Predicted
                                                                                                                  GHG
                                                                                                                  savings
                                                                                                                  (tonnes       Grant offer
                                                                                                                  CO2(e) per    (GST
State   Building address        Applicant              Project description                                        annum)        exclusive)

NSW     15 Blue Street, North   Brookfield Australia   The Fujitsu Centre, North Sydney will undergo a            1,049         $500,000
        Sydney                  Funds Management       strategic energy efficiency services upgrade in 2011
                                Limited AREF           with installations of new buildings services and
                                Brookfield Onyx        modifications. This will result in significant reduction
                                Property Trust         of energy usage and improved operational efficiency
                                                       for the base building services, while maintaining
                                                       current tenant services.
NSW     77 Castlereagh Street, Westfield Management    The project involves a building energy efficiency          1,234         $500,000
        Sydney                 Ltd ATF Westfield Sub   upgrade, including upgrade of central plant to replace
                               Trust G                 the chiller and other modifications, common area
                                                       lighting upgrade, and replacement of the Building
                                                       Management System..
NSW     461-471 Victoria     BNY Trust Company         The project will involve the replacement of chillers and   1,779         $500,000
        Avenue, Chatswood    Of Australia Limited      floor outlets, upgrade of BMS, installation of new T5
                             As Custodian For FKP      lighting on all office floors, new distribution boards
                             Property Trust            and metering to all floors.
NSW     1 Epping Road, North GTA Industrial            This project will involve a range of energy efficiency     508           $155,710
        Ryde                 Custodian Pty Limited     measures including the implementation of lighting
                             ATF Delhi Road North      upgrades, lighting controls, CO sensors, variable speed
                             Ryde Trust                drives (VSD) and a utility monitoring system.




                                                                                                                               Page 9 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                 Predicted
                                                                                                                 GHG
                                                                                                                 savings
                                                                                                                 (tonnes        Grant offer
                                                                                                                 CO2(e) per     (GST
State   Building address      Applicant              Project description                                         annum)         exclusive)

NSW     60 Margaret Street,   Mirvac Funds Limited   The project involves upgrades to air-conditioning fan       1,021          $500,000
        Sydney                ATF Mirvac             and pump motors, Building Management System
                              Commercial Trust       hardware and software, common area lighting and
                                                     installation of speed controllers and an ultra violet air
                                                     treatment system.
NSW     Holiday Inn Hotel     Schwartz Family Co.    This project will involve the installation of a building    1,200          $163,071
        Sydney Airport,       Pty Ltd ATF Schwartz   management system to control chillers, pumps, cooling
        Corner Bourke Road    Family Trust           towers, boilers, fan coil units and ventilation fans
        & O'Riordan Street,                          which will allow for the implementation of an energy
        Mascot                                       management system.
NSW     307 King Street,      Newcastle Permanent    This project involves removal of existing water-cooled      543            $412,225
        Newcastle West        Building Society       chillers and replacing them with energy efficient
                              Limited                Powerpax chillers. The project will significantly reduce
                                                     the building's CO2 emissions and energy consumption.
NSW     Tweed City Shopping   DEXUS Funds            This project includes optimisation of existing HVAC         1,766          $500,000
        Centre, 54            Management Limited     plant including the replacement of the cooling tower,
        Minjungbal Drive,     as Manager for SAS     chiller and tuning of BMS, a lighting upgrade replacing
        South Tweed Heads     Trustee Corporation    metal halides with LED downlights, installation of an
                                                     intelligent metering system to monitor ongoing
                                                     building performance and an advanced controls system
                                                     to augment the existing monitoring system to gain
                                                     additional visibility on the plant areas.




                                                                                                                              Page 10 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                     Predicted
                                                                                                                     GHG
                                                                                                                     savings
                                                                                                                     (tonnes        Grant offer
                                                                                                                     CO2(e) per     (GST
State   Building address        Applicant               Project description                                          annum)         exclusive)

NSW     Plumpton Market         DEXUS Funds             The improvement program involves implementing                606            $368,771
        Place Shopping          Management Limited      HVAC optimisation strategies which include replacing
        Centre, Corner Jersey   as Manager for SAS      remaining AC units and retrofitting remaining
        & Hyatts Roads,         Trustee Corporation     economy air cycles; upgrading existing metal halides
        Plumpton                                        with energy efficient LED downlights; reducing
                                                        temperature loading through SkyCool roof paint and
                                                        installing an intelligent metering system to monitor
                                                        ongoing building performance.
NSW     90 Arthur Street,       GE Real Estate          This project includes the Building Management System         635*           $500,000
        North Sydney            Investments Australia   upgrade, installation of new economy air cycles and
                                Pty Ltd                 gas boilers, upgrade of car park lighting and the
                                                        replacement of electric hot water with a solar system.
NSW     60 Carrington Street,   GE Real Estate          This project includes the installation of a new chiller, a   978*           $500,000
        Sydney                  Investments Australia   Shaw Method of air conditioning dedicated outdoor
                                Pty Ltd                 air-handling unit, replacement of boilers, and a
                                                        Building Management System upgrade.
NSW     99 Walker Street,       GE Real Estate          This project includes the upgrade of metering, car park      1,678*         $500,000
        North Sydney            Investments Australia   controls, and the Building Management
                                Pty Ltd                 System, and replacement of the chiller.




                                                                                                                                  Page 11 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                   Predicted
                                                                                                                   GHG
                                                                                                                   savings
                                                                                                                   (tonnes        Grant offer
                                                                                                                   CO2(e) per     (GST
State   Building address       Applicant             Project description                                           annum)         exclusive)

NT      Crowne Plaza Hotel,    Investnorth Pty Ltd   This project consists of the partial redesign of              1,211          $440,090
        82 Barrett Drive,                            the HVAC system to reduce outside air requirement; it
        Alice Springs                                includes the installation of Energy Recovery
                                                     Ventilation units; CO2 sensors, specialised return air
                                                     filtration, installation of a high efficiency low load
                                                     Chiller and the replacement of the electrical resistive
                                                     heater elements with air to air heat pumps.
NT      Casuarina Square       GPT RE Limited        A comprehensive upgrade of Casuarina Square will              2,585          $500,000
        Shopping Centre, 247   AREF General          deliver emissions savings, through a program of
        Trower Road,           Property Trust        efficiency upgrades. Major works include the
        Casuarina                                    installation of new chiller controls, variable speed
                                                     drives, lighting controls, reflective roof paint, solar hot
                                                     water and an enhanced energy management system to
                                                     further build on the energy efficiency achieved at the
                                                     site through intelligent dynamic monitoring. The
                                                     project incorporates a holistic approach to maximising
                                                     energy efficiency.




                                                                                                                                Page 12 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                  Predicted
                                                                                                                  GHG
                                                                                                                  savings
                                                                                                                  (tonnes        Grant offer
                                                                                                                  CO2(e) per     (GST
State   Building address       Applicant                Project description                                       annum)         exclusive)

QLD     Suncorp Metway         Suncorp Corporate        This project involves a chiller and building              810            $500,000
        Centre, 36 Wickham     Services Pty Ltd         management system upgrade (which will incorporate
        Terrace, Spring Hill                            smart metering to track building energy consumption),
                                                        and installation of variable speed drives for pumps.
                                                        Invented in Australia, the Shaw Method of Air-
                                                        Conditioning is an energy saving technology whereby
                                                        incoming outside air is pre-treated (dehumidified and
                                                        cooled) by a separate, outside air coil before merging
                                                        with inside air.
QLD     Holiday Inn Hotel,     BG Hotels (HIC) Pty      This project will reduce energy consumption and           1,085          $400,205
        Corner Abbott &        Ltd                      greenhouse gas emissions. Project activities involve an
        Florence Streets,                               upgrade of the Building Management System;
        Cairns                                          installation of CO2 sensors on air handling units;
                                                        installation of variable speed drives on pool pump
                                                        motors; replacement of chiller with an energy efficient
                                                        machine which incorporates a heat recovery system
                                                        and retrofitting of LED lamps.
QLD     Hilton Hotel, 34       BG Hotels (Cairns) Pty   This project will involve replacing the HVAC system;      1,320          $469,985
        Esplanade, Cairns      Ltd                      installing LED lamps; installing CO2 controls on
                                                        various air handling units; installing variable speed
                                                        drives on the pool pump control; and an upgrade of the
                                                        building management system.




                                                                                                                               Page 13 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                 Predicted
                                                                                                                 GHG
                                                                                                                 savings
                                                                                                                 (tonnes        Grant offer
                                                                                                                 CO2(e) per     (GST
State   Building address      Applicant               Project description                                        annum)         exclusive)

QLD     Clifford Gardens      Commonwealth            This project will optimise air-conditioning plant          821            $324,509
        Shopping Centre,      Managed Investments     operation to deliver saving through: increased
        James Street,         Limited AREF CFS        utilisation of free cooling from outside air, tuning of
        Toowoomba             Retail Property Trust   cooling plant operation and optimisation of daily plant
                                                      starting times. The airflows in the building will be
                                                      balanced and variable speed drives will be installed on
                                                      fan motors to save fan energy through reducing fan
                                                      speeds in day to day operation.
QLD     Myer Centre, 91       Commonwealth            This project consists of implementation of smart           1,999          $333,349
        Queen Street,         Managed Investments     energy efficiency controls on the chiller plant,
        Brisbane              Limited AREF CFS        installation of and commissioning a variable speed
                              Retail Property Trust   drive to condenser water pumps to reduce pump
                                                      speeds, installation of an independent cooling system
                                                      for the lift motor room, and conversion of the air
                                                      conditioning system to operate with variable volume
                                                      airflows.
QLD     Grand Plaza           Commonwealth            This project consists of upgrading chilled water valves;   882            $115,455
        Shopping Centre,      Managed Investments     re-programming air-conditioning zone controls,
        Corner Mt Lindesay    Limited AREF CFS        optimising chilled water pumping, increasing
        Highway & Browns      Retail Property Trust   utilisation of free cooling from outside air, and
        Plains Road, Browns                           installing variable speed drive controls on various fans
        Plains                                        and pumps.




                                                                                                                              Page 14 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                   Predicted
                                                                                                                   GHG
                                                                                                                   savings
                                                                                                                   (tonnes        Grant offer
                                                                                                                   CO2(e) per     (GST
State   Building address       Applicant               Project description                                         annum)         exclusive)

QLD     Stockland Cairns       Stockland Trust         The project involves upgrading the air-conditioning         1,133          $107,750
        Shopping Centre, 537   Management Limited      system to demand control ventilation by installing CO2
        Mulgrave Road,         AREF Stockland Trust    sensors, outside air dampers, modifying the building
        Earlville                                      management system and building tuning.
QLD     Stockland Townsville   Stockland Trust         The project involves an upgrade of the existing light       1,975          $500,000
        Shopping Centre, 310   Management Limited      systems to reduce energy usage, and the installation of
        Ross River Road,       AREF Stockland Trust    new water cooled air-conditioning and sub-metering
        Aitkenvale                                     systems.
QLD     Queens Plaza           Commonwealth            This project consists of tuning chilled water valve         1,073          $69,404
        Shopping Centre, 226   Managed Investments     operation, tuning air-conditioning zone operation,
        Queen Street,          Limited AREF CFS        installing high efficiency chiller controls, increasing
        Brisbane               Retail Property Trust   utilisation of free cooling from outside air and
                                                       converting air conditioning system to operate with
                                                       variable volume airflows.
QLD     Capalaba Central       DEXUS Funds             The project involves a lighting upgrade, the installation   1,315          $500,000
        Shopping Centre,       Management Limited      of variable speed drives on specific pumps and fans,
        Moreton Bay Road,      as Manager for SAS      the implementation of an intelligent metering system,
        Capalaba               Trustee Corporation     plus the augmentation of the monitoring system
                                                       through the installation of an advanced controls
                                                       strategy.
QLD     313 Adelaide Street,   F. A. Pidgeon & Son     The project will involve extensive works including the      1,664          $500,000
        Brisbane               Pty. Ltd.               upgrade of the HVAC system, chilled water, energy
                                                       meters and BMS, electrical system, water heating and
                                                       lifts.



                                                                                                                                Page 15 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                    Predicted
                                                                                                                    GHG
                                                                                                                    savings
                                                                                                                    (tonnes        Grant offer
                                                                                                                    CO2(e) per     (GST
State   Building address       Applicant                Project description                                         annum)         exclusive)

QLD     247 Adelaide Street,   Lake Nathan Pty Ltd      The project will involve the installation of a new gas-     678            $500,000
        Brisbane               ATF 247 Adelaide         fired micro turbine trigeneration system which will
                               Street Trust             produce electricity to service the entire base building.
                                                        Waste exhaust heat will run an absorption chiller for
                                                        HVAC requirements, while solar thermal units, LED
                                                        lighting and BMS upgrades will further reduce energy
                                                        consumption.
QLD     Sofitel Brisbane       Thakral Operations Pty   This project will involve the implementation of an          1,652          $317,203
        Central Hotel, 249     Ltd ATF The Property     EDGE intelligent system, lighting upgrades, CO2
        Turbot Street,         Operations Unit Trust    sensors, variable speed drives (VSD) and heat pump
        Brisbane                                        upgrades.
QLD     Kawana Shopping        Mirvac Funds Limited     The project involves the conversion of air handling         1,294          $500,000
        Centre, 119 Point      AREF Mirvac Property     units to chilled water; construction of a high efficiency
        Cartwright Drive,      Trust                    chiller plant; and the installation of SMAC air
        Buddina                                         conditioning.
QLD     Stamford Plaza         Stamford Heritage Pty    The energy saving project at the Stamford Plaza will        2,081          $500,000
        Brisbane Hotel, 39     Ltd                      include a lighting and chiller upgrade, installation of a
        Edward Street,                                  cooling system variable speed drive controls and a
        Brisbane                                        bathroom occupancy detection system.
QLD     179 North Quay,        GE Real Estate           This project includes the implementation of the Shaw        382*           $488,500
        Brisbane               Investments Australia    Method of Air Conditioning with chiller replacement,
                               Pty Ltd                  and air handling unit refurbishment.




                                                                                                                                 Page 16 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                     Predicted
                                                                                                                     GHG
                                                                                                                     savings
                                                                                                                     (tonnes        Grant offer
                                                                                                                     CO2(e) per     (GST
State   Building address      Applicant                 Project description                                          annum)         exclusive)

QLD     127 Creek Street,     GE Real Estate            This project includes the replacement of the low and         1,058*         $500,000
        Brisbane              Investments Australia     high load chillers, the addition of a dedicated outdoor
                              Pty Ltd                   air handling unit, and a Building Management System
                                                        upgrade.
QLD     Westfield Carindale   Westfield Shopping        The project involves replacing one chiller with state of     2,526          $500,000
        Shopping Centre,      Centre Management         the art, high efficiency chillers that have exceptional
        1151 Creek Road,      Co. (Qld) Pty. Limited    part load performance and the installation of variable
        Carindale                                       speed drives on chiller plant pumps and cooling towers
                                                        to further enhance the efficiency of the chiller plant. It
                                                        will also include replacing lamps with energy efficient
                                                        retrofits.
SA      45 Grenfell Street,   45 Grenfell Str Pty Ltd   This project will transform a 40 year old building by        1,162          $500,000
        Adelaide              ATF 45 Grenfell Street    installing a new high efficiency chiller, gas fired
                              Unit Trust                cogeneration engine, variable speed driven fans and
                                                        pumps, digital BMS control system, an upgrade to base
                                                        building lighting, and the establishment of ongoing
                                                        optimisation regime and reporting platforms.
SA      81-95 Waymouth        KTS Properties Pty Ltd    This project consists of the replacement of mechanical       518*           $175,000
        Street, Adelaide                                plant control systems; an upgrade of the Building
                                                        Management System and an upgrade of base building
                                                        lighting and lighting controls.




                                                                                                                                  Page 17 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                   Predicted
                                                                                                                   GHG
                                                                                                                   savings
                                                                                                                   (tonnes        Grant offer
                                                                                                                   CO2(e) per     (GST
State   Building address      Applicant                Project description                                         annum)         exclusive)

SA      70 Pirie Street,      Sunnycove Nominees       The project entails installation of variable speed drives   711            $500,000
        Adelaide              Pty Ltd                  to chilled water and condenser water pumps,
                                                       conversion of mixing boxes from constant air volume
                                                       to variable air volume, the replacement of a pneumatic
                                                       Building Management System with a digital system,
                                                       and the replacement of two existing chillers with new
                                                       high efficiency chillers.
SA      Stamford Plaza        Terrace Hotel            This project involves the installation of an energy         1,351          $262,000
        Adelaide Hotel, 150   (Operations) Pty Ltd     management system, an upgrade of the heating,
        North Terrace,                                 ventilation and air conditioning systems and
        Adelaide                                       replacement of the air compressors.
SA      Stamford Grand        The Grand Hotel (S.A.)   The project will involve upgrades of the room air           1,366          $434,000
        Adelaide Hotel, 2     Pty Ltd ATF Grand        conditioning and LED and fluorescent lighting, as well
        Jetty Road, Glenelg   Hotel Unit Trust         as installation of a solar photovoltaic system, bathroom
                                                       occupancy detection system, room air conditioning
                                                       controllers and cooling system variable speed drive
                                                       controls.
TAS     Wrest Point Hotel     Australian National      The project scope includes installation of high             1,719          $500,000
        and Convention        Hotels Pty Ltd           efficiency variable speed chillers, natural gas DHW
        Centre, 410 Sandy                              and heating water systems and fan variable speed
        Bay Road, Hobart                               drives. Optimization of hydraulic plant and air handling
                                                       plant via mechanical modifications and smart control
                                                       strategies with an upgraded Building Management
                                                       System.



                                                                                                                                Page 18 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                Predicted
                                                                                                                GHG
                                                                                                                savings
                                                                                                                (tonnes        Grant offer
                                                                                                                CO2(e) per     (GST
State   Building address       Applicant               Project description                                      annum)         exclusive)

VIC     140 William Street,    Retail Employees        This project involves the upgrade and replacement of     1,824          $394,543
        Melbourne              Superannuation Pty.     key mechanical plant and core lighting systems and
                               Limited ATF Retail      includes modification to the core HVAC system
                               Employees               configuration and controls to maximise operational and
                               Superannuation Trust    energy efficiency.
VIC     Park Hyatt             Ausco Fitzroy Pty       This project will involve implementation of an energy    2,734          $373,600
        Melbourne Hotel, 1     Limited                 management control system using variable speed drive
        Parliament Square,                             controls in guest rooms for HVAC and lighting
        Melbourne                                      (including movement sensors) and replacement of
                                                       current lights with LED lights.
VIC     Sofitel Hotel, 25      AMP Capital Investors   The project involves room energy management systems      2,932          $500,000
        Collins Street,        Limited ATF AMP         and lighting upgrades. The room controls are provided
        Melbourne              Capital Wholesale       via an innovative occupancy sensing based system and
                               Office Fund             its operation will be transparent to hotel guests.
VIC     350 Queen Street,      Blakford Pty. Limited   The project will involve upgrade of BMCS                 1,329*         $440,000
        Melbourne                                      system, upgrade of chillers, installation of variable
                                                       speed drives for air handling units and upgrades to
                                                       lighting and controls.
VIC     108 Lonsdale Street,   Blakford Pty. Limited   The project will involve upgrades of BMCS,               1,013*         $320,000
        Melbourne                                      chillers and lift motors, installation of CO2 sensors
                                                       and variable speed drives for air handling units and
                                                       upgrade of lighting and controls.




                                                                                                                             Page 19 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                 Predicted
                                                                                                                 GHG
                                                                                                                 savings
                                                                                                                 (tonnes        Grant offer
                                                                                                                 CO2(e) per     (GST
State   Building address       Applicant               Project description                                       annum)         exclusive)

VIC     Crown Promenade        Crown Melbourne         The project involves an upgrade to the main air           3,030          $493,123
        Hotel, 8 Whiteman      Limited                 conditioning plant which will include retro-
        Street, Southbank                              commissioning of the thermal plant; installation of CO2
                                                       outside air control to function and public areas;
                                                       and upgrades of the existing lighting systems to energy
                                                       efficient lamp technologies and controls throughout the
                                                       hotel.
VIC     Citiclub Hotel, 111-   Eighth Grange Pty Ltd   The project involves the installation of a new combined   2,485          $500,000
        129 Queen Street,      ATF Harold Chua         heating, cooling and power (tri-generation) system,
        Melbourne              Family Trust No. 8      lighting controls and sub-metering system as well as a
                                                       façade upgrade.
VIC     Melbourne Central      Melbourne Central       This project includes chiller and cooling tower           2,356          $500,000
        Shopping Centre, 211   Custodian Pty Ltd ATF   upgrades, installation of lighting controls, lamp
        LaTrobe Street,        Melbourne Central       replacement and CO sensors introduced to the car park,
        Melbourne              Unit Trust              all commissioned and monitored to improve energy
                                                       consumption.
VIC     90 Collins Street,     GE Real Estate          This project involves the significant upgrade of the      1,336          $500,000
        Melbourne              Investments Australia   building with the installation of a new Building
                               Pty Ltd                 Management System, chiller, ventilation system and
                                                       local thermal zone controls.




                                                                                                                              Page 20 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                  Predicted
                                                                                                                  GHG
                                                                                                                  savings
                                                                                                                  (tonnes        Grant offer
                                                                                                                  CO2(e) per     (GST
State   Building address      Applicant                Project description                                        annum)         exclusive)

VIC     301 Burwood           Burwood Highway JV       Project works will include installation of High            655            $500,000
        Highway, Burwood      Pty Ltd as Nominee for   Efficiency Chillers including Variable Flow Pumping,
                              Laxo Pty Ltd & VBS       SMART Air Solutions Control System, Energy
                              Burwood Pty Ltd          Manager and NABERS Tracker, Variable Frequency
                                                       Drives on Air Handling Units, and high efficiency
                                                       lighting.
VIC     19 Lonsdale Street,   Lo Holdings Pty Ltd as   This project consists of the replacement of Mechanical     102*           $55,000
        Melbourne             trustee for the Lo       Plant; an upgrade of the Building Management System
                              Family Trust             and an upgrade of base building lighting and lighting
                                                       controls.
VIC     Bendigo Marketplace   PPS Nominees Pty         The project involves installation of energy meters on      445            $65,440
        Shopping Centre,      Limited ATF Private      mechanical boards, installation of variable speed drives
        116-120 Mitchell      Property Syndicate       on water pumps, upgrade to BMCS functions and
        Street, Bendigo       Unit Trust               interface connectivity, a process of commissioning and
                                                       the subsequent 12 month process of centre tuning.
VIC     Highpoint Shopping    GPT Funds                This project involves a lighting upgrade in common         1,874          $310,950
        Centre, 200           Management Limited       areas and car park, installation of CO sensors in car
        Rosamond Road,        ATF GPT Retail           park, upgrade to cooler systems and upgrade of
        Maribyrnong           Subsidiary Trust         controlling technologies to assist the monitoring
                                                       systems.




                                                                                                                               Page 21 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                Predicted
                                                                                                                GHG
                                                                                                                savings
                                                                                                                (tonnes        Grant offer
                                                                                                                CO2(e) per     (GST
State   Building address      Applicant                Project description                                      annum)         exclusive)

VIC     700 Collins Street,   Cromwell Property        This project consists of a number of building tuning     1,928          $364,000
        Docklands             Securities Limited ATF   improvements including the rebalancing of variable air
                              Cromwell Diversified     volume boxes and air diffusers, reinstatement of
                              Property Trust           economy cycle algorithm; utilisation of demand
                                                       management and passive "night purge" ventilation;
                                                       modification of Controls algorithms; adopting variable
                                                       primary pumping strategy and placing the existing
                                                       chillers in series.
VIC     Stamford Plaza        Minteyville Lt Collins   This project involves the upgrade of the chiller,        1,363          $442,250
        Melbourne Hotel,      Street Pty. Ltd.         upgrade of lighting to LED, installation of a room
        111 Little Collins                             occupancy detection system and the installation of a
        Street, Melbourne                              variable speed drive control system for the cooling
                                                       system.
VIC     22 William Street,    Ronald Investments       This project consists of the installation of variable    474            $187,871
        Melbourne             Pty. Limited             speed drives to the HVAC equipment; upgrade of the
                                                       Building Management System; installation of the
                                                       economy cycle and an upgrade of base building
                                                       lighting with T5 lamps.

VIC     Royal Domain Centre Mirvac Funds Limited  The project proposes the installation of a natural gas        1,136          $500,000
        380 St Kilda Road,  ATF 380 St Kilda Road generator, a new chiller, heat exchanger and energy
        South Melbourne     Trust                 metering system.




                                                                                                                             Page 22 of 23
Green Building Fund
Funding offers for Round 7, Stream A

                                                                                                                        Predicted
                                                                                                                        GHG
                                                                                                                        savings
                                                                                                                        (tonnes        Grant offer
                                                                                                                        CO2(e) per     (GST
State     Building address        Applicant                  Project description                                        annum)         exclusive)

VIC       Simplot Building,         The Trust Company       This project consists of three energy efficiency            616            $63,166
          Chifley Business          Limited as Custodian    building improvement works: an upgrade to the
          Park, 1 Chifley           for GAI 1 Chifley Trust building's mechanical systems including modifications
          Drive, Mentone                                    to the air handlers, adding full outside air economy
                                                            cycles, installation of variable speed drives, an upgrade
                                                            to the Building Management System and an upgrade of
                                                            base building lighting and lighting controls.
 WA       Karratha                  Ringthane Pty Ltd ATF The project involves an upgrade of air-conditioning           664            $451,507
          International Hotel,      Karratha International  systems, installation of heat pump hot water systems, a
          100 Hillview Terrace, Hotel Trust                 lighting upgrade and the installation of performance
          Karratha                                          management meters and systems.
 WA       14-16 Victoria            GE Real Estate          This project includes the installation of a new chilled     682            $500,000
          Avenue, Perth             Investments Australia   water system, Building Management System, foyer
                                    Pty Ltd                 lighting, and floor local zone controls.
 WA       66 St Georges             AMP Capital Investors The project will deliver energy reductions for the            577            $500,000
          Terrace, Perth            Limited ATF Property building by replacing the existing chillers, upgrading to
                                    Income Fund             digital BMCS, installation of variable speed drives and
                                                            replacement of lighting and controls.
* applicant part of consortia of applications




                                                                                                                                     Page 23 of 23

								
To top