									 Integrated Land Management Bureau
 Northeast BC - Proof of Concept Charter                                             Date Prepared: April 25, 2012




                                                                          PROJECT CHARTER

1.0        PROJECT IDENTIFICATION

 Project Identification: (double click on box below to select)
 Project Name:                          Northeast BC - Proof of Concept
 Project Number:
 Project Manager:                       Roger Balser
 Project Classification:                    A Class                  B Class                 C Class
                                        Bill Anderson, Acting Director BMGS,
                                        Mark Todd,     Woodlands Information Coordinator, Canadian Forest
 Project Sponsor:
                                                       Products Ltd., Prince George Division
                                        Doug Kelly,     Manager Engineering and Real Estate and Operations

 Division/Unit:
       Regional Client Services Division (RCSD)                    Species-At-Risk Coordination (SaRCO)
       Strategic Initiatives Division (SID)                        Project Management Office (PMO)
       Corporate Resource Information Management
                                                                   Bureau Management (e.g. Exec; IAMC)
       (CRIM)


1.1        BUSINESS NEED

Base data in British Columbia needs to be updated and maintained in cost effective manner. The
purpose of this project is to test and verify a practical, no/low cost method, based on business
requirements, to directly pull one data type (operational road data) from a forest industry client
(Canfor). Currently government requires industry to submit data using various electronic submission
technologies. This process is time consuming and cost-ineffective for industry as several submissions
are often required.

In a joint initiative to streamline the data submission process, Canfor established an ftp site to allow
Base Mapping Geomatics Services (BMGS) to access their operational data directly with no additional
cost to industry. As Canfor maintains 60-70% of the industries resource roads attribution, the data
collected will be integrated with the current TRIM roads archive to address the estimated 100,000 km
of road missing from the government’s corporate road database.

The recommendations from the Working Group for the Northeast British Columbia Base Data
Maintenance and Update Pilot Project to obtain current and appropriate attribute data directly from
industry was accepted by the Steering Committee.

In doing so, the Working Group was directed to address the concerns of current business needs and
the technical aspects of updating and maintaining the base data. These business requirements are
the driving force behind the Resource Road Act whose enactment is anticipated in the fall of 2008.
This Act will establish the coordination of a multi-ministry regulatory and permitting process and set
the standards for all road submissions by industry.

                                                                                                      Page 1 of 7
    Integrated Land Management Bureau
    Northeast BC - Proof of Concept Charter                                          Date Prepared: April 25, 2012




1.2           PROJECT SCOPE

This is a trial to transfer data as it currently exists in the Canfor operational system. The scope of this
project is restricted to dealing with the road data and its attribution as it is currently managed in
Canfor’s operational data base.

While bearing in mind the requirements of the GeoBase, the data will be integrated to the current
TRIM base until such time as the GeoBase road layer is specified.

The scope of the project includes:
        Develop business model
        Develop data process model
        Review attribution requirements (from NEBC Pilot work) against the attribution held
         operationally by Canfor
        Create an ftp site of road data at Canfor (this exists)
        Access the ftp site by BMGS and pull down the data (unattended)
        Evaluate data and attribution
        Integrate data with TRIM roads (GeoBase road layer)
        Report to NEBC Working Group and Steering Committee on results

1.2.1. Activities Excluded in Project Scope:

The following items are out of scope and provided here to help clarify the scope boundaries of the
project:
        Any data other than roads
        Other industry partners
        Developing, specifying the GeoBase road layer
        Capture of any new data on behalf of Canfor
        Building a “feature” data base

1.2.2 Assumptions and Constraints:

The following assumptions have been identified:
    Canfor can create the ftp site

The following constraints have been identified:
    NEBC Data Update and Maintenance Project – The project has completed its dependence work
     with the submission of its report. The Proof of Concept builds from that and verifies the action
     items.

                                                                                                      Page 2 of 7
    Integrated Land Management Bureau
    Northeast BC - Proof of Concept Charter                                                Date Prepared: April 25, 2012



        GeoBase BC - The creation of the GeoBase BC road network is reliant upon creating a model
         that will integrate the format of the Canfor Data so that it can be managed. The data must be
         feature based to meet partner requirements so that the partner can access it in the same format
         it was submitted.

1.3           PROJECT DELIVERABLES

    Milestone                                         Responsibility                End Date (YYYY/MM/DD)
         Confirm resources                                 Roger Balser                   2008/01/20
            Finalize Project Team                          Roger Balser                   2008/01/20
            Establish a working group                      Roger Balser                   2008/01/02
            Prepare and obtain approval of the             Roger Balser                   2008/02/11
             Project Charter
            Review attribution requirements                    BMGS                           2008/02/15
             (from NEBC Pilot work) against the
             attribution held operationally by
             Canfor
            Develop business model                             BMGS                           2008/03/21
            Develop data process model                         BMGS                           2008/03/21
            Create an ftp site of road data at                 Canfor                         2008/01/18
             Canfor
            Acquire data from ftp site                         BMGS                           2008/01/18
            Integrate data with TRIM roads                     BMGS                           2008/02/29
             (GeoBase road layer)
                                                             Canfor/BMGS                       2008/03/14
            Access the ftp site by BMGS and pull
             down the data (unattended)
            Final report to NEBC Working Group              Canfor/BMGS                       2008/03/28
             and Steering Committee on results


1.4           PROJECT RESOURCE REQUIREMENTS

    Internal Resources
    Role                                                Business Area           Confirmed (Y/N)        Estimate ($):
    Project Sponsor                                      BMGS/Canfor                   Y
    Project Manager                                        BMGS                        Y
    Project Team Leads                                   BMGS/Canfor                   Y
    Business, Policy, Technical Analysts                 BMGS/Canfor                   Y
    Total Internal Resource Cost Estimate:                                                                $15,000

    External Resources
    Role                                             Business Area       Confirmed (Y/N)          Estimate ($):
    Non-Government Organizations                        Canfor                  Y                    $5,000
    External Consultant                             BMGS Contractor             Y                    $5,000
    Total External Resource Cost Estimate:                                                          $10,000


                                                                                                            Page 3 of 7
 Integrated Land Management Bureau
 Northeast BC - Proof of Concept Charter                                                   Date Prepared: April 25, 2012




1.5        PROJECT BUDGET

 Total Project Cost Estimate
 A. Internal Resources (from above)                                                                  $15,000
 B. External Resources (from above)                                                                  $10,000
 C. Internal Fixed Costs and Expenses
 D. External Fixed Costs and Expenses
 E. Contingency                                                                        %
 F. Total Project Cost Estimate                                                                      $25,000

 General Project Budget Notes:
 Internal & External resources funded from current operational budget

1.6        FUNDING SOURCE

 Funding:
      Operational
      Capital


 Funding Source(s):                                                         Percent          Confirmed? (Y/N):
      Operational                                                            80%                    Y
      Forest Investment Account                                               %
      Capital Budget                                                          %
      Treasury Board Lift                                                     %
      First Nations Contingency Fund                                          %
      CLUPE                                                                   %
      Other - Canfor base budget                                             20%                        Y

1.7      CHANGE CONTROL

Changes to objectives, timelines and resources may recommended by the Business Leads. Changes
must be approved by at least one Project Sponsor.

1.8        PROJECT RISKS
                                           Probability   Impact
Risk Description(s)                                                     Risk Response
                                           (H/M/L)       (H/M/L)
Inability of Canfor to create the                                          Go directly to a database design
ftp site                                      High          High
                                              Medium        Medium
                                              Low           Low
Conflict and lack of clarity                                               Communicate that project is
surrounding the direction of                  High          High            operational in nature and the
GeoBase BC                                    Medium        Medium          outcome will be required irrespective

                                                                                                            Page 4 of 7
 Integrated Land Management Bureau
 Northeast BC - Proof of Concept Charter                                                    Date Prepared: April 25, 2012



                                            Low             Low               of the announcements of GeoBase
                                                                              BC

                                                                             To address this, alternative
Lack of internal resources                  High            High              contracting options not dependent
                                            Medium          Medium            upon net new procurements are
                                            Low             Low               being examined.
Difficulty integrating the data into                                         Integrate data into existing TRIM
GeoBase BC as the database is               High            High              data and model
not yet operational                         Medium          Medium
                                            Low             Low

1.9        ISSUE MANAGEMENT

The Project Manager will maintain a Project Issue Log to document issues that arise that may affect
the achievement of the project deliverables. Documented issues will be reviewed regularly by the
Project Manager for action and resolution.

1.10     COMMUNICATIONS

1.10.1 Stakeholder Identification

 Stakeholder Group: Name                   Represented by                Interests, Expectations, Concerns
                                                                      Progress reports
                                     Bill Anderson, BMGS
                                                                      Issues managed
 Project Sponsor                     Mark Todd, Canfor
                                     Doug Kelly, MoFR                 Deliverables are met

                                                                      Progress Reports
                                                                      Issues Managed
 Project Manager                     Roger Balser
                                                                      Deliverables are met
                                                                      Tasks are assigned
                                     Paul Quackenbush                 Project status awareness
                                     Paul Austin, Contractor          Collaborative approach to initiative
 ILMB-BMGS staff
                                     Yao Cui                          Manage and update base data
                                     Ron Walker                       Business and technical procedures
                                     Roger Balser, Contractor         Links to GeoBase BC
                                     Dennis Thideman, Contractor
                                     Mark Todd                        Provide data to government with no hidden
                                     Annette Bailey                    costs
 CanFor                              Jordan Kirk                      Business and technical procedures and
                                     Nathan Strand                     processes
                                     Frank Ogiamien
                                     Donna Stapely                    Links to RRA and ABR
 MoFR
                                     Brian Howden
                                                                      Provides project direction and guidance
                                     Paul Quackenbush                 Ensures stakeholder interests
 Steering Committee                  Mark Todd                        Discusses/resolves issues
                                     Donna Stapley                    Reviews/approves changes and
                                                                       deliverables




                                                                                                              Page 5 of 7
 Integrated Land Management Bureau
 Northeast BC - Proof of Concept Charter                                                       Date Prepared: April 25, 2012




                                     Ron Walker, BMGS                     Ensures stakeholders interests
                                     Frank Ogiamien, Canfor               Discuses/resolves issues
 Working Committee                   Nathan Strand, Canfor                Reviews/approves changes & deliverables
                                     Annette Bailey, Canfor               Provides expertise
                                     Jordan Kirk, Canfor
                                     Yao Cui, BMGS                        Provides expert advice to sponsor (and/or
                                     Paul Austin, Contractor               Steering Committee)
 Technical Advisory
                                     Brian Howden, MoFR
 Committee
                                     Frank Ogiamien, Canfor
                                     Nathan Strand, Canfor
                                                                          Review Status Reports
 PMO Contact                         Jessica Byers
                                                                          Advise/counsel

1.10.2 Communication Strategy

 Stakeholder Group                   Communication Type            Frequency      Communication Purpose
                                     Email/meeting                  Monthly        Update on Project Status
 Project Sponsor
                                     communication
 Project Manager                     Project Status Reports         Bi-weekly        Update on Project Status
                                     Project Status Reports         Bi-weekly        Update on Milestone Status
 Project Team Members                Email/meeting
                                     communication
                                     Project Status Reports         Bi-weekly        Update Executives on Project
 PMO Contact
                                                                                      Status
                                     Email/meeting                  Bi-weekly        Provide input/direction on
 Steering Committee
                                     communication                                    Project
 Working Committee                   Email/meeting                  Bi-weekly        Provide input/direction on
                                     communication                                    Project
 Technical Advisory                  Email/meeting                  Bi-weekly        Provide input/direction on
 Committee                           communication                                    Project

1.11     APPROVAL PROCESS

1.11.1 Project Manager Submission

 Name:                                 Position:              Signature:                             Date:
 Roger Balser                          Project Manager


1.11.2 PMO Review (This is an A Class Project)

 Name:                                 Position:              Signature:                             Date:
 Kevin Edquist                         Director




                                                                                                                Page 6 of 7
Integrated Land Management Bureau
Northeast BC - Proof of Concept Charter                              Date Prepared: April 25, 2012



1.11.3 Project Sponsors

Name:                                 Position:         Signature:         Date:
Bill Anderson                         BMGS Director
                                      CanFor,
                                      Woodlands
Mark Todd
                                      Information
                                      Coordinator
                                      MoFR, manager
                                      Engineering and
Doug Kelly
                                      Real Estate
                                      Operations




                                                                                      Page 7 of 7

								