									    Sample Progress Certificate Form
    Progress Certificate # 5

DATE:           6 August, 1996                              JOB NO:          9460

PROJECT:                    ABCDEF SECONDARY COLLEGE, DXY CAMPUS - STAGE 1

PROPRIETOR:                 ABCDEFG SECONDARY COLLEGE

CONTRACTOR:                 GEORGE BUILDER

CERTIFICATE NO:             6 (Claim dated 30 June, 1996)


Current adjusted contract sum                               $ 3,741,608.00
Estimated value of works executed to date                   $ 1,999,588.00
Less retention (Bank Guarantee Held)                            ---
Amount Payable                                              $ 2,024,333.00
Less previously certified                                   $ 1,640,354.00
AMOUNT DUE                                                  $    383,979.00
It is hereby certified that the Contractor is now entitled to receive from the Proprietor the
sum of three hundred and eighty three thousand nine hundred and seventy nine dollars ---

Architect

On presentation of the original certificate to the Proprietor, the Contractor is entitled to
payment within 20 working days.



Summary

Original Contract Sum                                       $ 3,716,863.00
Contract Variation Adjustment                               $     24,745.00
Current Contract Sum                                        $ 3,741,608.00
Deduct Builders Claim to Date                               $ 2,024,333.00
Balance to Complete Contract                                $ 1,717,275.00


(Note: Contract sum excludes contingency sum)

								