Bids Log - 2012
Bid Information Front End Documents Bid & Award Process Agreement
Review Addendum Routed for Agree.
Request to Blue Sheet # & Bid Bond Award & Executed Notice to Bond / NOC Record In
Name Project Manager Package Legal Ad Pre-Bid Mtg Issued Bid Opening NOI Issued Board Date Execution - Returned to
Prepare Date Routed Release Agree./Non-- Returned Proceed Returned Access
Sent (Adden #) Name Contractor
Award-Date
12/13/11
Stevens &
B-12-01 Sunniland Boulevard Rob Phelan, DOT 9/26/11 10/07/11 10/18/11 None 11/02/11 20110984 12/13/11 12/13/11 Layton
#1 - 12/5/11
#2 - 12/9/11
Lakes Park & Powell Creek Anura Karuna-Muni- CL 11/30/11 @ #3 - 12/21/11 @
B-12-02 Preserve Natl Res 9/23-9/26 Reviewed n/a 8:30 am 12/14/11 3:00 pm 01/04/12 20120008 01/24/12
Powell Creek Restoration Wanda Wooten-Natl CL 10/27/11 @ #1 - 11/2/11 11/9/11 @3:00 12/13/11
09/27/11 10/14/11 12/07/11 01/10/12
Dredge Res Reviewed 10:00 am #2 - 11/7/11 pm 20111050
B-12-03
#1 01/10/12
B-12-04 A&W Bulb Road Rob Phelan-DOT 10/07/11 10/28/11 11/17/11 '11/21/11 11/30/11 12/19/11 20111070 '01/10/12 Better Roads 01/31/12
# 1 - 12/5/11
#2 - 12/7/11
Briarcliff Filter Marsh Anura Karuna-Muni- CL 11/30/11 @ #3 - 12/9/11 12/21/11 @
B-12-05 Quality Improvements Natl Res 9/23-9/26 Reviewed n/a 8:30 am #4 - 3:00 pm 01/09/12 02/21/12
CW Resurfacing Roadway CL 01/20/12
B-12-06 Improvemetns Randy Cerchie-DOT Reviewed 12/16/11 01/04/12 01/18/12 01/19/12 20120069 02/21/12
Ten Mile Canal Filter Marsh Steve Farah-Natl Res 2/28/12 @ 3/14/12 @ 3:00
B-12-07 Water Quality Improvements 533-8829 01/23/12 02/10/12 10:00 am pm
B-12-08 CW Bike Path Improvements Dirk Danley-DOT 1/5/2012 2/10/2012 2/17/2012 03/01/12 03/07/12
CW Resurfacing - FY 12
B-12-09 Contract 2 Randy Cerchie-DOT 02/02/12 02/10/12 02/24/12 03/07/12 03/28/12
Big Carlos Pass Scour 4/2/12 @ 4/11/12 @ 3:00
B-12-10 Reapirs Ehab Guirguis, DOT 3/33/12 03/23/12 10:00 a.m. p.m.
B-12-11 Pine Rdige Sewer 4/11/2012 @
Replacement Luis Soto - Utilities 03/23/12 10:00a.m. 4/25/12 @ 3:00
Updated: 6/6/2012 S:PWKFORM/LOGS-MASTER/LOG-Bid.xls
Bids Log - 2012
Bid Information Front End Documents Bid & Award Process Agreement
Review Addendum Routed for Agree.
Request to Blue Sheet # & Bid Bond Award & Executed Notice to Bond / NOC Record In
Name Project Manager Package Legal Ad Pre-Bid Mtg Issued Bid Opening NOI Issued Board Date Execution - Returned to
Prepare Date Routed Release Agree./Non-- Returned Proceed Returned Access
Sent (Adden #) Name Contractor
Award-Date
Updated: 6/6/2012 S:PWKFORM/LOGS-MASTER/LOG-Bid.xls